Deliver the Approved Materials and Equipment to the Fabrication Area 1d 9-Feb-19 9-Feb-19
Check the Approved Materials Equipment Based on Purchase Order 1d 10-Feb-19 10-Feb-19
and Job Order
Pipe Cutting Grinding 5d 11-Feb-19 16-Feb-19
Pipe and Fittings Jointing/Welding 25d 17-Feb-19 17-Feb-19
Welding Inspection and Testing (NDT) 6d 18-Mar-19 24-Mar-19
Welding and Valves Certification 4d 25-Mar-19 28-Mar-19
Pipe Coating 4d 30-Mar-19 2-Apr-19
Assembly and Fabrication 5d 3-Apr-19 8-Apr-19
Hydro and Leak Test 4d 9-Apr-19 13-Apr-19
3 Delivery 8d 14-Apr-19 22-Apr-19
Outgoing Inspection by QA/QC 1d 14-Apr-19 14-Apr-19
Issue Delivery and Sales Invoice 1d 15-Apr-19 15-Apr-19
Material Loading at the Trailer 1d 16-Apr-19 16-Apr-19
Material Delivery at Site 1d 17-Apr-19 17-Apr-19
Msterial Unloading 1d 18-Apr-19 18-Apr-19
Free Hot & Cold Commissioning with the Present of Client,Suppliers 3d 20-Apr-19 22-Apr-19
and Consultant
November-18 December-18 January-19
Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3 Week 4 Week 1 Week 2
January-19 February-19 March-19
Week 2 Week 3 Week 4 Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3
March-19 April-19
Week 3 Week 4 Week 1 Week 2 Week 3 Week 4