Академический Документы
Профессиональный Документы
Культура Документы
075-053-10
Table of Contents
4.6 Cabling 60
1 The DC Power System 1 4.7 Power Up Procedure 62
1.1 DC Power Overview 1
4.8 Initial Charge and Discharge Test 63
1.2 Rectifier 5
4.9 Documentation 63
1.3 Battery 12
1.4 Distribution 20 5 Power System Commissioning 67
1.5 Battery Return Bus 23
1.6 Supervisory and System Control 24 6 Retrofit Installation 69
6.1 Precautions 69
1.7 Low Voltage Disconnect Contactor 28
6.2 Tools List 69
1.8 CEMF Cell 30
6.3 Distribution Circuit Addition 70
1.9 Battery Temperature Compensation 31
6.4 Common Ground Bus Addition 70
1.10 DC - DC Converter System 35
6.5 Distribution Panel Addition 71
1.11 DC Power System Integration 37
6.6 Rectifier Addition 72
1.12 Inverters/UPS 39
6.7 Shunt Replacement 72
M
ost communication equipment, including PBX’s, telephone switches, microwave transmission,
fiber optic transmission, mobile radio, cellular, etc. are designed to operate from a DC input
voltage. A DC source has the inherent benefit of higher reliability as compared to an AC
source. This is because the battery, which is often used for backup, is directly connected to the
load with no intermediate stage such as an inverter that may fail and disrupt power to the load. The basic
power system consists of a rectifier and usually a battery, but may include various other components. The
various components are discussed in detail later in this section.
+24V evolved from the mobile radio industry, where equipment was designed to operate from either
an automotive (+12V) charging system or a truck (+24V) charging system.
-48V evolved from the telephony world where 48 volts was chosen because it was the maximum
voltage that was considered safe as technicians had to make live connections. The negative polarity
(positive ground, similar to the old British -6 VDC automotive charging system) was chosen as it
reduced the galvanic corrosion that occurred when the lead sheathed telephone twisted pair cables
were originally deployed and buried in the earth.
1.2 Rectifier
1.2.1 Description
The rectifier is a device that changes an AC (alternating current) input to a regulated and filtered DC
(direct current) output. The DC output supplies power to the load (communication equipment) and
charges a backup battery if required (see Figure 4).
1.2.2 Connection
The rectifier is connected in parallel with both the load and the battery (if applicable). Multiple rectifiers
may be connected together in parallel, with their corresponding (+) and (-) leads connected together.
AC-ON - The rectifier supplies current to the load and provides a trickle charge current to the battery.
AC-OFF - The rectifier turns off and the battery will supply current to the load until the battery is
completely discharged.
AC-ON - The rectifier supplies current to the load, any extra current available from the rectifier will be
used to recharge the battery.
N+1 redundancy should always be considered. N is the number of rectifiers required to satisfy the
total capacity requirements of the load and the “1” is an extra rectifier added so that a failure of a
rectifier in the system will not jeopardize system integrity.
Correct choice of either positive ground (-48 VDC) or negative ground (+24 VDC) is critical. The
grounded potential is connected to a common point and the “live” cable is connected through either fuses
or circuit breakers.
Tight voltage regulation (line and load) to ensure that the battery is properly charged and the load
does not receive fluctuating voltages.
Modular vs. monolithic configuration; modular rectifiers allow for easy replacement and expansion.
Unity power factor (P.F.>.95) is becoming more important as the utilities move toward increased
monitoring of power factor. A poor power factor at your Telecom facility may result in the electrical
utility adding a surcharge to your electrical bill. In Europe, unity power factor is a CE requirement for
Residential and light commercial applications. North America may soon follow this trend. There are
two types of power factor measurements displacement and true. The displacement component of
power factor is the ratio of the active power of the fundamental wave (60 Hz), in Watts, to the
apparent power of the fundamental wave in volt-amperes. This is the value used by utilities to
determine billing. True power factor is the ratio of the total power input, in Watts, to the total volt
ampere input, this includes the fundamental wave (60 Hz) and all the harmonics (120, 180, 240, 360,
480 Hz, etc. This value is used for efficiency calculations. Early Argus rectifiers utilize passive power
factor correction to achieve reasonable power factor at low cost. The Pathfinder rectifiers offered by
Argus have a true power factor of >.99.
Low THD (total harmonic distortion) and damaging harmonic currents, to meet CE requirements
and to eliminate AC generator and transformer overheating and interaction problems. THD refers to
the distortion of the incoming AC voltage or current waveform when the rectifier is connected and is
expressed as a percentage.
Three phase AC input - For higher power applications this becomes more important to ensure even
balancing of load on a three-phase AC source.
High efficiency as well as having the obvious power savings benefit, reduces the size of the input
feeder circuit breaker, input cabling, and air conditioning requirement.
Wide AC operating window for both frequency and voltage to tolerate fluctuations without the
rectifier shutting down. Argus rectifiers have a wide input tolerance range for both frequency and
voltage. This allows uninterrupted operation and also allows universal operation for 208/240V 60Hz
operation and 220V 50 Hz operation with no modification or reconfiguration required.
Pathfinder 48-3kW & 24-3kW rectifiers (208/240 VAC I/P) will continue to operate down
to 90 VAC (with reduced output)!
Compact and lightweight helps reduce installation, maintenance and shipping costs.
Balanced load sharing should be achieved between units of the same design and with other types of
rectifiers. Argus rectifiers accomplish this with a combination of forced sharing (master/slave) and/or
adjustable slope regulation. Adjustable slope allows you to tailor the voltage regulation characteristics
of different brands of rectifiers.
Forced sharing works by the rectifiers electing a master unit (the rectifier with the highest
output voltage). The other rectifiers are forced to adjust their output voltage to track the
master and therefore share the load.
Slope Regulation (Output Voltage) allows the user to drop the output voltage of the
rectifier a small amount from no load to full load. This is done at a fixed rate. The slope in
the voltage regulation of the rectifiers helps to allow the user to set the rectifiers to load
share easily and also allows you to tailor the voltage regulation characteristics of different
brands of rectifiers.
Adjustable current limit restricting output current of the rectifier, in either a discharged battery or
overload condition. The rectifier can operate in this condition without damage.
Power limit allows the rectifier to supply greater output current when the output voltage of the
system is low. This reduces battery recharge time and also provides greater overload capabilities
reducing the need for redundant rectifiers.
FIGURE 9 Power Limit (Pathfinder 48V-3kW) - Current Limit (RSM 48/50) Comparison
2. Equalize mode for boost charging (at a higher charging voltage) of batteries when
required. This boost charging eliminates any sulfation on the battery plates resulting in cell
voltage imbalances and poor performance. This is an important feature for vented lead
calcium batteries floated at reduced voltage levels. Typically not required with VRLA
batteries under normal operating conditions.
Automatic high voltage shutdown (HVSD) or over-voltage protection (OVP) to switch the rectifier
off in case of a high output voltage condition, preventing damage to the batteries and load. An
automatic restart feature should be included in the event that a site temporary abnormality surge as a
ground surge resulted in the HVSD.
Soft-start gradually steps each rectifier on-line at power up. This eliminates start-up current surges
associated with many rectifiers. The feeder breaker and feeder size requirements are decreased,
reducing the installation costs of the rectifier.
Adjustable delay start allows staggered start-up of rectifiers reducing stress on the AC generator and
also allows the rectifiers to be started after the site air conditioner compressor (drawing high surge
current) has started.
Alarms provide indication of rectifier failure and should be of “fail safe” design. Local indication plus
remote relay contacts are required.
Remote sensing leads are connected directly from the battery to the rectifiers via a sense fuse
distribution panel located in the supervisory panel. This allows the charger output voltage to be
regulated at the battery improving voltage regulation at the battery. This is important with power
systems that incorporate separate charge and discharge circuits or power systems where there may be
a significant voltage drop in the battery cables. If this feature is not connected, the rectifiers
automatically revert to internal sensing, regulating the rectifier output voltage to the rectifier output
terminals.
Remote Control and Monitoring allows the rectifiers to be remotely controlled and monitored from a
central supervisory and control panel.
Paralleling Diode (optional) prevents disruption of DC system output power in the event of a
rectifier internal fault in systems without batteries. A blocking diode prevents current from flowing
back into a failed rectifier from parallel rectifiers in some circumstances. It is not usually needed as
energy stored in the system battery or parallel rectifiers will clear the rectifier output fuse or circuit
breaker.
