Академический Документы
Профессиональный Документы
Культура Документы
2012 E.C
By Girmay kasaye
Surface Mining Methods
If a mineral deposit lies close to the surface, is of sufficiently big size, and its overburden is
not too thick, surface mining can be the most suitable method to extract the ore. Surface
mining is the exploitation method in which minerals are mined from the surface. It seems
to be the most commonly used mining method in the world. Two types of methods may be
used in surface mining: mechanical extraction and aqueous extraction. The former,
predominates, the latter cannot be employed unless there is sufficient water quantity
available.
Surface mining is considered more advantageous than underground mining in relation to
recovery, grade control, economy, flexibility of operation, safety, and the working
environment. However, there are many deposits that are too small, irregular, and/or deeply
buried to be extracted economically by surface mining methods. Moreover, even where
mineralization goes to a greater depth in open pit mines, the increasing amount of
overburden to be handled can make mining unprofitable. In such the situation, mining has
to be either abandoned or converted from surface to underground operations. Furthermore,
the selection of excavation methods and equipment is more complex for surface mining than
for underground mining. In surface mining, blasting patterns have to be properly planned to
get adequate fragmentation of overburden.
Mechanical Extraction Methods
The mechanical extraction involves mechanical processes to obtain minerals from the
earth. There are four mechanical extraction methods:
(1) Open pit mining,
(2) Quarrying (of dimension stone),
(3) Open cast mining, and
(4) Auger mining.
In open pit mining, a thick deposit is mined in benches or steps. However, a
comparatively thin deposit may be excavated from a single face as in the case of
quarrying, auguring and open cast mining. In the case of these methods, a large capital
investment is necessary, however, they can provide high productivity, low operating costs,
and satisfactory safety conditions. Prior to or during mining, it is necessary to remove any
overburden by a stripping operation.
In open cast (or strip) mining, overburden is removed by casting into mined-out areas, and
mineral is excavated in consecutive operations. Open pit or open cast mining is used to
mine a mineral deposit close to the earth’s surface that is of low stripping ratio, shows
large extension, and is fairly uniform. It should be noted here that a stripping ratio of 2 to1
means that there is twice as much waste rock mined as mineral (ore, coal, etc.)
Quarrying is a highly specialized small-scale method, slow and the most costly of all
mining methods. Only square set stoping method is as much expensive as quarrying.
However, quarrying is the only method able to provide both a sized and shaped product .
BY Girmay kasaye
Auguring is employed to recover coal from the high wall at the pit limit. This method is
also specialized but involves low costs. Open pit and open cast methods can be widely and
variably applied. They use a conventional mining cycle of operations to extract mineral:
rock breakage is achieved by drilling and blasting, which precedes the material handling
operations of excavation and haulage (Hartman, 1992).
4.1.2 Aqueous Extraction Methods
The aqueous extraction methods must be provided with the access to water or an aqueous
mixture during mining and processing. They recover the valuable mineral by jetting,
slurrying, melting or dissolving. There are of two types of these methods:
(1) Placer mining methods and
(2) Solution mining methods.
Placer mining is used to mine mineral deposits that are not consolidated, such as sand,
gravel or alluvium in which a valuable heavy mineral exists freely. Valuable heavy
minerals such as diamonds, native gold, native platinum, and titanium can be found in
placer form. There are possible two methods for placer mining:
A) hydraulicking
B) Dredging.
A) Hydraulicking (hydraulic mining) uses a high-pressure stream of water to undercut
and force an exposed bank to fall down. Dredging utilizes floating vessels from which the
ore minerals are extracted mechanically or hydraulically. Since the waste material is
usually lighter than the valuable heavy mineral to be extracted, this mineral can be
removed from water-base slurry by concentration in both methods Solution mining
employs in situ techniques and surface techniques. Salt wells, uranium dissolution, and the
Frasch process to melt Sulphur are examples of the in situ techniques. Surface techniques
utilize mainly solvent leaching of mineral values from heaps or dumps.
