Академический Документы
Профессиональный Документы
Культура Документы
Divisional Office ) Project: S513 Pipeline Replecement & Process Platform to balongan Gathering Station Assessor(s) : Refer to HAZID attendance list
Hazard ID Job ) Task Cause of Adverse Effect ) Adverse Effect ) Type of Mitigating Controls L S RRN Incorporate Doc
Environmental Aspect Environmental Impact Responsible Person Number
MOBILISATION ( PLB Stealth,Faulkner, AHT, Cargo Barge, Tow Tug, and Crew Boat)
S513-MCE-RA-001 1) Towing Calculation)Analysis and approved towing arrangement.
2) Conduct MWS - to obtain Towing)Sail Away Certificate Port Engineer, Barge
Broken mooring lines ( Failure towing ) rigging
Personnel injury and equip damage 3) Ensure all marine spread has completed OVID Inspection, Correct supervision, Clear communication, Certified 1 4 4 Superintendent, Project
arrangement)
Marine Crew Engineer, TUG Capt
1) Approved tow route, Require MPA Pilot assist if required, Ensure navigation chart and
navigation equipment work in order PMN (Port Marine Notice) approval
2) Certified and experienced Marine Crew, Correct navigation chart in place, Review weather and tidal stream
conditions (3rd Party daily forecast),
3) Adequate communication (established by MPA), Obtain Indonesia Port Information Booklet, Obtain
updated)current information from PMN website, Install towing flag, Ensure correct navigational shapes and lights
are displayed
Mobilisation marine spread from Vessel collision ) Personnel injury and
Navigation Hazard 4) Safety boats are in place, Obtain daily ship movement schedule 1 4 4
Port Yard to location. Tow to site equipment damage
5) Approved towing procedure, Early notification to stakeholder,Daily communication to MPA and stakeholder in
the area,
6) Approved and valid vessel certificates and vessel inspection done prior mobilisation and used adequate weather
monitoring equipment
7) STOP mobilisation if weather not permitting
1) Maintain regular communication with relevant authorities, Increase watch keeping 24)7 2) Comply with Port
Security Procedure, Vigilant Routine, Walk around, Buddy System, 3) Induction and safety check for incoming
Loss of Equipment Personnel Risk Thief )
Security Hazard personnel onboard 1 2 2
Piracy
1) Barricade Area whilst lifting in progress, Conduct pre inspection and check correct rigging arrangement and
approved drawing prior commence any lift, Maintain adequate communication
2) Approved lifting procedure
3) Use tag line every lifting and avoid direct hand contact with load,
No person unders suspended load, Maintain adequate supervision,
4) Implement STOP Intervention if there any unsafe work
Lifting Failure (rigging ) crane failure) Personnel Injury and Equipment Damage 5) Certified Rigging, Certified Crane, Certified and offshore experienced Crane Operator,Dedicate rigging team 3 3 9
and Signal Man, Comply color coding, Quarantine uncertified rigging, Conduct pre- inspection prior lift, Implement
PTW System, Review JSEA and Toolbox Talk with personnel prior commence work Comply with HSE Lifting
Guidelines
1) Ensure adequate storage area identified as per approved deck plan (included in Method Statement),
2) Correct sea fastening i.e. welding)lashing,
3) Approved NDT report and MWS Report
4) Conducte NDT test for all fastening and Padeye
5) Adequate supervision, to Ensure competent rigger to carry out sea fastening
Falling Equipment) Inadequate Storage Personnel injury and equip damage 6) Adequate access)escape route 2 3 6
7) Linepipe will only be Max 7 stack high, to ensure use a round sling for lifting linepipe 8) Correct segregation of
Storage Project Material as per material, diving oxygen to be as per requirement (to be assessed)
approved Deck Layout & Sea
fastening all equipment
1) Proper Manual Handling, Use Mechanical Device, Manual handling refresh trainning 2) Good
Pinch Point (Caught in Between), Sharp corners & housekeeping 1 2 2
Material
3) Adequate signage
Anchor Handling
S513-MCE-RA-002
1) Regular maintenance & inspection of AHT mechanical equipment,
2) Conduct 3rd party MWS survey of AHT prior to Mob, ensure all vessel equipment is certified ) operable & in
good working order & condition
Damage to equipment ) facilities. Schedule Barge Foreman,
AHT engine broken down 3) AHT engine room fully manned & systems checked 2 3 6
impact Superintendent, AHT Capt
4) Use towing vessel ) AHT alongside barge to assist maneuvering during the approach & setting of initial anchors
on sea-bed
5) Ensure good comms between AHT & Barge
1) Primary and secondary navigation systems thoroughly tested & confirmed as good operating
2) Surveyors to continuously check displays as correct & inform Captain of any malfunction.