The transistor switching circuit chops the raw supply into nominally 525VP-P, 100 kHz rectangular
waveform with a nominal 66% duty cycle. This waveform is fed into a ferrite power transformer, which
steps down and isolates the high frequency switching waveform. A rectifier circuit converts the power
transformer output to a DC pulse train of nominally 136 V peak. A two-stage output filter averages and
smoothes this pulse train down to provide the nominal 52 VDC output with low noise.
A voltage error amplifier circuit senses the output voltage and compares it with the voltage reference to
provide a voltage error signal. Similarly, a current error amplifier senses the output current using a shunt
resistor and scaling amplifier to compare the output current to the desired maximum output current to
provide a current error signal.
These signals are fed into the pulse width modulator (PWM) via OR-ing circuitry so that either voltage or
current regulation is achieved. The pulse width modulator controls the "ON" time of the switching
transistors to vary the output as commanded by the error amplifiers. It also senses the switching transistor
current on an instantaneous basis to provide cycle-by-cycle protection of the switching transistors. An
auxiliary supply, powered via a small 50/60 Hz transformer, and a DC/DC converter power the control
circuit and front panel circuitry. The PWM receives the ON/OFF command and clock signal from the
front panel circuit and control circuitry.
1.3 Battery
1.3.1 Description
The battery is an electro-chemical means of energy storage. When AC power is interrupted to the
rectifiers or when there is insufficient current available from the rectifiers to support the load
requirements, the battery will automatically supply current to the load. The battery may be used in
combination with a generator to provide back-up power for extended time periods to the load. A battery
consists of a series connection of multiple cells. The number of cells in series is determined by the
operating voltage of the system and the operating voltage of each cell.
1.3.2 Connection
The battery is connected in parallel with the rectifier and the load.
1.3.3 Operation
As detailed in the rectifier operation section.
Float charge the battery at the voltage recommended by the battery manufacturer (temperature
dependent).
Some batteries may require periodic equalization. Equalization is where a higher boost voltage is applied
to the battery to ensure the proper cell voltage balance and correct conditioning of the battery cells.
End voltage (the lowest voltage that the cell is discharged down to). The end voltage used in
calculations is usually the minimum voltage that the battery can be discharged down to without
damage. A more conservative end voltage will increase the life expectancy of the battery but reduce
back up time.
Refer to IEEE battery sizing guidelines for calculating battery size for complex load profiles
Evaluate battery charge rate for sizing intercell and inter-tier connectors
2. Apply temperature performance correction factor for average temperatures below 25 deg. C,
(77 deg. F), if applicable (See: Table F).
3. Ensure that the battery operating voltage coincides with the acceptable operating voltage window
for the equipment connected.
4. Apply the beginning and end of life de-rating factor. This factor is 20% and allows for:
The battery shipped at less than 100% capacity, typically 90% (Full capacity is achieved
after a short period of float service).
5. Battery capacity is determined by the number & size of the plates, therefore the larger the battery
the greater the capacity.
6. Battery strings may be connected in parallel to obtain additional capacity. Strings should be equal
in capacity and interconnecting cables should be of approx. the same size and length to obtain
optimum charge and discharge characteristics. The maximum recommended number of parallel
strings is three.
7. Smaller applications commonly use mono-block batteries. Mono blocks are batteries that have
more than one cell contained in the assembly (i.e. an automotive battery is a 6 cell 12 VDC mono-
bloc).
IEEE-485-199- IEEE recommended practice for sizing large lead-acid batteries for stationary
applications.
IEEE-1184 IEEE guide for the selection and sizing of batteries for uninterruptible power
systems.
IEEE-1689 IEEE guide for the selection of valve-regulated lead-acid (VRLA) batteries for
stationary applications.
EA-5 230 4.6 11.1 18.8 26.6 44.0 49.9 59 75 87 102 152 197 290 530
EA-7 270 4.8 12.9 23.7 33.3 49.0 58.5 73 98 120 154 226 291 426 790
EA-9 350 6.4 17.2 31.6 44.4 65.3 78.0 97 131 160 205 298 380 548 1010
EA-11 440 8.0 21.5 39.5 55.5 81.7 97.5 122 164 199 257 367 465 685 1270
EA-13 530 9.6 25.8 47.4 66.6 98.0 117 146 197 239 308 435 558 792 1460
EA-15 620 11.2 30.1 55.3 77.7 114 137 171 229 279 359 507 651 924 1700
EA-17 710 12.8 34.4 63.2 88.8 131 156 195 262 319 411 571 728 1010 1870
EA-19 800 14.4 38.7 71.1 99.9 147 176 219 295 359 462 634 801 1100 2030
EA-21 890 16.0 43.0 79.0 111 163 195 244 328 399 513 694 870 1190 2200
*Rates shown depict average values and are subject to IEEE-485
End
Point 5 15 30 60 2 3 4 5 6 7 8 10 12 20 24 48 72 100
Volts min. min. min. min. hr. hr. hr. hr. hr. hr. hr. hr. hr. hr. hr. hr. hr. hr.
per
Cell
1.75 274 162 105 61.5 34.8 25.0 19.6 16.2 14.0 12.3 11.0 9.08 7.79 5.00 4.19 2.13 1.43 1.04
1.80 240 151 99.0 60.1 34.0 24.2 19.0 15.8 13.6 11.9 10.7 8.80 7.58 4.89 4.10 2.10 1.42 1.03
1.85 203 136 92.0 55.0 31.4 22.8 18.0 15.0 12.9 11.3 10.1 8.44 7.23 4.67 3.92 2.02 1.37 0.99
1.90 156 110 75.0 47.0 28.9 21.0 16.8 14.0 12.0 10.6 9.50 7.90 6.73 4.34 3.65 1.88 1.26 0.91
Cell size
Electrolyte ºC Temperature ºF
correction factor
-3.9 25 1.520
-1.1 30 1.430
1.7 35 1.350
4.4 40 1.300
7.2 45 1.250
10.0 50 1.190
12.8 55 1.150
15.6 60 1.110
18.3 65 1.080
18.9 66 1.072
19.4 67 1.064
20.0 68 1.056
20.6 69 1.048
21.1 70 1.040
21.7 71 1.034
22.2 72 1.029
22.8 73 1.023
23.4 74 1.017
23.9 75 1.011
24.5 76 1.006
25.0 77 1.000
25.6 78 0.994
26.1 79 0.987
26.7 80 0.980
27.2 81 0.976
27.8 82 0.972
28.3 83 0.968
28.9 84 0.964
29.4 85 0.960
30.0 86 0.956
30.6 87 0.952
31.1 88 0.948
31.6 89 0.944
32.2 90 0.940
35.0 95 0.930
37.8 100 0.910
40.6 105 0.890
43.3 110 0.880
46.1 115 0.870
48.9 120 0.860
51.7 125 0.850
TABLE F Temperature Performance Correction Factor Table
Cycling requirement - different cell plate alloys and plate configuration affect the cycling (charge and
discharge) performance of the battery. Determine the cycling requirement of your application (i.e.
float with light cycling, float with heavy cycling and full cycle service) and choose the correct battery
for the application.
Rate of discharge:
Maintenance requirements.
VRLA batteries of both AGM and “gel” type are usually the first choice for backup. Some of the
important features to look for in a VRLA battery are:
Jar material with low water vapor diffusion rate i.e. polypropylene or PVC to prevent dry
out.
Even compression of plates through a fixed method of jar compression to maintain, plate
to microporous separator integrity (AGM).
Packaging – the battery may be packaged on a traditional battery stand or be of bolt together self
supporting construction. For smaller battery strings the use of relay rack shelves or cabinets is a
consideration. There are also AGM batteries available from the manufactures prepackaged for easy
installation into a relay rack.
1.4 Distribution
1.4.1 Description
Fuses and circuit breakers are used to safely distribute the DC power from the rectifier and battery to the
loads. These devices protect the loads and load cables from short circuits, overload conditions and allow
easy manual shutoff . This helps to isolate faults between circuits. Circuit breakers and fuses are also used
for protecting the battery and battery cables and to allow an easy means of disconnecting the battery from
the system for safety, fire prevention and maintenance.
1.4.2 Connection
Primary Distribution
Load fuses or circuit breakers located at the power system are connected in series between the power
system and the loads and/or between the power system and the battery.
