Вы находитесь на странице: 1из 84

by rail engineers for rail engineers AUG/SEPT 2019 – ISSUE 177

Achieving
net-zero
OLERT OVERHEAD SYSTEM MONITORING
An award-winning new system that uses video monitoring to assess
ELECTRIFICATION
the condition of both the overhead lines and a train’s pantograph.
/ POWER

ELECTRIFYING INNOVATION BETTER BY DESIGN


In this electrification and power issue of In a pair of articles, Graeme Bickerdike and
Rail Engineer, Steve Cox discusses the need for Malcolm Dobell discover how all the bits and
electrification and the latest high-speed system. pieces make the system work.

www.railengineer.co.uk
Motor testing
at its best

MTR105
Rotating Machine Tester
The new Megger Baker MTR105 hand-held static motor tester
is designed for performing multifunctional tests on motors.

All in one device at an affordable price.

n Insulation Resistance tester


n DLRO (Digital Low Resistance Ohmmeter)
n Voltmeter
n Motor rotation tester
n LCR meter
n Temperature measurement
n CAT III 600 V (up to 3000 m)

Learn more
at megger.com/MTR105
14 CONTENTS
3

10|
Achieving net-zero
David Shirres considers the Committee on Climate
Change report on stopping global warming.

14|
Rail decarbonisation
The All-Party Parliamentary Rail Group’s recent
discussions, and a letter to the minister.

18|
Finishing the job:
redoubling Aberdeen to Inverurie
The latest stage of the Aberdeen to Inverness
Improvement Project opens on schedule.

26| Putting the

26
passenger first
Korec explains how

18
innovation was the key
to replacing Willesden
North junction.

42

28| 58|
Making user-worked crossings safer Anglia OLE renewals:
Paul Darlington investigates why Network Rail is changing success through collaboration
the signs at a user-worked crossing that goes nowhere. Furrer+Frey’s solution to sagging wires on the Great
Eastern moves to Thameside.

32| 60|
Bearing Up for Reliability Safer, quicker and sustainable cable protection
Clive Kessell reviews the latest version of the RailBAM Lightweight elevated cable troughing from Scott Parnell
bearing monitoring system from Track IQ. protects critical rail systems.

36| 64|
Azuma from Edinburgh Better by design
LNER’s new Hitachi Class 800 trains reach the Scottish Graeme Bickerdike visits Ellis, and discovers there is more
capital in passenger service. to cable cleats than he expected.

42| 68|
Tackling electrification Sustainability and decarbonisation
Amey has been working with Transport for Wales to ATL Transformers’ Neville Haide explains transformer
develop a Central Metro. losses and considers whole-life costs

46| 72|
Bringing more power to Merseyrail It’s the bits and pieces that makes it all work
AECOM is upgrading the traction power supply network Malcolm Dobell displays a mechanical engineer’s interest
ready for Merseyrail’s new train fleet. in Arthur Flury’s OLE components.

50| 76|
Sicat joins Network Rail’s UK Master Series Transformers: Aluminium or Copper?
Siemens Mobility’s latest overhead line system is both Paul Walker of FT Transformers decides that aluminium
lightweight and approved. may not be the best solution.

52| 78|
Electrifying innovation OLErt: overhead line and pantograph monitoring
Steve Cox discusses the need for electrification and Peter Stanton encounters Big Data and considers its role
Alstom’s latest high-speed system. in OLE monitoring.

Rail Engineer | Issue 177 | Aug/Sept 2019


YOUNG ENGINEERS AND
APPRENTICES RAILWAY
SEMINAR: DELIVERING A
SUSTAINABLE RAILWAY

29-30 October 2019


National College for High Speed Rail, Birmingham

THE THEME IN 2019 IS


'DELIVERING A SUSTAINABLE
RAILWAY'. RAIL TRAVEL MAY
BE SEEN AS A MORE
ENVIRONMENTALLY-FRIENDLY
MODE OF TRANSPORTATION,
HOWEVER THERE ARE MAJOR
CHALLENGES TO OVERCOME IN
ORDER NOT ONLY TO PROTECT
THE ENVIRONMENT, BUT ALSO
TO MAKE THE SUPPLY CHAIN
MORE SUSTAINABLE AND
COMPETITIVE.

EVENT PARTNER:

Book your tickets at: www.imeche.org/years


RAIL ENGINEER MAGAZINE EDITORIAL 5

Electrify everything

This exhortation to electrify everything concerns much more than upgrading the third-rail DC system power supply for these new trains is
railways. It is one of the main thrusts of the report ‘Net Zero: The a complex task.
UK’s contribution to stopping global warming’ produced by the Electrification must also be utterly reliable. To this end, we also report
UK Government’s Committee for Climate Change. This explains on the improvement of OLE reliability in Anglia and Thameside from
how, by using mostly known technologies, the UK can achieve net- the replacement of 1960s fixed-tension OLE with auto-tensioned
zero carbon emissions by 2050 without significantly affecting the systems, while Peter Stanton describes how the OLErt system, using
nation’s economy. an intelligent camera, has been developed to monitor the critical
The report sees electrification of, for example, domestic heating, pantograph/OLE interface.
industrial processes and road transport, through the provision of A very different monitoring technology uses acoustics to monitor
electric vehicles, as the only way of weaning the nation off its fossil the condition of bearings on passing trains. As Clive Kessell explains,
fuel dependence. Our feature on the net-zero report is essential this offers significant benefits by supporting a predictive maintenance
reading for anyone with an interest in climate change and provides regime whereas hot axle box detectors can only detect failures.
the context for the recently published final report of the rail industry The commissioning of 26 kilometres of new double track railway
decarbonisation taskforce. marks the end of the three-year first phase of the Aberdeen to
Although this report concludes that there needs to be “additional Inverness (A2I) improvement project. We describe how the second
progressive electrification of more intensively used routes”, our review stage of this redoubling was completed in a 15-week blockade and the
concludes that it understates the benefits of electric traction and significant passenger improvements that it will provide.
overstates the potential of non-diesel self-powered vehicles. We also The 137 kilometres of new cable laid by the A2I project shows the
conclude that Government requires a short clear statement of the need for cable protection, for which we feature one solution. It also
key issues. For this reason, our report includes an open letter on rail highlights the need for cable cleats, the design and manufacture of
decarbonisation to the Secretary of State for Transport, explaining which has been investigated by Graeme Bickerdike. His report reveals
why a rolling programme of electrification is essential for significant rail unexpected complexities and shows how installation time and whole-
carbon reductions. life costs can both be reduced by using the right cleat.
Yet there must be a business case for electrification. For intensively People need protection too, and user-worked crossings have,
used lines, this should not be a problem. However, on less well-used statistically, a higher rate of collisions and fatalities than other types
lines, the financial case for electrification is not so strong, as current of level crossings, when the usage rate is taken into account. Paul
appraisal rules do not adequately value the carbon savings that the Darlington has been investigating plans to improve safety at the 2,500
Government requires. such crossings on the network.
Furthermore, electrification must be affordable. In this respect the Finally, we report on the successful launch of LNER’s Azuma trains
Railway Industry Association’s electrification cost challenge report between Edinburgh and London and the passenger benefits that these
demonstrates how the industry has now got electrification costs under new trains will provide. Like many new trains, their service introduction
control. This includes descriptions of various initiatives to reduce costs, had been delayed due to unforeseen issues, including the fact that one
such as the use of surge arrestors to avoid bridge reconstructions. of the route’s OLE power feed stations will not be upgraded until at
We feature other novel techniques, with Alstom and Siemens least 2021. However, as we explain this is mitigated by the Azuma’s bi-
explaining how their overhead line systems offer cost, design, mode capability, which also delivers carbon savings as LNER trains from
installation and maintenance savings. Malcolm Dobell also explains how London to Inverness and Aberdeen will no longer be diesel-powered
the bits and pieces that bind overhead line equipment together have under the wires for most of their journey.
been the subject of considerable innovation. Our feature includes an interview with Hitachi’s head of engineering,
A novel approach that will significantly reduce the cost of electrifying Koji Agatsuma, who offers his thoughts on battery and hydrogen
the lines north of Cardiff will use tri-mode trains that are battery- traction. He also explains the design philosophy of the bi-mode
powered under permanently earthed sections, so avoiding the need Azuma trains, which will have a useful transitional role if there is to be
for costly civil engineering work, as Graeme Brindle and Nathan Sealy widespread electrification. However, as the rail
explain. decarbonisation report makes clear, there can
New trains require extra power for their improved performance be no long-term role for bi-mode trains in a
and air conditioning, as is the case on Merseyrail, where 40-year old zero-carbon railway. DAVID
RAIL ENGINEER EDITOR SHIRRES
trains are soon to be replaced with a new fleet. As our feature shows,

Rail Engineer | Issue 177 | Aug/Sept 2019


6 THE TEAM NEWS

Editor
David Shirres
david.shirres@railengineer.co.uk

Production Editor
Nigel Wordsworth
nigel.wordsworth@railengineer.co.uk

Production and design


Adam O’Connor
adam@rail-media.com
Matthew Stokes
matt@rail-media.com

Engineering writers
bob.wright@railengineer.co.uk
clive.kessell@railengineer.co.uk
collin.carr@railengineer.co.uk
david.bickell@railengineer.co.uk
Simple and lightweight mounting
graeme.bickerdike@railengineer.co.uk
grahame.taylor@railengineer.co.uk
lesley.brown@railengineer.co.uk
for digital signalling equipment
malcolm.dobell@railengineer.co.uk
mark.phillips@railengineer.co.uk
paul.darlington@railengineer.co.uk AECOM, the global infrastructure services firm,
peter.stanton@railengineer.co.uk is developing one of the UK's first 3D-printed
stuart.marsh@railengineer.co.uk
commercial products made from graphene-
Advertising reinforced polymer. The company's CNCTArch is
Asif Ahmed asif@rail-media.com designed to drive down the costs associated with
Chris Davies chris@rail-media.com installing digital signalling systems on transport
Craig Smith craig@rail-media.com
networks, using a graphene arch that sits over
Rail Engineer
rail tracks and eliminates the need to attach new
Rail Media House, digital equipment to existing infrastructure.
Samson Road, Coalville
Leicestershire, LE67 3FP, UK. Derived from graphite, graphene Bristol, where AECOM is working with
Switchboard: 01530 816 444 is one of the strongest materials in the Network Rail’s Western region team and
Website: www.railengineer.co.uk known universe. It was first isolated its Bristol Parkway signalling training
by researchers at the University of school to test the arch. Sensors have
Rail Engineer Videos Manchester in 2004. been installed to monitor, in real-time,
http://rail.media/REYouTube The AECOM team came up with the how the arch performs in different
concept of CNCTArch in response to weather conditions, measuring oscillation
Editorial copy to clients’ concerns about the cost and time and deflection.
Email: news@rail-media.com of digitising the signalling systems on The six-month trial is the next step
their networks. The company looked at towards commercialising the product,
Free controlled circulation replacing the traditional ‘bolt and screw’s with the results enabling AECOM to
Email: subscribe@rail-media.com method of deploying digital systems further validate the feasibility of using
in tunnels, which takes four shifts to the arch as an alternative to traditional
The small print install, by developing an arch on which methods of installing digital equipment.
Rail Engineer is published by the digital technology is attached that
RailStaff Publications Limited and doesn’t bolt to any existing infrastructure
printed by PCP Ltd. and would take only one shift to install.
While developed for use in tunnels,
© All rights reserved. No part of this the CNCTArch can also be used in open
magazine may be reproduced in any
environments and has the potential to
form without the prior written
permission of the copyright owners. transform the deployment of digital traffic
management systems.
Part of: An example of this new lightweight
® arch, 4.5 metres high, is currently being
tested on an outdoor track at Network
www.rail-media.com Rail’s workforce development centre in

Rail Engineer | Issue 177 | Aug/Sept 2019


NEWS 7

Levenmouth re-opening
taken forward

On 8 August the Scottish Cabinet


Secretary for Transport, Michael
Matheson, announced the go-ahead
for detailed design work to support
the proposed reopening of the 9.5km
railway serving Levenmouth, in Fife, at
an estimated cost of £70 million.
The mothballed-single track line was closed to passengers
in 1969 but remained open for freight up to 2001. It is owned
by Network Rail, though out of use under Short Term Network
Change (STNC) provisions. Thus, the line has no blockages. It has
four river bridges but no major structures and connects with the
main line from Edinburgh to Perth and Dundee at Thornton North
Junction, which is still operational but secured out of use.
The re-opened line will have stations at Leven and Cameron
Bridge. Levenmouth is the largest settlement in Scotland without
a rail service and the new line would provide a rail head for East
Fife and its tourist attractions. Furthermore, as Europe’s largest
grain distillery, owned by Diageo, is at Cameron Bridge, there is
significant potential for freight traffic.
In his announcement, Matheson noted that: “The detailed
appraisal work that has been carried out suggests that improved
transport links, which give Leven a direct rail link to Edinburgh,
will lead to an enhanced local economy, bringing better access to
employment and education and the potential for new investment.
Easier and more sustainable travel options will make it easier for
people to reach hospitals, schools and visit other areas of the
country as well as giving better access to Levenmouth.”
Matheson also committed an additional £5 million to a
Levenmouth Blueprint fund available to partners to maximise the
benefits of the Scottish Government investment in the area.
His announcement is the culmination of the long-running
Levenmouth Rail Campaign’s work to persuade the Scottish
government of the need to reopen the line. It is expected that,
when it opens in a few years’ time, trains to Edinburgh will take
70-75 minutes.
LOOKING FOR
YOUNG TALENTS?
More information at innotrans.com/career

Messe Berlin GmbH · Lisa Simon


Messedamm 22 · 14055 Berlin
Germany
T +49 30 3038 2124
lisa.simon@messe-berlin.de

Rail Engineer | Issue 177 | Aug/Sept 2019


8 NEWS

Work to restart on Rastatt


German national rail infrastructure manager DB Netze has announced that
construction work to complete the tunnels under the town of Rastatt will
recommence in 2020, with the tunnels now due to open in 2025.

The Rastatt tunnels are led to a seven week closure August 2017 when a landslip into The remaining 200 metres of the
a key part of the long-term of the line and caused major the newly constructed eastern undamaged western bore will be
plan to quadruple the entire disruption to European logistics tunnel bore not only disrupted completed by the ARGE Tunnel
line between Karlsruhe and services as no alternative routes construction but severed the Rastatt consortium using the TBM
the Swiss border at Basel. were readily available. The costs existing main line on the surface. that is already in position (having
This is one of the busiest of the closure and disruption A 160-metre-long section of been shut down in August 2017).
sections of railway anywhere to rail users and wider industry the tunnel including the TBM The existing surface main line is
in Europe, with lengthy double have been estimated at up to was then filled with concrete to protected from any unexpected
track sections used daily by €2 billion. stabilize the site. tunneling issues as it is on the
nearly 400 trains, more than Construction of the twin bore The route re-opened on 2 concrete slab built in September
half of them freight, in 2019, tunnels, designed for 250km/h October 2017, after a 275-metre- 2017.
according to DB. operation, began in 2013 long concrete slab had been laid To permit construction of the
The previous collapse of one using tunnel boring machines to support the railway on top of eastern tunnel under the existing
of the tunnels underneath the (TBMs) at shallow depths in the area that collapsed. main line without danger of
existing main line on 12 August alluvial sedimentary rocks. DB has now agreed its plans further disruption to the route,
2017 (issue 156 October 2017) However, work ceased from 12 to complete the Rastatt Tunnels. DB will first move a 700-metre

Rail Engineer | Issue 177 | Aug/Sept 2019


NEWS 9

section of the line so it follows


the course of the completed
line will be moved back above
the eastern bore. Construction
New kid on the block
western bore (on the surface) of remaining cross passages
to slew it away from the and entrance portals plus fit East Midlands Railway is the new name
construction site; approval for out will take until 2024. DB on the UK rail network, following its
this has been granted by the
German Federal Railway Office
currently expects the Rastatt
Tunnel to open in 2025 along
successful bid to run the East Midlands
(EBA). with approach lines on either franchise.
DB and ARGE Tunnel Rastatt side, resulting in a four-track The new franchise
then plan to excavate the railway from Karlsruhe to came into being on
remaining part of the eastern Offenburg. Sunday 18 August
bore using open excavation Following the 2017 accident, 2019. One day later,
methods (cut and cover) detailed evaluation of ground the first EMR-liveried
having first inserted concrete conditions, including 70 bore train, Class 222
walls to the required depth. holes, and other factors has Meridian number
This will include removing been underway to ascertain 222104, was revealed
the 160-metre-long concrete responsibility for the tunnel to stakeholders and
plug and the remains of the collapse and subsequent the press at Derby
TBM. A concrete line trench 17 disruption to the railway line station.
metres deep will be dug and through Rastatt, which resulted The expected
the tunnel constructed in it in substantial financial costs speeches were made,
before it is back filled. This work for both DB and multiple by the managing
is expected to commence in private freight operators. A director of Abellio UK Dominic Booth (“Abellio is delighted…”) and the
2021; DB Networks has applied conciliation and arbitration City Mayor of Leicester and chairman of the East Midlands Councils Sir
for the necessary planning process is underway to establish Peter Soulsby (“We’re pleased to welcome East Midlands Railway…”),
approvals to the EBA. responsibility and financial but there were some serious promises for the future being made as well.
Once the two tunnel bores damages, with the aim of A fleet of 33 new five-car trains is being ordered from Hitachi at
are completed, the surface avoiding lengthy legal action. Newton Aycliffe for delivery in 2022. They will be AT300 trains, similar
to the Class 800/802 units already being supplied to GWR and to LNER.
However, they will have coaches only 24-metres long, rather than the
26 metres of the other two classes, and they will have one extra diesel
engine, four spread over the five carriages.
In addition, Class 360 all-electric trains will be brought in for the
London to Corby service once electrification is complete, and Class 170
diesel multiple-units will be used for cross-country services.
Julian Edwards, managing director of East Midlands Railway, was keen
to stress that passengers would get improved services as well as new
trains.
The timetable will change from December 2021, correcting some of
the current anomalies. Catering will be sorted out and improved Wi-Fi
will be available throughout all trains. The current offering is seen as
being sub-standard and it will be improved.
There is more of course - £20 million investment in stations, easier
ticketing, more customer assistance, better staff training - but customers
want comfortable trains that are on time and provide decent catering
and good connectivity, and that’s what EMR has pledged to offer.

Rail Engineer | Issue 177 | Aug/Sept 2019


10 FEATURE

Achieving
DAVID
SHIRRES net-zero
T
he 2008 Climate Change Act was the first in the world to make a In June, the
government legally accountable for delivering its greenhouse gas (GHG) CCC’s net zero
emissions target, which was at least 80 per cent lower than the 1990 2050 target became
baseline. The Act is the basis for the UK’s approach to tackling and legally binding as the Climate Change Act
responding to climate change. It requires five-yearly carbon budgets to be set and was amended to adopt it.
established the Committee on Climate Change (CCC) to provide independent, Achieving net zero will affect everyone in
expert, evidence-based advice. Britain and require some lifestyle changes.
Yet, whilst some might believe that
By 2017, the UK was over half-way are understood. However, it was also reducing emissions requires an economic
to meeting its 2050 target with GHG considered to be hugely demanding slow-down, the good news is that it
emissions 43 per cent below those of and only achievable if there is urgent need not make the UK poorer. The CCC
1990. However, this was not good enough government action to drive the significant report explains the technologies needed
as this was largely achieved through the urgent policy changes required. to both reduce emissions and maintain
relatively easy measures of burning gas
instead of coal and using more renewables
to generate electricity. Furthermore, it was
becoming increasingly clear that the 80 per
cent reduction target was not enough.
In May 2019, the CCC published its
report ‘Net Zero: The UK’s contribution to
stopping global warming’. This reviewed
the latest scientific evidence on climate
change and concluded that the UK should
adopt a target of net-zero GHG emissions
by 2050 which, if replicated across the
world, would deliver a greater than 50 per
cent chance of limiting the global average
temperature increase to 1.5°C.
The report considered this target
was achievable as the technologies
and approaches to achieve net-zero

Rail Engineer | Issue 177 | Aug/Sept 2019


FEATURE 11

economic growth as well as the policies that the


government must adopt if these technologies
are to be deployed.
The technical report that supports the CCC’s
recommendation is available online and is a
daunting 304 pages. For this reason, we thought
our readers might appreciate a summary,
especially as this report provides the context for
rail decarbonisation.

