Академический Документы
Профессиональный Документы
Культура Документы
OUTAGE REPORT
Rev. : 00
DOCUMENT TITLE
ELECTROSTATIC PRECIPITATORS #1
DRY CLEANING AND INSPECTION
Cover Page 1
Table of Contents: 2
Introduction:
Executive Summary 3
Cleaning & Inspection Methods 3
Equipment Summary 4
Appendix 1:
Mapping on The All Field of ESP 14
Insulation Test on The All Field 15
1 of 15
INTRODUCTION
Executive Summary
This report covers the inspection findings, repair work and dry cleaning performed on the ESP #1
Boiler Precipitator during the Agust. 27 – Sept. 07, 2019 outage. AEP performed service on this unit
for the first year in unit #1.
This outage work consisted mainly of dry cleaning, inspection and repairing anvil plate because bolt
loose also re-alignment position pin wheel small to pin wheel big in the Rapping Hammer System. A
detailed inspection was performed and dry cleaning of maintenance were addressed. Please refer to the
following report for a complete description of all work performed and a status of all the precipitator
equipment.
Before arrival, proper safety training was documented and received. Lockout/tag out, Confined Space
permits, and hot work permits were then acquired to begin work. This unit was inspected from top to
bottom several times. The first inspection was done before manual rap down to see how and where
saltcake was accumulating, and get a first-hand look at the interior operating conditions of the
precipitator.
The purpose of the dry cleaning and inspection was to cleaning sticky fly ash on the Collecting
Electrode, Discharge Electrode, Casing, hopper and identify additional work that would need to be
done during the outage. After a manual rap down of the top of the precipitator; a second, very
thorough, inspection was completed of all of the internal parts of the top of the precipitator. Moving to
the bottom, a thorough inspection was performed. At this time, the outlet and inlet fields were also
inspected. Maintenance and repair work was then initiated in the bottom.
Inspection, cleaning, and maintenance of the T/R sets. A detailed examination of the rappers was
conducted, where some repairs were made. Components inside the penthouse were also inspected for
damage to ensure reliability for the coming year. After all repairs were made and the scope of work
completed, a final inspection with run test of rapper system, Insulation tets and tolerances were all in
acceptable that the precipitator was in as good condition.
2 of 15
Equipment Summary
3 COLLECTING ELECTRODE
3.1 Material IS : 513
3.2 Width x Height mm 750 x 11500
3.3 Thickness mm 1.25
3.4 Clear gap between two electrodes mm 400
3.5 Total no. of gas passages Nos. 37.00
3.6 No. of rows of collecting electrode Nos. 38.00
3.7 No. of collecting electrode plates Nos. 760.00
3.8 Total collecting area m² 12765
4 EMITTING ELECTRODES
4.1 Type Spiral
4.2 Material of Electrode Stainless Steel
4.3 Material of Frame M.S., IS 1161, YST
240 IS
4923 YST 240
4.4 Electrode size (Diameter) mm 2.7
4.5 Total no of emitting electrodes per ESP Nos. 6660
4.6 Effective length of electrode , approx.
5 ELECTRICAL ITEMS
5.1 TR UNITS
a No. of TR units provided Nos. 4
b Location ESP Roof
7 Geared Motors
Rapping of Emitting Electrodes
# Quantity 4
# Rating kW/RPM 0.37 / 2.2
Rapping of Inlet GD
# Quantity 4
# Rating kW/RPM 0.37 / 1.1
# Location ESP Inlet Funnel
Input voltage V 380, (+10% / - 15%)
4 of 15
Dry Cleaning, Inspection and Findings:
5 of 15
1. Preparation for dry cleaning work into the ESP, begins with the installation of Terpauline as an
isolation area that protects the Environment and the dismantle of the flexible joint in the ashes
hopper discharge. For temporary hose to stream dry ashes to bag sack.
Installation Terpauline for isolation ESP. Temporary hose installed on eighth discharge
hopper to drain ash into sacks.
2. Work Permit and Confined Space procedures before entering the manhole for dry cleaning and
inspection. Finding the thickness of ashes that sticks on RDEs and CE plates. Open TR bus duct
inspection doors, found Insulator seal leaked in TR field #4.
Open all field manhole in roof side Open all field manhole in middle side
6 of 15
Salt cake build-ups in top hanger, RDEs Sticky ash almost along the CE plates.
and CE plates.
Oil leak and teflon crack at TR #4 Repair by the electric team by tightening the oil
seal bolts so it doesn't leak back.
3. Dry cleaning with high pressure air to remove sticky ash on all fields from the roof and middle
manhole, Perforated diffuser plates, all cone ceramic housing and Transformers, also manually
cleaning on hopper. fly ash in the sacks collected transferred to Ash Pond with the help of a
Forklift and Loader.