Secondary Distribution
Large main fuses are installed in the power system to distribute dc power to remote BDFB’s (Battery
Distribution Fuse Board’s) or BDCBB’s (Battery Distribution Circuit Breaker Boards). From the BDFB
power is distributed to the loads with smaller individual circuit breakers.
1.4.3 Operation
Fuse
Excessive current flowing through the fuse melts the internal link, disconnecting the load from the power
system. A guard fuse is connected in parallel with the main fuse and will blow when the main fuse blows.
The guard fuse provides a local indication and also will send an external alarm signal via a built-in contact.
Circuit Breaker
Excessive current flowing through the circuit breaker causes excessive heat (thermal) or an excessive
magnetic field (magnetic) to trip the circuit breaker to the off position. Alarm sending is via breaker
auxiliary contacts or electronic trip detection circuitry.
Breaker OFF with no load voltage on breaker output is high (due to bypass resistor) no alarm.
Breaker OFF with load voltage on breaker output is low (due to load forcing voltage down to zero V)
alarm is indicated.
Voltage will be measured on the output of a circuit breaker even when the breaker is off,
however current flow is limited to a few mA due to the 10,000 ohm resistor.
Sizing
Most communication equipment requires fuses or circuit breakers with short delay curves “fast blow” to
provide proper protection Fuses with different curves may be utilized to match specific load requirements.
Load fuses and circuit breakers should be sized 1.25 to 1.5 times the maximum continuous anticipated
load on the circuit for reliable operation.
Battery fuse/circuit breaker should be sized at 1.25 times the maximum current rating of all the rectifiers
in the system (minimum).
Ensure that the current capacity of the circuit breaker panels is not exceeded by the current draw of the
connected loads.
The interrupting capacity (highest fault current that the device is rated to safely interrupt) of the protection
device should match the application. Battery protection devices require higher interrupting capacity due to
the high short circuit current capability of a battery and the large cables (low impedance).
Combination – various types of fuses and circuit breakers can be combined in different panels to
meet load requirements.
Current monitoring via series shunts to ensure circuits are not overloaded or power consumption
monitoring for billing purposes.
Battery protection
EPO - Emergency Power Off control capability using contactor or shunt trip breaker for
locations that require a mandatory emergency power shutdown to meet local fire codes.
Manual battery disconnection - Single string disconnection for maintenance and fault
isolation.
Fuse blocks:
Type Rating-Range (block size)
GMT 0-15A
70 Type 1/2A used for indicating purposes
BAF 0-30A
Cartridge 0-30A, 31-60A, 61-100A, 101-200A
TPL 61-800A
Breakers:
Manufacturer Type Rating Interrupting Capacity Usage
Heinemann AM 5 - 100 A 5 or 10kA Load or battery
Heinemann CD 5 - 100 A 10,000A Load or battery
Heinemann GJ 100-700 A 25,000A Load or battery
1.5.2 Connection
The ground lead of all DC load inputs, batteries and rectifiers should be connected to this point. This bus
must also be connected to the site ground grid (see grounding network section).
1.5.3 Sizing
Ground bars are sized according to load requirements.
1.5.4 Features
Allowances for termination of two-hole lugs of various sizes should be provided.
Ground bars must be isolated from the relay rack through glastic insulators so that the power
system can be integrated correctly into the site single point ground network.
1.6.2 Connection
Various connections are made to the supervisory panel from different components so that different
parameters and levels may be monitored and controlled.
Shunts can be installed in the grounded or live load, battery or system conductor. See Figure 14.
1.6.3 Operation
The battery (charge) and load (discharge) voltage is monitored with a direct connection of the sense leads
to the source; battery or load.
The battery (charge) and load (discharge) current is monitored with an external shunt. Shunts are
calibrated low resistance resistors designed to provide a specific voltage drop at a specific current (linear
relationship). This voltage drop is measured by the ammeter. A typical shunt rating would be 200A,
50mV. Therefore 200 amps of current flowing through this shunt will cause a voltage drop of 50mV.
Calculated values may also be displayed such as total rectifier output current (numerical addition of
individual rectifier output currents). In systems where there is no battery shunt an estimation of battery
current can be calculated by subtracting the discharge current from the rectifier total output current.
Events such as distribution fuse alarm, battery fuse alarm, rectifier failure, converter failure, etc. are
monitored by the supervisory panels.
Alarms are based on an analog or digital event. Each alarm has a two to five second delay before
extending an alarm. The delay eliminates false triggering due to line transients or false alarms. Analog
alarms usually incorporate a hysteresis into the trigger level to prevent oscillation of an alarm condition
caused by a level fluctuating around the set point. Alarm functions provide both local (visual and audible
(optional)) and remote (relay contact) indicators.
Relay contacts may be configured as form “A” (NO), form “B” (NC), or form ”C” (NO & NC).
Control functions are extended from the supervisory panel to control various other power system
components.
Microprocessor based supervisory panels have direct communications with rectifiers for monitoring and
single point control. Communications is via RS-485 connection.
1.6.4 Sizing
Shunts are sized according to load requirements and limit the initial capacity of the power system. Current
flowing through a shunt must not exceed 80% of its nominal rating on a continuous basis.
Controls
Control features are used to control power system devices such as rectifiers and contactors.
Manual equalize - Allows the user to initiate all the rectifiers into the equalize mode with one
common switch. Used for maintenance purposes with VRLA batteries, i.e. equalizing cell voltages in a
battery string.
Auto-equalize - Common in applications where flooded batteries are deployed. This function initiates
the rectifiers into the equalize mode (boost charge) for a preprogrammed amount of time (duration).
It is used with vented batteries floated at low voltages to prevent lead plate sulfation or where a
quicker recharge of the battery is required after a power failure. Auto-equalize is initiated in one of
three ways:
2. periodic equalize; where the batteries are equalized at the interval programmed in days.
3. manual initiation using the duration setting to return the rectifiers to float after the
duration has expired.
HVSD/OVP - automatically shuts down all the rectifiers when an output DC over-voltage condition is
detected.
LVD - controls 1 or more contactors that automatically open when a low battery voltage condition is
detected and close when the battery voltage returns to normal. See LVD section.
Battery temperature compensation is used to adjust the rectifier output voltage to ensure that the
battery float voltage is correct for the operating temperature of the battery. See battery temperature
compensation section.
Charge current control is used to limit the flow of current into the battery when recharging
commences after a power failure. It is programmed typically at C/5 (capacity of the battery/5). This
ensures that the battery is not charged too quickly, resulting in excess heat generation and possible
reduction in battery life. This can be very important for VRLA type batteries.
Battery diagnostics
Battery run time prediction - the algorithm predicts the number of hours that the
battery will last, before the battery will be fully discharged or a LVD will occur, at the
present discharge rate.
Rectifier group single point adjustment - allows the operator to setup and adjust all the rectifiers at
one central location.
Test - Combined with an external power supply, allows the user to test and calibrate the power
system while in service (SD series only).
ALCO (Alarm Cutoff) - Is provided to clear the relay contacts and audible alarm associated with each
alarm condition this allows extended alarms to be canceled while alarm condition is being resolved by
local personnel.
2. Prevention of damage to the battery due to over-discharge. Discharging a battery below the
lowest recommended end voltage (see battery section) might permanently damage the battery.
1.7.2 Connection
The low voltage disconnect can be connected in series with the load (load disconnect) or in series with the
battery (battery disconnect).
1.7.3 Operation
The supervisory panel continuously monitors system voltage.
After an extended AC outage the batteries will discharge down to the disconnect point. The disconnect
point is typically set to the lowest acceptable battery discharge voltage (end voltage). In a Telecom
application the end voltage typically used is 1.75 volts per cell (21 VDC in a 24 VDC system and 42 VDC
in a 48 VDC system). When the disconnect point is reached the load or battery will be disconnected from
the system.
The load or battery will remain disconnected until AC outage is over. On return of AC a load disconnect
and a battery disconnect system function differently (see below).
Load disconnect The rectifiers will pre-charge the batteries for a few minutes until the battery voltage
reaches the reconnect point (typically 25 VDC or 50 VDC). When the reconnect point is reached, the
load is connected on line at this voltage level.
Battery disconnect Immediately after the reapplication of AC, the load will see a slowly increasing
DC voltage (0-50 VDC over an 8-10 second period, due to the soft start feature in the rectifier). At
the 50 VDC point the battery will be connected on line.
