Академический Документы
Профессиональный Документы
Культура Документы
KANHANGAD
CONTENTS
INTRODUCTION 2
INTRODUCTION
Kasaragod is the northern most district of the State and was formed on the 24th May, 1984
and lies between 12º 12' and 12º 48' north latitudes and 74º 52' and 75º 26' east longitudes.
The district lies between the Western Ghats and the Arabian Sea. The eastern part of the
district is hilly with small forest tracts. The district is bound in the east by Kodagu and
Dakshin Kannada districts of Karnataka State, in the west by the Arabian Sea, in the north by
Mangalore Taluk and Dakshin Kannada District of Karnataka and in the south by Kannur
District in Kerala.
Kasaragod District has an area of about 1989 sq.km. It accounts for 5.13 percentage of the
total area of the State (38852 sq.km). Even though the population density is moderate there is
no sufficient hospital facilities. The available facility are very poor with insufficient
infrastructure, furnishing and equipment facilities. Patients and endosulphan victims are
suffering a lot due to this scarcity and development in this area is a very urgent necessity.
Now most of them needs to go through long distances for health needs and this many times
lead mortality.
As the part of improvement of health and hospital facilities, proper electrification is necessary
which in tern leads to facilitate to run modern health equipment’s electronic machineries even
basic hospital requirements, scan, X rays, MRA’s Operation theatre equipment’s, ECG’s
Oxygen Succes Systems, etc.. Along with Lift and Fire equipment’s. Hence proper electrical
wiring systems and electrification is urgent necessity in every hospital. Hence the important
of this proposal is for installation of lift in new IP Block for the District Hospital at
Kanhangad is stated in this report.
decided to prepare the Detailed Project Report for including the project in Kasaragod
Development Package for the year 2019-20. As per the direction Arsha N First Grade
overseer of Kasaragod development Package at LSGD using the available details of supply
and installation of lift has prepared the DPR.
The scope of the study is limited to the installation of lifts at proper locations so as to increase
its functional efficiency. The main objective is to commission a passenger lift which meets
the technical specifications (as mentioned in upcoming section); as it is a basic infrastructural
requirement for a hospital building. Design, Fabrication, Supply, Installation,
Commissioning, packing, forwarding, transportation to new IP block Kanjhangad site,
unloading, furnishing of final drawings and manuals, handling at site, performance
demonstration and performance acceptance etc. of passenger capacity lift (as per table 1), to
make the system complete in all respects and required civil work as per technical
Specification & as per the tender document.
Standards:
The following Indian Standard Specifications and Codes of Practice, currently applicable and
updated as of date irrespective of dates given below, shall apply to the equipments and the
work covered by this contract. In addition the relevant clauses of the Indian Electricity Act
1910 and Indian Electricity Rules 1956 as amended up to date shall also apply. Wherever
appropriate Indian Standards are not available, relevant British and/or IEC Standards shall be
applicable
1. Code of Practice for installation, operation and maintenance of electric passenger & goods
lifts.IS-14665 (Part 2) Sec-1 :2000
2. Code of practice for installation, operation and maintenance of electric service lift.IS-
14665 (Part 2) Sec-2 : 2000
3. Safety Rules Section-1 Passenger and Good lifts IS-14665 (Part 3) Sec-1 : 2000
4. Safety Rules Section-2 – Service Lifts IS-14665 (Part 3) Sec-2 : 2000
5. Outline dimension for electric lifts. IS-14665 (Part-1) : 2000
6. Inspection Manual for Electric Lifts IS-14665 (Part 5) : 1999
7. Electric Traction Lifts – Components
8. Installation And Maintenance of Lifts For Handicapped Persons (Code of Practice) IS-
14665 (Part 4) Sec-1 to 9 :2001IS 15330 :2003
9. Specification for lifts cables. IS-4289 (Par-1) : 1984 Reaffirmed 1991
10. Specification for hot rolled and slit steel tee bars. IS-1173-1978 Reaffirmed 1987
11. Method of loading rating of worm gear. IS-7443-1974 Reaffirmed 1991
12. Code of practice for selection of standard worn and helical gear box.IS-7403-1974
Reaffirmed 1991
13. Isometrics screw threads. IS-4218-(Part-II)1976 Reaffirmed 1996
14. Degree of protection provided by enclosure for low voltage switchgear and control gear.
IS-2147-1962.
15. Classification of insulating materials for electrical machinery and apparatus
in relation to their thermal stability in service. IS-1271- 1985 Reaffirmed 1990.
16. Code of practice for earthing. IS-3043-1987
17. Electrical installation Fire Safety of Building. IS-1646-1997
18. PVC insulated electric cable for working voltage up to and including 1100 volts. IS-694-
1990
19. Code of practice for electrical wiring and installation IS-732-1989
20. PVC insulated (Heavy Duty) electric cables for working voltage up to and including 1100
volts. IS-1554-1988 (Part-1)
21. Flexible steel conduits IS-3480-1966
22. Accessories for rigid steel conduit for electrical wiring IS-3837-1976
23. Boxes for the enclosure of electrical accessories IS-5133-1969 (Part 1)
24 Guide for safety procedures and practices in electrical work. IS-5216- 1982 (Part-1)
25. Conductors for insulated electric cables and flexible cordes IS-8130- 1984
26. Miniature Circuit Breakers IS-8828-1996
27. Rigid steel conduits for electrical wiring (Second revisions) IS-9537- 1981
28 Methods of test for cables IS-10810-1998
29. Earth Leakage Circuit Breakers. IS-12640-1988
30. Moulded Case Circuit Breakers IS-13947-1993
31. General requirement for switchgear and control gear for voltage not exceeding 1000
volts.IS-13947-1993
32. 1100 volt grade XLPE insulated armoured cables IS 7098
33. Specifications for hoistway door-locks IS 7754-1975
34. Rules for design, installation, testing and operation of lifts, escalators and moving parts.IS
1735-1975
In addition the relevant clauses of the following, as amended upto date shall
apply.