Survey system failure. Possible damage to equipment ) facilities. 3) Callibration of survey equipment 2 2 4
4) Captain to stop if indicates abnormal in the survey system
5) Ensure competent and experience personnels
1) Barricade area, "no personnel movement" & closely monitor ) control cable tensions 2) Announce "Anchor
Handling operations on deck, all personnel keep clear" on vessel PA system (main vessel & AHT), all crew to keep
Wires under tension Injury ) Fatality clear of winches. 2 3 6
3) Use certified towing gears
4) Ensure the competent personnel
5) Ensure adequate emergency response plan
1) Ensure mobilization crew to the agreed coordinates location by harbour master 2) Ensure project crew has been
approve and review by TIMAS before mobilization 3) Mobilization crew at day time
Mobilization project crew 4) Ensure permitting weather 2 2 4
5) Minimize boat to boat personnal transfer
1) mobilize adequate project crew for first anchor drop ,Ensure emergency response procedures are communicated
& understood by all parties. 2) use approve anchor pattern
3) Ensure full set of latest area charts on board, charts to show all sub-sea facilities & debris surveyed
4) Ensure Survey BMS has correct software & operates on known parameters. Also ensure coordinate systems
and calibration of survey equipments are accurate.
damage to equipment ) existing facilities.
Dropped anchor in wrong position 5) Survey display to indicate all existing facilities, debris, proposed anchor positions, midline buoy positions & barge 2 3 6
Environment impact,
position
6) Confirm drop location with survey before lowering to sea-bed & take final position fix @ touchdown
7) Ensure ) confirm no sub-sea facilities are the proximity of touch down point prior to lowering
8) Ensure PTW ) SIKA is in place prior to Anchor Handling operations within the 500m zone
9) communicate and confirm radio channel with Platform
1) Confirm vessel management & control systems are in place & communicated with facility marine control.
2) Comply to specific Anchor handling procedures
Vessel or AHT collision with main barge 3) Conduct 3rd party MWS survey of AHT prior to Mob, ensure all vessel equipment is certified ) operable & in
Injury & or Fatality, damage to equipment )
(Competencies) & equipment failure (steering, or good condition 2 2 4
facilities.
propulsion) 4) Enforce exclusion zone entry requirements
1) Competent personnel
2) Ensure good comm's between rigger foreman & crane operator
Exposure to Pinch points or caught between objects Injury & or Fatality. 3) awarenes of pinch point 2 2 4
4) keep clear from the pinch point or risk of impact
Rigging lifting anchors & Buoys to 5) use adequate tools
AHT deck
1) Familiarize all crew with cranes warning signals (horn & swing alarms), & to look up for possible overhead load
when sounded
Overhead crane loads while transferring to AHT Injury & or Fatality. 2) good communication 2 3 6
3) Barrier tape all anchor & pennant cables on deck
4) monitoring weather permission and weather forecast update
1) Primary and secondary navigation systems thoroughly tested & good condition
Survey equipment failure Damage to subsea facilities 2 2 4
2) Surveyors to continuously check displays as correct & inform Anchor Forman of any malfunction no matter how
AHT running anchors to final small.
location
Broken anchor wire Damage to equipment. 1) Regular inspection of wires & ensure valid certificates for same. 2 3 6
2) ensure adequate anchor wire spares and other equipment
1) Conduct 3rd party MWS survey of AHT prior to Mob, ensure all vessel equipment is certified ) operable & in
good condition
Shark Jaw failure Injury & or Fatality. Damage to equipment 2) Regular maintenance & inspection of anchor handling equipment 2 3 6
3) Ensure winch dog is engaged as secondary stopper when running anchors
1) Mechanics to monitor (Hand Radio) winch during Pretensioning, ensure good comms 2) Barricade area, "no
Winch Failure Injury & or Fatality. Damage to equipment. unauthorized personnel movement" 2 3 6
3) Winch controller to monitor engine gauges at all times & inform Mechanic of conditions
1) Monitoring weather forecast
Deteriorating weather conditions - Rapidly changing Injury & or Fatality. Damage to equipment, Loss
2) Closely monitor site conditions during set up. 2 3 6
conditions with little prior notice control of barge
3) Anticipate local squalls, storms etc.
Injury & or Fatality, damage to equipment ) 1) Ensure slow controlled movement towards platform at all times.