Electrify everything
As fossil fuels have a high energy density and
can be readily stored and transported in fuel
tanks, tankers and pipelines, it is not surprising
that the modern world is utterly dependant on
them. However, if net zero is to be achieved,
we must be weaned off them. To do this, the used to power heat pumps to heat buildings as
CCC report stresses the need for extensive this would produce three units of heat for one
electrification, particularly in respect of transport unit of electricity. There is also the potential to
and heating. use hydrogen in the existing gas distribution
The obvious reason for this is that electricity system to heat buildings.
can also readily transport huge amounts of By 2050, the UK will require a low-carbon
energy, albeit only to fixed locations. An electricity generating capacity of 150GW to
exception to this is electric trains, which are thus generate a total of 645TWh to satisfy this
the only form of high-speed and mass transport extensive electrification. This compares with
that offers potentially zero emissions. No doubt today’s 104GW which produces 300TWh. The
for this reason, the report recommends a rolling CCC envisage a vast increase in solar, off-shore
programme of railway electrification, otherwise and on-shore wind generation. However, its
rail transport is hardly mentioned except for the scenarios take a cautious approach, limiting
need for modal shift from road and air to rail. the share of variable renewables to under 60
Yet any significant modal shift would require a per cent as these are not suitable for base load
huge increase in rail capacity, such as that HS2 and peak power which needs to be supplied
will provide. by nuclear power and gas turbine plants with
The CCC report considers that the carbon capture and storage (CCS).
electrification of road transport (19 per cent
of the UK’s GHG emission) will be by battery Aviation and shipping
and hydrogen-powered vehicles. Advances Aviation and shipping accounts for 10 per cent
in battery technology and the provision of of UK GHG emissions and, unfortunately, cannot
the required charging infrastructure will make be electrified except perhaps for short distance
electric cars increasingly practicable, so that no domestic shipping. Aviation makes up seven
more petrol or diesel vehicles should be sold per cent of the UK total, of which 96 per cent is
after 2030. However, the report points out that international flights from which emissions have
the solution for HGVs is not clear and is likely increased from 15 to 35MtCO2e (Metric tons of
to be a combination of hydrogen and battery carbon dioxide equivalent) between 1990 and
technology, such as extremely fast chargers 2017.
at motorway service stations. It also moots By 2050, there are unlikely to be any
the use of a motorway pantograph system to commercially available zero-carbon planes.
continuously charge HGVs. Measures to manage aviation emissions will
Electrical industrial and domestic heating is therefore include more efficient engines and
also essential to reduce fossil fuel consumption. airframes, improved airspace management, the
The report notes that there is an urgent need use of sustainable alternative fuels and measures
to engage with the public on a strategy to to reduce growth in demand. While biofuels
move away from gas heating as GHG emissions could be a substitute for aviation fuel, this might
from buildings accounts for 17 per cent of UK not be the best use of this scarce resource for
emissions. It envisages that electricity should be which there are alternative uses that may save

Rail Engineer | Issue 177 | Aug/Sept 2019


12 FEATURE

more emissions. Synthetic carbon-neutral geological capacity to store CO2 at this 13 per cent of the UK’s land area to
fuels are another alternative, although it is rate for 500 years. Exhausted oil and gas between 17 and 19 per cent, so increasing
likely their costs will be very high. fields and their pipeline infrastructure this carbon sink to between 16 and
There are a range of options to reduce present significant CCS opportunities. 36MtCO2e by 2050.
shipping emissions, some of which The net-zero report also envisages In contrast, the biological processes
may allow shipping to get to near-zero that hydrogen should be produced by inherent in crop and livestock production
emissions. These include more efficient methane reforming with CCS for the make it impossible to reduce agricultural
hull and engine designs, improved resultant CO2 emissions. Hydrogen needs non-CO2 emissions to zero. Currently,
operations and the use of alternative fuels to be produced in this way as if it was agriculture accounted for nine per cent of
such as ammonia and hydrogen. all produced by electrolysis. This would all UK emissions, half of which were from
increase annual electricity production by ruminant livestock. The report considers
CCS and BECCS 400TWh (more than 50 per cent of the that there is significant potential to
One key technology that has yet to projected 2050 demand). It predicts that, reduce emissions by more efficient use
be developed is Carbon Capture and by 2050, UK hydrogen use will be the of nitrogen, better manure management,
Storage. In contrast, the production of annual equivalent of 270TWh (compared improved crop productivity, better
biofuels is a well-developed technology with 27TWh in 2017). thermal efficiency of agricultural buildings
and accounts for three per cent of road Most of this hydrogen is required and low-carbon alternatives for tractors
fuels. However, there is a finite limit to its for heating, both to satisfy industry’s and other machinery.
production, given land constraints and requirement for high temperature gas The report shows how consumer lifestyle
the requirement for food production, and heating and to be used in existing choices can help to reduce agricultural
growing biomass requires a significant domestic gas distribution networks. Buses emissions as healthier diets rely less on
carbon input. Therefore, the production of and trains would require respectively carbon-intensive animal products (like
bio energy with CCS (BECCS) is required if 3TWh and 0.3TWh, a small fraction lamb, beef and dairy). Reducing food
biofuels are to contribute to the net-zero of total hydrogen production. Unlike waste is also a key step that individuals
target. heating, the hydrogen used in fuel cells can take to reduce emissions as a
CCS can capture and store up to 90 per must be of a very high purity and so is significant amount of agricultural land
cent of the GHG emissions associated better produced by electrolysis. This is devoted to the production of the 10
with fossil fuel power generation and would be a more appropriate option million tonnes of food which are wasted
industrial processes. The UK’s first where train depots may be some distance each year, of which 70 per cent is binned
carbon storage facility is expected to be from a large steam reforming plant but within households.
operational by the mid-2020s. This will could be close to a wind farm and use Other lifestyle choices to support net
capture 200,000 tonnes of CO2 from a otherwise unwanted energy during the zero emissions are indicated by the
gas terminal near Peterhead and use the night, for example. current breakdown of average household
existing pipelines to store it in a depleted emissions which are: heating (31%),
gas field. Land and lifestyle transport (27%), diet/agriculture (18%),
By 2050, the CCC expect the annual In 2017, the UK’s woodlands absorbed aviation (12%), electricity (9%) and
UK storage requirement is expected to two per cent of Britain’s GHG emissions waste (3%). Whilst the reduction of GHG
be about a thousand times this amount or 10MtCO2e. The report envisages that emissions from heating and electricity
(i.e. 176 million tonnes of CO2). Storage annual afforestation rates of between will largely come from technological
potential is not considered to be a 30,000 and 50,000 hectares would improvements, other aspects require
constraint for the UK, which has sufficient increase woodland cover from its current changes in consumer behaviour such as

Rail Engineer | Issue 177 | Aug/Sept 2019


FEATURE 13

diet and waste. The CCC report mentions Delivering this ambitious net-zero chance of achieving substantial carbon
the requirement to make more use of programme will require significant reductions.
public transport and to fly less, noting capital investment for which the The net-zero report shows the huge
that the growth in air travel cannot be report recommends that HM Treasury changes that will need to be made
unfettered. undertakes ‘a thorough review of the across all sectors. It is a bold vision
costs and benefits of meeting a net-zero which includes the following issues
Who pays? target and the appropriate policy levers relating to the rail industry:
Net zero by 2050 is estimated to cost to achieve an efficient and fair transition’ »» The benefits of electrification
between one and two per cent of GDP, to attract sufficient low-cost capital. generally and for rail the requirement
which is the same cost of the 80 per In this respect, it considers that ‘cost- for a rolling programme;
cent target which Parliament accepted benefit analysis (CBA) is not suitable for »» That there will be far greater use of
when the 2008 Climate Change Act was climate change action’. battery and hydrogen technology in
passed. Incidentally, it is also similar to The CCC is clear that decarbonisation the automotive sector than on rail;
the entire defence budget (1.8 per cent action must progress with far greater »» That biofuels and synthetic fuels are
in 2018). urgency. Of all its recommendations, likely to be a scarce resource, the
As well as savings from the avoidance of perhaps the most urgent is ensuring that use of which may only be justified in
climate damages, the CCC considers that the right financial levers are in place. applications for which there are no
there are likely to be significant benefits The required investment may not be other zero-carbon options;
from the required decarbonisation forthcoming if government investment »» The requirement for modal shift
programme. These include better air appraisals do not adequately value from road and air needs a significant
quality, energy self-sufficiency, with little carbon savings. increase in rail capacity, such as that
demand for imported fossil fuels and their As an example, business cases for provided by HS2;
associated price volatility, and industrial projects that deliver the required modal »» The urgency to act now;
opportunities from the UK being the first transfer from road to rail are weakened »» If net zero is to be achieved by 2050,
to adopt such a radical carbon reduction under current rules which require them the need for Government financial
programme. For example, delivering the to take account of the cost of the policies that incentivise carbon
goals of the Paris Agreement will require resultant loss of fuel duty. No doubt savings.
annual $2 trillion global investment in low- such decarbonisation disincentives will A credible rail decarbonisation
carbon technologies up to 2050. be addressed, otherwise there is little programme must address these issues.

Rail Engineer | Issue 177 | Aug/Sept 2019


14 FEATURE

Rail decarbonisation
a letter to the Minister

T
here are hundreds of All-Party Parliamentary Groups (APPG) formed by MPs
and Members of the House of Lords who share a common interest in a policy
area, region or country. These informal cross-party groups have no official status DAVID
within Parliament, yet they fulfil a valuable role by keeping Parliamentarians SHIRRES
informed. APPG meetings are about asking questions rather than argument.

On 9 July, the All-Party Parliamentary APPRG presentations of transport energy. He referred to the
Rail Group (APPRG) considered rail Jim Skea made the point that we have net-zero Committee for Climate Change
decarbonisation. In a packed meeting 12 months to start saving the world. (CCC) report, which assumed that
room, its members questioned Professor He stressed that net zero by 2050 was those sectors which can relatively easily
Jim Skea, co-chair of the working group of “humongously” challenging and stressed decarbonise should support others.
the Intergovernmental Panel on Climate the need for urgent action. He felt that Helen McAllister noted that the
Change (IPCC); Helen McAllister, Network that role of rail has been a blind spot in technology already exists to deliver a
Rail’s head of strategic planning (freight climate change reports as it has a big zero-carbon railway. However, there was a
and national passenger operators); the contribution to make by modal shift, need to determine where electrification is
Railway Industry Association’s technical noting that, globally, rail carries eight most appropriate considering deliverability,
director David Clarke and RSSB’s head of per cent of passengers, seven per cent affordability, operation and efficiency. She
sustainable development, Anthony Perret. of freight and consumes two per cent felt that appraisal techniques needed to
factor in carbon reductions.
David Clarke acknowledged that some
electrification programmes, especially
Great Western, had not been well
delivered. He felt that, after 20 years with
no electrification, too much was done too
quickly, with 11 electrification projects
spreading resources too thinly. However,
RIA’s electrification cost challenge report
had identified what went wrong and
shown that recent programmes had been
well delivered. He was convinced that, if
we want to decarbonise the rail network,
a rolling programme of electrification was
essential.
Anthony Perret, advised that the soon-to-
be-published final report of the rail industry
decarbonisation task force would show

Rail Engineer | Issue 177 | Aug/Sept 2019


FEATURE 15

(Left) The largely electric passenger


fleet has reduced its emissions by
taking advantage of the comparable
reduction in power station GHG
emissions over the last decade. In
contrast over this period there was no
reduction in emissions from the, largely
diesel, freight locomotive fleet.

tanks take up almost a third of the


three-car Breeze, although it is possible
that the tanks on a bespoke UK-gauge
hydrogen train might not encroach into
the passenger space.
It is noteworthy that, when giving
presentations on Alstom’s hydrogen
trains, the manufacturer’s representatives
always stress their benefits for use where
how the rail industry can decarbonise. He This would not seem to be the urgent appropriate and acknowledge that they
noted that rail was already a low-carbon action that Professor Jim Skea emphasised are not a universal solution.
mode, but a lot more needed to be was required, especially as the technology Perhaps the greatest flaw in the
done. He advised that the report would for rail decarbonisation already exists. decarbonisation report is that its analysis
show that the existing electrified network It took some time to review the table, which categorises rolling stock
needed to be used as much as possible and 20,000-word rail decarbonisation report, to show how trains can be powered,
that there should be more electrification which covered traction, property and only considers distance and maximum
where it makes sense. The report also infrastructure, of which traction is the speed. Hence, it does not address the
considered that there were no alternatives greatest carbon source. This showed fundamental requirement to consider the
to diesel traction for freight but, for that the report does not address issues acceleration needed to give an acceptable
passenger services, batteries allowed for discussed at the APPRG meeting or in journey time with the required number
discontinuous electrification and hydrogen the CCC net zero report. Instead, it takes of stops. Therefore, it would be wrong
was a feasible alternative to diesel traction. the stance: “Our focus throughout this to use this table to inform the Traction
He did not mention the limitations of report has been to challenge whether Decarbonisation Network Strategy.
hydrogen traction. electrification is the best solution to A high rate of acceleration is particularly
achieve a net zero carbon railway in important for urban and inter-city services
Rail decarbonisation report a manner consistent with delivering and is essential if rail is to be sufficiently
The final rail industry decarbonisation passenger benefits.” attractive to attract modal shift.
report was published 10 days after the The report also fails to stress the Rail Engineer understands that Grant
APPRG meeting and was welcomed by limitations of alternative self-powered Shapps, the new Secretary of State for
industry stakeholders. It stressed that traction, for example that hydrogen Transport, has imposed a two-page limit
rail was already a carbon friendly form trains require 2.5 times more electrical on information he receives about Britain’s
of transport, for example, per tonne energy than electric trains. There was no railways. In view of this, and the above
kilometre, rail freight has only 25 per cent mention of Alstom’s Breeze hydrogen issues, Rail Engineer would like to offer
of the GHG (greenhouse gas) emissions of train concept, which would modify the following short letter to the Secretary
road freight. Amongst its recommendations a Class 321 EMU to give a 140km/h of State outlining how the rail industry
was one for “additional, progressive train with a range of 1,000 kilometres. can best support the UK Government in
electrification of more intensively used As an indication of the constraints of delivering its obligations under the 2008
routes”, which was welcomed by the hydrogen’s energy density, hydrogen Climate Change Act.
Department for Transport. This indicates a
policy shift in favour of electrification as the The decarbonisation task force launches its report.
interim report, published in January, stated
that “we recognise that the lowest cost
and lowest carbon impact whole system
solution may identify some additional
electrification.”
However, the report, which took 17
months to produce, recommended the
development of strategic plans to deliver
against the agreed targets, of which the
first step is a Traction Decarbonisation
Network Strategy that will probably take a
similar period to finalise (three years since
the start of the decarbonisation report).

Rail Engineer | Issue 177 | Aug/Sept 2019


16 FEATURE

1 September 2019

Rt Hon Grant Shapps MP


Secretary of State for Transport
Department for Transport
Great Minster House
33 Horseferry Rd
Westminster
London SW1P 4DR
Dear Secretary of State
ouse gas emissio ns target
The rail industry's contrib ution to the 2050 net zero greenh

giving the UK Government a legally


With the recent amendment to the 2008 Climate Change Act
to be helpful in explaining how the rail
binding target of net–zero by 2050, this letter is intend ed
conclusions of the Committee for Climate
sector can help you deliver this target. It is based on the
ers and articles in Rail Engineer written
Change's net zero report, discussions with senior rail engine
by our expert engineering writer s.
gas (GHG) emissio ns, despite an overall UK
As the transport sector has hardly reduced its greenhouse
ution to the government's climate change
reduction in emissio ns of 42 per cent since 1990, your contrib
decarbonisation presents significant
obligations is particularly onerous. Furthermore, transport
In contrast, decarbonisation of the rail
challenges, particularly in respect of aviation and HGVs.
industry is relatively straig htforward.

carbon footprint, offers the only


This is because the rail sector, which already has a low
t, mass transi t and high–speed passenger flows in the
potentially zero–carbon transport for freigh
current they can draw from the overhead
form of electric trains, whose power is only limited by the
do not have to carry fuel, nor the plant
wires/third rail. Unlike self–powered trains, electric trains
sion losses, takes a great deal of limited
to power the train which involves unavoidable energy conver
space and adds significant weight.
than self–powered vehicles. Their use is
Hence, electric trains are far more powerful and efficient
ises the general benefits of electrificatio n
also consistent with the CCC net–zero report which emphas
n progra mme. This is the result of the
and, for rail, mentio ns the need for a rolling electrificatio
than any lack of technology.
underlying physics of transport and energy storag e rather
emissio ns from electric rail passenger
Electric trains already offer significant benefits, as GHG
es. These emissio ns are entirely from
vehicles are, on averag e, 26 per cent those of diesel vehicl
will be halved by 2028 and, by 2050, will be
electricity generation which, according to DfT projections,
n is needed to realise these benefits.
eight per cent of the current emissio ns. Railway electrificatio
from air and road to rail, as required
The reduction of transport sector emissio ns by modal shift
t of your decarbonisation strategy. For
by the CCC net zero report, must also be an essential elemen
to accept this shift, for which HS2 and
this to happen, the rail network must have the capacity
from other modes, trains must also offer
other capacity improvements are essential. To attract custom
ation and speed for commuter services
an attractive alternative and so need the required acceler
onisation option that can provid e this
and inter–city services. Electrification is the only decarb
performance.
ed, there is a role for battery and
On lightly used lines, where electrificatio n cannot be justifi
energy storag e limitations. For the same
hydrog en passenger trains. However, these have significant
tractio n battery pack or eight times the
volume, a diesel tank can store 36 times the energy of a
in a heavy pressu re vessel. Hence, battery
energy of hydrog en stored at 5,000 pounds per square inch
and the space availa ble for passengers
trains can only be suitable for short distance applications
e on hydrog en trains.
may be reduced due to the volume required for fuel storag
Taking into account the production of
Furthermore, hydrog en trains are intrin sically inefficient.
tional electric trains for the same
hydrog en, they require 2 /2 times more electricity than conven
1

er's January 2019 report 'The Future for


power, as explained in the Institution of Mechanical Engine
Hydrog en Trains in the UK'.

Rail Engineer | Issue 177 | Aug/Sept 2019


FEATURE 17
For rail freight, electrificat
ion is the only decarbo nisation
and hydrog en tractio n. A rece option due to the limitation
nt study for the National Inf s of battery
the challenge for freight` – ras tructu re Commission – `Bet
showed that electrification of ter Delivery:
two–th irds of exis ting freigh 515 kilometres of track would
t services to be electrically allow nearly
freight locomotives are electric hau led. Currently, only 17 per cent
. of

Clearly, further electrificat


ion needs to be justified in
capital investment. However, a business case that reflects
Treasu ry appraisal rules do the significant
ind eed, penalise pro posals tha not adequately value carbon sav
t deliver the required modal ings and,
business cases mus t show the transfer from road to rail, as
cost of the resultant loss of their
are to be ach ieved, it is esse road fuel duty. If net–zero GHG
ntial that Government ensu res emission s
incentivise the required investm the rig ht financial levers are
ent. in place to

Electrification also mus t be


affordable. In this respect, you
to the unacceptable cost and r predecessor was rig ht to act
time overruns of the Great Wes in response
However, since then, other pro tern Electrification Progra mme
gra mmes have run to time and (GWEP).
fallen sharply, as explained budget and electrification cost
in the Railway Industry Asso s have
report which explain s how elec ciat ion's `Electrification Cost Cha
trification costs are now 33–5 llenge`
describes how new technology 0 per cent of the GWEP cost.
can further reduce costs by, This also
reco nstruction. for exa mple, avoiding the need
for bridge

The graph below indicates how


the `sto p–go` nat ure of UK elec
GWEP's hig h cost. Electrifica trification was an und erlying
tion is a specialist activity, cause of
skills. Unlike countries such requiring its own design and
as Germany, the UK has had an ins tallation
Each time it halts, expertise intermittent electrification pro
is permanently lost, and supply gra mme.
chains need to be recreated.
With no further electrification
authorised,
this was teful cycle is about
to repeat itself
as successful tea ms disband and
the supply
chain focuses on markets out
side the UK. When
the electrification progra mme
is eventually
restarted, as it mus t be if Bri
tain's railways
are to be decarbo nised, hard–w
on lessons from
recent schemes will have been
for gotten and
will need to be relearnt.