A wide voltage differential between the in and out settings (i.e. out 42V, in 50 V in a 48V system) prevents
the contactor from oscillation because the battery voltage will naturally rise after the load has been
removed from it and reconnection without the rectifiers on-line would not be desirable.
Load vs. battery disconnect. - In some cases battery, instead of load, disconnection is desirable. The
advantage of this system is that an accidental operation of the LVD will not disrupt power to the load
unless the AC is also off. The disadvantage of the battery disconnect that the load will see a slowly
increasing input voltage 0-50V as the rectifiers perform the soft start this may cause damage to the load or
inadvertent fuse or circuit breaker tripping. Careful evaluation of the load specifications is required to
verify that this method of disconnection will not affect the load.
1.7.4 Sizing
Low voltage disconnect contactors are available in various sizes. The rating of the LVD indicates its
maximum current carrying/switching ability.
CEMF cells are rarely used in modern telecommunications systems as they introduce step voltage changes
to the load voltage when switched in or out that may affect load operation. It also introduces another
single point of failure.
It was historically used with both step by step and crossbar telephone switching offices.
A common alternative to the CEMF cell is to remove one battery cell from the string and lower the
rectifier output voltage to reduce the operating voltage of the system; for example: 23 cell system with
VRLA batteries 23 x 2.25 V per cell = 51.75V.
1.8.2 Connection
The CEMF cell is connected in series with the load.
1.8.3 Operation
The supervisory panel continuously monitors system voltage.
1. CEMF cell normally IN to reduce load voltage in the float and equalize mode. The normal
system float voltage is above the IN setting of the CEMF cell the CEMF contactor is opened
so that current flow is through the CEMF diodes and the load voltage is reduced. When a
power failure occurs and the voltage drops the contactor is closed to increase the voltage at
the load to ensure maximum back up time. When power is restored the contactor will open
when the voltage returns to normal diverting current through the diodes and reducing the
load voltage.
2. CEMF cell normally OUT to reduce load voltage in the equalize mode only. In this system the
IN setting of the CEMF is set higher than the float voltage and the contactor normally
bypasses the diodes. When equalize mode is selected the voltage rises above the IN setting
and the contactor is opened, current flows through the diodes and the voltage at the load is
reduced. When the rectifiers are returned to float mode the voltage drops below the out
setting and the diodes are again bypassed by the contactor and the load voltage returned to
normal.
1.8.4 Sizing
Voltage drop required.
1.8.5 Features
Monitoring of cell status.
VRLA batteries have a negative characteristic called “thermal runaway”. This occurs when the internal
temperature of the battery rises due to overcharge, high ambient temperature or internal fault. The rise in
internal ambient temperature causes the battery to draw more float current which in turn elevates the
internal battery temperature. This cycle continues until the battery fails. The failure of the battery may be
quite dramatic.
1.9.2 Description
Temperature compensation is the process of automatically reducing the charge voltage applied to the
battery at high temperature (to increase life and prevent thermal runaway) and increasing the voltage
applied to the battery at low temperatures (to increase the battery capacity and to ensure correct charging
of the battery).
1.9.3 Connection
Connection is as follows:
1. Traditional rectifiers with non-SM supervisory panels use a temperature compensator module
(TCM) connected in series with the rectifier remote sense line input and the battery that
requires temperature compensation.
2. Smaller rectifier systems (i.e. RSM 48/7.5 and 48/10) have this feature built in; there are no
additional sense/battery connections required.
Temperature probes (1-4) are mounted directly to either the same battery negative termination post or to
multiple negative posts to monitor multiple battery strings.
1.9.4 Operation
Operation is as follows:
1. Non-SM based systems, the TCM adjusts the output sense voltage to the rectifiers based on
ambient temperature detected at the battery. The rectifiers will adjust their output voltage
according to the sense voltage level detected at their remote sense input. (See Table H & I).
2. Small systems adjust the rectifier output voltage based on ambient temperature detected at the
battery. (See Table H & I).
3. SM based systems, the SM will automatically adjust the rectifier float voltage based on the
battery temperature detected. It will repeat this process at the interval programmed. The
rectifier RS 485 communications link is used for this purpose.
At temperatures below 25 deg. C, the rectifier will increase its output at a fixed rate(ex. -2.5 mV per cell
per deg. C change from 25 deg C reference).
At temperatures above 25 deg. C, the rectifier will decrease its output at a fixed rate(ex. -2.5 mV per cell
per deg. C change from 25 deg C reference).
To prevent excessive voltage from damaging the load, the battery or causing a high voltage alarm
condition; the battery voltage maximum compensation may be limited (lower break point) at a fixed
temperature (ex. 0 deg C).
To prevent excessively low voltage from undercharging the battery or discharging the battery; the battery
voltage maximum compensation may be limited (upper break point) at a fixed temperature (ex. 50 deg C).
1.9.5 Sizing
Temperature Compensation Slope
Match the compensation slope to the recommendations of the battery manufacturer. Default to
conservative 2.5 or 3.5 mV if this information is unavailable.
Breakpoint
The selection of the breakpoint is critical. This determines the maximum and minimum voltage that will
be applied to the battery and the load. Match the breakpoints to the recommendations of the battery
manufacture. Carefully select the lower breakpoint as this determines the maximum voltage applied to the
load.
Check load acceptable input voltage operating window; for example: a 4.5 mV slope with a -
40 deg C breakpoint in a 48V system will result in 61 volts applied to the load in a low
temperature condition.
TCM Internal
This feature is available built into Argus non-sense line equipped rectifiers, including RSM 48/7.5, RSM
24/15 and RSM 48/10.
SM System Controllers
Control larger RSM rectifiers and pathfinder rectifiers through the communications link.
These tables are provided as a guideline only. If battery temperature falls between values on
the above scale, estimate the voltage setting based on the closest numerical values.
These tables are provided as a guideline only. If battery temperature falls between values on
the above scale, estimate the voltage setting based on the closest numerical values.
A converter system consists of single or multiple parallel DC-DC converters and may incorporate many
of the features found in the main DC power system including distribution, common ground bus and
supervisory.
DC-DC Converters should have dedicated fuse/circuit breaker positions on the main DC power system
for protection and isolation.
If converters are located in the same relay rack as the main DC power system, direct
connection to the busswork on the input is permissible.
1.10.3 Operation
Since the converter system does not have a battery connected to its output adjustment of the output
voltage is less critical and LVD’s, temp comp, etc. are not required. The output voltage of the converters
is adjusted to match the requirements of the load and to ensure correct load sharing between parallel
converters.
1.10.4 Sizing
The converter system should be sized to adequately supply the load under all conditions.
There should be substantial converter redundancy built in to the converter system to account for fuse
clearing and circuit breaker tripping. If this redundancy is not built in, the converters may not be able to
clear a fault and current limiting will take effect and the output of the converter system may be affected.
Always use fast acting fuses in converter system distribution circuits and do not use excessively high fuse
ratings.
DC - DC converter systems can add substantial load to the main power system, allowances should be
made for this when sizing the main system.
Modular vs. monolithic configuration. Modular converters allow for easy replacement and expansion.
Supervisory and distribution may be incorporated into a modular converter system.
Physical constraints in most new facilities demand compact designs. Lightweight converters combined
with space saving designs help reduce installation and shipping costs.
Balanced load sharing should be achieved between converters. Argus converters accomplish this
with output slope regulation it is adjustable on CS units to allow load sharing with other types of
converters. CSM units utilize a fixed slope set at 1%.
Current limiting should be provided, Argus units are factory set at 105% of rated output, to provide
protection in a overload condition.
High voltage shutdown to switch converter off in case of high output voltage condition, preventing
damage to the load.
Soft-start to gradually bring the converter on line from zero load to the load requirement, eliminating
high inrush currents surges. The feeder breaker and feeder size requirements are decreased, reducing
the installation costs of the converter.
Alarms provide indication of converter failure and should be of “fail safe” design. Local indication
plus remote contacts are required.
CS Series Monolithic
Traditional converter packaging - each individual converter is a stand-alone unit.
1.11.2 Connection
Intersystem
In a typical power system there should be provisions for easy termination of intersystem cables.
Buswork should be copper; cables should meet electrical code requirements and utilize quality
compression lugs.
