CONSTRUCTION
DETAILS 246
INTRODUCTION This section only contains construction For an alternative separating wall
Timber double stud walls details for separating walls between system, use the innovative Knauf
are commonly used as dwellings. [For systems and InterHome system. [Refer to the latest
separating walls, providing installation, refer to Section 3.1.2] InterHome brochure on the website]
fire safety and acoustic
separation between
dwellings.
245
FIRE RATED
TIMBER SEPARATING WALL BASE AND SUSPENDED GROUND FLOOR – ELEVATION
FireShield
Skirting board
Fire sealant required
to maintain fire and
acoustic integrity
3.3.3 Timber Separating Walls
FireShield
Skirting board
Fire sealant required
to maintain fire and
CONSTRUCTION DETAILS
acoustic integrity
FireShield
Skirting board
Fire sealant required
to maintain fire and
acoustic integrity
CONSTRUCTION DETAILS
FireShield
Skirting board
Fire sealant required
to maintain fire and
acoustic integrity
Additional nogging
Half-saw cut
installed to support
in flooring
FireShield and fire
sealant
Floor joists perpendicular to
separating wall. Minimum joist
bearing must be maintained.
Floor joists
FIGURE 4 Separating Wall with Upper Storey Floor
perpendicular to
separating wall
PLAN VIEW
Roof sarking
3.3.3 Timber Separating Walls
FireShield
Roof sarking
CONSTRUCTION DETAILS
Install trimmer for ceiling
Non-fire rated plasterboard
plasterboard perimeter support
FireShield
Fill any gaps with fire sealant to
maintain fire and acoustic integrity.
External cladding
Fill any gaps with fire sealant to
maintain fire and acoustic integrity.
3.3.3 Timber Separating Walls
Roof sarking
Separating wall
Truss parallel to continued through
separating wall roof cavity
CONSTRUCTION DETAILS
FireShield
External cladding
Truss parallel to
separating wall
Roof sarking
CONSTRUCTION DETAILS
plasterboard
FireShield
FireShield
Top plate
FireShield or other
non-combustible lining
Top plate continued over eaves
Wall stud
Eave lining
External
wall stud
Fill with fire resistant mineral
wool in cavity to maintain FRL.
Non-fire rated
plasterboard
5-10mm clearance to plasterboard.
Fire sealant required to maintain
fire and acoustic integrity.
Fill with fire resistant mineral
Additional stud installed to support wool in cavity to maintain FRL
FireShield and fire sealant
Moisture barrier
CONSTRUCTION DETAILS
Fill any gaps with fire sealant to
maintain fire and acoustic integrity.
Non-fire rated
plasterboard
5-10mm clearance to plasterboard.
Fire sealant required to maintain
fire and acoustic integrity
Vertical damp
proof course
Additional stud installed to support
FireShield and fire sealant
FireShield
Vertical damp
proof course
Non-fire rated
plasterboard
FIGURE 13 Separating Wall to External Brick Wall with Return Moisture barrier
CONSTRUCTION DETAILS
Non-fire rated
plasterboard
5-10mm clearance to plasterboard.
Fire sealant required to maintain
fire and acoustic integrity If cladding battens are used,
fill cavity with fire resistant
mineral wool to maintain FRL
Additional stud installed to support
FireShield and fire sealant
External cladding
FireShield