Thus, the hig h GWEP electrif


ication costs
were an aberration, but the
industry has
since shown itself capable of
delivering affordable electrif
imperative, show that there is ication. Both this, and the deca
an overwhelming case for a stra rbo nisation
tegic electrification rolling
progra mme.
Such a progra mme takes advant
age of the greening of the gri
freight customers, is the onl d and, for almost all passeng
y way to both decarbo nise rai ers and
In the long–term, diesel tractio l tra nsport and offer an accepta ble
n, including on bi–mode trains, service.
and engineering trains on une mus t be eliminated except for
lectrified lines, for which car freight
bon offset measures are requir
ed.
There is clearly a role for bat
tery and hydrog en trains. How
make them unsuitable for inte ever, as their performance lim
nsively used routes, they are itation s
passeng er traffic. onl y suitable for a small pro por
tion of

This letter is intended to sho


w clearly how and why electrif
the only long–term rail deca ication is, for almost all rai
rbo nisation option. I am confid l traffic,
rail engineers I know and resp ent that this reflects the views
ect. of the

I do hope you find this helpfu


l,
You rs sincerely,

David Shirres

Editor, Rail Engineer -

Rail Engineer | Issue 177 | Aug/Sept 2019


18 FEATURE

FINISHING THE JOB


redoubling Aberdeen to Inverurie

L
ast year, the Aberdeen to Inverness Improvement network to support operational
Project (A2I) redoubled 8.5km of track between and station systems along the
Aberdeen and Dyce as reported in issue 168 (October route. This required further
DAVID
SHIRRES 2018). However, this redoubled track could not carry network upgrade works both
any passenger trains until this year’s completion of the 25.5km between Aberdeen and Dundee
Aberdeen to Inverurie redoubling work in August on which we and between Inverness and
report this month. Perth to ensure diverse routing.
Other telecommunications
work included the provision of
an internet protocol telephone
concentrator at Inverness, for
the user-worked crossing phones
previously controlled by the
closed signal boxes, and the
alteration of GSM-R call routing
due to the transfer of control to
Inverness.
The investment of £330
million on A2I phase one
follows the 2009 Scottish
Government Strategic
Transport Projects Review,
which concluded that A2I was
one of Scotland’s top four
The completion of this This work was completed transport priorities. Over the
redoubling marks the end in October 2017. It also past ten years, there has been
of phase one of the A2I included signalling and an 87 per cent increase in
programme which, as reported telecommunications patronage between Inverness
in issue 158 (December 2017) improvements which saw the and Aberdeen with most of this
included earlier work to section of the line from Inverness increase between Aberdeen
provide a relocated station to Keith controlled from a new and Dyce (146 per cent) and
at Forres, on a new straight Highland workstation at the Inverurie (247 per cent).
1.25km loop, and work at Inverness signalling centre. Journey time over the
Elgin, which included platform Prior to that, 173-kilometre-long Aberdeen
extensions, the provision of a telecommunications and Inverness route is around 2
turnback facility and extension enhancements provided a new ¼ hours with an irregular, about
Don viaduct of the loop from 650 metres to multi-protocol label switching
strengthening work. 1.5km. (MPLS) transmission

Rail Engineer | Issue 177 | Aug/Sept 2019


FEATURE 19

Removing original
cross girders on
PHOTO: DEREK SIME
28 May.

two-hourly service frequency. The 2018 blockade depths into the ground with
At each end of the route there The track laid last summer timbers inserted between the
is also a roughly hourly local between Kittybrewster and webs of the H section.
service between Inverness and Dyce was the first stage of For these reasons, redoubling
Elgin and between Aberdeen to the redoubling of the line this 26km corridor required
Inverurie. between Aberdeen and significant reconstruction of
Whilst the Scottish Inverurie. The new double the railway corridor, for which
Government’s long-term track starts at Kittybrewster, a blockade was the only
objective for the Aberdeen to 1.5km from Aberdeen station, option. As it was considered
Inverness line is the provision as redoubling the Hutcheson unacceptable to close the
of an hourly service with a Street and Schoolhill tunnels railway for the six months that
two-hour journey time, A2I also would have required track this would take, it was decided
delivers the more immediate lowering at significant cost that it would be done in two
requirement of improving and was not necessary for a summer blockades, each of
local services at either end of 15-minute service. about three months, with the
the line and the provision of This involved much more loop at Dyce enabling the
additional stations at Dalcross than just putting the track redoubling to be staged into
and Kintore without affecting back as, since it was lifted two parts.
journey times. For this reason, in 1968, numerous assets On completion, the newly
the provision of the proposed have been placed on the laid track was left unused,
new station at Dalcross will track bed, the single line which presented an unusual
require the provision of a new now followed the double signal-sighting problem as
two-kilometre loop. trackbed racing line and some the new Up line could not be
Both these stations are underbridges only had a used by trains until the end of Kintore station under
subject to separate funding single-track deck. Moreover, the 2019 blockade. Until then, construction.
agreements. For Kintore, this the original earthworks
was agreed between Transport cannot accommodate a
Scotland, Aberdeenshire double track in accordance
Council and North East with current standards and
Regional Transport Partnership this largely built-up section
(Nestrans) and the £14.5 required significant neighbour
million contract for the engagement as a result of
station’s construction was tracks being laid closer to
awarded to BAM Nuttall in adjacent houses.
May. This enabled much of its Earthworks retention was
construction to be done during therefore a large part of the
the 2019 blockade. work. This was achieved by
Although planning permission interlocking concrete blocks,
has been agreed for Dalcross high friction fill material or king-
station, arrangements for its post retaining walls. These use H
funding have yet to be finalised. piles driven to pre-determined

Rail Engineer | Issue 177 | Aug/Sept 2019


20 FEATURE
2018 BLOCKADE 2019 BLOCKADE – 4 May to 19 August
12 May to 19 August 10 kilometres
4/5 to 14/6 Dyce to Inverurie 27 kilometres

15/6 to 9/8 Dyce to Huntly


10/8 to 12/8 Aberdeen to Inverness
Hutcheson
13/8 to 19/8 Aberdeen to Huntly
and Schoolhill
tunnels Kittybrewster
UB20 UB24 UB34 UB40 UB46-49 UB54 UB55 UB57 UB62 UB67

ABERDEEN UB22 OB64


Inverness
1 2 3 INVERURIE
Waterloo multi DYCE KINTORE
modal terminal
Don viaduct strenthening Turnback
Track Level crossings
Existing New Removed

Closure 1 – Pitmedden MSL 4 – Cairnhall UWC


Bridgeworks
Upgrade 2 – Kirkton of Kinellar UWC 3 – Boat of Kintyre MCB – OD
Redeck Deck extension Remove / infill
5 – Fullerton UWC 6 – Inverurie old – MSL

Redecked what was to become the Down instead of being in an urban For the first six weeks, the bus
underbridge 54. line remained as the single area it was largely through replacement services were
bi-directional Up/Down line. farmland and so had various between Dyce and Inverurie,
This meant that, until the 2019 level crossings to contend with. then buses ran for another
commissioning, some signals The programme required a eight weeks between Dyce
for Up direction trains were large amount of bridge works, and Huntly, where temporary
relocated as temporary signals including two underbridge welfare facilities had to be
to the right of the single line replacements, seven provided for train crews. The
as the new Up line prevented underbridge bridge extensions, final nine days of the blockade
them being located on the left. one infill, strengthening six saw buses between Aberdeen
These temporary signals were underbridges and the removal and Inverness for three days
replaced by new permanent of two overbridges. This and then six days of buses
signals on the left of the year’s blockade also required between Aberdeen and Huntly.
new Up line during the 2019 significant work to strengthen Rail Engineer visited the
blockade. the five-span viaduct over redoubling works on 17 July
With the newly laid track left the River Don, just south of during week 11 of the 15-
unused, the operational railway Inverurie. week blockade and had an
was essentially unchanged Advantage was also taken opportunity to tour the site with
by the 2018 blockade and of the blockade’s extension to its programme manager, Colin
therefore did not require Huntly, as described below, MacDonald, at BAM Nuttall’s
significant signalling work. This to extend the short platforms project office and compound
also meant that it was only at Insch to 160 metres to at Inverurie. This site office
necessary to bus passengers accommodate ScotRail’s also includes ‘Hotel BAM’,
between Aberdeen and Dyce, Inter7City sets. These are the which provides temporary
as Dyce station could stay open newly refurbished five-coach accommodation for around
during the blockade. High Speed Trains which now thirty and has a fully equipped
serve Scotland’s seven cities. gym. With a shortage of hotels
The 2019 blockade The 2019 work also involved in the immediate vicinity,
Contractual arrangements work on the existing railway at this is a cost-effective way of
for this year’s blockade both ends of the new double accommodating the workforce.
were the same as for other track section which meant Building this temporary
A2I phase one works in changes to the replacement accommodation is one solution
that Network Rail engaged buses during the blockade. to the problem of the project
Redecked Siemens for the signalling and
underbridge 54. telecommunications work and
BAM Nuttall for everything
else. BAM Nuttall’s main sub-
contractors were AECOM and
Jacobs for design, Babcock for
track work and Stobart Rail for
ancillary civil engineering work.
This year’s blockade was
from 4 May to 19 August and
differed significantly from last
year’s work. It laid nearly 15km
of new track, almost twice that
of last year’s blockade, though
the complication of the racing
line was not such a significant
issue this time. Furthermore,

Rail Engineer | Issue 177 | Aug/Sept 2019


FEATURE 21

PHOTO: DEVLIN PHOTO

being a three-hour journey from all cross girders - replaced by integral part of the project as (Right) Kirow crane
Scotland’s central belt, where deeper ones - and additional a whole. With limited access to laying S&C at
many of its project personnel plating on the side beams. the north side of the line, it was Inverurie on 7 July.
are based. For example, as The abutments had also been important to make best use of (Left) Tamping new
well as overseeing the work on strengthened to resist the worst- the blockade to construct the double crossover
site, the Network Rail project case scenario of the force of a north-side platforms. north of Inverurie.
team must liaise with engineers, braking ballast train. Further Nearby, Boat of Kintyre
designers, operational planners protection against such forces level crossing was being
and others based in Glasgow. is provided by shock absorbers upgraded from a single line
that have been installed at the AHB (automatic half barrier) to
Touring the work pillars and abutments. a MCBOD (manually controlled
The tour started at the Next stop on the tour was a barriers obstacle detection)
newly laid S&C by the bridge overlooking the station double-tracked crossing. The
Inverurie project office. This work at Kintore. When built, signaller’s workload was a
is the western limit of the this will be an unmanned significant factor in the choice
new double-track section, station with a 166-space car of the MCBOD crossing as this
where a new turnback park. The station is immediately does not require the close study
facility has been provided adjacent to the A96 dual of CCTV images to determine
capable of accommodating carriageway, so it is expected when it is safe to lower the
ScotRail’s Inter7city sets. Two to be a busy park and ride barriers.
synchronised S&C tampers station. Colin explained that, This level-crossing work (Below) Don viaduct
were seen working together to although this was a separate required a road closure for the and compound.
simultaneously tamp the ballast contract to the main blockade duration of the blockade, with (Insert) Before the
under the crossing bearers. works, its construction was an only pedestrian access across strengthening work.
At the Don viaduct works,
Colin explained that this
presented significant challenges
in view of the requirement
to avoid putting significant
additional weight on the
substructure, as this would
have required costly in-river
work and could have delayed
the project. For this reason,
the ballasted track option,
which would have added 2,000
tonnes to the weight of the
bridge, was rejected. Rails over
the viaduct have therefore been
laid on longitudinal timbers in
new timber cradle units.
Works to strengthen the
viaduct were viewed from a
temporary crash deck below the
bridge superstructure. These
PHOTO: NETWORK RAIL
included the replacement of

Rail Engineer | Issue 177 | Aug/Sept 2019


22 FEATURE

PHOTO: DEVLIN PHOTO Programming the blockade


To allow track laying to
commence at the start of the
blockade, almost all the civil
works required for track laying
were completed beforehand.
This included retention work
that could safely be done
whilst the single line was open.
Night-time ‘rules of the route’
possessions were used for
work that affected the track
support zone or had plant and
equipment that could not be
safely separated from trains.
Other than the Don viaduct,
the only bridgework done
during the blockade was the
re-decking of underbridge 67
over the old canal, immediately
south of the viaduct.
Disruptive possessions from
20 to 22 April (72 hours) and
27/28 April (54 hours) saw work
done on six underbridges,
including deck renewals
Re-decking UB67. the railway. It also needed although it is normally possible and extensions, retention
extra land by the crossing for to reach suitable agreements earthworks, track formation
its equipment housing, which with those affected, such issues work and ancillary civils works.
had to be built on most of the present significant risks to The latter was sequenced to
garden of the adjacent house major projects, such as A2I, that give priority to the subsequent
that the owner had agreed to have no compulsory powers. work (equipment bases and the
sell. There may not be an alternative troughing between them) so
The A2I redoubling works design solution if someone that cables could be run out.
also required the upgrade of doesn’t wish to sell their land In this way, most of the
three user-worked crossings under any circumstances, a lineside signalling infrastructure
and the closure of two more situation which could cause was completed prior in
- as a result of arrangements major problems. advance, which was key to
negotiated with those affected, The last call on the guided allowing track installation to
this included the purchase of tour was to see the retention commence from the outset of
a house that could only be work at Kinaldie, where the blockade.
accessed by the crossing. king-post retaining walls Track laying used a seven-
Another deal had to be made could be seen supporting sleeper spreader beam to
to allow the demolition of the the embankment to the east lift sleepers from wagons
paper mill bridge near Inverurie, for a kilometre or so, a clear and place them into position
the central pillar of which would indication of the work required with the correct spacing.
have obstructed the double to replace a track lifted fifty Continuously welded rail,
tracking. Colin noted that, years ago. which had previously been laid

1.25 km of retention PHOTO: NETWORK RAIL

work was required at


Kinaldie.

Rail Engineer | Issue 177 | Aug/Sept 2019


FEATURE 23

Rosenqvist CD400SP
PHOTO: DEVLIN PHOTO
fastclipping machine.

alongside the existing single disappear from the Highland at Kittybrewster and Raiths
line, was then thimbled into workstation panel only to Farm, were also transferred to
position by road-rail vehicles reappear about an hour later. the Highland workstation.
and clipped up by a fastclipping This recontrol required The new signalling equipment
machine. the modification of includes 51 signals, many of
The programme required interlockings, changes to which are single lens LED
the completion of all work train describers and the colour lights, and nine new
requiring engineering trains and provision of fringe controls switch and crossing units. It is
road-rail vehicles by 13 August at Insch, for Inverness’s controlled by Siemens Westrace
to support the final phase of Highland workstation, and at interlockings and train detection Doubling and
signalling commissioning and Kittybrewster for the NX panel is by a combination of 92 newly upgrade of Boat
associated wheels free testing. at Aberdeen signalling centre. installed Frauscher axle counters of Kintore crossing
The new double-track railway Control of the blockade’s level and some DC track circuits where equipment
was commissioned in the early crossings, as well as the sidings between Aberdeen and Dyce. required extra land.
hours of 17 August to allow
three days of familiarisation
runs for the route’s 176 drivers,
with the passenger service
resuming on 20 August.

Signalling black hole


Prior to the blockade,
signalling between Aberdeen
and Inverness was controlled
by Aberdeen signalling centre,
mechanical signal boxes at
Dyce, Inverurie, Insch, Huntly
and Keith, and the Inverness
signalling centre’s Highland
workstation, which was
commissioned as part of the
October 2017 A2I works.
The 2019 blockade saw the
closure of Dyce and Inverurie
signal boxes with control of
the line from Kittybrewster
to Insch transferred to the
Highland workstation. The
long-term aspiration is that
this workstation will eventually
control the route throughout.
However, for now trains
between Keith and Insch

Rail Engineer | Issue 177 | Aug/Sept 2019


24 FEATURE

On the Don viaduct, Job done At the other end of the line, projects - as well as a series
Up line timbers ready Completion of the blockade an additional six Elgin-Inverness of enhancements to provide
to receive their rails. marked the end of the services will add to the nine more-efficient loop operation.
Aberdeen to Inverness phase such services introduced in On a single-track railway, this is
one works. 25 kilometres of December 2018, giving Elgin perhaps likely to offer greater
track had been laid on 39,000 an hourly all-day service. Those time savings than line speed
sleepers using 110,000 tonnes who wish to travel longer enhancements.
of ballast, of which 20,000 distances from stations on As Inverness to Aberdeen
tonnes was recycled ballast. the route will also benefit in is the only UK inter-city rail
Laying this track required the December from the provision service operated largely over
removal of 20,000 tonnes of of six through services from a single track, it’s good to see
spoil and the provision of 5,000 Inverness to the central belt of serious money spent on such
tonnes of engineering material, Scotland via Aberdeen. targeted enhancements. It
along with 27 kilometres of It has taken four years to will be interesting to see how
embankment retention. The deliver A2I phase one - one of phase two can bring further
signalling work also required the UK’s longest redoubling improvements.
over 137 kilometres of cables.
New shock absorbers. Impressive though these
statistics are, what counts
for passengers is the extra
train services, made possible
by this project, that ScotRail
will introduce during the
December timetable change. A
total of 20 additional services
a day between Aberdeen
and Inverurie will provide
a minimum of a half-hourly
service - every 20-minutes at
the peak. ScotRail will also
introduce a new Montrose to
Aberdeen service that, in most
hours, will be extended to
provide a Montrose to Inverurie
service.

Rail Engineer | Issue 177 | Aug/Sept 2019


FEATURE 25

Reduce Costs SLEEPER


SPACING
The rail industry is changing, fast. The need to improve efficiency and
INDEPENDENT
reliability, whilst minimising disruption and costs has never been greater.
Innovative solutions are needed.
Whether it’s a temporary, semi-permanent or permanent access point,
whatever the sleeper spacing, our customers can install a 10.8m
RRAP in less than 90 minutes, reducing possession times and costs.
Quick and easy to install
Rosehill Rail – Setting New Standards
For more information, or to enquire about training, please
call the Rosehill Rail sales team on +44 (0)1422 317 473,
or email info@rosehillrail.com

24 - 27 September 2019
AMBEREXPO, Gdańsk, Poland
Locking plates link field and gauge panels

Road Crossings // Road Rail Access // Pedestrian Crossings // Anti-Trespass

Rosehill Rail_Rail Engineer Half Page Advert JULY2019_Reduce Costs.indd 1 11/06/2019 13:38

www.jobson-james.co.uk/rail

We Are A Rail Specialist Insurance METAL FABRICATORS SPECIALISING IN


Broker (RISQS Link up approved) PRODUCTS FOR THE RAIL INDUSTRY -
£14M TURNOVER
WE INSURE

• RRV and Plant Companies


• S&T, S&C, SMTH, OLE and Civils contractors
• Rolling Sock Turnkey Modifications companies
• Manufacturers, Wholesalers and Installers of rail products
• ROSCOs and TOCs supply chain
• Rail Consultants, Surveyors and Engineering Companies
• It was identified that the factory buildings were underinsured due to the
WHY US? previous broker failing to advise on how to correctly calculate rebuilding costs.
• Other gaps within the cover were identified and the need to make major
improvements was explained.
• Specialist Rail Knowledge
• Working with the client and reviewing safety documentation enabled us to
• NEBOSH/Safety approach producing lower premiums make risk management suggestions.
• Contractual Liability checking • Despite substantially increasing the cover to more thoroughly protect the
• Better Technical advice business a 19% premium saving was still achieved with savings of nearly
• Specialist rail safety consultancy site audits funded by insurers £10,000 a year.

£9,240 SAVING £14 M 19%


ON INSURANCE PREMIUM TURNOVER SAVING
Contact Keven Parker on
07816 283949 / 0121 4528717 / 0207 9839039 BUSINESS CRITICAL
22-PAGE
Email: Keven.parker@jobson-james.co.uk
IMPROVEMENT S
IN COVER RISK REPORT TO
HAPPY TO
COVER CLOSED INSURERS RECOMMEND

Offices in London and Birmingham. Nationwide coverage.

Jobson James Insurance Brokers Limited are authorised


and regulated by the Financial Conduct Authority

Rail Engineer | Issue 177 | Aug/Sept 2019


26 FEATURE

“Game changer” The Trimble GEDO IMS.