7 of 15
Before
Dry cleaning on all field from roof side Dry cleaning on all field from middle side
After
8 of 15
Field #3 inside Field #4 inside
Before
After
All T/R on the roof of ESP All cone ceramic housing on the roof of ESP
9 of 15
4. In the cleaning process found anvil plate and bolts in the ash vessel, based on inspection, here’s
the list of missed out Hammer Anvil’s Plate, missed out Bolt and Nut, and loosen Bolt and Nut:
Field #1 : 31 Set
Field #2 : 6 Set
Field #3 : 7 Set
Field #4 : 12 Set
1 set hammer rapper is also missing in field # 4 at the top, will be shown in Mapping on the Field
of ESP #1 in Appendix.
Before
Anvil plate rapper and bolt/nut missing Hammer rapper missing and anvil plate was
found detached
After
Fabricated preparing anvil plate material Anvil plate rapper installation in all fields
** Repair the broken Hammer’s Anvil with replace the Bolt from 8.8 to 10.9. Tighten the bolt and
its nut, then Tag Weld to keep them at their position right after adjusting its position.
* Hammer replacement can not be done because spare parts are not available. The boiler engineer
will prepare for the master item for the PR submission.
10 of 15
5. Inspection into the field on discharge electrode rapping drive. found no alignment of pinwheel
small position to pinwheel big, visible gear wheel small erosion on the field #1. The Field # 2 / # 3
/ # 4 there are no abnormalities found in the rapping drive system component. Action with repairs
to repositioning the bushing shaft on the rapping drive and re-alignment in Field # 1, as well as
repairing re-welding of broken support on the screen plate to perforated diffuser.
Before After
Repair to reposition the bushing shaft on the rapping drive and re-alignment in Field # 1
** After alignment check, all bolts are re-tightened and tag-weld in the bottom bearing to the
support, shaft drive to the pinwheel to ensure no slip when running.
* Discharge electrode rapping drive system on the all field in great condition.
11 of 15
Before After
6. Emitting Electrodes and Collecting Plates Alignment as uniform spacing of the emitting and
collecting systems. If these tolerances are not carefully observed throughout the entire precipitator,
maximum performance will not be attained. From the measurement of the distance between CE
and CE to DE distance in safe conditions.
** In general, most ESPs are not affected by a misalignment of less than about ± 5 mm (3/16
inches).
12 of 15
7. Install all expansion Joints and replace the broken gasket and the ESP floor was cleaned of all
loose material and dirt upon departure.
13 of 15
MAPPING ON THE FIELD OF ESP
37 * * * * * * * * * * * * * * * * * * * * 37
36 * * * * * * * * * * * * * * * * * * * * 36
35 * * * * * * * * * * * * * * * * * * * * 35
34 * * * * * * * * * * * * * * * * * * * * 34
33 * * * * * * * * * * * * * * * * * * * * 33
32 * * * * * * * * * * * * * * * * * * * * 32
31 * * * * * * * * * * * * * * * * * * * * 31
30 * * * * * * * * * * * * * * * * * * * * 30
29 * * * * * * * * * * * * * * * * * * * * 29
28 * * * * * * * * * * * * * * * * * * * * 28
27 * * * * * * * * * * * * * * * * * * * * 27
26 * * * * * * * * * * * * * * * * * * * * 26
25 * * * * * * * * * * * * * * * * * * * * 25
24 * * * * * * * * * * * * * * * * * * * * 24
23 * * * * * * * * * * * * * * * * * * * * 23
22 * * * * * * * * * * * * * * * * * * * * 22
21 * * * * * * * * * * * * * * * * * * * * 21
20 * * * * * * * * * * * * * * * * * * * * 20
GAS OUTLET
GAS INLET
19 * * * * * * * * * * * * * * * * * * * * 19
18 * * * * * * * * * * * * * * * * * * * * 18
17 * * * * * * * * * * * * * * * * * * * * 17
16 * * * * * * * * * * * * * * * * * * * * 16
15 * * * * * * * * * * * * * * * * * * * * 15
14 * * * * * * * * * * * * * * * * * * * * 14
13 * * * * * * * * * * * * * * * * * * * * 13
12 * * * * * * * * * * * * * * * * * * * * 12
11 * * * * * * * * * * * * * * * * * * * * 11
10 * * * * * * * * * * * * * * * * * * * * 10
9 * * * * * * * * * * * * * * * * * * * * 9
8 * * * * * * * * * * * * * * * * * * * * 8
7 * * * * * * * * * * * * * * * * * * * * 7
6 * * * * * * * * * * * * * * * * * * * * 6
5 * * * * * * * * * * * * * * * * * * * * 5
4 * * * * * * * * * * * * * * * * * * * * 4
3 * * * * * * * * * * * * * * * * * * * * 3
2 * * * * * * * * * * * * * * * * * * * * 2
1 * * * * * * * * * * * * * * * * * * * * 1
Hammer, Anvil, and bolt nut in good condition Collecting plate in good condition
Plate for anvil loose, reassembled with bolt/nut 10.9 and tagweld **** Emitting electrode in good condition
Bolt/nut for anvil come loose, install bolt 10.9 and tagweld The bolt loose, replaced with 10.9 and in tagweld
14 of 15
INSULATION TEST ON THE ALL FIELD
# PICTURE RESISTANCE
Field #1 5.61 GΩ
Field #2 4.64 GΩ
Field #3 5.26 GΩ
Field #4 7.20 GΩ
15 of 15