The Indian Electricity Rules 1956
The Indian Electricity Act 1910
Fire safety regulations pertaining to lifts
12.2. Methodology
The passenger lift as per specification is to be supplied and installed as per IS specifications
and after trails running the lift will become fully operational.
responsibilities in ensuring quality control, the Contractor shall employ qualified technical
personnel at site, as agreed in the contract.
It shall be the responsibility of the Overseer in charge to directly supervise all items of work
and ensure that works done are as per the specifications and that quality standards are
achieved. Overseer shall inspect all materials supplied then and there and ensure that the
materials conform to standards. He shall not allow the Contractor to supply materials not
conforming to specifications and standards. He shall ensure that only good quality work is
done at site. Any instance of violation of his instructions during supply of materials or
carrying out work shall be recorded in Workspot order book and reported to the Assistant
Engineer in writing immediately. He shall not permit the Contractor to proceed with the work
in case his instructions are not complied with.
Assistant Engineer shall ensure that work is being carried out by the Contractor as per
specification and standards. He shall visit the site of work frequently and issue instructions
enabling adherence to specifications and strict quality control. If any defective work is
noticed during inspection, the Contractor or his authorised representative at site shall be
instructed to stop bad quality work and rectify the defects of the work done. The Assistant
Engineer shall record details of such defective work noticed and instructions issued therein in
the Work spot order book. The fact of having done rectification satisfactorily shall also be
noted subsequently in the Workspot order book. Notice shall be issued under intimation to the
Agreement Authority, in case of non-compliance of instructions issued at site.
The Agreement Authority shall initiate action to terminate the contract and initiate penal
action, if the desired level of quality is not exercised in the construction. Assistant Executive
Engineer shall monitor the entire quality control process and ensure that his subordinate
officers are carrying out their duties promptly. In case of lapse on the part of any officer, he
shall report to the Executive Engineer for initiating disciplinary action. He shall also report
lapse, if any on the part of the Contractor to the Agreement Authority for penal action as per
rules of registration and contract conditions.
severity). Risks affect project outcomes in diverse ways. Risk effects are usually apparent in
direct project outcomes by increasing costs or schedules. Some risks influence the project by
affecting the public, public perception, the environment, or safety and health considerations.
Risk can also affect projects in indirect ways by requiring increased planning, review, and
management oversight activity. The risk assessment phase has as its primary objective the
systematic consideration of risk events, their likelihood of occurrence, and the consequences
of such occurrences. Risk assessment is fundamentally a management activity supported by
persons familiar with risk management activities. Managers tend toward qualitative
assessment of risks. They evaluate risks on their worst-case effects and their relative
likelihood of occurrence. Internal risks are those that arise within the scope and control of the
project team. Most internal risks can be referenced to a specific project document such as a
cost estimate or a schedule. External risks are items that are generally imposed on the project
from establishments beyond the limits of the project. Interactions with citizens groups or
regulators are typical external risks. . Risk mitigation ensures that each risk requiring a
response has an owner. The owner of the risk could be an agency planner, engineer,or
construction manager, depending on the point in project development, or it could be a private
sector contractor or partner, depending on the contracting method and risk allocation. .
Mitigation steps, although costly and time consuming, may still be preferable to going
forward with the unmitigated risk. The project manager and team decide to accept certain
risks. They do not change the project plan to deal with a risk or identify any response strategy
other than agreeing to address the risk if it occurs. Given a clear understanding of the risks,
their magnitude, and the options for response, an understanding of project risk will emerge.
This understanding will include where, when, and to what extent exposure will be
anticipated. The understanding will allow for thoughtful risk planning and construction.
after the progress of the particular task. Contractors, architects, structural engineers and civil
engineers are assigned for each task and works closely with the task manager/supervisor. The
implementation/construction can be divided into phases depending on the bookings by
customers and the availability of materials and labor. The problem comes with the material
quality and delivery, labor issues, Safety issues, Compliance, Coordination etc. which
ultimately results in the scope creep, cost overruns and hinders customer delivery and
satisfaction. Thus in order to achieve the target, a project manager has to closely monitor the
progress and avoid bottlenecks.
16.0 IMPLEMENTATION SCHEDULE
The Project Implementation Schedule chart that clearly lists all the tasks necessary to
complete the project and related deadlines. This is the most important part of planning
because it will become the tool to use for the monitoring and evaluation phases of the project.
List of all the tasks required for the implementation of the project is required in this stage.
Ranking of tasks should be done according to their importance. There will be tasks that need
to be concluded in order to start another task and tasks that could be done in a more flexible
way. Highlight all the urgent tasks and visually connect tasks that require the completion of a
previous task to be started. A well-designed project implementation schedule clarifies and
describes what the project should deliver and within what time-frames. The estimated
duration of the project is six months.
17.0 ANNEXURE
Approved drawing
Detailed estimate
Copies of statutory approvals