Hydraulicking, dredging, and the solution mining are the most economical exploitation
methods. They use unique and different cycles of operations entirely different from
mechanical extraction methods.
GEOMETRICAL CONSIDERATIONS
INTRODUCTION TO OPEN PIT MINING
The ore deposits being mined by open pit techniques today vary considerably in size,
shape, orientation and depth below surface. The initial surface topographies can vary from
mountain tops to valley floor. In spite of this there are a number of geometry based design
and planning considerations fundamental to them all.
The ore body is mined from top to the down in the series of horizontal layers of uniform
thickness called benches and after a sufficient floor area has been exposed, mining to the
next layer can begin. The process continues until the bottom bench elevation is reached and
the final pit outline achieved. To access different bench a road or ramp must be created.
BY Girmay kasaye
The width and steepness of this road or ramp depends upon the type of equipment to be
accommodated. Stable slopes must be created and maintained during the creation and
operation of the pit.
BENCH WIDTH: The bench width is the distance between the crest and toe measured
along the upper surface.
of the order 2 3 of the bench height. At the end of mine life, the safety benches are
BY Girmay kasaye
A safety berm is also left along the outer edge of the bench to prevent trucks and other
machines from backing over. It serves much the same function as a guard rail on bridges
and elevated highways. Normally the pile has a height greater than or equal to the tire
radius. The berm slope is taken to be about 35O, i.e. also called the angle of repose.
The steps which are followed when considering bench geometry are:
BY Girmay kasaye
Fig. 2a: Functions of a catch bench
DEVELOPMENT OF ACCESS ROAD: (ORE ACCESS;)
In mining literature, going the initial knowledge about the physical access to the Ore body
is of great importance. For this, the question arises that: “How does one actually begin the
process of Mining?” Obliviously the approach depends upon the topography of the
surrounding ground. To introduce the topic, it is assumed that the ground surface is flat.
The overlying vegetation has been removed as has the soil/sand/gravel overburden. In this
case it will be assumed that the ore body is 700 feet in diameter, 40feet thick, flat dipping
and is exposed by removing the soil overburden. The ore is hard so that drilling and blasting
is required. The bench mining situation is shown in figure: 3.
BY Girmay kasaye
Figure 3: Geometry of the ore body
A vertical digging face must be established in the ore body before major production can
begin. Further more a “ramp” must be created to allow truck and loader access. A drop cut
is used to create the vertical breaking face and the ramp access at the same time.
To access the Ore body, the “ramp” shown in figure: 4 will be driven it has an 8% grade
and a width of 65 feet.
Although not generally the case, the walls will be assumed vertical. To reach the 40ft
desired depth, the ramp in horizontal projection will be 500ft in length.
1
Rw 2 horizontal H
1 H
1 H 100 H
Rw 2 g
BY Girmay kasaye
:. Volume of Ramp = V= 50 H2/g × Rw; (ft3)
Example # 01:-
Determine the volume of Ore body by waste rock to develop access road at the slope of
8%. Depth of cylindrical Ore body is 30 feet and diameter 500 ft, width of ramp is 65 feet.
Data:
Slope = g = 8%
Depth = H = 30 feet
Diameter = d= 500 feet
Width of ramp = Rw = 65 feet
Solution:
as V = Volume of ramp
H2 and V
= 50 × × Rw g
V = 50 × =
V = 365625 ft3 Ans
.
Example # 02:-
Repeat example # 01 for Depth (H) = 40 ft and Ramp width (Rw) = 60 ft.