“Putting the passenger first”


INNOVATION IS KEY WHEN IT COMES TO

O
ver the Easter weekend, the West Coast main line was closed over accuracy for as-builts behind the tamper,
four days during the replacement of Willesden North junction. This ultimately improving track quality.
included two NR60D crossovers and 400 metres of new line. The Downtime was reduced because the
aim of the project was to re-open the track on Tuesday morning at IMS was used whilst walking behind
90mph, with no train delays and no evidence of an engineering presence beyond the tamper with no line of sight issues
clean ballast and new track. leading to enhanced productivity. The

The West Coast main line is rarely of impeding on a site with cherry pickers “Day one of 90mph
closed, so, when it is, the demands for for OLE, signalling teams and welders.
high productivity, high quality work Instead, the GEDO IMS can be easily
handback running
and a timely job can make for a busy taken on and off track in the event of over Willesden North
and challenging site. The S&C South obstacles, is easily manageable and has Junction fast lines.
Alliance - the partnership between a short initialisation time for rapid use.
As smooth as it gets.
Network Rail, Colas Rail and AECOM
that develops, designs and installs major Using the Trimble GEDO IMS Very impressive. Well
track programmes across the South Pre-blockade, the team from Colas Rail done to all concerned!”
of the UK - was therefore keen to use familiarised itself with both the GEDO Peter Bowes, managing
a number of innovative approaches. IMS and the Trimble SX10. Using the
These included the use of the Trimble GEDO IMS, a design validation survey
director, Virgin Trains
GEDO IMS Track Measuring Device was undertaken (DVS) and control West Coast (based on
(a self-contained trolley designed to was checked. In this case, control was drivers’ feedback)
capture track position, gauge and cant already established every 60 metres on
in a single operation) and the Trimble overhead gantries and through the use
SX10 (high-accuracy total station and of chequer boards (70:30), although it GEDO IMS proved stable and reliable,
3D laser scanner combined in a single could have been easily done using the performing well despite the vibration
instrument). IMS and GEDO Profiler (used to measure and shock from the tamper.
In particular, the Trimble GEDO distance and height offsets between Alignment was measured in relation to
IMS has a highly accurate inertial the track and any object adjacent to the tamping on the large clear display of the
measurement unit, removing the need track). Trimble T10 tablet running the GEDO
for a total station on the track and the During the blockade itself, the IMS field software. This allowed for the
attendant challenges this can bring such GEDO IMS was used to survey the detection of the inner and outer track
as line of sight issues, and the possibility track, providing the team with greater geometry for the immediate spotting of

Rail Engineer | Issue 177 | Aug/Sept 2019


FEATURE 27

error or tamping mistakes. At The Trimble SX10 was used


the end of each chord, readings for Progressive Assurance.
showed the difference to design
for immediate lift and slew.
The team created a front
offset file on the tablet and then
transferred it to the tamper via a
USB after every chord, so that at
no point was the tamper waiting
for calculations to be made.
Previously, this was a time-
consuming process that involved
a rail shoe and the manual entry
of many numbers. Now the
process requires just one system “The KOREC/
and one operator who controls limited windows after the dig GEDO VORSYS two trolley Trimble teams
the whole process. and stoning, the SX10 provided system, a move to the GEDO
The track was handed back a fast alternative to traditional IMS was a natural evolution. He
were always
on time at line speed of 90mph, survey methods - a resection said: “The main advantage of there during the
having used Progressive to the existing control allowed GEDO IMS is it is based on a introduction of
Assurance throughout the the scan to be coordinated and single trolley. This overcomes
the Trimble IMS
weekend. This is a process which using the polygon framing on the line-of-site issues often
ensures that every stage of the the SX10 the extents of the dig encountered onsite while for the Alliance…
process is measured and signed were scanned. using two trolleys. The track including being
off by a named ‘responsible The data produced by the position is recorded continually on site during
person’ for each stage. This SX10 could be used immediately using GEDO. This continuous
creates an evidence file, critical in Trimble Business Center (TBC) measurement is far better than
the works. They
for assessing the line as fit for office software for checking the discreet data gathered by provided a world
reopening at a certain speed. against the 3D model to ensure using a detail pole and total class service to
In this case it was not possible that everything was correct. In station every five metres.
to open the line at 120mph TBC, noise such as machines and “The introduction of GEDO
the Alliance.”
because the formation stiffeners people can be removed and the IMS to the S&C South Alliance Nick Matthews,
weren’t sufficient to support the formation/design that goes into will be a game changer. It will programme
high-speed handback. the cabs can be laid onto this for ensure that continuous data is
Following handback, the track checking live in the field. always captured by the survey
engineering
was monitored over a period The SX10 could also be used and delivery teams rather than manager
of several weeks using the during the pre-works as a tool discrete data using total stations transformation
GEDO IMS and GEDO Office to assist site planning and build and detail poles. The KOREC/
S&C South
software. A baseline survey up area organisation. There is Trimble teams were always
was undertaken and then potential for a complete survey there during the introduction Alliance.
comparison surveys were used of the renewals site from which of the IMS for the Alliance.
to calculate any movement. the safety team can investigate This included representation at
Further GEDO IMS follow-up the hazards that could potentially meetings, training and being
tamps were carried out as part of impact on the workforce. on site during the works. They Passenger Satisfaction -
the hand-back procedure. Using the combination of point provided a world class service to the track was successfully
cloud data and 3D imagery, the the Alliance.” opened, on time, at 90mph.
Trimble SX10 Scanning Total engineers and surveyors can Throughout the four-day
Station overlay the new track designs blockade, the Alliance was
The question that the S&C and organise the site prep works supported on site by Matt
South Alliance wanted to answer prior to installing new control. Moss (Trimble Rail applications
was whether the SX10 could On this project, the SX10 was engineer) and Tom Williamson
perform in the harsh conditions part of a trial with Network (KOREC Rail applications
of a blockade, delivering under Rail and, in the future, the data engineer). The adoption of
the stresses of dust, vibration can be used to locate previous the Trimble technology on this
and restricted access in a troublesome areas or soft spots. site underlines the S&C South
decreased working area. Alliance’s commitment to
The SX10 would be used both Conclusion continuous improvement and
for Progressive Assurance and Nick Matthews, S&C South KOREC and Trimble were proud
as an alternative to having a Alliance programme engineering to be a part of this great effort
surveyor in the dig capturing manager for transformation, that saw the successful hand
data for a 3D model, all whilst reported that, as a result of back of Willesden Junction, on
setup in a position of safety. With being familiar with Trimble’s time, at a line speed of 90mph.

Rail Engineer | Issue 177 | Aug/Sept 2019


28 FEATURE

PAUL
DARLINGTON

Making user-worked crossings safer

U
ser-worked crossings
(UWC) are intersections
where a railway crosses
a right of way such as a
road on private land, a footpath or
a bridleway. Any gates or barriers
provided often need to be operated
manually, with some crossings
requiring users to telephone a signaller
to check that it is safe to cross.

The rate of collisions and fatalities at


these types of level crossings is higher Diverse users
when compared to other level crossings owners of the For many years, users of UWCs were
when the usage rate is taken into account. land and those who also have a legitimate generally local and familiar with the
Often, the only technology to assist the right to use the affected road also have a operation of the crossing. Trains were also
user is a sign informing them how to legal right to use the crossing. slower and noisier than they are today.
operate the crossing. However, work is User-worked crossings were also In recent times, the profile of users has
now underway to improve the signs and required to maintain access between diversified significantly. They are no longer
reduce the risk of such crossings. lands severed by the railway where a just the local landowner, farmer, postman
When the railway was first built, the roadway or track did not previously or shopkeeper. Users now include a wide
former railway companies were required exist. The most common being the field- range of couriers, delivery drivers and
to provide access across the railway for to-field crossing. Along with footpath members of the public, many of whom
those affected. Where this resulted in and bridleway crossings, these types are unfamiliar with how to use these types
the construction of a level crossing, it of crossing present one of the greatest of level crossing safely and who may not
was operated by the user, and unless the safety risks to today’s railway, with have English as their first language.
landowner has agreed to give up their the user responsible for making sure Users are also likely to be ‘connected’,
rights to use it, it is still the responsibility it is safe to use the crossing and for using headphones or texting on their
of Network Rail to maintain the crossing opening or shutting any barrier or gates phones. They may have mobility issues
for the safe benefit of all users. The provided. or be riders on horses or bikes. Tractors

Rail Engineer | Issue 177 | Aug/Sept 2019


FEATURE 29

are faster and drivers are likely to be in users at UWCs, including those at field-to-field
noise-reducing cabs, with the heating or air- farm crossings. The project explored which signs
conditioning fan running, and be incentivised to and signals best convey the particular points of
move quickly to increase productivity. information that users need when approaching
On top of all this, trains are now often more these crossings.
frequent and are considerably quieter. It made use of the methods and findings of a
There are around 2,500 such private crossings recently completed project examining signs and
in Great Britain, representing more than a third signals at public road crossings, and drew on
of all level crossings on the network. The Rail good practice in signage in general and in the
Accident Investigation Branch (RAIB) published railway environment in particular. Existing signs
a report on its investigation into a fatal collision at level crossings were compared with good
in October 2017 involving a high-speed train practice and, where it was judged that they
and a delivery van at a private crossing at a farm were not the best solutions, other signs were
in Teynham, Kent. This recommended that the considered.
government, in conjunction with the Office of The project focused on proposed
Rail and Road and Network Rail, should review improvements to signs and markings, and
and revise signs at private crossings so that they carried out an initial evaluation of the proposed
clearly and unambiguously convey information improvements and identified barriers to
and instructions on how to use the crossings implementation. It was identified that users
correctly. did not always associate the existing user-
The technology available to the rail industry to worked crossing sign with the crossing being
manage level crossings and enhance protection approached. The sign was too ‘wordy’ and did
has also developed in recent years, such as not use a pictorial representation of a crossing.
through technical advances in miniature stop lights As a result of the research three types of draft
(MSLs). However, the signage at crossings has not signage were proposed with simple, clear and
developed at the same rate, and this presents a unambiguous instructions, and making good use
potential safety risk to members of the public. To of pictorial icons:
improve safety at these crossings, Network Rail 1. Universal user-worked crossing ‘triangle’
is now working closely with the Department for sign. The proposed sign, unlike the
Transport (DfT) and the Office of Rail and Road existing signs, shows the three separate
(ORR) to revise and make improvements to the crossing elements as icons: a train, a gate
signage provided at UWCs. and a railway track.
2. High level instruction ‘blue’ signs to
RSSB report T983 inform users to ‘Stop look and listen’ or to
The work started with the production of T983 ‘Stop and telephone’.
- Research into signs at private level crossings - 3. Detailed instruction signs. These would
by RSSB. This considered, from first principles, have a mixture of illustrations and text to
the types of signs that should be presented to clearly instruct users.

Rail Engineer | Issue 177 | Aug/Sept 2019


30 FEATURE

T983 identified that it was important


that the proposed signs were legible and
well understood, or it could make matters
worse instead of better. It recognised that,
while the proposals may be clear when
viewed on the desk or on a computer The site consists of approximately 12
screen, trials were recommended to metres of track that leads nowhere and
compare the legibility of the designs with with no trains involved, but it is so realistic
the current instruction signs. many visitors believe it is a real railway.
Most of the required infrastructure was
Trial evaluation already in place, although a POGO had
Network Rail is now involved with to be installed. The Transport Research
all stakeholders to take forward the Laboratory (TRL) had assisted RSSB in the
benefits of the T983 report and to T983 report with virtual reality modelling,
implement a ‘root and branch’ review of so TRL was also employed by Network Implementation
the UWC signs proposals in a systematic Rail to facilitate the trials and to provide The first operational installation trial is
way, to establish where and how the continuity with the process. planned for Jacky Duffin Wood crossing,
improvements can be made. The three Initially, 15 different users per day for a UWC POGO MSL on a freight line on
proposed signs produced by RSSB three days of all ages, gender and abilities the London North East route.
were reviewed in workshops at which were involved with the trials in April, with Once all the captured data is analysed
specialists, including route level crossing another similar trial a few weeks later. The and evaluated, the plan is to republish
managers, representatives from DfT and users were people who were all unfamiliar the Network Rail standard for level
ORR and with signage experts, discussed with any type of UWC. Some people went crossing signage, and any other
everything from level crossing risk to over each crossing type as pedestrians standards affected, with the new signs
ergonomics. and others as car drivers. available from early 2020. They will be
The proposed signs were produced by One initial finding was that people used then deployed on the various Network
Royal British Legion Industries (RBLI), then the crossings in various ways, even if all Rail routes, using their local knowledge
installed and trialled at a user-worked of them were safe. Users were fitted with and crossing risk profiles and liaising
level crossing ‘mock up’ site which had head cameras and asked to complete a with project teams which may be doing
already been established by the ORR questionnaire - all the captured data will work in a particular area.
and Network Rail at Cannock Chase, be subject to qualitative and quantitative New legislation will also be required
Staffordshire. This is a facility used as a analysis before the recommendations are to amend the Private Crossings
training resource for those organisations finalised. This will include the format, the (Signs and Barriers) Regulations 1996,
who regularly come into contact with user- size of the signs, font and icons, together however Network Rail is working closely
worked level crossings. with a Welsh version. One change to the with the DfT so that there should be
Five different crossing types were T983 report proposals already identified nothing to prevent the new designs
evaluated, including common and is that the icons on the signs will be at being brought onto the network in
complex types of UWC. These were non- the top and read left to right, rather than 2020 via a nationwide trial authorisation
telephone UWC, telephone UWC, power vertically on the left. process.
operated gate opener (POGO), MSL and Further trials are planned with users who The new signs will be enforceable
a POGO MSL crossing. are familiar with the operations of UWCs. during the nationwide trial period.

Rail Engineer | Issue 177 | Aug/Sept 2019


FEATURE 31

FINDING YOUR WAY AT NIGHT AND IN FOG!


pedeSOLAR - The optional LED lighting for pedeSTRAIL level crossings.

¬ Technology: solar-powered LED ¬ Service life: more than 8 years


¬ Output at full power: ¬ Temperature range: -20°C (- 4°F) to 85°C (185°F)
up to 240 hours without additional solar radiation ¬ LED configuration: one-sided and two-sided reflectors
¬ Colours: yellow, red, white, green, blue ¬ Charging time: approx. 3 hours on a sunny day
(two colours per cover possible)

STRAIL (UK) Ltd. - Richard Whatley


Tannery Lane // Send / Woking // GU23 7EF // Great Britain // Phone +44 (14 83) 22 20 90 // Fax + 44 (14 83) 22 20 95 // richard@srsrailuk.co.uk

Rail Engineer | Issue 177 | Aug/Sept 2019


32 FEATURE

Bearing Up for Reliability

SNCF depot installation.

CLIVE
KESSELL

A RailBAM installation in Australia.

W
ith the ever-present
focus on putting
passengers first, train
reliability has to be
high up the priority list to achieve this.
Modern rolling stock is being equipped
with many electronic systems that bring
their own maintenance and reliability
challenges.

One fundamental element is nonetheless


the train wheel and the axle journal
bearing upon which it rotates. Should this now universally available. RailBAM (Rail All bearings emit noise and that noise
bearing catastrophically fail, then the train Bearing Acoustic Monitor), produced will vary according to the condition of
is likely to be declared a failure and to by Track IQ, a Wabtec company, is well the rolling surfaces within it. The RailBAM
be taken out of service for an expensive established in this technology, as well system captures the sound emitted from
repair. At worst case, the train could as providing other trackside monitoring every axle journal passing a trackside
derail, with the risk of this being a major systems in the UK. At a recent meeting monitoring site to check for defects
accident. of the London & SE section of the IRSE, developing on the rolling surfaces. In the
The monitoring of axle journal the RailBAM system was explained, just event of a defect detection, an alert is
bearings is therefore an important safety proving that signal engineers are eager sent to the rolling-stock maintainer, thus
precaution. Equipment to detect hot to learn about technology in all rail allowing remedial work to be planned
axle boxes (HABD) has been available disciplines! without impacting on the day-to-day train
since the 1960s and has been refined in service.
subsequent decades. This technology, Origins Such predictive advice allows defects
whilst effective, has reliability issues and An introductory article on the to be fixed long before anything more
offers only reactive alarms when a failure RailBAM system appeared in issue 151 serious happens whilst in traffic.
has occurred. HABD systems are not (May 2017), written by Stuart Marsh.
compatible with third-rail electrification This explained how the technology System components
infrastructure and mainly target the major was developed by the Australian The principal units are two acoustic
freight routes, where derailment is known company Trackside Intelligence, which cabinets mounted trackside and a third
to be a higher risk. subsequently became branded Track enclosure away from the track that
Alternative acoustic technology, IQ and was taken over by Wabtec in houses all the necessary electronics,
originating from Australia in the late 2015, enabling a larger penetration into communications and power equipment
1990s and trialled in the UK in 2007, is worldwide rail markets. for operation of the system. Wabtec’s

Rail Engineer | Issue 177 | Aug/Sept 2019


FEATURE 33

FleetOne web-based server RailBAM and wheel


allows the rolling-stock condition monitor at
maintainer to access its own Skatval, Norway.
fleet data and create email
alarms and alerts to suit its
business.
The acoustic cabinets
incorporate a motorised
shutter that opens upon
detecting the approach of a
train, thus exposing the array
of microphones to the side
of the train. Ideally, a cabinet vehicle needs a pragmatic stock and are powered by the
will be placed on either side of consideration. A fixed- trackside reader as the train
the track so as to collect sound formation diesel or electric passes.
from bearings on both sides of multiple unit will probably The RailBAM system has
an axle in one pass, and this is only require two tags, one been successfully operating
typically the arrangement on associated with each cab end. for over 20 years. Its flexible
single-track lines. On double or On a passenger train, where and robust design enables
multiple-track railways, there coaches may be swapped installations in the extreme
is limited space between the around, a tag is needed on heat of the UAE and the icy
running lines, so the system every vehicle. This includes cold of North America. Power
is split across adjacent tracks, the high-speed train (HST) can be taken from the local
allowing complete coverage to fleet. On freight trains, a tag is electricity provider or solar
be achieved over a return trip. needed on the locomotive(s) battery supplies. Connection
Identifying the train is vitally and every wagon (or fixed to the internet is either via
important, which is achieved wagon pair or triple) if robust wired networks (often the
by fitting the train with RFID bearing monitoring is to be railway internal network),
(Radio Frequency Identification) achieved. Tags are passive units cellular radio, or even satellite
tags. Just how many tags programmed with the identity communications in extremely
are required for each train or of that particular piece of rolling remote locations.

Reduce the cost of rolling stock maintenance


BGM BIM WPM RailBAM/RailBAM IB WCM
The Bogie Geometry Monitor Brake Inspection Monitor reports Wheel Profile Monitor records Rail Bearing Acoustic Monitor Wheel Condition Monitor identifies
enables bogie hunting and poor brake consumable wear rates allowing service critical wheel dimensions identifies bearing defects unsafe loads and poor wheel tread
angle-of-attack to be identified maintenance to be scheduled and generates alarms when acoustically, enabling preventative condition and generates alarms when
and reported. efficiently and material use optimised. exceedances are reported. maintenance to be undertaken. customer thresholds are exceeded.

Condition Monitoring Systems


Global product and software solutions for the rail industry
Track IQ has a global reputation for being specialist manufacturers, suppliers and maintainers of wayside
condition monitoring equipment and data management systems to the rail industry. Track IQ’s complimentary
systems provide a holistic view of rolling stock and their relative health and safety. The powerful and
customisable FleetONE database and visualisation tool presents, prioritises, alarms and reports to meet each
customer’s specific requirements, driving down the cost of rolling stock maintenance, whilst increasing safety.

tiqtrackiqinfo@wabtec.com trackiq.com.au wabtec.com

2019_A5_AD_General_PRINT.indd 1 08/05/2019 13:52


Rail Engineer | Issue 177 | Aug/Sept 2019
34 FEATURE

Operation
The principle of operation is that, as a
train passes the acoustics sensors, the
sound profile of each axle journal bearing
is captured and stored. The acoustic
reading is then linked to the train tag
data, the pass-by date and the time.
Knowing the train identity allows the
FleetOne system to compile the train
consist and associate each dataset with
the correct wheel position and axle journal
bearing. Repeat pass-bys are recorded to
provide updated data for each bearing,
thus allowing the data to be used to
observe any worsening condition and
trigger alerts while also enabling analysis
of behaviour trends and patterns. »» Rolling surface defects, including wheel UK performance and statistics
With the acoustic system being sensitive flats and wheel roughness; Whilst the majority of systems have been
enough to detect even small defects »» Roller bearing wear, including for an installed overseas, the first UK application
in the bearing, it is then typically over individual roller; was a limited trial in 2007 on Southern at
100,000km before the defect would »» Cup/cone spalls (flakes of metal broken Three Bridges, targeting the Class 377
mature into a service-affecting failure. This off from the bearing components); fleet. Although successful, the trial was
means that, generally, no action need be »» Multiple spalls; not expanded.
taken until the next routine maintenance »» Extended spalls. In 2009, Siemens installed the first
visit. Since the RailBAM system is aimed RailBAM system in the UK and the first
There are some constraints as to where at discovering developing defects globally to target only passenger stock.
and how the trackside sensor units should rather than catastrophically damaged This was on the South West Trains
be positioned. For optimum results, they components, a root-cause history can be network and monitored Class 444 and 450
should be on straight track which is in investigated and built up, which in turn units with the trackside unit installed at
good condition - if any ‘sleeper pumping’ will lead to the implementation of bearing Swaythling, between Southampton and
is happening, this can cause noise and improvements and a reduction in the Eastleigh. The system captures data for
confuse the readings. The site also needs bearing attrition rate. the whole Siemens fleet as well as other
to be where normal train speeds are As would be expected, the RailBAM trains using the route.
between 13 and 80mph. This does not system is continually evolving and A second trackside unit was later
present a challenge on high-speed lines, improving. The data from over 100 installed at Mortlake with the fitting of
as even the fastest trains have to slow as RailBAM systems worldwide is hosted on tags to more of the SWT fleets, thus
they approach stations or junctions, which Track IQ’s own data server in Adelaide enabling all units on what is now South
are usually ideal locations for the trackside (Australia), allowing the performance to Western Railway to be monitored.
readers. be monitored daily and improvements Noting the results, First Great Western
The types of defect that are detected deployed globally. installed a trackside unit at Kensal Green,
include: near to North Pole depot, and began
equipping its HST fleet with tags. This was
then expanded to take in other classes of
FGW trains.
As one would expect, the number of
axles monitored by the three RailBAM
installations is counted in the millions as
the statistics show:
»» More than 265 million bearing data sets
reads in total;
»» Equates to an average of 35 million
bearing data sets/year;
»» 8,600 collective days of operation
across the three sites;
»» Monitoring of approximately 5,000
tagged assets;
»» Successful identification of several
hundred defective bearings.
The overall system has achieved 99.99
per cent reliability and more fleets are
being tagged as franchises are renewed.

