Академический Документы
Профессиональный Документы
Культура Документы
versus
JAIPRAKASH POWER VENTURES LTD.
..... Respondent
Through: Mr. Shanti Bhushan, Senior Advocate
with Mr. Vishal Gupta and
Mr. Mukesh Pandit, Advocates.
CORAM: JUSTICE S. MURALIDHAR
JUDGMENT
15.05.2012
Background Facts
2. Jaypee Karcham, the predecessor-in-interest of JPVL, a generating
company within the meaning of Section 2 (28) of the Electricity Act,
O.M.P. 677 of 2011 Page 1 of 43
2003 (‘EA’) was incorporated on 29th April 2002 for implementing
the project comprising of four units of 250 MW each. On 31st March
2003, the Central Electricity Authority (‘CEA’) under Section 4(b) of
the Electricity Supply Act, 1948 (‘ESA’) granted Techno-Economic
Clearance (TEC) to the project at an estimated capital cost of US
Dollar (‘USD’) 117.44 million (Rs.5345.88 crores @ 1 USD = Rs.48).
One of the conditions of the TEC was in Clause (xviii) which stated
that the “tariff shall be decided by the Central Electricity Regulatory
Commission (‘CERC’)”. Under Clause 9 of the TEC in the event that
the time gap between the TEC by the CEA and the actual start of work
of the project was more than three years, a fresh TEC of the CEA had
to be obtained before actual start of work.
3. Under the PPA entered into between the parties, Jaypee Karcham
was to sell and the Petitioner was to purchase 704 MW gross capacity
and corresponding energy from the project at the Project Bus Bar for a
period of 35 years from the Commercial Operation Date (‘COD’) of
the project for onward sale on a long term basis. The Petitioner is a
trading licencee which meant that it is engaged in the trading of
electricity by purchasing all forms of electric power from independent
producers, captive power plants and other generating companies for
sale to electricity boards, power utilities, transmission companies and
other organisations buying power whether in the private or the public
sector. In terms of the recital ‘E’ of PPA, the Petitioner was to enter
into suitable arrangements with one or more purchasers for sale of the
contracted power from the project. A condition precedent was set out
in Article 3.1.3 (iv) of the PPA in terms of which the Petitioner was to
execute a Power Sale Agreement (‘PSA’) with the purchaser approved
by the appropriate Commission for the entire contracted power and
11. Lanco then appealed to the APTEL against the order dated 6th
May 2008 of the MPERC. While PTC opposed the appeal, it
conceded that MPERC could not have directed Lanco, a generating
company, to apply for the fixation of tariff for supply of electricity to
PTC, which was a trading licencee. Following its earlier decision in
Gajendra Haldea, the APTEL allowed the appeal and set aside the
order dated 6th May 2008 of MPERC. The contention of Madhya
Pradesh State Electricity Board (‘MPSEB’) that MPERC had
jurisdiction to fix tariff under the PPA by virtue of the clause in the
PPA whereby the parties had agreed that Lanco would file a petition
before the appropriate Commission for approval of the tariff was
rejected by holding that SERC derived jurisdiction only from the EA
and that parties could not by agreement confer jurisdiction on the
SERC.
12. On 9th April 2009, the Supreme Court gave its decision in Central
Electricity Regulatory Commission v. Gajendra Haldea (2009) 11
16. The Petitioner by its letter dated 13th January 2010 protested
against the above decision of Japyee Karcham. It filed OMP No.25 of
2010 in this Court under Section 9 of the Act for seeking an ad
interim stay of termination of the PPA by Jaypee Karcham and to
restrain Jaypee Karcham from entering into an agreement for sale of
power with any other party.
17. By an order dated 19th February 2010 this Court dismissed the
said petition on two grounds. The first was that Clause 13.3 of the
PPA did not constitute a negative covenant and, therefore, no relief
restraining Jaypee Karcham from either terminating the contract or
from entering into another sale agreement with any third party could
be granted. The second was that the Petitioner could be compensated
in terms of money under Clause 14.6.1 of the PPA. Therefore, in view
of the bar under Section 14(1)(a) to (d) read with Section 41 of the
Specific Relief Act, 1963 the petition was dismissed.