H2
Solution: - V = 50 ×
× Rw g
V = 50 ×
V = 600000 ft3 Ans
BY Girmay kasaye
DEVELOPMENT OF ACCESS ROAD: (ramps)
i) In waste rock (Fig. 5a)
.
ii) Ramp in ore body (Fig. 5b)
.
iii) Ramp starting in waste and ending in ore (Fig. 5c)
BY Girmay kasaye
SURFACE MINE DESIGN AND PRACTICE
penetrates to the point that the face. It then moves parallel to itself and takes another frontal
cut as shown in fig: 7.1;
With a long face and sufficient bench width, more than one shovel can work the same face,
as shown in fig. 7.2.
Another possibility when the mine geometry allows is the parallel cut with drive by. This
is diagrammatically shown in figure 8. The shovel moves across and parallel to the digging
face. For this case bench access for the haul units must be available from both the directions.
It is highly efficient for both the trucks and the loader. Although the average swing angle
is greater than for the frontal cut, the trucks do not have to back up to the shovel and the
spotting is simplified.
The expansion of the pit at the upper levels is generally accomplished by using parallel
cuts. Due to space limitations there is only access to the ramp from one side of the shovel.
This means that the trucks approach the shovel from the rear. Then, they stop, turn, and
back into the load position.
Sometimes there is a room for double spotting of the trucks (fig: 9.1) but sometimes for
only single spotting as shown in figure 9.2.
bench (wb) is equal to the width of the minimum required safety bench plus the width of
the cut.
The easiest way of demonstrating the principles involved is by way of an example: For this,
the following assumptions will be made:
The general arrangement of working bench (in x-sectional view) is shown in figure 10.
Step # 01:- Highest of the berm should be at least same as the radius of the truck
tire, i.e.; = 4 feet.
Step # 02:- The distance b/w the crept and centre line of the truck = Tc = 21:
Width of Berm = 8 feet.
Clearance distance b/w safety berm and the wheels of truck = 5 feet
and; the total width of truck = 16 feet.
Step # 03:- The distance b/w the centre line of the Shovel and centre line of the
truck is also called as “Dumping radius” denoted by B; B = 45.5 feet.
Step # 03b:- The Maximum duping height (A) is more than sufficient to clear the
truck;
A = 28 feet.
Step # 03c:- Distance b/w the centre line of Shovel and toe = G ;
G= 35.5 feet
Note: All the parameters and /or dimensions used above, depends upon the size of the
machinery which is used.
Note: This is applied to the width of the pile of broken material. Therefore, to allow for
swell and throw of the material during blasting. The design cut width should be less than
this value. Thus a value of 60 feet has been assumed.
CUT SEQUENCINGS:
Let us consider a pit consisting of four benches as shown in fig: 11
After the initial geometry of the bench is completed; the mining of first bench is started as
shown in figure: 12.
The above figure shows that while performing the cut mini ng operation of bench # 01, the
overall slope angle was “θ01”.
After the mining of bench # 01, the next bench (i.e.: Bench # 02) is mined, as shown in
fig. 13:
Fig: 13:- Cut mining from bench # 02
Engr. Izhar Mithal Jiskani - 17 -
SURFACE MINE DESIGN AND PRACTICE
Now consider the slope consisting of “5” such benches (shown in figure). The angle made
with the horizontal of the line connecting the lowest most toes to the upper most crests is
defined as the overall pit slope.
θoverall tan 1
4x535x50 tan755x(Y50)O 50.4O
:.
tan
yx'
y 50 50
x '
13.4' tanθ tan75
3.732
Since we have 5 benches,
i.e.: - 5 slopes, X= (4*x) + (5*x’).
X = (4 x 35) + (5 x 13.4) = 140 + 67 X = 207’ Y
= 5 x 50 Y = 250’
:. Overall pit slope angle = θ overall
θoverall 50.4O
Y 50 50 24 Y 124feet
The inter-ramp wall height is 125 ft for each segment. Generally the inter ramp wall heights
and angles for different slope segments would not be the same. From a slope stability view
point each inter-ramp segment would be examined separately.
50
4x35 ' 5 tan75 O ' 125'
The working bench is treated in the same way as a ramp in terms of interrupting the slope.