Rail Engineer | Issue 177 | Aug/Sept 2019


FEATURE 35

The business case


The whole justification for
this technology is to allow
predictive rather than reactive
maintenance. This yields
huge savings, in the order of
millions of pounds when taking
into account the material
optimisation as well as the
penalties imposed when rolling
stock failures occur.
The main beneficiary is the
train maintenance provider, be
this a train operator (TOC) or
a leasing company (ROSCO).
In most cases, the upfront
investment is borne by the
maintaining organisation, which
seeks the approval of Network
Rail to allow Track IQ to install
the lineside units. With a typical
system installation costing less
than £300,000, the benefit for
the rolling stock maintainer and
the infrastructure provider is bearings. The effectiveness of With all elements of RailBAM in the UK at
extremely strong, whilst also acoustic monitoring on shell rolling stock monitoring (above) Mortlake and
improving safety. bearings, of which there are a now becoming the norm, (below) Swaythling.
One question is whether the number remaining in service, is a holistic approach to link
RailBAM system can replace still being evaluated. RailBAM into other systems,
HABDs, of which there are So, for the present, there are such as FleetOne, is under
228 on Network Rail. Whilst no plans to remove the HABDs. consideration and is all part of
the acoustic equipment can However, since the detection of the goal to improve overall train
detect defects well in advance axle journal bearing problems and infrastructure reliability.
of hot axle box systems, thus is made much earlier and more
redefining what is ALARP (as reliably, it is estimated by the Thanks to Nicholas Kay of Track
low as reasonably possible) RSSB and Network Rail that as IQ and Paul Baker of Bakerail
for bearing monitoring, it is few as 35 trackside acoustic Services for taking time to
primarily designed for trains sites are needed to provide explain the system to a bunch of
with the more common roller national coverage. signal engineers!

Rail Engineer | Issue 177 | Aug/Sept 2019


36 ELECTRIFICATION/POWER

Azuma from Edinburgh

DAVID
SHIRRES

I
t can take a long time to introduce a new train. In 2007, the Department for Transport (DfT) issued its invitation to tender for
its Intercity Express Programme (IEP), for trains to replace the ageing Inter City 125 fleets on the Great Western and East Coast
main lines. Five years later, after various contract negotiations, the train chosen by the DfT was the Hitachi AT300 product
family which was to be built at a new plant in Newton Aycliffe, County Durham. Production commenced in 2015.

These trains were the subject of a £5.7 billion contract to supply The IEP trains were developed to meet the DfT’s capacity
and maintain 866 vehicles. 497 of these were for East Coast and performance requirements, which include the requirement
services, consisting of Class 800 bi-mode trains (13 nine-car and for bi-mode trains to run beyond the electrified network. After
10 five-car) and class 801 electric trains (30 nine-car and 12 five- Great Western electrification was cut short, there was a greater
car). The London North East Railway (LNER) has branded its new requirement for diesel running which resulted in the Class
trains ‘Azuma’, which means ‘East’ in Japanese. 800 diesel engines being uprated from 560kW to 700kW. Koji
The Azumas will replace the current East Coast fleet of 30 IC225 advised that this wasn’t a problem as Hitachi had anticipated this
nine-coach sets powered by a Class 91 electric locomotive and customer requirement and allowed for it.
15 Inter City 125 trains, which provide diesel trains from London The extra capacity of the IEP trains comes from the use of
to Aberdeen, Inverness, Lincoln, Hull, Sunderland, Harrogate and 26-metre-long coaches, three metres longer than the present
Stirling. When the bi-mode Class 800 Azumas are used for these vehicles, which results in passenger space forming a greater
services, they will only operate under diesel power for the smaller proportion of the train. Furthermore, unlike the current trains,
part of the journey, where there is no electrification. the electric and diesel traction equipment is above and below
Newton Aycliffe rolled out its first Class 800 in December 2016. the passenger space. The result is that the Azumas have about a
In October 2017, these units were introduced on Great Western hundred seats more than the Class 91 trainsets they will replace,
services. It had originally been intended that the East Coast Azumas with seven centimetres more legroom in standard class.
would start running in September 2018, however, as with many new
trains, delays postponed their launch to May when Azumas were The first Newton Aycliffe-built IEP is rolled out on
introduced on services between London, Hull and Leeds. 9 December 2016.

Hitachi’s design philosophy


Rail Engineer recently gained insights about the Azuma’s design
from a wide-ranging interview with Hitachi Rail Europe’s head
of engineering Koji Agatsuma, who observed that the Japanese
custom is to take a long time considering what a customer needs
and developing a product before offering it to the customer. As
an example, he cites the development of the Class 395 Javelin
trains, which were delivered in 2009 after the contract was let in
2005.

Rail Engineer | Issue 177 | Aug/Sept 2019


ELECTRIFICATION/POWER 37

The nine and five-coach IEP units have,


respectively, five and three motor coaches each,
with all axles powered and a power output of
one megawatt under electrical power. Thus, over
half of the axles on the train are motored. Koji
mentions that the train is geared to have high
acceleration from low speed in order to reduce
journey times.
As previously mentioned, all equipment is
carefully packaged to maximise passenger
space. Koji mentions an example, for which
Hitachi has a patent, of the use of a common
supply converter designed to be fed from either
the secondary winding of a 25kV AC transformer Pre-service celebrations Diesel generator unit on
or the diesel generator unit. He also stresses the The first Azuma passenger services from both bi-mode class 800.
Hitachi philosophy of reducing weight wherever Edinburgh and York to London ran on 1 August,
possible, of which the trailer bogies’ inner frame for which there were suitable celebrations in the
structure is an example. two cities beforehand. On 30 July, an Azuma
Electromagnetic compatibility between the IEP had a photo call with Mallard, the world’s
trains and the legacy solid-state interlockings fastest steam engine, at York station. The next
had delayed their service introduction north of day Edinburgh greeted the train’s arrival with
Doncaster. Koji explained that this was due to bagpipes and a new tartan.
the higher frequency harmonics from modern At the Edinburgh launch event, LNER’s
traction control for which the solution was managing director David Horne explained how
passive filters. In addition, Network Rail had the Azumas will bring a real revolution of rail
improved cable screening. travel to the East Coast route, which has a proud
Finally, Koji reflected on the use of battery history of pioneering express trains. Over the
and hydrogen rail traction. He considered that past five years, the East Coast route had seen
it was perfectly feasible to fit batteries to the a 25 per cent increase in patronage for which
company’s Class 385 units to give them a last- the Azumas would provide much needed extra
mile capability. However, he felt that hydrogen capacity. Class 800/1 800 104 at
power is not yet of age as it would seem to be David also emphasised the importance of Edinburgh Waverley on
costly and its equipment takes up too much sustainability, noting that an Edinburgh to 31 July about to leave for
space. London rail journey has one sixth of the CO2 special trip to Berwick.

Rail Engineer | Issue 177 | Aug/Sept 2019


38 ELECTRIFICATION/POWER

emissions of the plane journey. The Azumas will further improve


rail’s sustainability benefits as their bi-mode operation will
ensure that all East Coast services under overhead lines will be
electrically powered.
On a special Azuma run from Edinburgh to Berwick and back
for press and stakeholders, Rail Engineer had the opportunity
to talk to LNER’s engineering director, John Doughty, who
explained that the original launch date had been delayed due to
a combination of infrastructure compatibility, teething problems
and LNER taking delivery of its first Azuma in March 2019 instead
of the original date of August 2018.

Getting trains operational


John stressed that LNER had been “very careful not to run risks” Azuma standard class coach.
whilst introducing these new trains, the priority was to ensure
that everything was right before the launch. One issue that had which also specified the seating configuration. On most routes,
to be addressed was the hazard of someone contacting the the five-car sets will run coupled together as 10-coach trains.
overhead line equipment after using the sets of jumper cables The five-car bi-mode Azumas will enable LNER to introduce a
between coaches as a ladder. Following discussion with the ORR, new regular service to Lincoln later this year, as well as more
LNER’s mitigation of this risk has been approved pending the frequent services to Harrogate, and, in future timetable changes,
development of a permanent design solution. direct services from London to Huddersfield and Middlesbrough.
Another issue is that feeder stations at Doncaster and Marshall LNER’s website shows the planned introductions.
Meadows at the Scottish Border need to be upgraded to provide During September, it is planned to introduce Azumas on four
enough power to supply LNER’s full electric train service. Whilst more East Coast Scottish trains, including, from 23 September,
the feeder station at Doncaster is to be upgraded in October LNER’s sole London-Glasgow service. Between October and
2019, it is expected that Marshall Meadows won’t be upgraded December, more Anglo-Scottish services will transfer to Azuma
until at least 2021. Until then, to limit the load on the feeder operation.
station, a few Azumas will have to operate on diesel power for The December timetable change will see the introduction
approximately 30 miles on either side of the Scottish border. of LNER’s half hourly daytime service between London and
John advised that there are now seven of the nine-car Azuma Edinburgh - by next May, all these trains will be Azumas. To
trains in passenger service and that LNER has been working with manage seat reservations as the Azumas are fed into the service
Hitachi to ensure the trains are perfect. He emphasised that a key pattern, the plan for each service is fixed eight weeks in advance
reason for this is to ensure that staff have full confidence in their so that tickets can then go on sale.
new trains - the Azumas are currently achieving 9,735 miles per By December, bi-mode Azumas will operate LNER’s Aberdeen
technical incident which he considered was “not bad for a brand- and Inverness services. The latter service will be particularly
new train”. demanding, as it includes a 16-mile climb up a 1 in 70 gradient
He explained that he has a project team of eight people to the 1,484ft Drumochter pass, the highest point on the UK rail
accepting the new Azumas, with three needed for each nine- network. It will be interesting to see how Azumas in diesel mode
car train. Before LNER accepts a train, it must pass a static compared with the more powerful Inter City 125s that they will
acceptance test and accumulate 2,000 miles of fault-free running, replace. John has no doubt that Drumochter won’t be a problem
during which the mileage is reset if any faults occur. It typically for the Azumas, which have more than half their axles motored
takes a week to accumulate this mileage as it is difficult to get and so are less prone to adhesion problems. He also pointed
diagrams for it on the crowded East Coast route. out that, unlike the trains they replace, Azumas have self-closing
When asked about the five-car Azuma sets, John pointed out doors, which will reduce station dwell times on these routes.
that the split of five and nine-car sets was decided by the DfT,
Experiencing the Azuma
Having had the opportunity for a short trip from Edinburgh
over the border to Berwick and back, your writer was keen
to experience the Azuma on a longer journey so joined the
05:40 inaugural service from Edinburgh on 1 August. With
long stretches of 125mph running, this was an opportunity to
experience the Azuma at speed, when the ride was lively on
occasions. However, catering staff considered that it was better
than they were used to, so they didn’t expect to bruise their legs
on the tables.
The longer journey also provided an opportunity for a closer
look at the train which has 101 first-class and 510 standard-class
seats, all of which have their own power sockets. There is a
traffic light seat reservation system above each seat which turns
to green after the portion of the reserved journey has been
completed. Amber denotes that a seat has been reserved later in
Azuma first class coach. the journey.

Rail Engineer | Issue 177 | Aug/Sept 2019


ELECTRIFICATION/POWER 39

The coaches on the nine-car Azuma


are lettered A to C and G to M (with no
coach I). Coaches A to J are standard. A
has two wheelchair spaces, B has two bike
compartments, each holding two bikes, G has
the café bar, K has two bike compartments Each coach has two luggage racks, with Bike compartments and
and is half standard, half first class, L and M, toughened glass used for luggage shelves to café bar.
which has two wheelchair spaces, are first class enable passengers to see what they have put
coaches. There are ten toilets on the train, there without standing on the seats. When
including two universally accessible toilets. walking through the train, the five coaches
As the average passenger journey on East with generator sets underneath were evident
Coast services is typically twice the average by the slight ramp from the vestibule due to
on Great Western, LNER’s passengers expect their raised floor, which was otherwise not
more in the way of catering. Hence, the only noticeable.
difference between the coach layout on these
two routes is that LNER Azumas have a café bar Newcastle to London – average 105mph
in coach G (for grub), on Great Western the only The 05:40 Edinburgh to London train is LNER’s
catering offered to standard class passengers is Flying Scotsman, taking exactly four hours to
from a trolley. reach London. Its only stop is at Newcastle, after
The extra three metres gives the Azuma which it offers the UK’s longest non-stop run -
coaches a spacious feeling, although, in over the 268 miles between Newcastle and
standard class, seats are not lined up with the London - although it is the only train of the day
windows. Standard class seats are firm, but I to do this in either direction. On 1 August, the
did not find them uncomfortable. The first-class train left Newcastle at 07:05 and arrived at Kings
seats are lined up with the windows. They are Cross at 09:39, a minute early, having averaged Three generations of East
less firm than standard, though perhaps not 104.8 mph. Coast Traction at Kings
as comfortable as the plush seating of current The high average speed of this non-stop run Cross (LtoR) Azumas,
trains, that three years ago, were refurbished to is not new, as class 91 electric locomotives have Inter City 125 and Class
LNER rather than DfT standards. been operating this service for some years. 91 electric locomotive.

Rail Engineer | Issue 177 | Aug/Sept 2019


40 ELECTRIFICATION/POWER

David Horne, managing director of LNER,


with Azuma and Mallard at York.

An indication of what is new occurred when the train almost


wasn’t a non-stop run. Just before Grantham, it slowed down
to 19mph to enable a preceding train to be looped ahead of it.
The Azuma then demonstrated the high acceleration that Koji
Agatsuma had referred to by taking only 2 minutes 5 seconds to
accelerate from 29 to 100 mph up the 1 in 200 gradient south of
Grantham.
Combined with infrastructure improvements, it is this power
which will provide the required acceleration for a regular four-
hour London to Edinburgh journey with the current stopping
pattern, which is expected to be introduced in December 2021.
To mark the occasion, souvenir inaugural run Azuma key rings
and miniatures of Tomatin malt whisky (distilled next to the
Azuma’s route to Inverness) were handed out. As the Azuma
approached Kings Cross after its flawless inaugural run, LNER’s
managing director, David Horne, thanked those on board for
joining LNER on this memorable occasion. On arrival, the train
was greeted by a single piper and Azuma shopping bags were
handed out.
Before the inaugural return Azuma service left Kings Cross
at 17:30, its passengers were offered more shopping bags
and treated to a performance from the Red Hot Chilli pipers.
Although Tomatin miniatures and key rings were again handed
out on board, there wasn’t quite the buzz about this return
working, which took 4 hours 40 minutes to get to Edinburgh
having stopped at Peterborough, Newark, York, Darlington,
Durham, Newcastle, Alnmouth and Dunbar along the way.
This time there was no piper to greet the train at its final
destination, although LNER staff, clearly proud of their new train,
were taking selfies to mark the occasion. Over the past three
days, the Azuma had been given a special launch, now it was time
for the train to start routinely offering a high-class service on the
East Coast route.

Red Hot Chilli pipers play out the inaugural 1730 Kings
Cross to Edinburgh Azuma.

Rail Engineer | Issue 177 | Aug/Sept 2019


CALL US NOW ON 01206 396 446

GET GRP SAFE WITH STEP ON SAFETY


FABRICATE / SUPPLY / INSTALL

Fencing

Track- side ladder

Step on Safety have been on track since 2009, providing


innovative turn-key solutions within the Rail Industry. Utilising
GRP’S lightweight, durable, low maintenance, non-conductive and
non-corrosive properties to deliver out-standing design, supply,
fabrication and installation to all of our clients.
GRP Grating
Boasting a long line of prestigious projects from extensive work
on GRP Access Solutions in the Euro Tunnel to 220m of Multi-
Storey fully Composite Access Platforms at Stewarts Lane Depot.

GRP Step Over GRP Substructure

GRP Handrail

Trench Covers

GRP Deck

OUR KEY SYSTEMS


• GRP Track Side Walkways. • GRP Ramps. • GRP Station Platform.
• GRP Single/Multi Story TCD • GRP Bridge Decks and Treads. • GRP Grating Panels.
Access Platforms. • GRP Embankment Stairs. • GRP Station Platforms/Platform
• GRP Dagger Boards. • GRP Fencing. Extensions.
• GRP Ballast Retention/HCE • GRP Trench Covers.
Systems. • GRP Hand Railing/Barriers.

