Nº P. Insumo/Parámetro Und. Cant. Unit. (Bs) Parcial (Bs)
A MATERIAL 1 - CEMENTO PORTLAND KG 120.00 0.92 110.40 2 - ARENA COMUN M3 0.24 90.00 21.60 3 - GRAVA COMUN M3 0.32 90.00 28.80 4 - PIEDRA BRUTA m³ 0.60 60.00 36.00 5 - MADERA DE CONSTRUCCION PIE2 15.00 9.00 135.00 6 - CLAVOS KG 0.50 15.00 7.50 7 - ALAMBRE DE AMARRE KG 0.50 15.00 7.50 8 - AGUA LTS 120.00 0.03 3.60 D TOTAL MATERIALES (A) = 350.40 B OBRERO 1 - ALBAÑIL HR 5.00 17.50 87.50 2 - AYUDANTE HR 5.00 12.50 62.50
F Beneficios Sociales 0% de (B) = 0.00
G TOTAL MANO DE OBRA (B+F) = 150.00 C EQUIPO 1 - MEZCLADORA hr 0.20 70.00 14.00
H Herramientas menores 0% de (B) = 0.00
I TOTAL HERRAMIENTAS Y EQUIPO (C+H) = 14.00 J SUB TOTAL (D+G+I) = 514.40
L Gastos Generales 0.00% de (J) = 0.00
M Utilidad 0.00% de (J) = 0.00 N PARCIAL (J+L+M) = 514.40 O IVA 0% de (N) = 0.00 P IT 0% de (N) = 0.00 > Q TOTAL ITEM (N+O+P) = 514.40 > PRECIO ADOPTADO: 514.40