Therefore from following figure, two inter-ramp angles are shown:-
1 y
θIR 2 tan
x
; As; Y = 250 – 50 = 200 feet and
50
1 200 X 3 x 35 4
θIR 2 tan tan75O
158.6'
X 105 53.6 158.6'
θIR 2 51.58O or 51.6 O
As; for the above inter ramp angles, the inter ramp heights are ,
H1= 50’ and H2 = 2’
• R = resisting force;
• C = cohesion,
φ
• = friction angle.
• Wcosß= normal force
• Wsinß= driving force
• A= Area of the failure plane.
F cA Wcos β tanφ
Wsin β
If there is water present then;
Wsin β V
where,
U= water pressure along potential failure
surface, φa = friction angle (affected by
water), V= force along potential sliding plane.
H 100 sin B
as, b b
100
b 130.54feet
or 0.766
sin110
17040.692
0.279
2375.62 ft 2
V 2375.62 1ft3
(W) Weight of sliding block is = volume × unit weight
W V γ 2375.62 160lb/ft 3
W 380099.2lbs
As
F Wcosβcosβ cA
Wsinβ
A= Area of the failure plane, and
A= length of failure plane × thickness
A= b × 1ft= 130.54ft × 1ft
A= 130.54ft2
1600
291172.88
Engr. Izhar Mithal Jiskani - 32 -
SURFACE MINE DESIGN AND PRACTICE
F
F 1.2
X 2
i β β φ 2
70 50 50 30
2
X Slope angle function 400
or X 40
Y slope height function γγH/
Y 160 100 /1600
Y 10
ii. iii.
Example 02:
Determine the limiting pit slope angle (i) using the following data:
β500
i. Inclination of failure plane
φ350
Angle of internal friction
Cohesion = C 7800kg m3 γ
2.5tons m3
Height of slope = 150m
Solution:
c 7800 7.8
Y 48.07
From the slope design chart, at Y=48 and S.F = 1.0, X=18
:. We know that X 2 i
750
18 2 i 50 50 35 2 13i
Now, squaring both sides
2 2
18 2 15i 750
324 4 15i 750
324 60i 3000 60i
324 3000 3324
i 55.40
i 55.40
iv.
v.
Example 03:
Determine the height of slope using the following data.
β500
Inclination of failure plane
350
Angle of internal friction
Cohesion c 7800kg m2
γ 2.5t m3
Unit wt: of rock ;
Safety factor = S.F = 1.4;
Sol:
X 2
i β β φ 2
65 50 50 35
2
15 15 2 255 2 15
X 300
By using the graph of “slope design chart for plane failure including various safety factors”
Y H,
:. As c
H c 16 7800 49.92m Y
γ 2.5 H
49.92m
v. vi.
1
Area of Arc ‘AB’ = Rθ
Mc = (Area of Arc) × (cohesion) × (R)
Rθ C R Mc
CR 2θ
as, Mw+Mc= 0
wd CR 2θ 0
wd CR 2θ
CR 2
θ
or S.F
wd
If the portion is in equilibrium state, it
is stable, and will not slip down.