WWW.STEPONSAFETY.CO.UK STEP ON SAFETY LTD, FACTORY LANE, BRANTHAM, SUFFOLK, CO11 1NH
42 ELECTRIFICATION/POWER

TACKLING
ELECTRIFICATION
GRAEME NATHAN
BRINDLE SEALY

The challenge Rhymney

for Wales & Merthyr Tydfil

Borders
Aberdare

Treherbert

Ystrad Mynach
Stadler Flirt Tri-modes
Stadler Citylink Metro Vehicles

Caerphilly
Proposed new Transport for Wales (TfW) Tri-mode Vehicle. Lisvane &
Thornhill

Coryton

Queen
Street
Cardiff Central

Grangetown
Cardiff Bay

Penarth

Barry

Rail Engineer | Issue 177 | Aug/Sept 2019


*not to scale
ELECTRIFICATION/POWER 43

M
uch has been discussed view, which they have already done These factors mean that a great deal
recently about the state with the announcement of new rolling of investment is needed, either to lower
of electrification in the stock purchases and a new approach the track or raise bridges, to allow
UK, and how it is being to electrification that taps into hybrid for compliant clearances prior to the
delivered at a much higher cost than on technology already in use in road vehicles. electrification works. This costly work must
the continent. be avoided to make electrification a more
The article in Rail Engineer titled Balancing the budget cost-effective solution.
‘Getting electrification right’ (issue 164, The key challenge of electrification
June 2018) demonstrated the all or schemes to date has been the ever- A different approach to rolling stock
nothing method the UK Government has rising cost and time to complete the Bi-mode trains are being introduced
taken in its approach to electrification works. Overspend, programme delays on several of the UK routes to
and the resulting move towards and scope reduction of schemes are all overcome the limitations of the
diesel-powered, bi-mode vehicles; an reoccurring themes across the board reduced electrification scope. These
unsustainable option in the pursuit of on electrification programmes, largely trains operate on electric power when
reducing the nation’s carbon footprint. due to the complexity and extent of the under wires but switch to diesel where
North of the border, Transport Scotland work needed to fully electrify a whole overhead power is not available.
has taken a somewhat different approach, line. It’s a simple solution. However, trains
and one which seems to have been A significant proportion of the cost of must therefore carry pantographs and
more successful. Over 25 per cent of the any electrification scheme is made up transformers as well as heavy diesel
Scottish network is now electrified, and of the track and civils works needed to engines and fuel tanks, all of which need
a steady programme of electrification provide the necessary safety clearances. to be carried throughout the journey.
seems to have had results. All overhead line equipment (OLE) has Hybrid technology, now firmly
In Wales, the Welsh Government took minimum distances to be applied to keep established within the domestic car
over the franchising of the railway and the public safe, such as at any public market, seamlessly blends power
appointed KeolisAmey to operate and standing surface (station platforms) and at from the combustion engine with
develop the Wales and Borders rail service level crossings. power from an on-board battery pack.
and South Wales Metro, working in In addition, many historic bridges and Energy is recovered and stored in the
partnership with Transport for Wales, on a other structures over the railway, built battery through regenerative braking,
15-year contract from 2018 until 2033. over 100 years ago to much smaller dramatically improving fuel economy.
This lengthy contract term has gauge clearances, require considerable The latest ‘plug-in hybrid’ cars (PHEV)
encouraged both Transport for Wales alteration work to accommodate the use the battery pack as the primary
and KeolisAmey to take a long-term overhead catenary. power source, with the combustion

SPL Powerlines UK - The system supplier for railway electrification


Passion for Delivery
www.powerlines-group.com

Rail Engineer | Issue 177 | Aug/Sept 2019


44 ELECTRIFICATION/POWER

Proposed new Transport engine providing an increase in the mileage range These permanently earthed sections of
for Wales (TfW) Metro and a back-up in the event of an empty battery. OLE, similar to extended neutral sections,
Vehicle. KeolisAmey has come up with a solution for the are not a new solution and are already used
new Central Metro in Wales that will make use on conventional electrical schemes for some
of this state of the art yet well-established hybrid low structures where track or civils works are
technology in its new train fleets; both tri-mode not feasible. However, their use is usually only
and metro vehicles. possible in locations where a train has sufficient
This change from the existing diesel multiple momentum to ‘coast’ through a non-electrified
units (DMUs) on the network to hybrids will lead section - a risk assessment is needed to make
to a profound reduction in carbon footprint and sure that a conventional electric train will never
the on-board batteries will significantly reduce the stop and become stranded in this area.
cost of electrification. The hybrid capability of both new train types
On the Core Valley Lines (CVL), which is means that they can accommodate the use of
everything north of Cardiff Central, tri-mode a PES wherever electrical clearances cannot
vehicles will be used from Rhymney and Coryton be achieved, including in station areas. The
to Grangetown, powered by OLE and battery new rolling stock will switch to battery power
only. The addition of the diesel engine adds through these sections, with the pantograph
flexibility to the vehicles to continue on to remaining raised, and switch back to overhead
Penarth, Barry and Bridgend, and elsewhere on power when live OLE is detected.
the network if future needs demand. (See map, The widespread use of PES for the South
page 38). Wales Metro transformation will avoid up to 55
Queen Street to Rhymney will operate on OLE track or civils interventions across the Valleys.
and battery power, including an unwired section Complex station canopy alterations and the
between Caerphilly and Lisvane & Thornhill, where provision of protective screening are also
battery-only operation will be used to avoid costly avoided, with track lowering expected to be
waterproofing works in Caerphilly tunnel. needed at just 17 sites and only one bridge
Metro vehicles from the three remaining valley needing to be lifted.
heads (Treherbert, Aberdare and Merthyr Tydfil) The cost savings from the use of battery
through to Cardiff Bay will be OLE/battery hybrids power and PES to overcome areas that are
only, with no diesel engine. These trains will run difficult to electrify are evident and, unlike
wire-free to the new station at the bottom of the diesel, achieve the zero-carbon operation that
Cardiff Bay branch, which will lay the foundations is expected of a modern rail network.
for future ‘on street’ extensions into the city This approach to electrification by the
centre. Transport for Wales Rail Services, operated by
KeolisAmey, may well pave the way for similar
Permanently earthed sections methods to be adopted for other networks in
for cost efficiency the future and, with battery technology ever
This proposal for the electrification of the Valleys improving, it is clear that the rail industry must
will significantly reduce the number of track and not be left behind.
civils interventions. Why? Because the use of
permanently earthed sections (PES) will allow the Graeme Brindle is technical director and
OLE clearances at structures to be significantly Nathan Sealy is regional engineering director,
reduced, removing the need for many alterations. both with Amey Consulting.

Rail Engineer | Issue 177 | Aug/Sept 2019


Quality products for the
modern overhead contact line

Conical couplings and collar sockets


Catenary suspension
Clamps / Turnbuckles
Material for safety and earthing
Section insulator
Neutral Section / Phase Break
Insulators and installation material
Miscellaneous railway tools

ARTHUR FLURY (UK) LTD


Unit 218 Milton Keynes Business Centre
Foxhunter Drive
Milton Keynes Tel: 01908 686766
MK14 6GD Email: info@aflury.co.uk
URL: www.aflury.co.uk
46 ELECTRIFICATION/POWER

to Merseyrail
BRINGING MORE POWER

M
erseyrail will be introducing new trains to its network More power
around the Liverpool City Region from next year, Although modern trains
replacing the current fleet of electric multiple units are more efficient than those
which are now approaching 40 years old. built 40 years ago, they also
have additional electrical
Built and maintained by To improve passenger safety, requirements.
Swiss manufacturer, Stadler, and make the network more For example, they demand
the trains will be modern, fast accessible to all, the new trains more electrical power for
and comfortable. They will will have a sliding step that will traction and auxiliaries, such as
also be able to carry more allow level access. air conditioning. Regenerative
people, more quickly, helping Merseytravel, which oversees braking pushes power back into
support the growth of the City the operation of the Merseyrail the 750V DC supply network,
Region with the potential to network, will own the new trains which has to be capable of
run beyond the current ‘third on behalf of the Liverpool City accepting it (for example by
rail’ to places like Wrexham, Region Combined Authority, having another train in section
Skelmersdale and Warrington in which has set aside a reserve which is demanding power). If
the future. to help fund the project. the system is not receptive, then
Merseytravel will then lease the the train’s onboard batteries will
trains to Merseyrail. be charged.
Of course, there is more to the The power supply network
project than simply buying a fleet therefore had to be upgraded.
of new trains. The £460 million This was required to meet the
project includes provision for demands of the new fleet but will
power upgrades to the network also eradicate existing DC issues
and work on platforms and at the fringes of the network,
track to help manage the gap which had often caused delays
between the train and platform. on the Southport service.
There will also be major Contractually, the situation is
refurbishment of the depots somewhat complex. Network Rail
in Kirkdale and Birkenhead, so is undertaking the work, funded
they can be adapted to maintain by Merseytravel. VolkerRail is the
modern trains, moving to more delivery contractor, employing
computer-based diagnostics. AECOM as the lead designer.

Rail Engineer | Issue 177 | Aug/Sept 2019


ELECTRIFICATION/POWER 47

The substation work needed


was almost equally complex.
Seven were to be upgraded
(three on the Wirral lines and
four on the Northern lines) by
the provision of high-voltage
(HV) switchgear modules,
auxiliary transformers and
isolation transformers.
One track paralleling hut
(TPH) would be converted
to become a full DC
substation by the provision
of an HV switchgear module,
a DC rectifier module, a
transformer rectifier, an
auxiliary transformer and an
isolation transformer.
In addition, three completely
new HV / DC substations between Maghull North and sites. In addition, ground buildings);
would be built, each including Town Green stations. There investigation works, including »» Telecoms (SCADA
HV switchgear modules, will also be one between the soakaway testing, were connections for new
DC switchgear modules, new DNO substation building undertaken for all substations, substations);
DC rectifier modules, at Birkenhead North and UTX and URX sites. »» Geotechnical (ground
transformer rectifiers, auxiliary the upgraded substation at The design itself brought in the investigation factual and
transformers and isolation Bidston. skills of AECOM’s experts in: interpretive reporting,
transformers. Modifications to the »» Civil and structural slope stability analysis,
All this would draw existing High Voltage (HV) engineering (foundation slope remedial works and
down more power from route at Aintree substation designs, ancillary civils retention structures);
the distribution network required the existing works, cable management / »» Highways (road access for
operator (DNO), so three new HV cable to be cut and containment systems, UTXs, new substation sites, including
substation buildings would redirected into the existing URXs, brickwork and DNO road safety audits);
be required, constructed in substation to create two
accordance with Scottish separate HV feeders.
Power Energy Networks’ In addition, electrical
specification, to accommodate traction equipment (ETE)
a 33kV power supply and a enhancements include
33kV/11kV transformer to suit upgrades to the existing
the demands of Network Rail’s along-track continuity
upgraded substations and bonding, impedance bonds,
equipment. negative DC track feeder

HV feeders
cables and track isolation
switches.
WE’RE RECRUITING
ELECTRIFICATION
Modelling of the existing
Network Rail distribution Ongoing design
system identified several AECOM has now completed
areas of weakness within its
existing HV feeder network.
Based on these findings,
outline designs (GRIP 3) for
the HV feeders and ETE
works and is carrying out the
ENGINEERS
AECOM recommended detailed design (GRIP 4/5) for
the introduction of new HV the HV, ETE and substation
supplies to the proposed works.
new substation sites at Long It’s a complex job, requiring
Lane and Aughton as well both preparatory work and
as HV cable modifications at the interfacing of several
Aintree. different design disciplines.
Join us in your next
These HV feeder Before design could career move. Apply now
enhancements included the commence, topographical
provision of three new HV surveys were undertaken on
feeders. One will be between all of the substation, under-
Walton and Long Lane, another track crossing (UTX) and
at a site still to be determined under-road crossing (URX) aecom.com/uk/electrification-careers/

Rail Engineer | Issue 177 | Aug/Sept 2019


48 ELECTRIFICATION/POWER

The AECOM E&P team


The AECOM E&P team consists of 125 engineers
spread over nine offices in the UK, Madrid and
Bangalore.
All of AECOM’s rail disciplines feature a very
comprehensive competency process. In addition, there
is an independent process for internal assessment of
CRE and CEM competency. This ensures that, at all
levels, engineers are assigned to projects matched
appropriately to their skills. For E&P, this is especially
important as there are a large number of sub-discipline
specialisms to cover, for example earthing and bonding
in electrified areas.
This competency process is also used for staff training
and development to guide on appropriate mentoring
as required.
AECOM’s teams are competent in all elements of
trackside LV design, including points heating, signalling
power (there is in-house competency to undertake
testing and inspection); station and trackside building
M&E design (supported by the buildings division
with 350 M&E engineers) to have the capability and
»» Drainage (flood risk assessments, SuDS (sustainable drainage competence to undertake any size rail station scheme;
systems) suitability assessments); OLE design with demonstrable competence in all series
»» Environmental and ecological surveys and management. with recent Series 2 experience on GOBE (Gospal Oak
In addition, consideration had to be given to the key external to Barking Electrification); traction power (including
interfaces with both Scottish Power Energy Networks and traction simulation), substation (750V DC (Wessex
Siemens Switchgear. Capacity Alliance PSU) through to auto transformer
feeder station (Boreham feeder station design)) and
Smooth progress? HV design up to and including 66kV (the industrial
In the main, the design process went smoothly. AECOM power division covers design up to and including
principal engineer Azadeh Ghadamgahi, who has over 12 400kV); all elements of ETE design (S&C Alliance and
years of experience in the design and management of power Wessex Capacity Alliance) including protection studies
systems and electrification projects, commented: “The and stray current mitigation design; and full depot
design submission was comprehensive and received only systems design capability in the South West, which
minor comments back from the client. The team was aware can be demonstrated with recent commissions with
of the programme and deadlines by having effective/good Southwestern Railway at its Fratton, Farnham and
communication. Basingstoke depot enhancements for new rolling stock.
“While going through the technical quality review process, In addition, AECOM operates Bentley’s ProjectWise,
everyone, whether they are a designer, checker, CRE or lead which supports a common data environment (CDE), for
verifier, was accountable for their own work, which helped us all its projects, which allows for unrivalled workshare
to have a successful submission. ability across all offices and geographies. This, coupled
“As there are several sites within this project, with a with AECOMs desktop Jabber system (calls and screen
multitude of designers, our aim was to maintain consistency of sharing) and office-wide video-conferencing facilities,
approach in order to produce a standardised product. enables virtual side-by-side working and meetings
“As with any major project, there have been requested globally.
changes to the design from the client later in the process, AECOM’s UK design teams are able to interact with
which we have integrated faultlessly.” our systems modelling team in Madrid as a single
One of the features of this project was the number of young delivery unit to provide for the complete electrification
designers working on the team. One such was Luke Thurgood, solution:
who started his career as a rail design engineering apprentice »» Electrification system studies and modelling;
and has learnt his trade through the support of senior »» Overhead line design;
engineers around him. He now has a strong knowledge of the »» Third and fourth-rail design;
design of heavy-rail electrification systems, mainly focused »» Traction power substation (11, 22, 25, 33 and 66kV)
around third-rail contact systems, negative bonding and points modification/replacement;
heating supply and distribution. »» HV feeders 11, 22, 33 and 66kV (replacement or
In the past year, Luke has obtained Engineering Technician diversion);
(EngTech) status with the IET and continues to develop his »» Earthing and bonding and stray-current mitigation;
academic knowledge while working by undertaking further »» Points heating;
studies (HND) at London South Bank University. All his studies »» Lightning protection;
have been funded through the government’s apprenticeship »» EMC/EMI management;
scheme - AECOM is a keen supporter of this initiative. »» ECR modifications including SCADA.

Rail Engineer | Issue 177 | Aug/Sept 2019


ELECTRIFICATION/POWER 49

PELI 9600
Wide-Angle Lighting System

‡ SAFE: Eliminates hazardous


dark areas

‡ ECONOMIC: Reduced number


of lights & generators

‡ TOUGH: IP67 & drop


tested to 3 metres

‡ COMPACT: Inter-locking
stack system for ease of
transport & setup

‡ SIMPLE: Linkable system,


compatible with existing
poles & 110V cables

‡ EFFICIENT: Patented Peli™ LED


light engine, optimises beam
POWER INDUSTRIAL CONNECTORS
spread. Zero maintenance

ADJUSTABLE BEAM
Earth Hinge Solutions
T: 01457 869999 Stäubli Electrical Connectors specialise in providing
E: sales@peliproducts.co.uk PELIPRODUCTS.CO.UK
electrical connectors that meet the demands of harsh
environments, such as innovative integrated-earth
solutions, helping you improve safety and save costs.
9600 quarter page rail engineer 90 wide x 130high.indd 1 13/05/2019 11:18:44

Advantages

10 £99
■ Replaces the conventional hinge and the earth braid between

branded the door and the cabinet

polo shirts ■ Integration in confined environments with limited space

■ Quick and easy maintenance (mounting and dismounting)

■ Improved impedance of the door compared to braid solution

■ Enhanced EMC effectiveness

Pick 10 of our best selling


Pro RTX heavyweight Polo Your expert in railway connection solutions
Shirts for just £99.
Not only does this include the
price of the polo, but you also
get a logo applied to each www.staubli.com/electrical
garment, your logo set up
and free delivery!

MATCHING ITEMS AVAILABLE


Cargo Trouser
Hoodie
Micro Fleece
Security Sweater
Softshell Gilet
Sweater
Two Layer Softshell Jacket
Workwear Trouser
8 10 12 14 16 18 20 22 XS S M L 2XL 3XL 4XL 5XL 6XL

Polo shirt colours available.

To order, simply email deals@railshop.com


with your logo, sizes and colour.
We’ll send you a full proof for you to sign off, before production.

www.railshop.com
Terms and Conditions
All prices quoted are excluding VAT. Additional logos available at £2.50 per garment.
Staubli is a trademark of Stäubli International AG, registered in Switzerland and other countries.
Maximum logo size 100mm x 100mm. Maximum stitch count: 10,000 stitches. Workwear and uniforms for the Rail Industry © Stäubli 2019 | Photocredits: Stäubli
For full terms and conditions see railshop.com/terms

RailShop-A4-10-Polos-99.indd 1 12/07/2019 12:34

Rail Engineer | Issue 177 | Aug/Sept 2019


50 ELECTRIFICATION/POWER

Sicat joins DANNY


AISTHORPE

Network Rail’s UK Master Series

W
ith the need to electrify significant parts of Great Britain’s rail One of the main perceived advantages
network to meet rail decarbonisation targets, the industry of the traditional UKMS equipment (which
continues to design and develop innovative solutions that will covers line speeds up to 125mph) is its
deliver improved value over the life cycle of an asset. modular construction. However, system
procurement is often left until the later
One such solution, Siemens Mobility’s The light-weight, aluminium Sicat SA stages of the design process - thereby
Sicat SA cantilever, has received platform offers cost, installation and restricting the opportunity for any design
acceptance from Network Rail’s maintenance advantages, having been flexibility. In contrast, the Sicat cantilever
Contact Systems Group and so is now designed with a focus on ‘value creation’ arrangement can be designed and
included in Network Rail’s UK Master to address the challenge that the industry readily fabricated specifically to suit the
Series (UKMS). UKMS is a standard set has been given to reduce the cost of requirements of each site and so optimise
of Overhead Line Equipment (OLE) electrification schemes and optimise performance.
design ranges for use on new and their efficiency through the adoption of The components for each style of
refurbishment schemes on Britain’s rail alternative technologies and processes. cantilever are largely common throughout
network. the Sicat range and can therefore be
Demonstrating the advantages bulk ordered, even at outline design
Siemens was able to demonstrate the development phase. This not only gives
benefits of Sicat SA through its work on greater assurance in achieving programme
the TransPennine Route Upgrade (TRU) delivery targets, but also provides the
project through evalutaion and dynamic flexibility to meet any programme
testing processes. Working alongside changes. As the Sicat cantilever assembly
design consultancy TSP Projects and key is fabricated from lightweight aluminium
alliance partners to deliver a number tubing and aluminium components,
of value-engineering work streams to the system offers an effective balance
demonstrate the benefits of including between adjustability, ease of fabrication,
elements of the Sicat SA design range and ease of installation.
solution into the UKMS. Using like-for-like system parameters,
most UKMS cantilevers require a top
mast bracket to be positioned 1.1
metres higher than is required for
a Sicat SA cantilever, generating a
saving in material cost. As a result,
initial estimates show that the required
section of steelwork can be reduced,

Rail Engineer | Issue 177 | Aug/Sept 2019


ELECTRIFICATION/POWER 51

Clearances are an essential factor in the


planning phase of overhead line system
design. If a conflict of electrical clearances
occurs, then considerations have to
be made to either modify the relevant
structure (bridge, tunnel or building) or
representing a 25 per cent reduction the project identified that TSI dynamic lower the tracks, both of which require
in cross-sectional areas, and therefore performance criteria could be met with complicated, extensive and expensive
further saving in material costs. increased span lengths and is in the process design and construction works to achieve
One of the key differences between the of updating the Master Series to allow the required electrical clearance.
Sicat SA and UKMS OLE equipment is the spans of up to 74 metres. To address this issue, and so to reduce
weight of the support assemblies, with Longer span lengths can significantly or eliminate the costs of either having to
Sicat's cantilever and brackets being 28 per reduce the number of foundations, make modifications to the structure or to
cent lighter and the under-portal cantilever structures and cantilevers required, as well lower the track, Siemens has developed
35 per cent lighter. as the associated equipment, resulting in an alternative solution which uses a surge
At portal locations, there is also a significant cost reductions due to reduced arrester in circuit with the overhead line
significant difference in weight associated infrastructure, faster installation, reduced system. This offers significant benefits
with steelwork to support the assemblies, overall time on site and significantly both in terms of the cost and speed of
such that an additional machine with a reduced waste and materials surplus. electrification works, particularly compared
crane arm is required to install UKMS safely An early incarnation of the Sicat SA to any requirement for reconstructing or
and efficiently - whereas Sicat SA support overhead line system has been in operation modifying buildings, bridges or tunnels, or
steelwork can be safely installed from the in Scotland for more than 10 years, having for lowering existing tracks.
basket of a mobile elevated work platform replaced the life expired OLE equipment By introducing a surge arrester in this
(MEWP). on the 6.5-mile Glasgow Shields junction way, if over-voltages do occur (potentially
These savings in plant and installation to Paisley Gilmour Street line. More than as a result of lightning strikes), then these
time, together with safer manhandling ten years on, the equipment continues are limited by the surge arrester to a
at height (compared to that of heavier to deliver outstanding service, with magnitude of voltage which complies with
cantilevers), provide significant cost savings. exceptional reliability, availability and the available electrical clearance values
The system may also be constructed either maintainability (RAM) scores achieved on between the overhead line and structure.
on or off-site, offering further potential cost, this suburban route. Depending on the required protection
operational and safety benefits. Catering for a large number of multiple level, surge arresters can be applied to the
As well as new ‘green field’ electrification pantographs, the route called for overhead line equipment on both sides
schemes, the Sicat SA cantilever can be high availability and robust, long-life of the structure - for each contact system
used as a direct replacement for life expired performance. Sicat SA has delivered this, running through the structure requiring a
or damaged equipment on existing routes providing assurance that, over the system’s reduced electrical clearance.
and is compatible with existing MkI, MkII life, it can meet both operational and Surge arresters have now been specified
and MkIII overhead line systems cantilever environmental requirements, delivering by Network Rail for a structure in Cardiff,
assemblies. Therefore, when used in areas reliability and therefore high availability. where restrictions caused by the proximity
of existing electrification, the reduced of a canal, combined with a rail intersection
load of the Sicat cantilever increases the Clearances and surge arrestors bridge, mean that the track simply can’t
probability that existing masts may be re- Digitalisation enables transport operators be raised or lowered to accommodate
used, with resultant cost savings. worldwide to increase value sustainably compliant electrification clearances.
over the entire lifecycle, with one such The Sicat system has already been
Dynamic modelling solution being Siemens 25kV surge arrestor. installed on nine routes across the Danish
To identify the optimum solution for The cost of electrification programmes is railway network, covering a total of 1,300
each individual project, Siemens is able often adversely affected by the inevitable kilometres of new electrified line.
to carry out dynamic modelling of the proximity between live overhead-line
interaction between the overhead line conductors and trackside structures. As Danny Aisthorpe is engineering director,
contact system and different rolling-stock the overhead line system is energised at rail electrification with Siemens Mobility.
pantographs. This allows OLE designs 25 thousand volts, compliant electrical
to be fully optimised; for example, using clearance must be allowed at both
parameters derived from both UKMS and design and installation stages to ensure
Sicat for open route and discreet features, the electrification infrastructure doesn’t
with various pantograph and speed suffer unnecessary flashovers between live
combinations. conductors and lineside structures.
The TRU project has focused on value- The required electrical clearances are
engineering workstreams in support of defined within legislation and standards.
the Railway Industry Association’s Cost of These control the design and installation
Electrification challenge. The project team requirements and allow for a number
utilised Siemens’ OLE dynamic software of ‘worst case’ conditions, including, for
modelling tool to optimise overhead example, environmental conditions and
line parameters. Using this approach, pantograph uplift.