Lock washers or “Belleville” washers should be used on electrical/mechanical connections to ensure
integrity under different temperature conditions, (high/low load). All termination’s should have provisions
for connection of standard 2 hole lugs (typically 3/8” hole, 1” spacing).
Argus power systems include all these features and utilize tin-plated copper buswork to eliminate
oxidization.
The intersystem wiring and buswork determines the ultimate capacity of the power system.
The vertical discharge riser bus is used to connect the distribution panels to the charge/discharge
termination in a traditional power system.
Battery
Separate charge/discharge configuration - This method of connecting the battery was utilized in the
past to reduce the rectifier ripple voltage at the load. The vented battery was used as a filter. With the
advent of low ripple rectifiers this method of battery termination is generally not required.
Two busses are provided for both negative and positive termination. Rectifier negative output
cables are terminated to one bus (- charge bus) and a cable is run to the neg. battery terminal from
this bus. A second cable is connected from the negative battery terminal back to the second bus (-
discharge bus) and the neg. load feed is also connected to this bus. This is repeated for the
positive side also. This method has the added benefit of better load regulation and a slightly
reduced voltage level seen at the load.
Common charge/discharge configuration - This is the current standard method of terminating the
battery cables. One bus is provided for the negative connections and one for the positive connections.
Rectifier output cables, battery cables and the load feed are connected directly to these bus’.
1.11.3 Sizing
Power systems should be oversized by a factor of 20-25 %. To calculate the power system size multiple
the maximum anticipated load by a factor of 1.2 - 1.25. This over-sizing factor will ensure that the shunt is
not overloaded and that adequate capacity is available in the buswork and cables to accommodate both
the load and battery recharge current.
Up to 10 000 amps.
All maintenance and circuit termination may be performed from the front.
Up to 1200 amps.
There would be obvious limitations for either of these methods, but they do provide solutions for
specific applications and ensure flexibility of Argus equipment.
These fully self contained power systems (except for battery), may be configured in various packages
combining up to five rectifiers modules, distribution, supervisory, temperature compensation and low
voltage disconnect. Packages are 17” wide, 12 “ deep and 5.25” high.
RSM 48/7.5 AND 24/15
These fully self contained power systems (except for battery), may be configured in various packages
combining two or three rectifiers modules, distribution, supervisory, temperature compensation and
low voltage disconnect. Packages are 17” wide, 12 “ deep and of various heights from 3.5” to 7”.
US SERIES
Combine battery, rectifier and supervisory in a single package to provide either 5 Amps at 48V or 8
Amps at 24V backup time is approx. 2 hr. with internal battery. Extra extended backup battery
cabinets may be added.
1.12 Inverters/UPS
1.12.1 Description
The inverter or Uninterruptable Power System (UPS) is utilized to supply AC voltage to loads such as
computers in the Telecom environment. These systems are often connected to the DC power system.
There are a various options for providing uninterruptable AC for your loads including:
1. On-line Inverter - DC input, AC output. Connected directly to DC main power system. Has a
standby AC line available (optional).
2. Off-line Inverter - AC input, AC output. Has a standby DC line connection available. The
DC standby line is connected to the DC power system.
3. Double conversion UPS - Dedicated rectifier, battery and inverter, Traditional concept.
4. Line Interactive UPS - Ferroresonant transformer with small battery charger, battery, inverter
and intelligent control. Normal operation is through a Ferro circuit. Ferro provides filtering
and some energy storage. Inverter is switched on-line when required by the control. Battery
charger charges the batteries only.
Both inverter system designs (type 1 &2) will be discussed in this section since they connect to and affect
the operation and design of a DC power system.
1.12.2 Connection
On-line inverter- The inverter is connected in series with the DC power system and the connected loads.
A connection is made to a standby AC source for redundancy.
Off-line inverter- The inverter is connected in series with the AC source and the connected loads. A
connection is made to the DC power system for redundancy.
1.12.3 Operation
On-line inverter - In normal operation the inverter draws current from the DC power system and coverts
this to AC to power the connected load. If the inverter fails or the DC supply is interrupted there inverter
automatically transfers to a connected AC stand-by source.
Off-line inverter - In normal operation the connected load is powered from the AC source through the
inverter. Upon loss of the AC source the load is transferred to the inverter. There may be a ferroresonant
circuit to provide energy storage while the load is transferred to the inverter.
1.12.4 Sizing
Inverters/UPS should be sized such that the continuous load (VA) does not exceed 75% of the inverter
rating (VA).
Inverters often supply computers that incorporate switch mode power supplies and other non-linear
loads. If loads with high crest factors (i.e. > 2.5) are connected, the UPS rating may have to be de-rated.
See the manufacturer for further information.
Neutral current should also be monitored after UPS installation to ensure it is within the limits of the
conductor. Unbalanced loads and low power factor often generate substantial neutral currents. It is
possible for these currents to overload the neutral conductor since there is no protection for the neutral
conductor.
If the on-line inverter is utilized both the DC power system battery and the rectifiers will have to be
oversized to supply the additional load imposed by the inverter.
If the off-line inverter is utilized only the DC power system battery need be oversized since the inverter is
normally operating from the AC source and will only draw current from the DC power system when
there is a failure of the AC source.
Inverters may also draw substantial inrush current on start-up; breaker/ fuse curve coordination may be
required.
2.1 Calculations
2.1.1 Step 1 System Load Analysis
To determine your DC power system requirements evaluate your loads and the backup period required.
(B) Loads that require battery backup. Don’t forget AC loads i.e. computers that require backup.
Determine the individual load currents for the different load voltages required. The voltage with the
highest load is generally chosen as the main system voltage.
Warning: Check and record the polarity requirement of your connected loads. “Which
polarity is connected to the common ground”? This is vital information to ensure
functionality of the DC system and load.
Determine the total load that the converters will have on the main DC system. Use formula (i).
Determine the load that the inverter will have on the main DC system. Use formula (ii).
Determine the quantity and type of rectifiers required to meet the requirements of the total
rectifier capacity.
Discharge hours
Total system load
End voltage
Temperature performance
Size load and battery fuses and circuit breakers as per fuse/CB sizing section.
2.2 Formulas
2.2.1 Power System Design Formulas
Formula (i) Converter Load (Amps)
= secondary load (amps) x (output voltage/input voltage)
converter efficiency
If an off-line inverter is connected to the DC power system its load must be subtracted from
the total system load (1) when calculating total rectifier capacity.
Recharge factor is the recharge efficiency factor for the battery string. Typically 1.1 -1.2 for
lead acid batteries.
Environmental constraints including temperature, humidity, rain protection, dust, dirt, etc.; i.e.
don’t order a fan-cooled unit to be used in an extremely dusty environment.
Access for maintenance, future distribution connection and most importantly airflow. Each
rectifier or converter generates heat and the minimum ventilation requirements must be met for
reliable operation.
Custom engineering drawings are available from Argus to assist in the installation of system
components.
The battery should be located in a temperature-controlled environment also. The temperature should be
regulated at approx. 25 °C (77 °F). Significantly lower temperatures reduce performance and higher
temperatures decrease life expectancy. Provide adequate ventilation for the battery.
VRLA batteries, though not requiring the special ventilation requirements of a flooded
battery, should not be installed in an airtight enclosure. Hydrogen gas may be vented in a
fault condition; i.e. failed battery.
An arrangement of “I” beams may have to be bolted to the concrete floor and extend above the
computer floor to provide a strong platform.
Concrete Floor
The thickness of the concrete should be evaluated to ensure that its weight carrying capabilities meet the
requirements.
Steel plates may have to be installed on top of the concrete to reduce the point loading problems common
with the base configuration with most VRLA batteries.
Wood Floor
Steel plates
Concrete pads.
Check the placement of the floor trusses so that the weight is evenly distributed over as
many floor trusses as possible.
The site grounding system provides a low impedance path to ground for noise, lightning (high frequency),
transients and surges. It also provides a common ground reference point for all equipment.
3.2.2 Connection
The North American standard for the grounding network of a communications installation dictates that a
single point ground (SPG) philosophy is used See Figure 16.
The first stage of the grounding system is the ground grid that usually consists of multiple driven ground
rods interconnected in a ring configuration encircling the building to be protected. Metallic objects such as
towers or lightning arrestor’s are connected into this ground grid.
The second stage of the grounding network is the master ground bus (MGB). The connection sequence at
the MGB is important. Surge producers (AC ground bond, frame ground bonds, metallic ground bonds,
etc.) are separated from protected equipment (power system battery return reference) by the surge arrestor
(connection to the ground grid.