Barge collision with existing facilities 1 3 3
facilities. 2) Survey to monitor distance to platform & constantly inform Captain in 10m increments or as required.
3) AHT to standby & assist in barge movement if required
4) Ensure anchors are bedded in & wire running straight to the anchor (no bellies)
Deteriorating weather conditions - Rapidly changing Injury and or fatality, property damage, Barge 1) Monitoring weather forecast
2) Closely monitor site conditions during set up. 2 3 6
conditions with little prior notice loss of control
3) Anticipate local squalls, storms etc.
Injury and or fatality, property damage, Barge 1) Regular inspection of all anchor wire & ensure valid certificates for same.
Broken anchor wire 2 3 6
loss of control 2) monitor cable tension in control tower at stern)bow fairleads by decks crew during barge movement
3) Barricade area, "no unauthorized personnel movement"
Pull out barge to clear area 4) monitor cable tension at all the time
Injury and or fatality, property damage, 1) Ensure slow controlled movement towards platform at all times.
Barge collision with platform 1 3 3
production loss 2) Survey to monitor distance to platform & constantly inform Captain in 10m increments or as required.
3) PTW and JSEA communicated to all of crew and ensure understood
4) AHT to standby & assist in barge movement if required
1) primary and secondary navigation system through tested and confirm Good condition 2) Survey to continuosly
Survey equipment failure Subsea facility broken)damage 2 3 6
displays as correct and inform immediately if any malfunction
AHT retrieving anchors from 1) Regular inspection of all anchor wire & ensure valid certificates for same.
Broken anchor wire Injury and or fatality, equipment damage 2) monitor cable tension in control tower at stern)bow fairleads by decks crew during barge movement 2 3 6
location
3) Barricade area, "no unauthorized personnel movement"
4) monitor cable tension at all the time
Contact of anchor wire to existing sub-sea facilities Damage to subsea facilities 1) Monitor cable tensions when running anchor, ensure tension is applied when running over existing facilities 2 3 6
2) Ensure good communication between surveyor and AHT
1) Equipment must be in off position, no flamable tools, ensure correct procedure shall comply, ensure use correct
Personal and Equipment damage and fuel pump equipment
Refueling Fire, spills, 3 2 6
reputation 2) Ensure adequate drip pan and sopep kit ) oil spill kits,
3) Ensure adequate storage management
1) Ensure sufficient draft of the barge ) AHT for near shore work, ensure approve procedure,
Too near with shore, stack barge and propeller struck Equipment damage, personal injury, schedule 2) Update weather forecast,
Pipe pulling 2 3 6
a rock (grounding) impact 3) Re-asses actual conditon for approve anchor pattern (refer to pre-lay survey),
4) Adequate communication anchor handling team and barge foreman
1) Ensure wire and winch calculation, ensure certified rigging gears and equipment
Winch pull Winch wire failure Personal injury, Equipment damage 2) Ensure equipment and tools is certified and available, Clearance area 2 4
3) maintain adequate communication onshore-offshore
1) certified riggings equipment,
Drum installation to pipeline, riggings failure, drum 2) Ensure approve procedure, inspect integrity of drum before installation,
Drum installation Personal injury, Equipment damage 2 3 6
leaking 3) Increase of level awareness of pinch point,
4) Ensure use mechanical device for manual handling
1) Ensure sufficient draft of the barge ) AHT for near shore work,
2) Ensure approve procedure,
Too near with shore, stack barge and propeller struck Equipment damage, personal injury, schedule
Barge ) AHT Positioning 3) Update weather forecast, 3 3
a rock (grounding) impact
4) Re-asses actual conditon for approve anchor pattern (refer to pre-lay survey)
5) Adequate communication anchor handling team and barge foreman
6
1) Certified riggings equipment,
2) Ensure approve procedure
Rachets pounding can hit the swimmers, and boat,
Uninstall drum from pipe Personal injury, material damage 3) Increase of level awareness to line of fire 2 3
unstable wave condition
4) Ensure adequate control of the drum movement
5) Ensure use adequate right tools to cut the cargo strap
OFFSHORE PIPELINE INSTALLATION
S513-MCE-RA-004 1) Certified mooring rope
2) Install yokohama fender and Monitor weather condition Barge supt, Welding Supt, 135594-00-CN-00-PR- 041