Rail Engineer | Issue 177 | Aug/Sept 2019


52 ELECTRIFICATION/POWER

STEVE
COX

T
he UK has a clear target to
reach net zero emissions by
2050. Rail is already a naturally
low-carbon means of transport,
responsible for less than 2.5 per cent
of total transport emissions and about
0.6 per cent of the UK’s total emissions.
But in a world where electric cars are
becoming quickly commonplace, to
remain competitive, rail’s emissions can
and must be reduced even further.

Industry must play its part, not least by


meeting the Government’s challenge to
remove all diesel-only trains by 2040. As
the Committee on Climate Change’s report
in June outlined, decarbonisation by 2050
is achievable and affordable but it means
every sector, not just some, need to act. Electrifying Innovation
The need for electrification
At Alstom, we believe a two-pronged
approach is essential here. Electrification
is the only viable technology that can be
deployed for high-speed and very long-
distance passenger parts of the network, network can play its part in taking polluting diesel trains off the rails. This innovation brings
and it will have a crucial role in the coming a wider range of benefits too, from a reduction in construction risk, improved health and
years as the network winds down its usage safety during the works, and the need for less kit that, in turn, improves the public realm.
of diesel trains.
For other parts of the network, where Alstom’s electrification pedigree
electrification is not feasible due to costs Nestled in the foothills of the Italian Alps lies the beautiful Italian city of Lecco, situated
or practicalities, hydrogen is the most on the edge of Lake Como and the home to Alstom’s in-house centre for excellence for
viable answer. It is proven to work by electrification components. It is here that Alstom’s high-speed electrification systems, which
Alstom in Germany, and ready to enter are installed throughout Europe, are manufactured and supplied.
the UK network soon through Alstom In the UK, this has meant that the Lecco factory has also supplied much of the
and Eversholt Rail’s ‘Breeze’ project to electrification equipment for the railway systems being installed by Alstom’s joint venture
convert Class 321s to hydrogen-powered with TSO and Costain in the Crossrail tunnels. This electrification system is based on
at Alstom’s train modernisation centre in Alstom’s OCS3 range of equipment, with Alstom S&I Lecco rigid overhead conductor beams
Widnes. being used throughout the tunnels.
As a global leader in electrification, Having complete ranges of electrification equipment suitable for mainline, high-speed
Alstom also has the proven and innovative and urban schemes has been a critical factor in Alstom achieving its global leading
solutions to ensure electrification of the position in electrification. As part of this, Lecco has produced the Clever Cantilever, or

Rail Engineer | Issue 177 | Aug/Sept 2019


Book your place at
this essential rail event

Call 01530 816 456


or visit railsummits.com
or email events@rail-media.com
to secure your space

Rail Safety
Summit 2019
3rd October
Addleshaw Goddard
London

The Rail Safety Summit is proving time & time again that it is
a must-attend event for up to date rail safety information.
We have the following confirmed speakers:

· Ali Chegini (Director – System Safety & Health) RSSB


· Allan Spence (Head of Public & Passenger Safety) Network Rail
· Emma Gilchrist (CEO) Motion Rail
· George Bearfield (Director of Health & Safety) Rock Rail
· Lex van der Poel (CEO, Co-Founder) Dual Inventive
· Marcus Aldred (Managing Director) Brightboot
· Martin Frobisher (Group Engineering Director) Network Rail
· Mike Esbester (Senior Lecturer) University of Portsmouth
· Nicola Uijen (Route Director, HSEA) Network Rail
· Richard Peters (Chief Medical Officer) Network Rail
· Simon French (Chief Inspector) RAIB
· Stuart Webster-Spriggs (HSQE Director) VolkerRail
Don’t miss out – Book your ticket today!

The Rail Safety Summit is a CPD Certified Event

Safety
Summit
54 ELECTRIFICATION/POWER

CLever, developed specifically for use in to run ancillary wires such as earth wires
the UK and now fully part of the Network and feeder wires, providing a complete
Rail Master Series range of equipment. electrification delivery solution.
This innovative electrification support The advantage of the Alstom
system has now been in operation on the electrification installation system is that
UK network since 2016. three wire runs can be completed in
High-output delivery in the construction one shift, compared with four shifts
phase is something that Alstom has conventionally for one typical wire run. A
developed over a number of years in higher quality installed tension length is
specialist wiring techniques. In October achieved due to the mechanisation and,
2015, Alstom introduced its wiring as with all Alstom innovations, the focus
train in the UK. Modified specifically is on safety as the number of trackside
for use on the British network, this was workers is reduced. This innovative and
successfully deployed on the Edinburgh unique electrification delivery system
Glasgow Improvement Programme then was highly commended in the 2019 Rail
subsequently on Stirling, Dunblane, Alloa Partnership Awards for driving efficiency.
and Shotts. The train consists of seven With any infrastructure project,
vehicles, each of which has a specific successful delivery and commissioning
purpose - a traction crane and MEWP frequently requires long, costly
(mobile elevating work platform) unit, drum possessions. When combined with the
carrier, wire tensioner, manipulator and safety risk element of having multiple
MEWP, two independent MEWPs and a workforces on track, any innovative
traction unit with MEWP and pantograph. development that improves safety while
The wiring train has the advantage reducing the commissioning period,
of being classed as an OTM (on-track saving time and money, is valuable. In
machine) and, as such, can travel loco- this regard, Alstom’s industry-leading
hauled. Once the train gets to the work signalling business has developed its obtain all the information they require
site and into the possession, it can run SMARTCert tool suite to eliminate the from one single source of truth.
out catenary and contact wire together need to use spreadsheet trackers and SMARTCert allows for multi-user access,
at full line tension. The individual paper-based reporting - this tool can also a single source of information and
units that comprise the train can split, be applied to electrification projects to process improvements to the paper and
allowing registration activities to be provide efficiency benefits. spreadsheet-based process whilst still
undertaken and the fitment of any in-line The SMARTCert system allows all complying with the Network Rail test and
items such as section insulators and the stakeholders within the commissioning commissioning standards.
like. The wiring train can also be used process to interact and

Rail Engineer | Issue 177 | Aug/Sept 2019


ELECTRIFICATION/POWER 55

ADComms, a Panasonic company, applies


technology and technical expertise to the UK
Rail industry that delivers solutions for:

• Safety Critical & Security


• Customer Experience
• Infrastructure & Operations

Connectivity enables innovation, and innovation


delivers safer operations and journeys – we blend
technology to deliver CCTV analytics, access
control, onboard security and customer experience
with resilient network infrastructure.

Tel: 01724 292200


Website: www.alandickcomms.com
Email: info@adcomms.eu.panasonic.com

NOMINATIONS CLOSE ON THE 4TH OCTOBER 2019

NOMINATE
NOW ONLINE!
YOUR
TheRailStaffAwards
rail-media
@railstaffawards
AWARDS
WWW.RAILSTAFFAWARDS.COM
THE NEC, BIRMINGHAM // THURSDAY // 28TH NOVEMBER 2019
Rail Engineer | Issue 177 | Aug/Sept 2019
56 ELECTRIFICATION/POWER

The additional benefit gained from


Hesop is that, by optimising the electrical
power system, the distance between
traction substations can be increased
and, potentially, their number reduced
by 20 per cent. This reduces the amount
of infrastructure and hence construction
required, providing a capital and lifecycle
cost advantage as well as a safety benefit as
less construction eliminates the associated
health and safety risks.
For the urban environment another form
of innovative electrification is the SRS
system. Building on 15 years of expertise
acquired developing APS ‘third rail style’
technology, Alstom extends its feeding
systems portfolio with SRS, a conductive
ground-based static charging system for
trams or electric buses equipped with on-
board energy storage.
The electrification process Innovative systems SRS is a technological breakthrough in
Alstom, as a global leader in Not only is Alstom a leader in overhead electric public transport, enabling city
electrification, has developed a complete, electrification, its innovative reversible authorities to operate clean, quiet electric
efficient delivery process built on power-supply substation (issue 140, June fleets eliminating the need for catenary
four pillars: BIM (Building Information 2016) optimises the power required for masts and overhead lines. This is an added
Modelling), automation, complete light rail and metro traction systems advantage for cities with exceptional
capability and experienced people. and can capture up to 99 per cent of architectural heritage or constraints such as
Alstom is one of the few businesses that recoverable energy from regenerative narrow streets or bridges, where overhead
has a complete electrification offering braking. Hesop, of which there are units infrastructure is unsuitable or unfeasible.
covering design, manufacture, installation on London’s Victoria line, the Paris T1 The charging system can be used at stops
and maintenance. tramway and Riyadh Metro, increases while passengers board and leave the train
The Alstom electrification process is the energy efficiency of the electrical and also at line terminuses, in particular for
centred around BIM, using automatic system, resulting in a decrease in carbon electric buses which can fully recharge in
design tools to develop the model out emissions. This is achieved by converting the space of a few minutes.
of which schematics, bills of material and the energy emitted by trains during Alstom is a company that truly delivers
cross sections can all be developed. These braking into usable electrical power that ‘mobility by nature’, a leading global player
tools provide the maximum advantage can be used by station services such as in sustainable and smart mobility. Alstom
when deployed early in the scheme lighting and elevators. is investing in the UK, and through its
development, at GRIP 3 or 4 (option As the energy is reused, it removes a electrification products and new traction
selection and single option development). source of heat. This, when deployed in systems like hydrogen, it stands ready to
At this stage of the design process, tunnels, will have the effect of reducing play its part in decarbonising Britain.
accurate scheme layouts and BOMs can temperature - important in hot summer
be developed that help with both costing months or for railway systems installed in Steve Cox is Engineering & Technical
and planning for later GRIP stages of the UK and even hotter climates. Director SS&I at Alstom.
detailed design and delivery. The Alstom
BIM process allows for asset information
to be collected throughout delivery,
providing the maintainer with a high level
of information on the delivered electrified
asset.
Technical excellence and competence
are key pillars in Alstom’s delivery process,
in this regard a World Class Engineering
(WCE) structure has been developed. WCE
is Alstom’s way of identifying technical
expertise within the business globally
and providing a platform to sustain and
develop the technical expert community.
It means Alstom can measure experts and
competence in a consistent way across the
business and ensure the best people are
selected to deliver the clients project.

Rail Engineer | Issue 177 | Aug/Sept 2019


ELECTRIFICATION/POWER 57

Wiring Train Methodology

n Arrival into possession

n Loco uncoupled
worksite

n Wiring train self propels to worksite

APV250 RSM9 X2 PT500 CG002B + CG002A + RT250

n Wiring train uncouples into sub


systems and individual vehicles

n Arrival at the anchor mast

n Preparation to anchor

n Vehicle Setup at anchor mast

n Anchoring
Fixed connections
not via tensioner

Temp
n Commence running wire Droppers

n Continuous Production

RSM9
n Droppering activity Permanent
Droppers

APV 250 RSM9 RSM9


n Final Connection Tensor X Mid Point
Anchor
Connections

Mid Point Installation

Rail Engineer | Issue 177 | Aug/Sept 2019


58 ELECTRIFICATION/POWER

Anglia OLE renewals:


SUCCESS THROUGH COLLABORATION

CAROLINE
BACHER

S
ince 2007, Network Rail has steadily been replacing the overhead line to minimise costs and possession
equipment (OLE) on the Great Eastern line from London Liverpool Street, first requirements.
to Chelmsford and then on to Southend Victoria. The old system had reached At the end of 2018, Furrer+Frey won
the end of its lifespan was increasingly becoming a reliability issue. the contract to be the lead designer
on this project. This move makes it
A key goal for the project team was to London Fenchurch Street, the line that was possible to replicate the success of the
reuse as much of the existing infrastructure previously known as LTS (London - Tilbury - Great Eastern project, continuing the
as possible. Southend). successful and collaborative working
Working with OLE specialist Furrer+Frey, Like the Great Eastern, the first sections relationship between Network Rail
Network Rail developed a new, auto- of Thameside were initially electrified with and Furrer+Frey and bringing all their
tensioned, modern 25kV AC system DC equipment in the 1940s. This was relevant experience and expertise
that retained a vast number of existing further extended in the 1960s at 6.25kV, forward to the new project.
steelwork structures in order to save costs, before finally being converted to the more This consistency is also maintained
reduce risks and minimise disruption and common 25kV AC in the 1980s. As with on an individual level, as many staff
impact on service. It also aimed to address Great Eastern, the initial DC sections were members from the Great Eastern project
known reliability and performance issues, installed using fixed tension equipment, teams have now moved across to the
and in such was tailored to the region and meaning that there are no balance Mk1 Renewals project, both within
its specific challenges. weights or tensioning devices to keep Furrer+Frey and Network Rail, as well as
Upon completion of the new system’s overhead wires taught and instead wires Network Rail’s long-term partner CPMS,
development, a rolling programme of are fixed at a specific tension. This means project manager for the works, and the
electrification renewal was undertaken on that, on hot days, wires can sag requiring in-house installation team OCR. Finally,
this route and, after 10 years, is due to speed restrictions to be put in place. Furrer+Frey is once again supported by
finish. Once some initial teething issues Since the Thameside system was mainly OLE Ltd, another carry-over from the
were ironed out on the first few sections, installed in the 1960s, reliability had Great Eastern.
both design and installation went smoothly fallen over time and service disruptions The collaborative spirit of the teams
and without major drawbacks as the teams had become more common. The working together to deliver the project
grew closer together and the supply chain route has been installed primarily with is ensured by a number of contractual
worked well on all levels. Furrer+Frey and Mk1 equipment, which is an early UK elements to which all parties are
the Network Rail in-house installation team electrification system, thus the current committed. These include progressive
OCR were working hand-in-hand to deliver project has become known as the Mk1 design reviews, as an informal means
the renewals without major impact on the Renewals project. Due to the age of this to align and manage expectations, and
service. Mk1 equipment and its inherent reliability a series of collaboration workshops to
issues, there is an increased maintenance define behaviour and communication
Moving on to Thameside cost associated with this life-expired rules and address any issues outside the
With the Great Eastern largely complete, equipment. technical core of the project.
Network Rail has now started to plan the Once again, Network Rail decided to
next phase of this programme, renewing renew the electrification equipment but Caroline Bacher is head of UK projects
the OLE on the Thameside route out of retain the structures wherever possible, with Furrer+Frey.

Rail Engineer | Issue 177 | Aug/Sept 2019


BRINGING YOU RENTAL SPEC GENERATORS AND
LIGHTING TOWERS – FROM 10kVA TO 2500kVA

ULTRA SAFE
48V DC

ULTRA SAFE
NEW 48V DC

NEW

A B RU N O GROUP COMPA NY
BGG UK Limited · Delta House · Tendring Heath ·
Nr. Clacton · Essex · CO16 0BU
Tel 01255 830355 · info@bgguk.com · www.bgguk.com
60 ELECTRIFICATION/POWER

Safer, quicker and sustainable


CABLE PROTECTION

A
s the world, and the railway, goes more and more digital, the big width, this practice can be rather unsafe
growth industry seems to have been in the production of cable. Offices and, with slips, trips and falls maintaining
are festooned with cables linking computers, servers, storage devices, their number-one spot in workplace
alarms, CCTV cameras, printers, scanners and a host of other devices. incidents, it’s a risk that needs to be
Every desk has the potential to have a ‘rat’s nest’ of cables lurking underneath it. reduced.
And, of course, the manual handling
Homes are no different. To the cables for power cables - both traction and of cable troughing has to be carried
linking computers, routers, printers and signalling power - as they cannot be out safely and within prescribed weight
scanners can be added the ones to TV replaced. Communications cables, for limits. Solutions to improve this element
sets, control boxes, recorders, speakers, signalling control and other functions, of the project are very welcome.
CD players and satellite dishes. are often also needed for security and There are two solutions to these
One solution to this is, of course, to reliability reasons. problems. The first is to make the
make as much as possible wireless. Many So, the side of the railway starts to look troughs from lightweight polymer
devices now use Wi-Fi, Bluetooth or like the side of an office desk - cables, materials - several different solutions now
infra-red technology to get rid of those cables and yet more cables. available.
annoying cables. These cables need protecting. The second is to elevate the trough
Traditional methods see ground-based above the ground on posts. Then, no
Cable protection cable troughing used. However, where matter the angle of the side of the
The railway has the same problem. there isn’t a clear walkway alongside, embankment or cutting, the trough
Some wireless technology is creeping the trough lids are often walked upon. If is safely above it all. It also can’t
in, but there is no solution to the need the route is not of designated walkway be walked on - another plus - and

Rail Engineer | Issue 177 | Aug/Sept 2019


ELECTRIFICATION/POWER 61

designers, engineers and construction


teams to develop bespoke units to fit,
no matter what the infrastructure is that’s
presented to them - versatility at its best!
ArcoSystem has now been present in
the UK’s rail sector for three and a half
years and has been used on some major
schemes, from Crossrail Anglia and Weaver
Wavertree resignalling to, more recently,
HS2 enabling works at Euston. In such
a short space of time, it has become a
popular choice amongst contractors with
over 125km of route now installed on the
UK’s railway network.

Safer installation
Although Scott Parnell has seen
ArcoSystem go from strength to strength,
the company has certainly not just sat back
and rested on its laurels. It has also worked
presents cables for maintenance at waist The reduction in post centres not only on creating an installation technique
height, making things simpler for the protects workforces, but also decreases which was even safer for workforces to
maintainer. installation time by up to 60 per cent. implement. Following an overview of the
Network Rail prohibited the manual As possession times get more and more entire installation process, Scott Parnell
handling of metre-length C/1/43 ground- congested, with more contractors having to identified areas for improvement and
based concrete troughing units in 2014. share track time, this saving is invaluable. enhanced these accordingly.
Since then, the industry has kept a very ArcoSystem not only works well as a ArcoSystem offers a vast reduction in
strict eye on the installation of cable foundation-installed elevated route, it also manual handling by reducing the number
troughing and any methods introduced interfaces seamlessly with the complicated of holes installers need to dig into the
to reduce the risk to workforces were, rail infrastructure. Transitioning from ground for post foundations. As the
and still are, very welcome. With this in ground-based troughing up to an elevated six-metre distance between post centres
mind, Scott Parnell worked in partnership route then back to a wall mounted system cannot be expanded, the maximum
with Complete Composite Solutions is easy. Alternatively, it also works perfectly saving in manual handling is achieved.
to introduce the UK to a revolutionary for a suspended route by utilising handrails Furthermore, it is not possible to reduce
product which was already leading the on one of the many walkway systems. The the weight in the system components
way across Europe with full approval by system should be hung on the outer edge without affecting the integrity of
Deutsche Bahn. of the handrail to prevent the safe walking the product. Scott Parnell will never
area being reduced in size. compromise on quality, and therefore
Innovative system Should the standard range of ArcoSystem it was realised that improvements were
ArcoSystem is the only elevated not be suitable for certain areas, Scott possible and would be made. Stand by for
troughing system in the UK which can Parnell will work closely with project the innovation of the year...
span six metres between post centres.
Already fully approved by Network
Rail, the product offers a reduction in
hole centres (versus traditional elevated
systems) of up to 75 per cent. This saves
workforces from the process of digging
out foundations, mixing postmix and
water, and installing the posts every 1.5
to 2 metres, as is the case with traditional
systems. With this reduction in post
centres, there is also a decrease in the risk
of cable strike, which can occur during any
ground penetrating installation.
The ArcoSystem troughs are made from
a lightweight, pultruded, twin wall fibre-
reinforced polymer (FRP), which provides
the strength to support each length over
six metres. In addition to this, it means the
overall weight of each six-metre length
is under 36kg, making them safe for two
people to lift easily.

