Академический Документы
Профессиональный Документы
Культура Документы
1. Purpose of Estimate
Provisional of Prelim construction cost indication
Control of Resources Allocation
Cost study for alternatives schemes
Benchmarking of construction costs for similar projects
Particular to clients
Test viability of project
Seek funding from banks etc.
Set a limit on expenditure
Establish a scope which can be achieved for a specific level of investment
Negotiation with landlords – fitting out
Taxation – capital allowances
Particular to consultants
Ensure design ideas can be afforded
Ensure correct allowances are included for intended spec
Understand the budget so they can work within it
Fee calculation
Design / spec comparisons.
2. Definition of GFA, CFA, UFA , LFA & Fit out areas (Refer to DLS manual)
indication and
systems provided
(C) Scheme Prepare cost Plans, elevations Cost Plan - Elemental form based
upon App Qty priced at
Design plan & detailed & sections; current rates + data from
cost analyses for items
cost studies in Framing plans;
which cannot be quantified
order to confirm Foundation at this stage of the planning
cost limit / budget information;
Finishes level;
Building services
requirement
(D) Design Update cost plan Alternative design Revised - BQ / comparative cost
studies. Progressive
Developme & further cost proposal Cost Plan elemental estimates
prepared at appropriate
nt studies of
design stages as the
alternative planning develops each one
being reconciled with the
designs budget
(E) Tender Cost check of Complete design Pre-tender Reconciliation may be
final design (i.e. tender / cost required
working drawings estimate
& spec)
4. Adv. of element form of cost plan
Summarizes the design and cost characteristics of the project
Acts as a concise reference for subsequent cost checks
Enables rapid assessment of cost for subsequent design or quality changes
Explains why costs are high/low compared with other projects of similar building types (once a
sufficient data bank of projects is available)
Identifies the most fruitful areas to look for economics if these need to be made
Identifies any major measurement errors in the cost plan
Can later be used as a prelim bulk check for the BQ qty. Provides cost data in a form useful for
preparation of cost plan for other projects
Once a data bank of projects has been built up, future cost plans may not need to measure all the
element quantities since they can be derived from element ratios of other similar projects
5. Factors affecting cost estimate / plan
(a) Project information
Completeness of cllient’s brief
Determination of grade of building (3/4/5 star hotel, grade A/B/C commercial bldg)
Procurement (design responsibility)
Building shape
Building size
No. of storey
(b) In order to improve the environmental performance during the construction and throughout the lift
cycle of new buildings, construction of green and innovative buildings should be promoted in
order to encompass the following features:
Adopting a holistic life cycle approach to planning, design, construction and maintenance;
Maximizing the use of natural renewable resources and recycled/green building
materials;
Minimizing the consumption of energy, in particular those non-renewable types; and
Reducing construction and demolition waste.
List of green features that may be exempted from GFA and Site Coverage calculation:
Balcony
Wider common corridors and lift lobby
Communal Sky Gardens
Communal Podium Gardens
Acoustic fins
Sunshades and reflectors
Wing walls, wind catchers and funnels
Non-structural prefabricated external wall
Utility platforms
Mail Delivery rooms with mailboxes
Noise barriers
Communal sky gardens for non-residential building
Note: (1) Not apply to the non-domestic portion of composite buildings
(2) Residential accommodation fro commercial use such as hotel and service apartments
does not qualify for the exemption.