18. Aggrieved by the above decision, the Petitioner filed FAO (OS)
No.146 of 2010. By a detailed judgment dated 13th August 2010, the
Division Bench of this Court dismissed the appeal. In the concurring
opinion of Justice Mool Chand Garg, there was a discussion on the
24. Mr. Tripathi submitted that the EA was a special law which
overrode the general law. Reliance was placed on the decision in the
GUVNL case which held that all disputes between a licencee and a
generating company can be adjudicated either by the CERC, the
SERC or by an Arbitrator to whom such disputes are referred to by
the CERC, and not by a Tribunal appointed under the Act. Reference
was also made to the decision of the APTEL in Appeal No.200 of
2009 [M/s. Pune Power Development Private Ltd. v. Karnataka
Electricity Regulatory Commission] (hereafter Pune Power case) and
Review Petition No.6 of 2011 in Appeal No.184 of 2010 [Adani
Power Limited v. Gujarat Electricity Regulatory Commission]
(hereafter Adani Power case). It is pointed out that the very basis of
the earlier judgments of the APTEL in Gajendra Haldea, Lanco-I
and Lanco-II was taken away by its subsequent decision dated 4th
November 2011 in Appeal No.15 of 2011 in Lanco Power Limited v.
Haryana Electricity Regulatory Commission (hereafter Lanco-III) in
which the APTEL held that a transaction involving supply by a
generating company through a trader to a distribution licencee is not
outside the purview of the EA and that the appropriate Commission
has the jurisdiction to determine tariff. The APTEL in arriving at that
conclusion took note of the decision of the Supreme Court in Tata
Power Company Limited v. Reliance Energy Limited (2009) 16 SCC
25. Mr. Tripathi submitted that the power to ‘regulate’ under Section
86(1) (b) of the EA included the power to ‘determine’. Referring to
the decision in Booz Allen and Hamilton Inc. v. SBI Home Finance
Limited (2011) 5 SCC 53 it was submitted that disputes where rights
in rem were involved were not arbitrable and amenable to private
arbitration. It is submitted that the observation in Para 4 (x) of the
SOR of the EA which stated that in a direct commercial relationship
between the consumer and a generating company or a trader the price
of power would not be regulated, meant a transaction of direct transfer
of electricity from either the generating company to the consumer or
from a trader to the consumer. Where the trader was selling electricity
to the distribution licencee which was eventually supplying it to the
consumer, the tariff would be amenable to regulation.
27. Mr. Tripathi submitted that even assuming that CERC had
refused to approve the tariff, the parties could have done so in terms
of Schedule E of the PPA. In the instant case it was Section 9 of the
Sale of Goods Act, 1930 (‘SGA’) and not Section 10 which would
have applied. Relying on the decision in The Instalment Supply Ltd.
v. S.T.O., Ahmedabad-I (1974) 4 SCC 739 it was submitted that the
term ‘contract of sale’ defined in Section 4 (1) SGA included an
‘agreement to sell’ which was a sub-species of a contract of sale to
which Section 9 or Section 10 might apply depending on the facts and
circumstances.