Pipe transfer from Material 3) Competent personnel & Trained personnel
Collision between Cargo Barge, PLB and or AHT Equipment damage, personnel injury, 2 48 Project Engineer, Barge PLB Pipeline Installation
Barge to Installation vessel 4) Maintain adequate ) good communication
Foreman Procedure
5) Approved Engineering and Installation Procedure 6) ensure certified rigging gears
1) Install adequate barricading and guarding system - ensure rigging person only
2) Adequate lighting if lighting at night
3) Maintain good communication amongst the rigging team
Inadequate communications between crane driver 4) Implement PTW System for critical lift
Personal injury 2 2 4
and deck crew signal men 5) Wear correct PPE, e.g. gloves, helmet, glasses
6) Follow LO lifting procedure
7) Dedicated radio channel during lifting
8) Ensure available of benchman all the times
1) Install adequate barricading and guarding system - ensure rigging person only
2) Ensure adequate platform to be installed
Working at heights - Potential of falling between pipe 3) Adequate lighting if lighting at night
Personal Injury 2 2 4
stacks 4) Maintain good communication amongst the rigging team
5) Wear correct PPE, e.g. gloves, helmet, glasses
6) Follow LO lifting procedure
7) Dedicated radio channel during lifting K22
1) Eng control - adequate guarding system (protection), Barricade, Guarding system Signages
2) Approved Operation procedure,
Exposure to rotating equipment (Rollers, conveyors, 3) Training familiarisation and competent personnel
Crush injuries 2 4
tensioners) 4) Good housekeeping
5) Wear Correct PPE 6) ensure emergency control system in place (emergency stop buttons, alarm system,
spotters, PA system)
4
1) Install adequate barricading and guarding system - ensure rigging person only
2) Ensure adequate platform to be installed
3) Adequate lighting if lighting at night
Fatality (Single) 1 4
4) Maintain good communication amongst the rigging team
5) Wear correct PPE, e.g. gloves, helmet, glasses
6) Follow LO lifting procedure
7) Dedicated radio channel during lifting K22
1) Adequate Maintenance program and conduct function test prior commencing work.
2) Design Engineering (Approved)
Production loss 3) Competent person ) Operator and Project crew 2 2 4
4) Full time maintenance team (Permanent crew)
5) Spare part on hand
1) Install adequate barricading and guarding system - ensure rigging person only
2) Ensure adequate platform to be installed
3) Adequate lighting if lighting at night
Personal Injury 4) Maintain good communication amongst the rigging team 1 4 4
5) Wear correct PPE, e.g. gloves, helmet, glasses
6) Follow LO lifting procedure
7) Dedicated radio channel during lifting
3) Adequate ventilation
1) Competent welder and fitter
2) Guarding system (barrier) - install welding shield
Burns (Radiation) 4) Supervision and Communication 2 2 4
5) Correct & approved procedure
6) Wear correct PPE
1) Guarding system
2) Good housekeeping, remove all combustable or flammable things near to the hot work area
3) Fire extinguisher
4) Approved ERP and approved fire plan
5) Stand by person (fire watcher)
Fire 1 5 5
6) Good ventilation
7) Periodic inspection
8) Maintenance of fitting and hoses (leak testing)
9) Install flash back arrestor
10) Wear correct PPE
1)Good housekeeping 2) Periodic inspection 3) Traning and induction 4) signage 5) ensure adequate cable
Slip, Trip and Fall management 2 2 4
1) Adequate Maintenance program and conduct function test prior commencing work.
2) Design Engineering (Approved)
Tensioner Failure Production loss 3) Competent person ) Operator and Project crew 2 3 6
4) Full time maintenance team (Permanent crew)
5) Spare part on hand, available spare part onboard
1) Eng control - adequate guarding system (protection), Barricade, Guarding system Signages
2) Approved Operation procedure,
Impact to personnel injury 3) Training familiarisation n competent personnel 2 2 4
4) Good housekeeping
5) Wear Correct PPE
1) Guarding system
2) Good housekeeping
3) Fire extinguisher
4) Approved ERP and approved fire plan
Fire 5) Stand by person (fire watcher) 1 5 5
6) Good ventilation
7) Periodic inspection
8) Maintenance of fitting and hoses
9) Install flash back arrestor
10) Wear correct PPE
1) Approved procedure
Personal injury - caught in between 2) Competent personnel
3) Use mechanic aid to lift crawler 2 2 4
(entrapment)
4) Supervision and Communication
5) Wear correct PPE
1) Eng control - adequate mechanical device aid.