Type B) Total construction costs = Sum of (Elemental Qty) x Elemental Unit Rate
+ Preliminaries (12%) + Contingencies (10%)
(Standard element refer to DLS Practice Manual)
(e) Calculation of Elevation Area (if necessary, e.g. bay window adjustment in residential building,
curtain walling/cladding adjustment in office building)
1) Directly utilize layout plan
2) Alternatively, assume the following wall to floor ratios:
(i) 1 : 1 for residential building
(ii) 0.4 : 1 for office building
(iii) 0.4:: 1 for hotel
(iv) 0.4 : 1 for industrial building
(f) Calculation of Internal Wall Area (if necessary, e.g. non-bearing wall adjustment in intelligent
building)
Assume the following wall to floor ratios:
1) 1 : 1 for residential building
2) 0.5 : 1 for office building
3) 1.5 : 1 for hotel
(g) Indices
Tender Price Index
Building Services tender price index
Labour index
Material index
Consolidated labour & material index
Preliminaries
a) Higher scaffolding costs because of a) Generally no
a) Temporary latrines
higher rates for higher scaffolding difference
b) Safety precautions
b) Traffic for site staff and labour to upper
c) Plant
floors take longer which implies longer
d) Scaffolding
construction period is required and thus
e) Hoisting
costs more
f) Fire fighting
c) Transportation of plant and materials take
g) Removal of water
longer and costs more
h) Temporary drainage
d) More material hoists and passenger
i) Temporary water supply
hoists per tower may be required which
j) Temporary lighting and
may be offset by fewer towers
power
e) More watchman per tower may be
k) Hoarding, screens &
required which may again be offset by
walkways
fewer towers
l) Temporary access and
platform
m) Insurances
n) Surety bond
o) Industrial training and
pneumoconiosis levies
p) Noise control
q) Watchman
Foundation and
substructure
a) Generally bored piles cost more than H- a) Generally no
a) H-piles vs. bored piles
piles under the same loading (Assume difference
b) Pile cap
20~30m; $20/kg for H-pile; $6,000/m3 for
bored piles (12% of footprint under tower
and 5% under podium))
Basement
a) Generally no difference a) Proportionate
a) Excavation
b) Generally no difference in basement reduction in
b) Diaphragm wall vs.
construction method excavation (based
sheet piling
c) Bottom-up vs. top-down method on volume;
c) Structural frame and
$1,800~2,000/m2 for conventional $200/m3)
slab
bottom-up method; $3,000/m2 for top- b) $300/m2 for sheet
d) Waterproofing
down method (due to phased excavation, piling $10,000/m3
e) Dewatering
i.e. longer construction period and for diaphragm wall
f) Geotechnical monitoring
allowance for stanchion ($300/m2) or (1m thick down to
g) E&M services
cofferdam ($100/m2)) bedrock)
d) Generally no difference c) See the left column
e) Generally no difference d) Proportionate
f) Generally no difference reduction in
g) Generally no difference waterproofing
(based on surface
area; $300/m2)
e) Proportionate
reduction in
dewatering (based
on construction
period)
f) Proportionate
reduction in E&M
costs (based on
CFA)
g) Saving in
ventilation, fresh air
supply and smoke
extraction system
for fewer basement
levels (based on
CFA; $450/m2)
h) Saving in lighting
due to natural light
coming from outside
Tower/Podium
a) Columns and structural walls generally a) Proportionate
a) Structural frame and
larger and thicker for higher tower option increase in these
slab
Tower/Podium
a) Thicker glazing at upper floors to a) Proportionate
a) External walls, windows
withstand heavier windload increase in external
and finishes
b) More difficult to work on external walls walls, windows and
b) Roofing
due to heavier windload finishes (based on
c) External works and
c) Proportionate reduction in roofing (based CFA)
landscaping
on decrease in no. of towers; $50/m2) b) Generally no
d) Proportionate increase in landscaping on difference in roofing
podium roof (based on decrease in no. of and external works
towers; $1,500/m2)
Tower/Podium
Plumbing & drainage
a) Two sets of pumps are required to serve a) Proportionate
a) Pumps and sumps
the lower and upper floors respectively, increase in
b) Risers and distribution
i.e. one extra set is required per tower plumbing (based on
pipes
b) More powerful pumps are required to CFA)
c) Valves and accessories
serve the upper floors in the higher tower b) Generally no
d) U/G drainage
option, the cost of which may be offset by difference in design
e) Manholes, pits and
the reduced no. of towers
interceptor
c) Intermediate booster pumps or larger pipe
size for risers at lower floors to maintain
the same flow rate at upper floors
d) Longer risers are to be used due to higher
towers, the cost of which may be offset by
the reduced no. of towers
e) Heavier duty valves and accessories are
to be used under higher working pressure
f) Fewer but larger U/G drain pipes are
required
g) Fewer manholes, pits and interceptor are
required
h) The design is relatively more advanced
and sophisticated
Tower/Podium
Gas
a) Larger pipe size for risers at lower floors a) Proportionate
