Академический Документы
Профессиональный Документы
Культура Документы
Answer these questions first and the formulas will be calculated for you.
0.90
0.80
0.70
0.60
0.50
Cost performance index
0.40
Schedule performance
0.30 index
0.20
0.10
0.00
Variances
-20,000
-40,000
-80,000
-100,000
-120,000
Formula
Predict how much more the remainder of the project will costs
Predicts likelihood of reaching BAC
EV-AC
EV-PV
BAC-EAC
EV/AC
EV/PV
BAC/CPI
AC + BAC – EV
AC + [BAC-EV/(CPI x SPI)]
EAC-AC
(BAC-EV)/(BAC-AC)
(BAC-EV)/(EAC-AC)
Indication
PV=FV/(1+ i)n
Present value of money You enter info here Formula components
Future value 625000 625000
Interest 0.06 1.06
Years 5 1.3382255776
Present value $ 467,036.36
Build Cost 100000
Monthly Build Cost 12000