Вы находитесь на странице: 1из 15

Detail Project Report

1MWp SPV Power Plant

Assumption & Consideration

Shading consideration: No shading has been considered at the site during the calculation design. So it is advised that at
the time of execution, please check whether there is any kind of obstacle in the site which may cause partial/full shading
on PV strings and/or PV array. If the shading occurs, then the estimated power generation will not match the actual
power generated.

Load Factor: It is assumed that the produced power from the PV plant will be fed to the local utility grid. So, while
designing the system, no unbalanced load considered in 3 phase configuration.

Meteo data: The calculation based on the meteo data collected from Google satellite which is very reliable. Now, based
on the co-ordinates the values have been presented in this report. So, total design is based on this data.

Site consideration: this design has been done by considering the PV modules & array will be ground-mounted and the
site-elevation angle taken 30.

Cost Estimation: 1MW Solar PV power plant cost estimation is $1 000 000 000 USD. We can confirm our system will be
commissioned at ……………………………..USD.

CAD design & layout: I have not uploaded/attached the CAD design. If anybody interested in setting up the plant, then
only contact at the given e-mail ids to get the design file. Transmission & wheeling losses: Here, in this report, while doing
the technical assessment, the distance from nearest substation to the 1MW solar PV power plant taken within 15 KM and
so the wheeling losses considered as 3% of total power transmission. And in the financial assessment, no wheeling
charges have been considered.

Design Criteria: While designing & estimating the technical components & solutions, all the required/applicable standard
design codes have been considered, in particular the IEC (International Electro technical Commission) Codes, IS codes
from BIS.

www.renewpowerzone.in Page 1
Client Details
Country Zimbabwe
Location Chegutu
Contact ID
Contact
Person Eng Mhonde
Company CGM
Power generation for Poultry Processing
Purpose Enterprise

Project Details
Type of installation Grounded Mounted
Estimated array peak hour 1100KWp

Shading Considerations Shade free


Grid Voltage 11kV
Phase Connection 3-Phase
Grid Frequency 50Hz
Available / required area 2Ha
Safety Level IP65

Site & Meteo Details


Location
Coordinates Longitude: 13°03'35'' south
Latitude: 30°01'21'' east
Altitude: 1150m
Ambient Temperature © Max Average Min
28.5 27.2 25.5
Relative Humidity 72.50%
Daily Solar irradiation -Horizontal 5.19KWh/m2/day
Atmospheric Pressure 100.1KPa
Wind Speed 2.7m/s
Max Average Min
Earth Temperature 29.6 28.8 26.4
Height from sea level 10m

www.renewpowerzone.in Page 2
SITE LOCATION / LAYOUT

www.renewpowerzone.in Page 3
www.renewpowerzone.in Page 4
Performance Ratio (PR)
Normalized Production & Loss factor

Daily System Output Energy SPV Array Power Distribution

www.renewpowerzone.in Page 5
1MWp SPV Power Plant

Detail Project Report MWp SPV Power Plant

Overall Power plant performance Summery


Total no. of PV modules 4326 (250Wp)
Total nos. of Inverters 53 (20KW)
Max DC input per Inverter 21KW
Nominal PV power 1082 KW p
Max. PV power output 1027 KWdc
Nominal AC power 1060KWac
Max operating power @ STC 962KWac
Max operating power @Ambient Temp. 1027KWac
Plant production 1655 MWh/year
Specific production 1526KWh/KWp/year
Normalized production 4.2 kWh/KWp/day
Array losses 0.87 KWh/Kp/day
Overall losses 0.22 KWh/KWp/day
Performance ratio
0.80

www.renewpowerzone.in Page 6
1MWp SPV Power Plant
Time line of the project

• Preparation of design & estimation of the plant


• 15 working days required.
Design

• As per design requirement, proper land selection & acquisition processed.


Land • Time required 1 month
acquisition

• Power Purchase Agreement(PPA) with private power purchaser need to be finalized at a feasible rate.
• Required time is 15 working days
PPA

• Preparation of Detailed Project Report including technical feasibility of the project prepared.
• Time required 6 working days.
DPR

• Arrangement of finance/fund for the project from nationalized or private financing agency with significant interest rate
and equity share will be finalized.
finance • Required time for this stage is 1 month.

• After finalizing PPA and arrangement of fund for the project, procurement work starts including preparation & finalizing of
vendor selection, BOM, BOQ, order placing, follow-ups of delivery to site/warehouse.
procurement • Estimated time for this step is 1 month.

• After the processing of procurement, first civil construction at the site starts for PV mounting structure set-up and
control-room, administrative building. Finishing the civil works, PV installation & all electrical construction works including
the Grid Evacuation will be processed.
constructio n • Estimated time for this whole work is 2 months.