30. Mr. Bhushan next submitted that a dispute whether a contract for
supply of electricity by a generating company to a trading licencee
became void or not was not covered by Section 79(1)(f) of the EA,
and therefore, was outside the purview of the functions of CERC
regarding adjudication of disputes. Since in the present case, the
Petitioner was an inter-State trading licencee, the question of
applicability of Section 86(1)(f) also did not arise. Relying on the
decision of the APTEL in Lanco-II it was submitted that the word
‘licencee’ in Section 86(1) (f) referred to only a licencee which has
been granted a license by the SERC which claims to have the
jurisdiction to decide the dispute and not a licencee which has been
granted a license either by some other SERC or by the CERC. Since
the dispute in the present case was between a generating company and
an inter-state trading licencee which has been granted trading licence
by CERC and not by any SERC, no SERC would have jurisdiction to
32. Mr. Bhushan referred to paras 4 (ix) and (x) of the SOR and
submitted that in terms thereof a trading licencee was supposed to be
regulated by fixation of ceilings on trading margins if necessary as
provided in Section 79 (1) (j) and Section 86 (1) (j). It showed that
neither the purchases nor the sales made by a trading licencee would
be subjected to the determination of tariffs. This was why it was
necessary to fix trading margins in their case. If the tariff on which a
trading licencee would purchase electricity was also to be determined
by a regulatory commission and when it sold it to a distribution
licencee was also required to be determined by the regulatory
commission there would be no reason to fix any ceiling on trading
margin. Clause (x) further made it clear that every sale by a
generating company or a trader was not subjected to the power of
regulating the tariffs. It showed that when a generating company
directly sold to a consumer or a trader directly sold to a consumer, the
O.M.P. 677 of 2011 Page 18 of 43
tariff would not be regulated at all and only the transmission and
wheeling charges would be regulated. This system had ensured that no
surplus power available anywhere in the country would go unutilized
and any big consumer requiring such supply could get it by entering
into an agreement with a trader. The trader would keep information
regarding the availability of surplus energy anywhere in the country
and could also be contacted by a consumer needing electricity. In
such cases the EA intended that the price should be fixed by the seller
and the purchaser by private negotiations on the basis of market forces
and not be regulated by any statutory authority. Considering that the
determination of tariffs required an elaborate procedure, it was
contemplated for long term and not short term requirement. .
Reliance is placed on the decision of the ATE in Gajendra Haldea
and Lanco-I and of the Supreme Court in Tata Power Company Ltd.
v. Reliance Energy Ltd. and in particular to the observations in Para
83.
33. Mr. Bhushan submitted that the majority Award suffered from no
error and even if there was an error in interpretation of the clauses of
the PPA or of the provisions of the EA, that by itself did not permit a
challenge to the Award under Section 34 of the Act. Relying on the
decision in Oil & Natural Gas Corporation Ltd. v. Saw Pipes Ltd.
(2003) 5 SCC 705, he submitted that the impugned Award could not
be set aside unless it was opposed to the public policy of India which
meant that it should be patently illegal and the illegality should go to
the root of the matter.
35. On the basis of the above submissions, the following issues arise
(ii) Whether the dispute which was the subject matter of the
impugned Award could be adjudicated by CERC alone or was
it an arbitrable dispute that could be examined by the Tribunal?
42. It was contended by the Petitioner that Section 4 of the Act would
apply only in respect of a non-derogatory provision in an arbitration
agreement and where non-compliance alleged is not in Part-I of the
Act but a mandatory provision relating to the jurisdiction under the
EA. Reliance was placed on the observations made in Inder Sain
Mittal v. Housing Board, Haryana (2002) 3 SCC 175 wherein it was
held that where a ground was based upon the breach of a mandatory
provision of law, a party would be estopped from raising the same in
the objection to the Award even after participating in the arbitration
proceedings in view of the well settled maxim that there is no estoppel
against statute. While it is true that parties perhaps can raise such a
ground even after participating in the proceedings, clearly it has to be
raised in good time i.e. within the period of limitation provided under
Section 34(3) of the Act. Otherwise, the party would be precluded
from raising the objection as to the jurisdiction under Section 34 of
the Act.
43. For the afore-mentioned reasons, this Court decides Issue (i) by
holding that the Petitioner cannot challenge jurisdiction of the
Tribunal to decide the dispute between the parties referred to it since
the Petitioner failed to raise such objection before the Tribunal itself.
Issue (i) is decided against the Petitioner.
47. It was contended by the Respondent that Article 15.2 of the PPA
states that the agreement was solely for the benefit of the parties and
their successors and was not to be construed as creating any “duty,
standard of care or any liability towards any third person”. However,
with the goods in question being electricity which is not meant for
consumption by the purchaser of the electricity but for onward sale by
the trading licencee to distribution companies and ultimately to the
consumers, the above interpretation that Article 15.2 does not create
rights in rem is not correct.