The third stage of the grounding network is the battery return bus (BRB) on the power system. This is
where all the load ground connections are made. Typical communication systems also use this as the
reference point for logic ground reference.
Frame grounding is also very important for both safety and also to ensure proper operation of the rectifier
surge divertor metal oxide varistors (MOV). Industry standard is a cable connection from each relay rack
to the MGB.
3.2.3 Sizing
The cable from the BRB to the MGB should be sized to provide sufficient ampacity to clear the largest
fuse or breaker on the power system, excluding the battery protection fuse or circuit breaker. This is the
minimum requirement, other factors including length of cable and special grounding requirements of the
load should also be factored in. The intention is to provide the lowest impedance path to ground for high
frequency (lightning) transients see Table K.
The connection between power system frame and the MGB should be #6 AWG (16 mm)
minimum.
For protecting sensitive telecom facilities less than one ohm is desirable.
Stage one - This first stage of surge protection provides increased protection for the power system
rectifiers and other equipment in locations where lightning is prevalent. This stage is critical in high
lightning activity areas to prevent damage to the rectifiers.
Stage two - This optional level of protection provides increased protection over a level one and three
combination. It is also useful in locations where there are large surges and transients generated within the
site.
Stage three - This stage provides basic protection for each rectifier.
3.3.2 Connection
Stage one - This first stage of the surge protection for any site is located at the AC service entrance,
usually connected either to the AC distribution service panel or directly to the main building disconnect
switch.
Stage two - This optional level of protection can be located at the DC power system rack. This will
provide increased levels of protection for the rectifiers.
Stage three - This stage is built into the rectifiers. Short lead lengths are critical to keep let through
voltage low.
3.3.3 Operation
Various types of protection devices are available. The most common technology used is a either silicon
avalanche diode (SAD), metal oxide varistor (MOV) or a combination of both. These devices function as
non-linear resistors.
At voltages below their operating voltage they operate in the high impedance mode.
At voltages above the operating voltage they operate in the low impedance mode.
They are connected in parallel with the AC source either line to line or line to ground.
Surges cause these devices to conduct, effectively clamping the surge voltage.
3.3.4 Sizing
Stage one and two - Minimum size should meet the requirements of the ANSI/IEEE C62.41 category
B3/C1 standard. Higher capacities should be used in areas where frequent violent lightning strikes are
common.
Stage three - Minimum size should meet the requirement of the ANSI/IEE C62.41 category B3
standard.
MOV based SPD’s offer reasonable cost and high capacity but are slower to respond and have a higher let
through voltage (up to 1200 volts for a 240 volt rated SPD). MOV’s degrade with each surge absorbed by
the MOV.
3.4 Wiring
The cable chosen for use in power plant applications not only has to meet the requirements of the
electrical code for ventilated cable tray installations, ampacity and cable type. The cable size must also be
carefully selected to ensure minimum voltage drop across its length when fully loaded. Keeping the
voltage drop to a minimum insures maximum back-up time and best performance when the system is
operating on battery.
The information below can be used to calculate the cable size using typical voltage drop recommendations
for Telecom installations. Refer to Table L for more information.
3.4.1 AC Cabling
Individual circuit breakers and circuits are recommended for each rectifier. Use conduit or liquid type
cable matching the cable size to the ampacity of the circuit.
3.4.3 Battery
Battery cables should be sized for a .25 V loop drop from battery to the distribution panel at full load
including anticipated growth. The cables should also meet ampacity requirements of the protection
breaker in the circuit.
3.4.4 Alarms
Recommended cable size is 16-24 Ga.; from the power system supervisory panel to the site alarm
monitor.
3.4.5 Distribution
Refer to guidelines supplied with the load equipment. Typically distribution cables are sized to provide a .5
V loop drop at full load as well as meeting ampacity requirements of the protection fuse or circuit breaker.
3.4.6 BDFB (Battery Distribution Fuse Board) or BDCBB (Battery Distribution Circuit
Breaker Board)
Circuits feeding BDFB’s should be sized for .25 V loop voltage drop at maximum anticipated load (80 %
of the BDFB rating). Cables must also meet the ampacity requirements of the protection fuse or circuit
breaker.
3.5.2 Sizing
Determine the BTU’s generated by the power system and size the air conditioning accordingly.
Notes
Use system maximum output amps to size air conditioning correctly for worst case.
Batteries will radiate 5-10% of the energy used to recharge them and will also contribute
to heat rise.
Initial Installation
T
his is a generic installation guide intended to be applicable for various types of Argus power
systems, including front access and traditional power systems. For battery installation refer to the
manufacturers guidelines for more specific information.
Before working with any live battery or power system the following precautions should be followed:
Removal of all metallic jewelry i.e. watches, rings, eyeglasses, necklaces, etc.
Safety glasses with side shields must be worn at all times.
Metallic tools must be properly insulated. Standard hand tools may be insulated using the
following method: Apply one layer of half lapped rubber splicing tape. Cover the rubber spicing
tape with two half lapped layers of vinyl tape.
Extra care is required when working with flooded battery systems. Protective clothing, eye protection and
standard battery safety kits (as detailed on the next page) should be provided for installation personnel to
deal with accidental spillage of acid. Avoid short circuits and arcing, which could cause explosion of any
gases vented from the batteries. Follow battery manufactures safety recommendations when working
around battery systems.
Warning: Do not smoke or present an open flame when batteries (especially vented
batteries) are on charge. Batteries vent hydrogen gas when on charge which creates an
explosion hazard.
Installer should follow all applicable local rules and regulations for electrical and battery installations; i.e.
CSA, UL, CEC.
Batteries are hazardous to the environment and should be disposed of safely at a recycling facility. Consult
the battery manufacturer for recommended local authorized recyclers.
4.3 Inspection
All Argus products are shipped in rugged, double walled boxes and suspended via solid polyurethane
foam inserts to minimize shock that may occur during transportation. Packaging assemblies and methods
are tested to National Safe Transit Association standards.
Power systems are custom packaged in heavy-duty plywood crates with an equipment inspection window.
Power systems are also wrapped with a plastic sheet that is impregnated with CORTEX a corrosion
inhibitor.
Batteries are shipped on individual pallets and are packaged as per the manufacturer's guidelines.
Prior to unpacking the batteries, power system or components, note any damage to the shipping
container. Unpack the equipment and inspect the exterior for damage. If any damage is observed contact
the carrier immediately.
Continue the inspection for any internal damage. In the unlikely event of internal damage please inform
the carrier and contact Argus Technologies for advice on the impact of any damage.
Secure the power system to the floor utilizing either heavy duty concrete anchors 1/2” X 2 1/2” or for
wooden floors, heavy duty screw type lags 5/8” X 2 1/2” and appropriate flat washers.
It is recommended that the Relay Rack be secured to the overhead cable tray utilizing the brackets
mounted on either side of the top of the relay rack. Mechanical details necessary for overhead support are
not provided by Argus.
VRLA batteries, though not requiring the special ventilation requirements of a flooded
battery, should not be installed in an airtight enclosure. Hydrogen gas may be vented in a
fault condition (i.e. failed battery).
Before assembly, clean cells as per the battery manufacturer's recommendations. First neutralize any acid
with a baking soda and water solution. Then wipe the cells with clean water.
Address
Battery Location and/or Number
No of cells ____________ Type ______________ Date New
Date installed _____________ Float Voltage _______ Ambient Temp.
Cell Readings
Readings taken by
4.6 Cabling
4.6.1 AC Cabling
Cable and connect from the AC distribution panel to each rectifier, follow the connection information
detailed in the rectifier manual. With the modular rectifiers it is recommended to pre-cable all rectifier
positions to allow for easy addition of future rectifiers. If connection is to a 3-phase AC service, care
should be taken to balance the load across the phases.
SD Equipped System:
Built in internal sensing. No connections required.
Final connection to battery live should not be made, insulate and leave unconnected.
SM Equipped Systems:
With a SM system the rectifier will regulate its voltage to the charge voltage displayed on
the SM02.
To regulate at the battery the charge input connection to the SM02 should be removed
and the charge input connection should be directly to the battery.
