Вы находитесь на странице: 1из 3

Activities Predecessor Duration

(Days)
A. Reconnaissance - 2
B. Surveying Works A 4
C. Planning and Designing of Pipeline / Pontoon Tower B 13
D. Material Purchasing / Pre-fabrication of Materials for Construction - 19
E. Excavation Works C 5
F. Preparation of Gravel Bed at Section G-H D,E 2
G. Installation of Reinforcing Bars for Slabs at Section G-H F 1
H. Pouring of Concrete on Slab at Section G-H G 1
I. Removal of Forms from Slab at Section G-H H 1
J. Installation of Reinforcing Bars for Bottom Bars at Section G-H I 1
K. Installation and Fabrication of Forms for RCP Installations at Section G-H J 1
L. Laying Out of the RCP at Section G-H K 1
M. Collar Works of Joints at Section G-H L 1
N. Fabrication of Forms for Top Bars at Section G-H L 1
O. Installation of Rebars for Top Bars at Section G-H M,N 1
P. Concrete Pouring for Top Bars at Section G-H O 1
Q. Curing at Section G-H P 1
R. Preparation of Gravel Bed at Section F-G Q 1
S. Installation of Reinforcing Bars for Slabs at Section F-G R 1
T. Pouring of Concrete on Slab at Section F-G S 1
U. Removal of Forms from Slab at Section F-G T 1
V. Installation of Reinforcing Bars for Bottom Bars at Section F-G U 1
W. Installation and Fabrication of Forms for RCP Installations at Section F-G V 2
X. Laying Out of the RCP at Section F-G W 1
Y. Collar Works of Joints at Section F-G X 1
Z. Fabrication of Forms for Top Bars at Section F-G X 1
AA. Installation of Rebars for Top Bars at Section F-G Y,Z 1
AB. Concrete Pouring for Top Bars at Section F-G AA 1
AC. Curing at Section F-G AB 1
AD. Preparation of Gravel Bed at Section C-D D,E 4
AE. Installation of Reinforcing Bars for Slabs at Section C-D AD 4
AF. Pouring of Concrete on Slab at Section C-D AE 1
AG. Removal of Forms from Slab at Section C-D AF 2
AH. Installation of Reinforcing Bars for Bottom Bars at Section C-D AG 4
AI. Installation and Fabrication of Forms for RCP Installations at Section C-D AH 3
AJ. Laying Out of the RCP at Section C-D AI 4
AK. Collar Works of Joints at Section C-D AJ 2
AL. Fabrication of Forms for Top Bars at Section C-D AJ 2
AM Installation of Rebars for Top Bars at Section C-D AK,AL 4
AN Concrete Pouring for Top Bars at Section C-D AM 1
AO. Curing at Section C-D AN 1
AP. Preparation of Gravel Bed at Section E-F AC 1
AQ. Installation of Reinforcing Bars for Slabs at Section E-F AP 2
AR. Pouring of Concrete on Slab at Section E-F AQ 1
AS. Removal of Forms from Slab at Section E-F AR 1
AT. Installation of Reinforcing Bars for Bottom Bars at Section E-F AS 2
AU. Installation and Fabrication of Forms for RCP Installations at Section E-F AT 2
AV. Laying Out of the RCP at Section E-F AU 2
AW. Collar Works of Joints at Section E-F AV 1
AX. Fabrication of Forms for Top Bars at Section E-F AV 1
AY Installation of Rebars for Top Bars at Section E-F AW, AX 2
AZ Concrete Pouring for Top Bars at Section E-F AY 1
BA. Curing at Section E-F AZ 1
BB. Preparation of Gravel Bed at Section B-C AO.BA 2
BC. Installation of Reinforcing Bars for Slabs at Section B-C BB 2
BD. Pouring of Concrete on Slab at Section B-C BC 1
BE. Removal of Forms from Slab at Section B-C BD 1
BF. Installation of Reinforcing Bars for Bottom Bars at Section B-C BE 2
BG. Installation and Fabrication of Forms for RCP Installations at Section B-C BF 3
BH. Laying Out of the RCP at Section B-C BG 3