2) Approved Operation procedure,
Manual handling injury 3) Manual handling training 2 1 2
4) Good housekeeping
1) Approved proceduer
2) Maintenance program
Environmental Pollution -oil spillage 3) Competent personnel 1 3 3
4) Communication
5) SOPEP
1) Proper ventilation
2) Competent personnel
Toxic inhallation 3) Training 2 3 6
4) MSDS and SOPEP
5) wear correct PPE
1) Good housekeeping
Poor housekeeping ) Congested area ) Obstruction Slip, trip and fall 2) Competent personnel 2 2 4
3) Communication and supervision
4) Workplace inspection
1) Competent personnel,
2) approved procedure
3) traininig
Inadequate storage Environmental pollution - chemical spillage 1 3 3
4) adequate communication
5) Containment tray,availabiity MSDS and SOPEP
6) dedicated chemical storage
POST - TRENCHING
S513-MCE-RA-005
Positioning barge to achieve the Refer to Risk Assesement for Anchor handling
centre of pipeline location
1) Approved procedure,
Struck to equipment or material, slip or trip, 2) Good communication,
Setting pump and compressor Personnal injury, equipment damage 3) competent personnel 1 5 5
rigging failure, suspended load
4) use certified rigging gears
5) barricade lifting area
1) competent personnel only
Install water hose and air hose uncontrol movement, pinch point Personnel injury, equipement damage 2) awareness of pinch point 2 2 4
3) good communication line
1) Competent diver
Crush or impact hazard to equipment and 2) stand by diver and Medic diver
Deploy diver to check trencher Personnal injury, permanent material damage, 3) ERP
humans 1 5 5
position schedule impact 4) Training
)Air Lifting operations subsea 5) adequate system design (Spare air -emergency )
6) good communication line
7) stop and standby pump and compressor
1) certified rigging,
2) pre rigging inspection,
3) don't stand under suspended load
4) approve procedure (lifting study)
5) training,
Fatality (Multiple) 6) good communication 1 5 5
7) supervision,
8) correct storage of rigging equipment
9) maintenance
10) suitable rigging,
11) barricade area
Rigging (lifting gear) failure
1) certified rigging,
2) pre rigging inspection,
4) approve procedure (lifting study)
5) training,
6) good communication
Pipe Damage 1 5 5
7) supervision,
8) correct storage of rigging equipment
9) maintenance
10) suitable rigging,
11) documentation & quality control
1) certified rigging,
2) pre rigging inspection,
3) approve procedure (lifting study)
4) training (certified rigger)
Vessel damage 5) good communication 1 5 5
6) supervision,
7) correct storage of rigging equipment
8) maintenance and suitable rigging,
9) documentation & quality control
1) certified rigging,
2) pre rigging inspection,
3) don't stand suspended load
4) approve procedure (lifting study)
5) training,
Impact injury 6) good communication 1 5 5
7) supervision,
8) correct storage of rigging equipment
9) maintenance
10) suitable rigging,
11) documentation & quality control
1) certified rigging,
2) pre rigging inspection,
3) don't stand suspended load
4) approve procedure (lifting study)
5) training,
Fatality (Multiple) 1 5 5
6) good communication
7) supervision,
8) barricade area
9) maintenance suitable rigging,
10) documentation & quality control
Rigging (Methodology) failure
1) certified rigging,
2) pre rigging inspection,
3) don't stand suspended load
4) approve procedure (lifting study)
5) training,
Equipment &Vessel Damage 1 5 5
6) good communication
7) supervision,
8) barricade area
9) maintenance suitable rigging,
10) documentation & quality control
1) Adequate inspection
Environmental Damage ) Pollution due Oil leak
2) Maintenance 1 3 3
from Davit
3) Competent personnel (Mechanic & Operator)
4) Training SOPEP
1) certified rigging,
2) pre rigging inspection,
3) don't stand suspended load
4) approve procedure (lifting study)
5) training,
6) good communication
7) supervision,
Davit Operations Impact injury 2 3 6
8) correct storage of rigging equipment
9) maintenance
10) suitable rigging,
11) documentation & quality control
12) Correct PPE
13) cary out davit load test
14) installation of pneumo
1) certified rigging,
2) pre rigging inspection,
3) don't stand suspended load
4) approve procedure (lifting study)
5) training,
Fatality (Multiple) 6) good communication 1 5 5
7) supervision,
8) correct storage of rigging equipment
9) maintenance
10) suitable rigging,
11) documentation & quality control
Davit structural failure
1) certified rigging,
2) pre rigging inspection,
3) don't stand suspended load
4) approve procedure (lifting study)
5) training,