4.6.3 Battery
Battery cables should be sized for a .25 V drop from battery to the distribution panel at full load including
anticipated growth. The cables should also meet ampacity requirements. Cables terminating directly on
battery posts or connection details should be secured so that there is no stress on the battery posts. Lead
plated lugs and lead plated or stainless steel hardware should be used on all terminations with vented
batteries to reduce corrosion.
Cable and connect cables from power system to battery termination details. Terminating points should be
burnished and no-oxide “A” grease applied.
Final connection to battery live should not be made. Insulate and leave disconnected.
4.6.4 Alarms
All applicable alarms should be connected to the local alarm-sending unit from the power system. The
deluxe supervisory panels provide a central point for all external alarm lead connections. The more basic
panels provide for some alarm terminations such as low/high voltage but alarms such as rectifier or
converter fail may have to be connected directly to the rectifier or converter. The type of alarm input
required by the alarm sending unit determines how the alarm contacts are configured and wired; i.e. form
“A”,“B” or “C” wired for ground sending, battery sending, loop closure, loop open, etc. Some
supervisory panels require jumpers to be moved to configure the alarm contacts as form “A” or “B”.
4.6.5 Grounding
The isolated power system battery return bus (BRB) should be connected to the building master ground
bus (MGB) or floor ground bus (FGB) in a larger building. This acts as a system reference and as a low
impedance path to ground for surges, transients, noise, etc. The MGB or FGB should have a direct low
impedance path to the building grounding system; i.e. the water main. The cable from the power system
to the MGB or FGB should be sized to provide sufficient ampacity to clear the largest fuse or breaker on
the power system, excluding the battery protection fuse or circuit breaker; this is the minimum
requirement. Other factors including length of cable and special grounding requirements of the load
should also be factored in. The insulated cable should be equipped with two-hole crimp type lugs and
should not have any tight bends or kinks.
The power system frame must also be connected to the MGB or FGB. This is done for personnel safety
and to meet many telco-grounding requirements. Cable should be #6 AWG (16mm).
4.6.6 Distribution
Refer to guidelines supplied with the load equipment. Typically distribution cables are sized to provide a .5
V loop drop at full load as well as meeting ampacity requirements of the protection fuse or circuit breaker.
Battery warranty may be void if batteries are not initial charged following the manufacture's
guidelines and proper records are kept.
Some VRLA batteries do not require initial charging if placed on charge within 3-6 months of
manufacture, check with the manufacturer. After the equalization period battery voltage should be
reduced to the recommended float level.
Once the batteries have been initial charged it is suggested to perform a short duration-high rate discharge
test on the batteries to verify the connections on the batteries and also to verify that there are no open or
failed cells. Cell voltages should be monitored during this process.
4.9 Documentation
Complete all necessary documentation; i.e. battery reports (Table M), DC wiring lists (Tables N and O), AC
distribution tables (Table P), floor plans, etc. Tag wires, fill out identification strips, and identify circuit
breakers.
A
ll Argus power system components undergo thorough factory testing and all levels/alarms are
set to factory default values, unless custom levels are specified. Good installation practice is to
check the operation of all features and alarms and to set the power system levels as per the
specific requirements of your system. The manuals supplied with the equipment detail the
method to test and calibrate all system components.
Retrofit Installation
This is a retrofit installation guide intended to be applicable for installation of power system components
in “live” standard Argus power systems.
6.1 Precautions
When working on live power systems there are two very important criteria to be considered.
2. System integrity - “No” interruption of DC power can be tolerated during work on a power
system. Every power system upgrade, addition, maintenance procedure can be completed
while working live on a DC power system, without interrupting the load if the proper steps
and precautions are followed.
It is highly recommended that only personnel with DC power experience and training
perform operations on a live power system, including the operations detailed in this guide.
Consult the factory before beginning any operation that you are unsure of.
3. Temporarily wrap all live buswork on the power system with insulating canvas’ while work is
being performed on the power system, use tape or tyraps to secure the canvas’.
4. Crimp lugs on cables, connect and secure cables at the power system and then at the load.
5. Remove canvases.
7. Tag wires with identification tags and identify fuse/circuit breaker positions as required.
3. Secure ground bus to the top of relay rack and ensure that ground bus is fully isolated from
the frame.
4. Decide where the ground bus will be connected to at the power distribution system. The new
ground bus should be connected to the initial power system ground bus with a cable of
sufficient capacity to carry the full anticipated load to be connected to the new ground bus.
5. Temporarily wrap all live busswork on the power system with insulating canvas’ while work is
being performed on the power system, use tape or tie-wraps to secure the canvas.
7. Remove canvas.
6.5.1 Pre-provisioned
1. Temporarily wrap all live buswork on the power system with insulating canvas’ while work is
being performed on the power system, use tape or tie-wraps to secure the canvas.
2. Clean buswork to remove any oxidation of the copper buswork, with 3M scotch pads. Tin
plated buswork does not generally require cleaning before using.
3. Bolt new panel in place and connect to vertical distribution riser bus.
4. Connect fuse fail alarm card into power system.
5. Install protective cover on the rear of the fuse panel if required.
6. Remove insulating canvases.
6.5.2 Non-Pre-provisioned
Procedure is the same as for the pre-provisioned fuse panel addition except the following extra steps will
have to be taken to connect the new fuse panel into the power system. Insulating canvases should be used
to prevent short circuits between live buswork and chassis/load ground.
If there is room to add fuse/circuit breaker below existing panels the vertical distribution riser bus
may be replaced with a longer bus that will extend down to the new fuse/circuit breaker panel as
follows:
1. Using bridging cable(s) (sufficiently sized to carry the load on the existing fuse/circuit
breaker panel, check load with clamp on ammeter), bypass the vertical riser and connect
directly from the power system charge battery (live) bus to the fuse panel distribution bus.
2. Disassemble the vertical riser to fuse panel distribution bus connection and either replace
riser with longer bus or extend riser with additional bus section to the new fuse/circuit
breaker. panel. Clean buswork as required.
3. Tighten connections and remove bridging cable(s).
4. Install protective cover to cover the rear of the fuse panel (if ordered).
If there is no room below existing fuse/circuit breaker panels, the new fuse panel will have to be
cable connected to the existing power system as follows:
1. Locate fuse/circuit breaker panel in position.
2. Run appropriately sized cable (sized to carry max. anticipated load on fuse panel) in place.
3. Connect cable to new fuse/circuit breaker panel termination buswork.
4. Decide where connection will be made on vertical distribution riser on the power system.
5. Mark hole spacing for cable lug on bus and drill hole with isolated drill (use canvas,
plywood, etc. to protect equipment and to prevent short circuits).
6. Bolt cable in place.
7. Remove canvases, wood, etc.
Check and record power system load and verify that system capacity meets the load requirements.
Check and re-torque nuts and bolts securing cable lugs to buswork. Check and re-torque
mechanical lug set screws (if applicable).
Note: Caution should be used when performing field repair on power system supervisory
components. If there is a low voltage disconnect in the power system precautions must be
taken to ensure that the contactor is not accidentally tripped.
1. Assemble bridging cable; size cable to carry the full load on the contactor and check with a
clamp on ammeter.
2. Temporarily insulate adjacent grounded metal work while installing bridging cable across the
contactor.
3. Install bridging cable across LVD contactor, effectively bypassing the contactor.
4. If the power system is equipped with high voltage shutdown or remote sensing for the
rectifiers, remove these leads at the rectifiers. The rectifiers will automatically revert to internal
sensing. This will prevent problems occurring when the supervisory circuit board is being
replaced.
5. Identify wires terminating on the supervisory panel and tag wires to ensure wires are
reinstalled in the correct position.
7. Remove supervisory panel or PCB and install replacement board in position. Remove fuses in
new PC board and reconnect leads in reverse order.
8. Install fuses.
9. Check all PC board functions and set levels (refer to manual for more detailed information).
10. Reconnect high voltage shutdown and remote sensing leads at rectifiers as required.
11. Remove temporary bridging cable across the low voltage disconnect contactor and remove
insulating canvas.
Replace varistor(s) VR1 (VR2 & VR3) if in high lightning/surge activity area (located across input
circuit breaker).
Check and adjust levels; float voltage/equalize voltage at battery, load sharing, etc.
Consider sending unit to factory for full maintenance “tune-up” complete with 100 % unit
performance testing.
