This draft budget from contractor Mitra Jaya is for additional barrel space work at the PT Ocean Beach Hotel in Legian, Bali. The total estimated cost is 108,645,000 including 98,180,000 for civil and finishing work such as demolition, brick walls, glass walls, and painting, and 10,465,000 for electrical work like lighting, outlets, and switches. Work will be done from 12pm to 7am to avoid disrupting the restaurant.
This draft budget from contractor Mitra Jaya is for additional barrel space work at the PT Ocean Beach Hotel in Legian, Bali. The total estimated cost is 108,645,000 including 98,180,000 for civil and finishing work such as demolition, brick walls, glass walls, and painting, and 10,465,000 for electrical work like lighting, outlets, and switches. Work will be done from 12pm to 7am to avoid disrupting the restaurant.
This draft budget from contractor Mitra Jaya is for additional barrel space work at the PT Ocean Beach Hotel in Legian, Bali. The total estimated cost is 108,645,000 including 98,180,000 for civil and finishing work such as demolition, brick walls, glass walls, and painting, and 10,465,000 for electrical work like lighting, outlets, and switches. Work will be done from 12pm to 7am to avoid disrupting the restaurant.
NUMBER DEFINITION OF WORK QTY UNIT UNIT PRICE TOTAL COST
A CIVIL AND FINISHING WORK
1 Demolition and cleaning work 1 Ls 5,000,000 5,000,000
2 Brick wall for the support of the fix glass 12 m' 95,000 1,140,000 3 Plastering and Acian disassembly marks 1 Ls 1,800,000 1,800,000 4 Cement polishing 1 Ls 400,000 400,000 5 Plastering and acian brick wall 1 Ls 1,850,000 1,850,000 6 Glass wall frame (Iron material) 50 m' 220,000 11,000,000 7 Wall glass (T = 6 mm) 26 sqm' 475,000 12,350,000 8 Shelf table 12 m' 560,000 6,720,000 9 Calsiboard wall and column 1 Ls 5,850,000 5,850,000 10 Roof addition 1 Ls 400,000 400,000 11 Beachvan (90x60x445 cm) 1 Set 28,400,000 28,400,000 12 Calsiboard partition (150 x 265 cm) 1 Ls 900,000 900,000 13 Wall painting 162 sqm' 80,000 12,960,000 14 Paint glass wall frame 51 m' 80,000 4,080,000 15 Concrete beam painting 42 m' 85,000 3,570,000 16 Painting a bar stool 8 nos 220,000 1,760,000
TOTAL 98,180,000
B ELECTRICAL WORK
1 Cable for lighting installaton 13 point 235,000 3,055,000
2 Cable for power outlet installation 6 point 240,000 1,440,000 3 Cable for switch installation 2 point 230,000 460,000 4 Procurement and install lighting 3 nos 280,000 840,000 5 Procurement and install rell track 2 m' 160,000 320,000 6 Procurement and install switch seri 2 nos 150,000 300,000 7 Procurement and install universal socket + USB 6 nos 390,000 2,340,000 8 Reinstall rell track & spotlight 1 Ls 750,000 750,000 9 LED strip 12 m' 80,000 960,000 TOTAL 10,465,000
RECAPITUTILATION
A CIVIL & FINISHING WORK 1 Ls 98,180,000 98,180,000
B ELECTRICAL WORK 1 Ls 10,465,000 10,465,000
NB : Work in the restaurant room is done from 12 SUB TOTAL 108,645,000