BI. Collar Works of Joints at Section B-C BH 2
BJ. Fabrication of Forms for Top Bars at Section B-C BH 2
BK. Installation of Rebars for Top Bars at Section B-C BI,BJ 2
BL. Concrete Pouring for Top Bars at Section B-C BK 1
BM. Curing at Section B-C BL 1
BN. Preparation of Gravel Bed at Section A-B BM 1
BO. Installation of Reinforcing Bars for Slabs at Section A-B BN 2
BP. Pouring of Concrete on Slab at Section A-B BO 1
BQ. Removal of Forms from Slab at Section A-B BP 1
BR. Installation of Reinforcing Bars for Bottom Bars at Section A-B BQ 2
BS. Installation and Fabrication of Forms for RCP Installations at Section A-B BR 2
BT. Laying Out of the RCP at Section A-B BS 2
BU. Collar Works of Joints at Section A-B BT 1
BV. Fabrication of Forms for Top Bars at Section A-B BT 1
BW. Installation of Rebars for Top Bars at Section A-B BU,BV 2
BX. Concrete Pouring for Top Bars at Section A-B BW 1
BY. Curing at Section A-B BX 1
BZ. Preparation of Gravel Bed at Section X-A BY 2
CA. Installation of Reinforcing Bars for Slabs at Section X-A BZ 3
CB. Pouring of Concrete on Slab at Section X-A CA 1
CC. Removal of Forms from Slab at Section X-A CB 1
CD. Installation of Reinforcing Bars for Bottom Bars at Section X-A CC 2
CE. Installation and Fabrication of Forms for RCP Installations at Section X-A CD 2
CF. Laying Out of the RCP at Section X-A CE 2
CG. Collar Works of Joints at Section X-A CF 1
CH. Fabrication of Forms for Top Bars at Section X-A CF 1
CI. Installation of Rebars for Top Bars at Section X-A CG,CH 2
CJ. Concrete Pouring for Top Bars at Section X-A CI 1
CK. Curing at Section X-A CJ 1
CL. Preparation of Gravel Bed E-Y BA 2
CM. Installation of Reinforcing Bars for Slabs at Section E-Y CL 3
CN. Pouring of Concrete on Slab at Section E-Y CM 1
CO. Removal of Forms from Slab at Section E-Y CN 1
CP. Installation of Reinforcing Bars for Bottom Bars at Section E-Y CO 2
CQ. Installation and Fabrication of Forms for RCP Installations at Section E-Y CP 2
CR. Laying Out of the RCP at Section E-Y CQ 2
CS. Collar Works of Joints at Section E-Y CR 1
CT. Fabrication of Forms for Top Bars at Section E-Y CR 1
CU. Installation of Rebars for Top Bars at Section E-Y CS,CT 2
CV. Concrete Pouring for Top Bars at Section E-Y CU 1
CW. Curing at Section E-Y CV 1
CX. Fabrication of Forms of Pontoon Tower (Base) C,D,E 2
CY. Installation of Forms of Pontoon Tower (Base) CX 1
CZ. Installation of Rebars of Pontoon Tower CY 4
DA. Concrete Pouring on Base of Pontoon Tower CZ 1
DB. Fabrication of Forms for Walling of Pontoon Tower DA 2
DC. Installation of Rebars for Walling of Pontoon Tower DA 10
DD. Installation of Forms (Phase 1)Y DC 2
DE. Concrete Pouring (Phase 1) DD 1
DF. Curing (Phase 1) DE 1
DG. Removal of Forms (Phase 1) DF 1
DH. Installation of Forms (Phase 2) DG 2
DI. Concrete Pouring (Phase 2) DH 1
DJ. Curing (Phase 2) DI 1
DK. Removal of Forms (Phase 2) DJ 1
DL. Installation of Forms (Phase 3) DK 2
DM. Concrete Pouring (Phase 3) DL 1
DN. Curing (Phase 3) DM 1
DO. Removal of Forms (Phase 3) DN 1
DP. Installation of Rebars (Top of Pontoon Tower) DO 5
DQ. Installation of Forms (Top of Pontoon Tower) DP 2
DR. Concrete Pouring (Top of Pontoon Tower) DQ 1
DS. Curing (Top of Pontoon Tower) DR 1
DT. Removal of Forms (Top of Pontoon Tower) DS 1
DU. Joining of Pipeline and Pontoon Tower CW,CK 2
DV. Turn-Over DU,DT 1