Example:
A cutting in saturated clay inclined at a slope of 1 ver vertical height of 10.0 m. the bulk unit weight of soil
cohesion is 40 KN/m2. Determine the safety factor against immediate shear failure along the slip ticalcircle
and 1.5
as sh
Soln:
1 vertical Slope
1.5 horizontal S
18.5KN m3
C 40KN m2
Figure 23
SURFACE MINE DESIGN AND PRACTICE
5m θ1 Tan 1
16.7m
θ1 16.70
According to Pythagoras theorem,
R2 5 2
16.7 2
25 278.9 303.0
R 303.9
R 17.43m
φ
1 ?; since given slope of cutting plane “ad” is 1 vertical and 1.5 horizontal;
φ1 Tan 1 1 1.5
φ 900 φ 1 θ1
900 33.7 0
16.7 0
39.60 φ 39.60
6.7 cosθ 2
17.43
θ2 cos 1
0.384 θ2
θ φ
Δaod Δ1 1 R2 sin sin
Area of 2 sinΨ
Δ1 115.85m 2
In order to find the area of bcd , we must know any one side of bcd . Let’s find “DB”
Ap 120.62m2
1 2
2 180
aoc R
0
(as) Area of sector
As 17.43 84.1
0 π
12 180 0
As 222.86m2
V 102.24m3
W 102.24 18.5
W 1891.44KN CR
2
θ
S.F
Wd
40 17.43 2 80.10 π
S.F 1800
1891.44 6.54
S.F 1.44
STRIPPING RATIO
Figure 24 (a)
Vm = Vol. of mining
Vc = Vol. of cone
VT = Vol. of truncated portion
:. Vm = Vc- VT
Fig. 24 (b)
As we know that;
1 πr 2h
Vol: of cone= 3
πr h
Vo= 2 ……… (1)
Volume of (small) truncated tip of cone; VT
1 2
3
VT πr Δh…… (2) (:.) Height of small cone is ∆h). and Δh γtanθ
as height of big cone, is Hc;
and Hc h Δh
or Hc h γtanθ
2
Hc 1 πr 2 h Δh
Vc πR
3
or Vc πR 2 h γtanθ (3)
:. Mined Vol: Vm VC VT
1 2
Hc 1 πr 2Δh (4)
Vm πr
3 3
Vol: of waste: Vw Vm V0
Ww
Vw
SR (6) SR
V0 W0
or
Example:
A cylindrical ore body with radius of 50m and Depth of 250m is to be excavated by
developing a cone. Slopes of the sides of the cone with the horizontal are 550. Unit weight
of the ore is 3.1 tons/m3 and that of the waste rock is 2.6 tons/m3.determine the stripping
ratio (SR).
Solution
R H C0 13 2 H c R 321.4Tan55Tan550
VC πR
VC 17044879.24m 3R 225.04m
VT 1 πγ 2 Δh
3
VT 186924.76m 3
Vm VC VT 17044879.24 186924.76
Vm 16857954.48m 3
VW Vm VO 16857954.48 1963495.4
VW 14894459.08m 3
S.R
W waste Vw γw 14894459.08 2.6
S.R 6.36
S.R
Vo γ o 1963495.4 3.1
W ore
DETERMINATION OF “SR” BY AREA METHOD
50 50 1250ft
Area of Sec: (i) = 2
Area of Sec: (ii) = 100 50 5000ft 2
Aw 10000
S.R 0.36
Ao 275000
S.R 0.36
Ao2 50 2 50 2 25 70.71 25
Ao2 1767.75ft 2
PIT LIMITS
The minable material becomes that lying
within the pit boundaries. A vertical section
taken through such a pit is shown in figure A:
With an increase in price, the pit would expand in size assuming all other factors remained
constant.
The “pit” existing at the end of mining is called the “final pit” or the ultimate pit. In b/w
the birth and death of an open pit mine, there are a series of intermediate pits. This includes
a series of procedures based upon:
• Hand Methods,
• Computer Methods, and
• Computer assisted hand methods
The above mentioned methods are used for developing the pit limits. Within the pit
materials of differing values are found. Economics criteria are applied to assign destination
for these materials based on their value (i.e. mill, waste dump, loach dump, stock pile etc).
Once the pit limits have been determined and rules established for classifying the in pit
materials, then the ore reserves (tonnage and grade) can be calculated.
Cut-off Grade:-
The grade at which the mineral resources can’t longer be processed at a profit.
Example:
Determine the pit limits of an open pit mine as shown in figure: setting price of 1m3 of Ore
is US$ 1.9 and mining cost of 1m3 of waste is US$ 1.0.