Equipment & Vessel Damage 6) good communication 1 5 5
7) supervision,
8) correct storage of rigging equipment
9) maintenance
10) suitable rigging,
11) documentation & quality control
1) Good maintenance,
2) Proper certificate
3) SOPEP
Environmental Damage ) Pollution 1 3 3
4) Training - certified operator
5) communication
6) Oil Spill Control standby if needed
1) certified rigging,
2) pre rigging inspection,
3) don't stand suspended load
4) approve procedure (lifting study)
5) training,
Equipment damage 6) good communication 1 5 5
7) supervision,
8) correct storage of rigging equipment
9) maintenance
10) suitable rigging,
11) documentation & quality control
Davit break down
Manual handling, rigging failure, pinch point, Personnel injury, permanent material damage, E- Approved installation procedure
Riser preparation A-certified rigging gears, competent personnel, good communication, 1 3 3
suspended load schedule impact
Rigging failure, suspended load, adverse weather, Personnel injury, equipment damage, man E- Approved lifting analysis & installation procedure
Riser lifting 1 4 4
lack of communication, crane failure, pinch point, overboarad, permanent material damage A-certified rigging gears, competent personnel, good communication, barricade area, weather monitoring , ensure
unstable load, interfacing with platform activity safe distance crane sling with platform deck, to obtain SIKA approval from platform
Rigging failure, equipment broken, pinch point,
adverse weather, entanglement diver umbilical, E- Approved lifting analysis & installation procedure
strong current, lack of communication, inexperinced Personnel injury, permanent material damage,
Setup riser to riser clamp A-certified rigging gears, competent personnel, good communication, barricade area, weather monitoring , ensure 2 2 4
diver, poor visibility man overboard, schedule impact
safe distance crane sling with platform deck, to obtain SIKA approval from platform
Suction in the pipeline, rigging failure, pinch point, Personnel injury, permanent material damage, E- Ensure pipeline fully flooding
Removal of Initiation head 2 3 6
lack of communication, adverse weather schedule impact A-Familiarization with the material, competent personnel, good communication, weather monitoring
Rigging failure, equipment failure, hot work, personnel injury, permanent material damage, A-certified rigging gears, competent personnel, good communication, aware of pinch point, barricadefire extinguiser
Spool Fabrication 1 4 4
suspended lifting, pinch point, manual handling barricade, fire, ready, weather monitoring, obtain SIKA approval
Spool NDT and coating radiation exposure, radiography source, personnel injury, radiation A-barricade area, announcement, signage, radiation survey, competent people for NDT 2 3 6
Riggings and equipment failure, unstable load, E- Follow approve installation procedure, pre-installation flange inspection A- ensure clear explanation on diving
Personnel injury, permanent material damage,
Flange Mating adverse weather, entanglement diver umbilical, strng task plan, competent & experience diver personnel, good communication, weather monitoring, maintain good 2 3 6
schedule impact
current, lack of communication, pinch point umbilical, awareness of the pinch point
• Barricade area
• Good communication line
manual handling, burst, rotating equipement, high personnel injury, permanent material, • Follow approved procedure
Pig train • Competent personnel and only authorized person in inside the area 2 3 6
pressure equipment or existing facilities damage
• Wear proper and correct PPE
• Ensure the pressure in the pipeline is equal with the environment (as per design and procedure)
• Ensure the pump is turn off and zero pressure
• Close the valve before disconnecting the hose
• Good communication line
Completed flooding, cleanig manual handling, burst, pinch point, adverse weather, personnel injury, schedule impact, permanent • Follow the approve procedure and task plan sequence
1 3 3
and gauging pinch point, suction in the pipeline equipement or material damage, • Awareness of pinch point
• Monitoring weather forecast - sign off the gauging plate by client (TIMAS/PEP)
HYDROTEST
S513-MCE-RA-009
• Ensure the flooding, cleaning and gauging activity is completed and approved by client
• Ensure all equipment and instrument shall be checked and in good condition
• Competent personnel
• Ensure the PTW availability prior commencing the activity
• Maintain line communication between the onshore spread in Land Fall Point and on the platform / pre-com vessel