a) Risers and distribution
to maintain the same flow rate at upper increase in gas
pipes
Tower/Podium
Fire services
a) More powerful pumps are required to a) Proportionate
a) Fire hydrants and hose
withstand higher working pressure in the increase in gas
reel
higher tower option, the cost of which may pipes (based on
b) Sprinkler system
be offset by the reduced no. of towers CFA)
c) Drencher system
b) Intermediate booster pumps or larger pipe b) Generally no
d) Gas floor/BTM system to
size for risers at lower floors to maintain difference in design
transformer
the same flow rate at upper floors
room/computer room
c) Heavier duty valves and accessories are
e) Fire detection
to be used under higher working pressure
d) The design is relatively more advanced
and sophisticated
Tower/Podium
Electrical installation
a) The design is relatively more advanced a) Proportionate
a) Incoming mains
and sophisticated increase in gas
b) Transformer
b) Electrical loading is higher per tower and pipes (based on
c) HV/LV switchgear
hence higher rating is required as per CFA)
d) Emergency generator
transformer, HV/LV switchgear, b) Generally no
e) Uninterrupted power
emergency generator and electrical mains difference in design
supply system
and sub-mains, etc., the extra cost of
f) Electrical mains and
which may not be able to be offset by the
sub-mains
reduced no. of towers
g) Cable trunking and
c) Longer cable trunking is required and
supports
hence more supports per tower
h) Small power installation
d) Saving in lightning protection system due
i) Lighting installation
to the reduced no. of towers
j) Earthing system
k) Lightning protection
system
l) External lighting
Tower/Podium
HVAC installation
a) Air-conditioning available only in entrance a) Proportionate
a) Chillers and chilled water
lobby and hence fewer window-type air- increase in pipes
system
conditioners are required by the reduced (based on CFA) (if
b) Condensing water
no. of tower any)
system
b) Other systems generally not applicable b) Generally no
c) Condensate drain
difference in design
system
(if any)
d) Heating system
e) Air conditioning system
f) Ventilation system
g) Smoke extraction
system
h) Staircase pressurization
system
i) Temperature control
system
j) Boiler plant
k) Acoustic treatment
Tower/Podium
Lifts & escalators
a) Two sets of lifts instead of one are a) Generally no
a) No. of lift cars
required to serve the lower and upper difference
b) Capacity
floors respectively and hence no
c) Speed
corresponding reduction in no. of lifts and
d) No. of stops
no increase in capacity and no. of stops
e) Rise of escalators
($1,500,000/lift car)
f) Finish to lift cars
b) Higher speed for the set of lifts serving
g) Dumbwaiter
the upper floors is required
h) Cover to external
c) Longer conveyor is required for higher
escalator
towers
i) Finishes to escalators
j) Emergency access
hatch
k) Conveyor
Preliminaries
a) Generally similar to Scenario 1.1 a) Generally similar to
a) Foundation and
Scenario 1.1
substructure
b) Basement
c) Floor and ceiling finishes
d) Internal wall finishes
e) External walls, windows
and finishes
f) Curtain walling
g) Cladding
h) Roofing
i) External works and
landscaping
j) Plumbing & Drainage
k) Gas installation
l) Fire Services
m) Electrical installation
n) Lifts and escalators
o) Intelligent backbone
Tower/Podium
a) Proportionate reduction in chiller plant a) Generally similar to
a) Structural frame & slab
room and general finishes (based on Scenario 1.1
b) General finishes
decrease in no. of towers;
$6,000~7,000/m2))
b) Addition of 1 No. refuge floor per 25 floors
per tower ($5,000~7,000/m2)
Tower/Podium
HVAC installation
a) Proportionate reduction in no. of chillers a) Generally no
a) Chillers and chilled water
but higher capacity per chiller is required difference
system
due to heavier loading for higher towers
b) Condensing water
(based on decrease in no. of towers)
system
b) Larger pipe size for chilled water system
c) Condensate drain
to withstand higher working pressures
system
due to longer traveling distance
d) Heating system
c) The design is relatively more advanced
e) Air conditioning system
and sophisticated
f) Ventilation system
g) Smoke extraction
system
h) Staircase pressurization
system
i) Temperature control
system
j) Boiler plant
k) Acoustic treatment
Tower/Podium
Window cleaning
equipment a) Proportionate reduction in total no. of
a) Generally no
a) Gondola gondola and handling unit at roof (based
difference
b) Gondola handling units on decrease in no. of towers)
Tower/Podium
Security system
a) Generally no difference a) Generally no
a) CCTV
difference
b) Door phone
c) Alarm system
d) Carpark control
Tower/Podium
Building automation &
management system
a) Proportionate reduction in computer a) Generally no
a) Computer and
hardware (based on decrease in no. of difference
associated system
towers)
b) ELV system
b) Generally no difference in overall cables,
trunking and conduits
7. Reference
Cost implicating factors
Estimate checklist
DLS practice manual
All Cost Data
All samples