Sol:
For Strip # 01:-
Vo 1 5 1.25 1
Vo 6.25m3
Vol: of ore (Strip 1) 1
1
Vw 1 6.364 1.25 1 1.25 1.25
2
Vw 8.74m3
Vol: of waste (Strip 1) 1
Ins (S.R)
For Strip# 03
Vo 3 6.25m3
2
Vw 3 8.864 1.25 1 12 1.25
Vw 3 11.86m3
Vo 4 6.25
As can be seen that the net value changes from (+) to (-) as the pit is expanded, sometimes the N. V
become zero, so that this pit position is termed as “Break-even”, which is the location of final pit wall.
Δw 9.9 9.9
49m 2 thickness 1
overall vol: of waste 49m 3
5 5 1
49.5 12.5 1m
overall vol: of ore 62m 3
The ore is containing 0.55%, All the costs and revenues will be calculated in terms of 1 ton
of ore. Note that ore short ton= 2000 lbs.
Solution:-
Step # 01:- Complete the amount of saleable copper (lb/s per st of ore)
RM 11lbs 8.8lbs
Σ
i 1 gi di
n
Σ i 1 idi
Where, gi= given grade of ore at a point.
g= estimated grade of ore. di= distance b/w
known point and point of estimation.
Example:
Calculate the estimated grade of ore at point “C”, using inverse distance technique.
Known grades of an ore at points C1-C6 ore shown in fig: [in brackets]
Sol:
First let’s estimate the value of distances d1, d2...d6 by using Pythogona’s theorem.
As we know that; g g1 g 2d 2
g 6d 6 d1
1 1 d2
6 d6 d1
1316.23
1
0.0100
g g 4.484 10
0.0223
:. The estimated grade of ore =g g
= 0.45 %
Using this technique, the grade of ore is found, by using following equations.
n
gi
Σ i 1
di 2 g n
Σ i 1 di 2
Using the data of previous example; calculate the grade of ore by squared weighting
technique.
d1 282.84m ---------- d12 79998.4656m 2 d 2
2 2
316.23m ---------- d 2 100001.4129m d3
2 2
282.84m ---------- d 4 79998.4656m d5
g5 g6
g1 g 22 d 52 d 62
g d12 d2
1d12 1d 2 2
1d 5 2 1d 6 2
3.5885 10 5 g
8.5003 10 5
g 0.422%
x3 x1 y2 y1
12 x3 x2 y2 y3 1
x3 x1 y2 y3
x3 x1 y1 y3
Example:
Calculate the above of ΔA by using ore reserve estimation:
1100 1200
1500 1200
1100 800
Solution:-
Let
1
2
OR
1
2
1
2
0 16000 0
160000
A 80,000m2
ΔA b h
400 400
160000
ΔA 80,000m 2
Example:
Calculate the ore reserves in area, as shown in following figure. Density of the ore is
given as 2.5 tons/m3
Solution:-
As we know that:
ΔA 145000m 2
C1 C2 C3
t av: 3 5 4 12 4m
2 3
t av: 4m
Σtigi i 1n
- - - - - - - (1) Σti
:. Average thickness = (tav:) i 1
t av: 0.6 0.59 1.4 0.48 1.4 0.6 1.4 0.56 1.3 0.32
Calculate the reserves of ore shown in above fig: having a density of 1.35 tons/m3 by using
the weight age average thickness, when; t1=40m, t2=60m, t3=50m Solution: the weight
age average thickness is calculated as:
t1 θ1 t 2θ 2 t θ
3 3
3
t w 60 (1) from above
fig :
tw 60 3
9138.5
60
tw 3
tw
tw = 50.77 m
Solution:
As we know that
Rd = Re + So
.: Re = Rd – So -------> 1 and So = 0.75 Et.
Re = 47 – (0.75 Et)
Re = 47 – (0.75 ×11)
Re = 47 – 8.25
Re = 38.75 m
H
18.2
H