2. Disconnect live lead from rectifier at the power system charge bus.
4. Tag leads and remove input, output, alarm and control leads from rectifier and insulate.
6. Reconnect all cables and make the live connection at the battery charge bus last.
7. Power up and test rectifier as per the procedure outlined in the manual.
2. Open front panel, tag leads connected to front panel PC board, insulate and remove.
Disconnect ribbon cable.
5. Power up and fully test rectifier as per the procedures detailed in the manual.
2. Refer to RSM rectifier section for identifying and testing of MOV. Open front panel,
disconnect and remove MOV from load side of the input circuit breaker.
4. Power up and fully test rectifier as per the procedures detailed in the manual.
2. Loosen mounting screws and remove rectifier and install replacement rectifier in the same
position, tighten mounting screws.
3. Power up and test rectifier following the procedure outlined in the manual.
3. Insert module, tighten mounting screws, power up and test following the procedures outlined
in the manual.
3. With rectifier removed from the shelf, remove fan power leads and mounting screws.
5. Install power module, tighten screws, power up and test rectifier following the procedure
outlined in the manual.
3. Remove “warranty void” label and screws securing the front panel to the chassis.
4. Identify MOV’s; located usually on the load side of the input circuit breaker inside the rectifier
cabinet (a small disc approximately the size of an U.S. 5 cent piece).
5. Measure resistance of MOV. A short circuit or low resistance indicates a failed MOV.
6. Replace if failed.
3. Remove “warranty void” label and screws securing the front panel to the chassis.
Warning: Removal of the warranty void label will void the warranty.
4. Disconnect and remove MOV from load side of the input circuit breaker.
6. Install power module, tighten mounting screws, power up and fully test rectifier as per the
procedures detailed in the manual.
2. Remove rectifier and install replacement rectifier in the same position, tighten mounting
screws.
3. Set up and test rectifier following the procedure outlined in the manual. If the system is SM
equipped, perform an inventory update and then download all the rectifier settings from the
SM to the rectifiers.
2. Insert module, power up and test following the procedures outlined in the manual. If the
system is SM equipped, perform an inventory update and then download all the rectifier
settings from the SM to the rectifiers.
3. With rectifier removed from the shelf, remove fan power leads and mounting screws.
5. Install power module, power up and test rectifier following the procedure outlined in the
manual.
3. Remove rear rectifier cover by removing three screws on each side of the rectifier module.
4. Identify MOV’s; located beside the AC input fuses. MOV’s are small discs approximately the
size of an U.S. 5 cent piece.
5. Measure resistance of MOV. A short circuit or low resistance indicates a failed MOV.
6. Remove the MOV’s if failed using side cutters to clip the MOV leads, clean printed circuit
board of all metallic particles that may contaminate the PCB when the MOV fails.
2. Disconnect live output lead from converter at the converter distribution bus.
4. Tag leads and remove input, output, alarm and control leads from converter and insulate.
6. Reconnect all cables and make the live connections at appropriate bus last.
7. Power up and test converter following the procedure outlined in the manual.
3. Power up and test converter following the procedure outlined in the manual.
2. Insert converter module, power up and test following the procedures outlined in the manual.
General appearance, cleanliness - neutralize with baking soda and water solution as
necessary and wash cells with clean water.
Check and record pilot cell voltage, specific gravity and electrolyte temperature.
Measurements of voltage, specific gravity, conductance and impedance are useful in charting a cell
state of health over time and to alert personnel to a problem cell or battery.
Periodic evaluation of a battery system performance should also be completed. There are various
methods of evaluating battery condition. Performance can be measured automatically with the
SM02 or recorded manually.
1. Short duration high rate discharge.
2. Full discharge to 80% of capacity.
The battery end of life is determined when the capacity has dropped to 80% of nominal.
If any of the individual cell voltages fall out of range an equalizing charge will have to be applied. This may
be applied by one of the following methods:
On-line utilizing the power system rectifiers, to the voltage limits of the load.
Alternatively the battery string may disconnected in a multiple string application, boost
charged with an auxiliary charger and reconnected on line (see string/cell replacement
section).
On-line utilizing a single cell battery charger. The special single cell charger is connected
across cell in question and the cell is boost charged while system is on-line.
2. Match temporary battery string voltage to main power system voltage by either using an
external charger to raise the voltage of the temporary string or by lowering the voltage on the
power system to match the temporary string voltage (voltage should be within .5 volts).
6. Match power system voltage to the voltage of the disconnected battery string.
Troubleshooting
1. RST rectifiers.
2. RSM 48/100 rectifiers.
3. RSM 48/50 and 24/100 rectifiers.
4. RSM 48/30 and 24/50 rectifiers.
5. RSM 48/10 rectifier systems.
6. RSM 48/7.5 rectifier systems.
7. SD 03 and 05 supervisory panels.
8. SD 02 and 04 supervisory panels.
9. SM 02 supervisory panel.
10. Temperature compensation panel.
11. Circuit breaker, fuse and distribution centers.
12. Battery back-up.
13. CS converters.
14. CSM converters.
15. Pathfinder 1.5, 3, 10 kW rectifiers.
16. SM 03 supervisory panel.
2. Pre-Turn Up Inspection
2.1. AC Panel/Protection Inspection
2.1.1. General
AC Service ________V__PH__W
Main Breaker ________A Panel rating __________A
Surge Protection Model#___________ Type_________________
Rectifier feeder circuits _________A _______ Ga. or ________mm
Circuit breakers labeled yes no
Electrical connections ok yes no
Measured AC Voltage ___________V
2.2.2. Mechanical
Seismic Zone 4 required yes no
System secure bottom (required) yes no
System secure top (optional) yes no n/a
System bays bolted together yes no n/a
Box bay shipping braces removed yes no n/a
Verify busbar assembly yes no n/a
2.2.3. Electrical
Rectifier output cables ____ Ga.
Verify inter-bay cabling yes no
Verify shunt lead installation yes no
Verify comm's cable installation yes no
Live buswork insulated adequately yes no
Electrical connections ok yes no
Grounding method Single Point Ground Halo
Frame ground each bay ____Ga. Green Black
Power system battery return ground ____Ga. Green Black
Battery return ground isolated yes no
2.3.1.2. Mechanical
Seismic Zone 4 required yes no
System secure bottom (required) yes no
System secure top (optional) yes no
2.3.1.3. Electrical
Single feed ___________ MCM ___________A protection
A+B ___________ MCM ___________A protection
A,B,C+D ___________ MCM ___________A protection
Frame ground each bay ____Ga. Green Black
Live buswork insulated adequately yes no
Electrical connections ok yes no
2.4.1.2. Mechanical
Seismic Zone 4 required yes no
System secure bottom (required) yes no
System secure top (optional) yes no
Battery assembled correctly yes no
Cable connections tight yes no
2.4.1.3. Electrical
Battery cables __________________MCM/AWG
Temperature probes installed yes no n/a
Where installed?___________________________________________
3. Turn Up procedure
3.1. Ensure all batteries are disconnected, rectifier modules are removed, fuses pulled and circuit
breakers turned off.
3.2. Triple check the polarity of battery connections.
3.3. Install one rectifier.
3.4. Turn on the AC to the rectifier and allow it to start up.
3.5. Verify that the system starts up ok, controller turns on.
3.6. Check the battery polarity is correct and turn on the breakers, fuse or circuit breakers for the
batteries. Note: If there is no means of disconnecting the battery then the rectifier output voltage
should be reduced using the controller to match the rectifier voltage to the battery voltage to
avoid sparks.
3.7. The single rectifier in the system will now begin charging the batteries, this is normal. Install the
remaining rectifiers in the system. One at a time. Turning the AC on to each unit and verifying
breaker position.
3.8. If the SM type of controllers are used a inventory update followed by a download of the system
settings should be performed.
3.9. Install main fuse followed by the guard fuse for the BDFB (BDCCB’s) if required.
4. Test
4.1. Power Plant
4.1.1. Verify Analog Measurements complete
4.1.2. Load test power plant 100A complete
4.1.3. Verify, adjust and download system settings complete appendix____
4.1.4. Verify output alarm relay function complete
4.1.5. Shunt multiplexer complete n/a
4.2. Battery
4.2.1. Initial charge/report complete n/a appendix____
4.2.2. Discharge test/report complete n/a appendix____
5. Notes:
Note Action Details
6. Acceptance
_________________________ ______________________
Company Phone Number
DC-DC Converters
Output voltage
High voltage alarm
Low voltage alarm
High voltage shutdown or OVP
Slope
Current limit