Setup and prepare hydrotest • Dedicate the central control communication command and check between all work locations
Pinch point, incompetent personnel, manual handling Injury or fatality, schedule impact 1 4 4
spread • Conduct the final check prior the commencement work
• Conduct the function test and leak test spread prior commence any work and witness by Client
• Barricade the area
• Wearing appropriate and correct PPE
• Ensure access free from any obstruction
• Use mechanical device while require manual handling activity
• Ensure all valve are in correct position, check valve and sign by all parties
• Ensure follow the task plan sequence and maintain close monitoring the process
• Increase level of the awareness during the "HOLDING TIME / HOLDING POINT"
• Ensure adequate communication during lock out and tag out or isolation period
• Ensure install adequate locking device for valves
• Ensure install adequate guarding and protection system
• Barricade the area and ensure NO PERSONNEL at LINE OF FIRE during pipeline under pressure
Equipment failure, substandard equipment, personnel injury, damage to the existing
Leak Testing • Keep on eye and closely observe the PRESSURE condition 2 4 8
inadeqaute guarding or protection facilities, schedule impact
• Ensure to use approved and certified equipment
• Ensure competent person only
• Ensure PTW availability in place
• Conduct tool box meeting, JSEA review by concern parties and approve
• Conduct coordination meeting ( interface meeting with offshore and onshore team)
• Ensure adequate lighting
• Wear proper and correct PPE and PFD
• Ensure all valve are in correct position, check valve checklist and sign by all parties
• Ensure follow the task plan sequence and maintain close monitoring the process
• Increase level of awareness during the " HOLDING TIME / HOLDING POINT"
• Ensure adequate communication
• Ensure install adequate locking device for valves
• Barricade the area and ensure NO PERSONNEL at LINE OF FIRE during pipeline under pressure
Equipment failure, substandard equipment, in personnel injury, damage of existing facilities,
De-pressurization • Keep on eye and closely observe the PRESSURE condition 2 4 8
adequate communication, manual handling schedule impact
• Ensure use approve and certified equipment only
• Ensure competent person only
• Ensure PTW approved in place
• Ensure adequate lighting
• Ensure approval procedure made available and communicate
• Wear proper / correct PPE and PFD
1/ Approved procedures,
2/ Inspection.
Fire / Flash Fire Due to Ignited Mix of O2 and
3/ Correct Maintenance 4/ Flash Back arrestor 5/ ERP
Flammable Personal injury to diver 1 5 5
6/ Oxygen supply line to clean,
Material
7/ BIBS chamber DDC
8/Ensure NO steenless steel material -(O2 friendly) fitting 9/ Approved O2 Compressor (handling sysetm)
1/ Approved procedures,
2/ Inspection.
3/ Correct Maintenance 4/ Flash Back arrestor 5/ ERP
Fire / explosion 1 5 5
6/ Oxygen supply line to clean,
7/ BIBS chamber DDC
8/Ensure NO steenless steel material -(O2 friendly) fitting 9 Approved O2 Compressor (handling sysetm)
1/ Maintenance 2/ training
Equipment failure Personal injury 3/ approved procedure 4/ Spare equipment 5/ good housekeeping, 6/ regular inspection 7/ Adequate 1 5 5
communication
Diver disorientated, panic driven state of 1/ Competent diver 2/ stand by diver 3/ ERP 4/ Medic diver 5/ Trainig
Decompression Illness, Schedule impact 2 2 4
mind./Fatigue 6/ adequate system design (Spare air -emergency ) 7/ Adequate communication
1/ Approved procedure,
Crush or impact hazard to equipment and humans Personnal injury, permanent material damage,
2/ training 1 5
/Air Lifting operations subsea schedule impact
3/ design engineering (umblical length) 4/ Dive locatgon 5/ SIMOP and PTW 6/ Dive medic available
1/ Approved procedure,
Personnel injury, permanent material
Over head crane movement Mattress impact hazard to equipment and humans 2/ training 2 5
damage,schedule impact
3/ design engineering (umblical length) 4/ Dive locatgon 5/ SIMOP and PTW 6/ Dive medic available
1/ certified rigging,
2/ pre rigging inspection,
3/ don't stand suspended load 4/ approve procedure (lifting study)
Impact injury , Fatality (Multiple) 5/ training, 2 3 6 Barge Supt, Barge Foreman
6/ good communication 7/ supervision,
8/ correct storage of rigging equipment 9/ maintenance 10/ suitable rigging,
11/documentation & quality control (competent personnel)
1/ certified rigging,
2/ pre rigging inspection,
4/ approve procedure (lifting study)
Vessel and Equipment Damage 5/ training, 1 5 5