• Commissioning of the plant by authorized govt. body or certified 3rd party will be done followed by Completion of project
execution.
commissio n • required time for this step is 6 working days.
ing

Page 20
1MWp SPV Power Plant
Operation & Maintenance of Plant
Why do we need an O&M for Solar PV power plant?
As every plant needs a regular maintenance work to make it functional & in well-condition, so
in this case also, a PV power plant also requires a sound & efficient operation & management
team to perform all the work after plant commissioning.

Page 21
1MWp SPV Power Plant
Financial Analysis & feasibility
Initial Investment in terms of components’ cost & service charges

Sl. Components/services Total cost Remarks


No. (in USD)
1. Solar PV modules 403 000 4rs/Watt peak
2. Solar inverters 160 000 11rs/Watt peak
3. Protective devices 12 000 From international vendor
4. Wires/Cables 15 000 Considering IEC codes & ISO
certified
5. SCADA/RMS 11 000
6. Project execution & commissioning 18 000
7. Construction works 42 000
8. Grid evacuation 10 0000 Assumed because of having
no sufficient data
9. Other official works 7 000 Subject to change as per
rules
Total Project investment 678000 USD

Total expenses over the year for plant O&M and staffing = 15,000
This expense is considered for regular maintenance cleaning of PV array, checking the status of
inverter, cable-fault checking, emergency maintenance & replacement of components and
annual salaries of O&M team of the plant.

Loan Interest rate is @12% over 70% of total project cost which shall be completed within next
7 years (the rest 30% as equity shares).

Estimated time period 7 years 10 years


Total Loan amount 439 600.00 439 600.00
Interest rate 12% 12%
EMI
Monthly interest
total Interest paid

*all the amounts are considered in USD currency.

Page 22
1MWp SPV Power Plant
Detailed Analysis of Installment, EMI, Interest of the 70% project
finance/fund
Sl. Installments EMI Monthly principle Monthly Interest
No.
1) 0
2) 1
3) 2
4) 3
5) 4
6) 5
7) 6
8) 7
9) 8
10) 9
11) 10
12) 11
13) 12
14) 13
15) 14
16) 15
17) 16
18) 17
19) 18
20) 19
21) 20
22) 21
23) 22
24) 23
25) 24
26) 25
27) 26
28) 27
29) 28
30) 29
31) 30
32) 31
33) 32
34) 33
35) 34
36) 35
37) 36
38) 37
39) 38
40) 39

Page 23
1MWp SPV Power Plant
41) 40
42) 41
43) 42
44) 43
45) 44
46) 45
47) 46
48) 47
49) 48
50) 49
51) 50
52) 51
53) 52
54) 53
55) 54
56) 55
57) 56
58) 57
59) 58
60) 59
61) 60
62) 61
63) 62
64) 63
65) 64
66) 65
67) 66
68) 67
69) 68
70) 69
71) 70
72) 71
73) 72
74) 73
75) 74
76) 75
77) 76
78) 77
79) 78
80) 79
81) 80
82) 81
83) 82
84) 83
85) 84

Page 24
Net Cash Flow/year Estimation (all amounts are in USD)
Initial Investment 439 600.00
Expenses for O&M per year 15 000.00
Total amount paid/year for loan(7 years term
considered)
Tolerance factor
Total amount to be paid per year
Energy generated per year
PPA rate for next 12 years
REC floor price
Gross cash flow through PPA
Gross cash flow through REC trading
Net Cash Flow (NCF) per year
Detail Project Report
1MWp SPV Power Plant
NET CASH FLOW & PAY BACK PERIOD
Now according to Discounted Cash Flow method (considering @10% DCF)

years Present value of rs.1 @10%


1
2
3
4
5
6
7
8
9
10

So, Pay Back Period= 6 years 1 month (approx.)


Detail Project Report
1MWp SPV Power Plant

Most suitable vendors/suppliers of the project components


Solar PV modules 1. Vikram Solar
2. Waaree Energies
3. Sova Power
4. Canadian Solar
5. Trina Solar
6. First Solar
Inverter 1. Power One
2. SMA
3. Smart Power
4. REFusol
5. Delta
6. Schneider Electric
Transformer 1. ABB
2. Schneider Electric
3. Ascott transformer
4. Voltech
Switch gear 1. Schneider Electric
2. Megawin
DC Disconnect 1. Schneider Electric
Circuit breaker 1. Megawin
2. ABB

SCADA/RMS 1. Draker
Cables 1. Havells
2. Finolex cables
3. RR Kabels
4. Anchors
Isolator 1. ABB
2. Schneider Electric
3. Megawin
Detail Project Report
1MWp SPV Power Plant
THANK YOU

Вам также может понравиться