Академический Документы
Профессиональный Документы
Культура Документы
Contract Requirements
Variation claims
Problem/Success Impact
The EM/CM/QM was not fully engaged in the All requirements were not included in the
contract process. initial contract award.
BAM Infra have used ALLPLAN for 3D Modelling, All models should be transferable and
and then to AUTOCAD for drafting Shop drawing exported .ifc to allow for integration via
which does not allow exportability to REVIT from BIM360 by BAM Deco. Impact on
BAM Deco for the Model Integration for uploading, BAM Deco have produced its
Collaboration and BIM. own structural model. Time taken 2 weeks
to model B2 and B1.
The PM did not have a plan for addressing
scope creep and allowed some
Client continuously adding to the project scope
requirements to be added until the sponsor
throughout the project lifecycle. stopped it. Overall project delay of 3 weeks
was the result.
Potential
Recommendation
EM/CM/QM must be fully engaged in all
contract processes. This must be
communicated to both PM and contract
personnel.
2
3
4
Specifics:
1
2
3
4
5
6
QAQC Manager
1
BIM Engineer
Issue in integrating model created in ALLPLAN to REVIT and Navisworks (Transferability)
1
1
2
Rebar Engineer
1
Structure Engineer
1
2
3
Document Controller
1
3
tion Manager
Almost all drawings we worked with on site were drawings with handwritten
comments. I think we have missed the point if we need to work with scanned
drawings with handwritten comments…
Positive point, at least we have tried if some synergy would be possible.
Very sadly they let us down when we needed support with proper drawings the
most.
Initial work sequence discussed was not incorporated in the cutting and bending lists
of the tiebeams. Only long lengths…
Drawings don’t have elevations and cross references to check dimensions.
BIM plus was not usable because of duration loading model. Also not user friendly
for taking measurements
Overlaps / splicing is not clearly mentioned in the drawings.
Pour breaks are not mentioned in the drawings.
From supervisors point of view the drawings were not logically setup. A lot of looking
for the correct data / sections (if it was even there).
By thinking to squeeze a lot of info on one page does not benefit the purpose of why
the shopdrawings are made.
When making shopdrawings it is not about the quantity of shopdrawings….
BAM Infra drawing is not readable and create a lot of confusion on site, supervisor
always ask QA/QC to interpret the drawing.
There is always mistake on the BBS which needed to be adjusted on site as per actual
condition.
tural Engineer
During tender phase BAM Infra claims BIM Modelling is ready and set up. When
construction phase begins, BAM Infra proposes to extend the delivery schedule to
preparing the model.
BAM Infra claims that All Plan Modeling is easy to use for rebar checking. But after all
rebar in Basement 2 has been uploaded, modeling is no longer accessible due to
heavy data. BAM Decorient must suffer to check all BBS drawing by pdf print.
All the comment during coordination phase with client are interpreted by BAM Infra
as an additional task with potential charge rather than service to help end user.
BAM Infra demanding 1 Lead Engineer to stay for 8hrs/5days in the BAM Infra office.
The Engineer’s absence was claimed by BAM Infra as an excuse for the delay.
Engineer task is only to solve 2-3 small problems per day that can be solved by video
calls.
For BBS drawing, section and cutting list disordered, then supervisor and foreman
needed time to read and sometime discuss with engineer to get same perception.
Full of information on one page drawing, but required detail not showed / not clear
e.g. lap splice length, position of rebar, dimension etc.
Summary of rebar only showed for all diameter, not every diameter, then Engineer or
supervisor, who was needed rebar summary should be manually calculated and took
time.
The drawing that beam drawing that they submit are confusing.
BBS font are too small.
They lack in dimension for splice length notation.
BAM Infra submit drawing partially, it makes the submission of revised drawings not
in good sequence. Would be better if the 2nd submission is in line with the 1st
submission.
The size of font is too small and unreadable. It makes double work for BAM to re-
print in bigger size and increase the total copies to make.
BAM infra always transmits drawings using transmittal, which is good practice.