Вы находитесь на странице: 1из 10

Category Issue Name

Procurement Management Contract Requirements

Contract Requirements

Human Resources Manpower planning


Management

Scope Management Cross reference

Model files integration and


exportability
Scope Creep

Shop drawing quality


Quality Management output

None readable shop


drawing for rebar

Shop drawing delivery


Risk Management submission to BAM Deco.

Variation claims
Problem/Success Impact
The EM/CM/QM was not fully engaged in the All requirements were not included in the
contract process. initial contract award.

A contract modification was required which


added an impact during the project.

The meeting minutes, formal agreement, delivery


schedule, during pre-award was not established All requirements were not included in the
during contract process. initial contract award.

Impact on deliverable schedules.

There was no MANPOWER planning been


provided by BAM Infra to support the timeline During project execution the delivery
delivery schedule that BAM Deco requires for schedule was impacted and revised
IKEA-2. multiple times in the expense of BAM
Deco.

BAM Infra also explains during the meeting


that they can’t cope up with the current
manpower they have.

Impact on project delivery from


Engineering to Construction and Quality of
distributing S.D. for site use and Client
submission.
BAM Deco have to rely on 2D IFC drawings
from internal and come-up a proper
BAM Infra did not complete the concrete outline submission of RFI to client. Impact 2 weeks
and model of all pits following IFC reference from on engineering schedule.
Structural and the Architectural. BAM Infra Team
leader lacks experience in handling multi-
discipline project which require cross referencing
of trade drawings.

BAM Infra have used ALLPLAN for 3D Modelling, All models should be transferable and
and then to AUTOCAD for drafting Shop drawing exported .ifc to allow for integration via
which does not allow exportability to REVIT from BIM360 by BAM Deco. Impact on
BAM Deco for the Model Integration for uploading, BAM Deco have produced its
Collaboration and BIM. own structural model. Time taken 2 weeks
to model B2 and B1.
The PM did not have a plan for addressing
scope creep and allowed some
Client continuously adding to the project scope
requirements to be added until the sponsor
throughout the project lifecycle. stopped it. Overall project delay of 3 weeks
was the result.

Disruption on reading shop drawings on


Delivery output presentation was not formalized site both QAQC and Construction. Many
by BAM Infra during pre-award and even post misinterpretations happen, BAM Deco have
award. Instead it focused on its own policy rather to reprint and resize all BAM Infra’s
than what the End-user requirement. drawings before distributing to
Construction and QAQC for use.

BAM Deco have to incurred time to read


BAM Infra produced none readable shop drawing and do part-print of BBS to ensure that
for BBS. Construction have readable BBS for
production and procurement.

A risk was identified that there is potential delay


in receiving shop drawing from BAM Infra on time. Impact was minimal because the EM
included potential delays into the delivery
project schedule and planned mitigation
plan. PM has introduced new service
This was a success because it was identified early company to mitigate further delays
and planned for descoping for next level. (Archetype).

Potential
Recommendation
EM/CM/QM must be fully engaged in all
contract processes. This must be
communicated to both PM and contract
personnel.

All MOM, formal agreements, delivery


schedule must always be adhered.

The PM/OM should institute a quality


assessment on the capability of BAM Infra
during Pre-award then perform post-award
monitoring with BAM Infra to ensure that
they deliver what they promise during
contract negotiation.

BAM Deco should have review the


capability of BAM Infra in handling multi
information coming from trade IFC
drawings. No people no go!

BAM Deco not to engage a service


company that is not aligned with the BIM
interface platform to avoid double work.
The PM must have an approval process for
any proposed scope changes and
communicate this process to all
stakeholders.

Always plan quality standards and


allowances into the project plan. Always
listen to the End-user rather than horse
riding on Policy. This helps, disruption,
avoid delays and cost overruns.

BAM Deco have presented the appropriate


cope and scale during RFQ stage, however
BAM Infra disregard and establish its own
policy.

BAM Deco should have not engaged such


service provider does not listen to end-
user.

Always consider external impacts on the


project cost and schedule. This must be
continuous throughout the project
lifecycle.
Construction Manager
General:
1

2
3
4

Specifics:
1

2
3

4
5
6

QAQC Manager
1

BIM Engineer
Issue in integrating model created in ALLPLAN to REVIT and Navisworks (Transferability)
1

Snr. Structural Engineer

1
2

Rebar Engineer
1

Structure Engineer
1
2
3

Document Controller
1

3
tion Manager

Overall it is more disappointments than benefits.

Almost all drawings we worked with on site were drawings with handwritten
comments. I think we have missed the point if we need to work with scanned
drawings with handwritten comments…
Positive point, at least we have tried if some synergy would be possible.
Very sadly they let us down when we needed support with proper drawings the
most.

Initial work sequence discussed was not incorporated in the cutting and bending lists
of the tiebeams. Only long lengths…
Drawings don’t have elevations and cross references to check dimensions.
BIM plus was not usable because of duration loading model. Also not user friendly
for taking measurements
Overlaps / splicing is not clearly mentioned in the drawings.
Pour breaks are not mentioned in the drawings.
From supervisors point of view the drawings were not logically setup. A lot of looking
for the correct data / sections (if it was even there).
By thinking to squeeze a lot of info on one page does not benefit the purpose of why
the shopdrawings are made.
When making shopdrawings it is not about the quantity of shopdrawings….

BAM Infra drawing is not readable and create a lot of confusion on site, supervisor
always ask QA/QC to interpret the drawing.

There is always mistake on the BBS which needed to be adjusted on site as per actual
condition.

Issue in integrating model created in ALLPLAN to REVIT and Navisworks (Transferability)


.IFC Problem from Allplan. Some ATTRIBUTES (Properties and instance properties) are
not existing in REVIT.

tural Engineer

During tender phase BAM Infra claims BIM Modelling is ready and set up. When
construction phase begins, BAM Infra proposes to extend the delivery schedule to
preparing the model.
BAM Infra claims that All Plan Modeling is easy to use for rebar checking. But after all
rebar in Basement 2 has been uploaded, modeling is no longer accessible due to
heavy data. BAM Decorient must suffer to check all BBS drawing by pdf print.

All the comment during coordination phase with client are interpreted by BAM Infra
as an additional task with potential charge rather than service to help end user.

BAM Infra demanding 1 Lead Engineer to stay for 8hrs/5days in the BAM Infra office.
The Engineer’s absence was claimed by BAM Infra as an excuse for the delay.
Engineer task is only to solve 2-3 small problems per day that can be solved by video
calls.

For BBS drawing, section and cutting list disordered, then supervisor and foreman
needed time to read and sometime discuss with engineer to get same perception.

Full of information on one page drawing, but required detail not showed / not clear
e.g. lap splice length, position of rebar, dimension etc.
Summary of rebar only showed for all diameter, not every diameter, then Engineer or
supervisor, who was needed rebar summary should be manually calculated and took
time.

The drawing that beam drawing that they submit are confusing.
BBS font are too small.
They lack in dimension for splice length notation.

BAM Infra submit drawing partially, it makes the submission of revised drawings not
in good sequence. Would be better if the 2nd submission is in line with the 1st
submission.
The size of font is too small and unreadable. It makes double work for BAM to re-
print in bigger size and increase the total copies to make.
BAM infra always transmits drawings using transmittal, which is good practice.

Вам также может понравиться