Item: HORMIGON CICLOPEO H18 60% P.D. 61.

27 m³
Fecha: 17/sep/2019

Nº P. Insumo/Parámetro Und. Cant. Unit. (Bs) Parcial (Bs)


A MATERIAL
1 - CEMENTO PORTLAND KG 120.00 0.92 110.40
2 - ARENA COMUN M3 0.24 90.00 21.60
3 - GRAVA COMUN M3 0.32 90.00 28.80
4 - PIEDRA BRUTA m³ 0.60 60.00 36.00
5 - MADERA DE CONSTRUCCION PIE2 15.00 9.00 135.00
6 - CLAVOS KG 0.50 15.00 7.50
7 - ALAMBRE DE AMARRE KG 0.50 15.00 7.50
8 - AGUA LTS 120.00 0.03 3.60
D TOTAL MATERIALES (A) = 350.40
B OBRERO
1 - ALBAÑIL HR 5.00 17.50 87.50
2 - AYUDANTE HR 5.00 12.50 62.50

F Beneficios Sociales 0% de (B) = 0.00


G TOTAL MANO DE OBRA (B+F) = 150.00
C EQUIPO
1 - MEZCLADORA hr 0.20 70.00 14.00

H Herramientas menores 0% de (B) = 0.00


I TOTAL HERRAMIENTAS Y EQUIPO (C+H) = 14.00
J SUB TOTAL (D+G+I) = 514.40

L Gastos Generales 0.00% de (J) = 0.00


M Utilidad 0.00% de (J) = 0.00
N PARCIAL (J+L+M) = 514.40
O IVA 0% de (N) = 0.00
P IT 0% de (N) = 0.00
> Q TOTAL ITEM (N+O+P) = 514.40
> PRECIO ADOPTADO: 514.40