6/ good communication 7/ supervision,
8/ correct storage of rigging equipment 9/ maintenance 10/ suitable rigging,
11/documentation & quality control (competent personnel)
Rigging
1/ certified rigging,
2/ pre rigging inspection,
3/ don't stand suspended load 4/ approve procedure (lifting study)
Impact injury , Fatality (Multiple) 5/ training, 2 3 6
6/ good communication 7/ supervision,
8/ correct storage of rigging equipment 9/ maintenance 10/ suitable rigging,
11/documentation & quality control (competent personnel)
1/ certified rigging,
2/ pre rigging inspection,
4/ approve procedure (lifting study) 5/ training,
Vessel and Equipment Damage 1 5 5
6/ good communication 7/ supervision,
8/ correct storage of rigging equipment 9/ maintenance 10/ suitable rigging,
11/documentation & quality control
1/ certified rigging,
2/ pre rigging inspection,
3/ don't stand suspended load 4/ approve procedure (lifting study)
Impact injury , Fatality (Multiple) 5/ training, 2 3 6
6/ good communication 7/ supervision,
8/ correct storage of rigging equipment 9/ maintenance 10/ suitable rigging,
11/documentation & quality control (competent personnel)
1/ certified rigging,
2/ pre rigging inspection,
4/ approve procedure (lifting study)
Vessel and Equipment Damage 5/ training, 1 5 5
6/ good communication 7/ supervision,
8/ correct storage of rigging equipment 9/ maintenance 10/ suitable rigging,
11/documentation & quality control (competent personnel)
1/ certified rigging,
2/ pre rigging inspection,
4/ approve procedure (lifting study)
Equipment damage 5/ training, 1 5 5
6/ good communication 7/ supervision,
8/ correct storage of rigging equipment 9/ maintenance 10/ suitable rigging,
11/documentation & quality control (competent personnel)
1/ certified rigging,
2/ pre rigging inspection,
3/ don't stand suspended load 4/ approve procedure (lifting study)
Fatality (Multiple) 5/ training, 1 5 5
6/ good communication 7/ supervision,
8/ correct storage of rigging equipment 9/ maintenance 10/ suitable rigging,
11/documentation & quality control (competent personnel)
Collision between wharf and Vessel 1/Competent personnel 2/Training & competency 3/ Install life buoy 4/ PFD
Man Over board 2 2 4
1/Approved engineering
2/ Competent captain and crew personnel
Environmental damage/spollution 3/ adequate guarding system i.e. tyre fender / yokohama fender 1 4 4
4/ traning
5/communication and adequate AHT 6/SOPEP
1/Approved engineering
2/ Competent captain and crew personnel
Damage to vessel and/or wharf 3/ adequate guarding system i.e. tyre fender / yokohama fender 2 2 4
4/ traning
Uncontrolled bumping during mooring operations
5/communication and adequate AHT
(Vessel-Wharf)
1/Competent personnel 2/Training & competency 3/ Install life buoy 4/ PFD
1/Competent personnel 2/Training & competency 3/ Adequate mooring line 4/ Regular Inspection 5/ Install life buoy
Mooring line failure 5/ PFD
1/Approved engineering
2/ Competent captain and crew personnel
Vessel Damage 3/ adequate guarding system i.e. tyre fender / yokohama fender 1 4 4
4/ traning
5/communication and adequate AHT
Collapsed load
1/Training and competent personnel 2/ Correct procedure
3/ Inspection Crane and rigging condition (Certififed) 4/ Barricade area during lifting in progress 5/ Signage
Material/Equipment damage 2 2 4
1/Approved engineering
2/ Competent captain and crew personnel
Damage to vessel 3/ adequate guarding system i.e. tyre fender / yokohama fender 1 3 3
4/ traning
5/communication and adequate AHT
Lifting Rigging in the material
barge
1/ Competent personnel 2/Training & competency 3/ Install life buoy & lifeline
Man Over board 2 2 4
4/ PFD 5/proper sign and barricade if guard need to be removed 5/ Use work vest
1/ Control all lifting and rigging stuffs prior commencing the job,
Dropped objec during lifting operation Personal Injury 2 / competent persons in place 2 2 4
3/ Makesure the weather is allow to do the job
Property damage 2 2 4
1/ Correct lifting gear used 2/ Proper method
3/ Enough space for lifting operation 4/ housekeeping in work place
Hot Work on material Barge Electrical Shock Crush injuries 1/ Check all cable connection prior commencing the job 2/ No leaking cable use for the job 3/ Proper PPE during 2 2 2
working
Poor Housekeeping Slip / Trip 1/ Keep good housekeeping in place 2/ Makesure the welding cable in safe route 1 2 2
1/ Competent personnel 2/Training & competency 3/ Install life buoy & lifeline
4/ PFD 5/proper sign and barricade if guard need to be removed 5/ Use work vest
Barge shaking Man Over board 2 2 4