49. However, such an objection not having been raised at the relevant
stage before the Tribunal, this Court does not wish to permit the
Petitioner to raise this issue in the present proceedings. In other
words, this Court does not permit the Petitioner to assail the impugned
Award on the ground of lack of jurisdiction of the Tribunal. However,
this does not mean that in an appropriate case such a challenge would
not be entertained by the Court if properly raised by way of ground
under Section 34 of the Act. Issue No.(ii) is decided accordingly.
52. In order to examine the above issue, first the relevant portion of
the SOR to the EA requires to be referred to. Paras 4(ix) and (x) of the
SOR acknowledge that under the EA, trading in electricity was for the
first time being recognized as a distinct activity. The said clauses read
as under:
“(ix) Trading as a distinct activity is being recognized
with the safeguard of the Regulatory Commissions
being authorised to fix ceilings on trading margins, if
necessary.
53. A careful reading of Clause 4(x) of the SOR shows that it talks of
direct commercial relationship between (i) a consumer and a
generating company; (ii) a consumer and a trader. In the chain of
supply of electricity, it is possible that a generating company makes a
direct supply to a consumer. Sometimes, a trader could also be an
intermediary in the supply by the generating company to the
consumer. Such supplies would not be regulated by the appropriate
Commission. Where there is a direct transfer of electricity from either
the generating company to the consumer or from a trader to the
O.M.P. 677 of 2011 Page 30 of 43
consumer then the tariff would not be subject to regulation. However,
where a trader or trading licencee sells electricity to a distribution
licencee which in turn supplies to the consumer, the tariff would be
subject to regulation.
(2) to (4)…
(d) to (e)….
(2) to (4)…….”
57. The argument that wherever there is surplus power which might
be unutilized and there is a big consumer requiring such supply it can
get it by entering into an agreement with the trader, does not really
answer the situation where such trader has entered into an agreement
with a distribution company for supply to the consumer. Where a
trader has a direct supply to the consumer then again there may be a
situation where such a transaction may be unregulated within the
scope of Section 62. But in a situation where a trader is selling such
electricity to a distribution company through PSAs then Section 62
would apply. Fixation of trading margin by itself may not completely
ensure that electricity is available to the consumers at a reasonable
60. The Supreme Court in the above case was concerned with the
61. It cannot be debated that the whole scheme of the Act is that
from the very generation of electricity to the ultimate
consumption of electricity by the consumers is one
interconnected transaction and is regulated at each level by the
statutory Commissions in a manner so that the objective of the
Act are fulfilled; the electricity industry is rationalized and also
the interest of the consumer is protected. This whole scheme will
be broken if the important link in the whole chain i.e. the sale
from generator to a trading licencee is to be kept outside the
regulatory purview of the Act. If such a plea of the Appellant is
accepted, the same would result in the Act becoming completely
ineffective and completely failing to serve the objective for
which it was created.
63. Indeed, as has been observed by the APTEL in the Pune Power
case, the nature of the licencee i.e. inter-State or intra-State, is not of
relevance for the purpose of exercise of jurisdiction by the appropriate
Commission. Under Section 86(1)(f) all disputes relating to the
regulatory jurisdiction of the SERC which involve a distributing
licencee or a trading licencee or a transmission licencee has to be
adjudicated exclusively by SERC. Under Section 2(39) of the EA a
‘licencee’ means a person who has been granted a licence under
Section 14. It only depends on whether the transaction of sale of
64. The Tribunal in the present case did not discuss the changed legal
position as a result of the decisions of the APTEL subsequent to
Gajendra Haldea and Lanco I in light of the altered decisions of the
Supreme Court including the one in the GUVNL case. It went by
only a literal and not a purposive and contextual interpretation of
Section 62 EA. The majority of the Tribunal was, therefore, in error
in holding that the transaction involving supply by a generating
company to a trading licencee was outside the purview of regulation
by the CERC under Section 79(1)(f) read with Section 62 of the Act.
Conclusion
67. As a consequence, the majority Award dated 28th April 2011 is
S. MURALIDHAR, J.
MAY 15, 2012
s.pal