Rail Engineer | Issue 177 | Aug/Sept 2019


62 ELECTRIFICATION/POWER

When the foundation is ready, the two


bags are opened and one poured into
the other. A vigorous shake will mix the
two components together and then the
mixture is poured into the ground. Within
10 minutes, the product will expand to
twenty times its original size and within
twenty minutes the mix will have set.
Health and Safety protocols are no
different to that for the application of
postmix, and transportation and storage
costs are both dramatically reduced.
Scott Parnell’s new Techno-Crete is also
ideal when used as a foundation for a
variety of railway systems, from handrails
to fencing and DIS boxes. Anywhere
postmix can be applied, Techno-Crete
can be used as an alternative.

Innovative supply
Sharon Rice, national rail manager at
Scott Parnell, said: “The UK’s rail industry
has been aware of the implications that
manual handling has on its troughing
installation teams for some time and
huge progress has been made to improve
this. At Scott Parnell, we have worked
tirelessly to make sure we do our best to
For each post foundation which is not end there. With a curing time of just support this movement. For example, we
embedded into the ground, approximately 20 minutes, Techno-Crete can decrease were one of the first to provide six-metre
60kg of postmix is used, along with the installation time of ArcoSystem even length GRP troughs which sit comfortably
around 20 litres of water to mix it. This further. within safe weight limits for two people,
process, which has not changed since Where postmix has traditionally had a reducing not only the weight, but number
elevated troughing was first introduced curing time of 24 hours, this has meant of lifts required during installation.
into the rail sector, is one which is almost installation teams have had to plan “With the introduction of Techno-Crete,
always done manually, without the aid of work carefully and revisit site again to we are taking things one step further
machinery. It therefore has a considerable install the trough route onto the posts by eliminating the need for three 20kg
musculoskeletal impact on the installation once the postmix has set. However, one bags of postmix, which are currently
teams, especially those gangs installing recent installation using ArcoSystem required to install each individual post.
troughing systems shift after shift, project with Techno-Crete resulted in 22 metres Posts are often positioned in difficult to
after project. of route being installed within just four reach locations meaning that postmix,
hours - all while workers were being and the large water quantities needed
Introducing Techno-Crete suspended from ropes down a steep to mix it, causes a huge manual strain on
To combat this problem, Scott Parnell has embankment! workforces and often requires a costly
introduced Techno-Crete, a new product Techno-Crete also has sustainable RRV to get it to the installation point.
that provides an innovative solution by benefits. It is manufactured using 85 per One box of Techno-Crete weighs far less
replacing the need for both postmix and cent recycled and sustainably sourced than a single bag of postmix, meaning
the associated water, around 80kg of vegetable and rapeseed oils. This is a key that one person can easily carry the
product, with just 1.6kg! advantage as CP6 begins, which has the material for up to 12 foundations in a
To put this into perspective: toughest sustainability targets the sector single lift.
»» 1km of traditional two-metre span has ever seen. “With all this in mind, Techno-Crete has
troughing requires 30 tonnes of postmix; The CO2 saving compared to postmix the potential to make a real difference to
»» 1km of ArcoSystem six-metre span is over 70 per cent - approximately 10kg the rail sector and the way construction
troughing, with only one third the of CO2 per post foundation. Just 100 and improvements are carried out.
number of posts, takes 10 tonnes of foundations using traditional postmix In particular, the reduction in time to
postmix; would require six tonnes of concrete complete projects and the resulting
»» 1km of ArcoSystem six-metre span to be used. Also, at the end of its life, safety benefits of quicker installation
troughing, installed with Techno-Crete, Techno-Crete can be crushed and fully and manual handling makes it ideal for
needs just 267kg of Techno-Crete. recycled into products such as precast possessions”.
Techno-Crete is revolutionary in the concrete. With innovations such as this, it is clear
reduction of manual handling, but the Techno-Crete is delivered to site in to see why Scott Parnell is the supplier of
benefits of this innovative product do a two-part set - ‘Bag A’ and ‘Bag B’. choice for the rail industry.

Rail Engineer | Issue 177 | Aug/Sept 2019


Scott Parnell Rail Division

KEEPING
YOU ON
TRACK...
At Scott Parnell we are proud to have
set up our own dedicated Rail Division.

Our knowledgeable team provides an


unrivalled service offering a range of
innovative, industry leading products.

• ArcoSystem, GRP 6m span • First class service from


elevated trough - exclusively rail industry experts
supplied and delivered nationwide
• Extensive choice of stock including
• Sole suppliers of Touch Safe GRP platform, trackside drainage and
Palisade - the easy-to-install, signalling products
lightweight, non-conductive
and corrosive resistant barrier • The only distributor to hold FOR
stock of Cubis Multiduct ALL YOUR
CIVILS
• Sole distributors of Techno-Crete
– the lightweight alternative • Competitive rates
to postmix concrete
& RAIL
SPECIFIC NEEDS

For more details about our rail products call one of the
team in our dedicated rail office on 0208 805 5797.

scottparnell.com
64 ELECTRIFICATION/POWER

GRAEME
BICKERDIKE

Better by design
M
ajor projects, new trains, bewildering technology: cables’ length. What could
these are the big-ticket items that command be simpler? But there are a
everyone’s attention these days. And why wouldn’t number of factors affecting its
they? Who cares about the high-volume, low-cost ability to fulfil that role safely
bits and pieces that literally hold the railway together? Nuts, and effectively, including
bolts, pins, clips, arms, brackets… environmental conditions, the
materials used, performance
Politicians don’t cut Basic principles in the case of fire or impact,
ribbons at the installation In case you’re unfamiliar resistance to corrosion and the
of a cable cleat, but they with the term, a ‘cleat’ is used cleat’s strength.
might - conceivably - have to to secure electrical cables The latter is often determined
explain the havoc wreaked to a structure by installing using a mechanical tensile
by one failing following an them at intervals along the test; however, the results can
electrical big bang. A single
Ellis cleats in the London dodgy component can inflict
Power Tunnels. disruption and embarrassment
that’s wholly disproportionate
to its size and cost, by a very
significant factor.
With this in mind - as the
magazine’s unofficial Analogue
Correspondent (my heart
was hewn from the earth
by Victorian navvies) - I was
despatched to Rillington
in North Yorkshire to visit a
company that’s been keeping
cables in check for almost 60
years. In parts, the experience
proved surprisingly digital.

Rail Engineer | Issue 177 | Aug/Sept 2019


ELECTRIFICATION/POWER 65

As you walk around, you


get the sense of an open,
collaborative culture and
an engaged workforce.
Innovation is encouraged and
facilitated through ongoing
- and sometimes speculative
- investment in new kit. This is
not a company that’s resting
on its laurels, but neither
are staff being driven to
distraction. Managing director
Richard Shaw tells me they
are encouraged to go home
at the appointed time and Installing Ellis brackets in
not check their emails. One the Severn Tunnel.
prove misleading as the force Back on civvy street, he trained culprit habitually ignores the
is applied in a slow, controlled as a plumber and set about edict whilst another recycles
manner. The electromagnetic manufacturing plastic pipe redundant equipment to assist
forces in short-circuit conditions clips and cable clamps, with with his construction of a
act almost instantaneously and electricity boards as his major traction engine! This seems a
oscillate in every direction, customers. That was 1962; happy place.
sometimes with destructive today the firm has an annual
consequences. A cleat is most turnover of around £7 million. Vertical integration
likely to fail at peak current, The operation moved to its Unlike many competitors,
about 0.01 seconds after the current site in 1974, about a Ellis is fully resourced in-house
event starts; a breaker won’t mile from the York-Scarborough - not only designing its own
have woken up by then. line. Unfortunately, the village products, but also building CAD
So, the only reliable way of station had closed 44 years models and subjecting them
demonstrating that a cleat will earlier. Following Arthur’s to finite element analysis. “This
withstand the resulting forces is retirement in 1987, the tells us where a component will
to also conduct a short-circuit company was acquired by Chris break and under what force”,
test - International Standard Calvert - its current chairman says Richard. “Then we can
IEC 61914 provides a formula - and fellow investors from 3D-print it.
for calculating those forces Walkern Victoria Industries. It “We know the printed model
between two conductors in a acquired EDL Cable Supports is about 40 per cent of the
three-phase supply. Potentially, in 2002 and has since become strength of the real thing due
they can amount to several a global force, offering one to the difference in plastics so
tonnes. of the most comprehensive - when we test it - if it comes
Restraining cables during catalogues of cleats, clamps, out at 40 per cent of the figure
a fault is a fundamental role hangers and associated we were expecting, we know
of the cleat; it’s a means of peripherals to international we’re on the right track. We can Production of Centaur
protection as well as support. In clients and projects. do all that work without ever cleats.
order to withstand the applied
forces, the optimum spacing
between each cleat can be
determined using a formula
which takes account of the
required loop strength and
peak short-circuit current.

Potted history
None of this is news to the
specialist team at Ellis - formerly
Ellis Patents - which boasts a
skilled workforce of around 60,
mostly residing in the towns
and villages around Rillington.
The firm was founded by Arthur
Ellis, who piloted more than 90
bombing missions for the RAF
during the Second World War.

Rail Engineer | Issue 177 | Aug/Sept 2019


66 ELECTRIFICATION/POWER

bolts cleat, a unique device


conceived in response to a
Network Rail enquiry. The
action had something very
pleasing about it.
Inevitably, there is a
procurement challenge here.
Ellis’ polymeric products are
more expensive than its metal
variants, but being less heavy
improves installation efficiency
- a big issue for the rail industry
given the scarcity of possession
time - whilst their longevity
means that whole-life costs are
lower. Cleats can be supplied
pre-assembled with the requisite
fixings - pushing up the initial
purchase price but delivering
benefits that reduce costs
(Above) Emperor cleats. making anything, but it gives us Attention to detail overall. Until we get our heads
the exact volume of materials As we know, though, the around these issues and learn to
needed, how long it will take to railway is different; visit most of buy smarter, better products and
manufacture and the price.” our classic tunnels and you’re lower expenditure will elude us.
Beyond that, Ellis’ capabilities unlikely to see many cleats.
extend to prototyping and Instead, the approach taken All that glitters…
tooling for die-cast and since the advent of power, 2019 represents another busy
injection moulding. This creates telecoms and signalling was to year for Ellis as it continues to
enormous flexibility and an place the associated cables on grow the business. It has much
inventive mindset: when a client hangers, fixed to the sidewall. to offer the rail sector through
comes with a problem, ways It’s quick and makes life easy. a sharp focus on innovation,
and means are readily available But even here, there’s scope for responsiveness and value. Of
to develop custom-made improvement. course, its competitors would
solutions. Stephen Walton, Ellis’ technical say the same thing - they have
Through the 37 miles of director, revealed: “We’ve similar brochures, product
tunnel on High Speed 1, reworked the traditional pressed- ranges and part numbers. “Their
there’s an Ellis cable cleat every steel hanger to be stronger ‘innovation’ is copying us,”
600mm. When the consulting and safer by adopting a curved Richard reflects ruefully.
engineer first approached the profile; they use less material so It’s indicative of the company’s
company during construction, the shipping costs are cheaper. position in this market that
he told them he needed 70,000 We’ve also developed polymer others closely follow Ellis’ lead.
bespoke aluminium cleats in 12 hangers which are lighter-weight, However, whilst imitation is often
weeks. They were designed, offer more insulation resistance flattering, it rarely compares
tested and delivered on time. and will never corrode. favourably with the original.
Ellis products are deeply “A lot of what we’re doing
embedded on the London is about making the products
Underground and Hong Kong easier to carry and improve
Metro; they also formed part speed of install, responding to
of the design for the recent the needs of the contractors
installation of overhead line we’re increasingly working with.”
equipment through the Severn When legacy hangers become
Tunnel. Thousands of its life-expired, Ellis has a modular
Centaur cleats can be found retrofit system which can
in the London Power Tunnels be secured in place without
- extending for 20 miles under disturbing the existing cable
the capital - as part of the system. There’s a delightful
firm’s biggest ever order, worth simplicity and elegance about
£1.5 million. And the UK’s these products. I spent much
Astute-class nuclear-powered of my chat time with Richard
(Right) Production tooling submarines also feature its and Stephen fiddling with
manufactured by Ellis. products. a stackable twist-to-fit no-

Rail Engineer | Issue 177 | Aug/Sept 2019


#RAILMEDIAAPPY

GET RAIL MEDIA ‘APPY!


ALL THE LATEST RAIL
NEWS AT YOUR FINGERTIPS
The Rail Media App includes current and archived issues of Rail Engineer and RailStaff magazine.
There’s no limit to the number of issues you can read.
RAIL ENGINEER RAILSTAFF
Rail Engineer is written by engineers, for RailStaff focuses on the people in the rail
engineers. Our writers visit factories, worksites, industry, their activities and challenges. It
stations and depots all around the UK to includes regular monthly features, articles on
bring you the best in the latest projects and safety and training and all the latest projects
developments in the rail industry. and initiatives.

Download the app today – for iOS and Android.


68 ELECTRIFICATION/POWER

Sustainability and
Decarbonisation
What are transformer losses?

NEVILLE
HAIDE

I
t is a good question, and one that needs to be answered
and better understood by a wider audience within the
rail industry. The perpetual transformation of electrical
energy into thermal energy is seen within a transformer’s
two main loss components. The off-load standby losses derive
from reversing magnetisation and eddy-currents within the
core. These losses can be reduced heavily with the quality of London Bridge REB.
core material and designed levels of flux density.

The on-load losses are, in the main, generated from the ohmic Either way, selection of the cheapest or oldest products
resistance of the transformer’s nonferrous windings under load available for an electrical system do so to the detriment of
and can similarly be reduced with good design practices. A that system’s whole life efficiency. Whole life cost assessments
transformer’s core loss can be compared to an electric heater, favouring high-efficiency equipment demonstrate unarguable
guzzling electrical power continuously and so transforming carbon reduction and energy savings.
electrical energy into wasted thermal energy. With a transformer, Despite this data, competitive tendering governed by awarding
this also happens in a standby state, with no inductive or resistive bodies and the flexibility of standards continue to drive the use
loading present. A 60 per cent reduction in standby power of high carbon output solutions. Industry leaders who rethink the
losses is easily achievable and has been demonstrated as being selection of products for the power networks with an Archimedean
commercially viable. point view of a systems efficiency, environmental impact, and whole
It should be noted this is not a great discovery, nor some life cost can make significant changes for the future.
revolutionary new technology. Rather, it is the adoption of Top-level commitment in CP6 by route asset managers, principal
efficiency-conscious design methodology. In the case of a designers and those organisations that demonstrate best practice
points drive transformer rectifier, energy is being thrown to the in the development and/or deployment of low-carbon solutions
wind even when the points are not moving, so why are we still can align together to deliver a strong, traction-carbon reduction
deploying low-efficiency magnetics into these systems and other framework for CP6 and beyond. Significant carbon reduction
power distribution networks? and energy savings over the life of a power distribution system,
The UK must hit a CO2e (carbon dioxide equivalent) reduction while safeguarding the environment for future generations, are
target of 38 per cent by 2030. This, in part, can be achieved with attainable if we consider the ‘low hanging fruit’ solutions and
the enhancement of standards and legislative requirements to the technology already available to us.
supply chain and system designers. The world we leave for our future generations must not be one
Traction power demand annually is around 3,400GWh alone, heavily harvested of its depleting earth reserves when widely
taking into consideration a highly saturated legacy network of available alternatives exist. Alternative sustainable solutions for
mainly low-efficiency magnetics. electrical conductors need also be deployed and not just seen to
Studies show that at least three per cent of the power be discussed.
generated in the UK is wasted energy from the losses in Bauxite, the ore used to produce aluminium, is the most
transformers. abundant ore on our planet, yet we continue to harvest depleting
To put this into context, around 102GW of traction power could copper reserves that some environmental analysts predict, with
be attributed to the wasted energy of its associated magnetics. a growth in demand of just two per cent, will be commercially
This is the equivalent of unplugging the domestic supply to exhausted within the next 25 years.
around 30,000 homes in the UK for a whole year. A coherent policy is needed that considers, where practical,
Decarbonisation schemes focus heavily on the development high-efficiency products, and those with advancements in the
of new technology to support a reduction in future carbon application of alternative sustainable materials. These should
emissions. High-efficiency solutions already exist, but they are not be adopted by all responsible manufacturers, system designers,
being considered by a large majority of regional projects. Why is and project delivery institutions if we collectively are to meet our
this? Is there a lack of understanding of the technology, a culture environmental obligations and targets.
of ‘copy and paste’ engineering or the age-old commercial driver
to satisfy a project at the lowest possible cost? Neville D Haide is managing director of ATL Transformers.

Rail Engineer | Issue 177 | Aug/Sept 2019


ELECTRIFICATION/POWER 69

Advanced magnetics supporting industry


in-service failures of the ATL transformers,
demonstrating how reliable this new
GARY product has been. RAIL PARTNERSHIP AWARDS 2019
TAYLOR
Gary Taylor CEng MIET, engineering HIGHLY COMMENDED
manager - power engineering, Siemens NETWORK RAIL PARTNERSHIP
SME OF THE AWARDS
YEAR
Mobility. 2017
ATL TRANSFORMERS
Siemens adopted the ATL Transformer
NETWORK RAIL PARTNERSHIP AWARDS
‘aluminium’ range for its new Westlock
2017
Putting Passengers First
WESTRACE Trackside System (WTS) as that
move aligned with the copper-reduction
strategy championed by Network Rail. ISTVAN from the same network, their x16 inrush has
BAZSINKA
The aluminium range also provided CDM created a rather big problem for protection
benefits with significant weight savings and settings and discrimination.
an increase in reliability. ATL proposed its unique range of
The team at ATL Transformers worked ATL Transformers, as a product and as transformers which have helped to eliminate
closely with the Siemens WTS team in a company is indeed fantastic. I first came the problem with the excellent 1.96x FLC
developing the new range of products, across their low-inrush transformer range figure. The company’s knowledge and
which was first adopted as part of during the development phase of 4LM (4 support throughout the project were spot
the Thameslink London Bridge Area Lines Modernisation - the resignalling of on, its factory testing facility and scheduling
Partnership Scheme, completed in 2018. London Underground’s sub-surface lines) flexibility helped save the day and, with our
Following the Thameslink scheme, ATL Wayside LVAC power supply design. combined effort, we were able to provide
transformers and transformer rectifiers have We were in need of finding a working a leaner design without the need of any
been adopted on all WTS schemes that solution to our individual radio power individual inrush limiters.
Siemens have commissioned, including supply inrush-current problem and the If a similar situation would occur on any
on Weaver to Wavertree, Liverpool Lime inrush limiters on the market just did not other projects of mine, I would not hesitate
Street, Derby remodelling, Victoria 2B and do the job - either they were not in range to contact them immediately as the very
Huddersfield to Bradford Resignalling. or their RAMS (reliability, availability, first company in mind.
Following these numerous maintainability and safety) figures were too Istvan Bazsinka CEng MIET, project design
commissionings, there have been no low. As hundreds of these are powered authority, Thales.

Rail Engineer | Issue 177 | Aug/Sept 2019


70 ELECTRIFICATION/POWER

A KNOWLEDGEABLE AND SUPPORTIVE SUPPLIER

As part of our product research and specification of electrical


power products, Amey Consulting has attended several CPD
ABDUL REHMAN (Continuous Professional Development) sessions and exhibitions
SAVANT to support the personal development of staff and the business.
ATL’s Neville Haide has been a great supporter of this, delivering
sessions at our offices and practical sessions on hassle-free

T
hroughout the large portfolio of rail engineering installation solutions at exhibitions.
projects that we have worked on or are presently
working on at Amey Consulting, we have built very
good relationships with suppliers and manufacturers
that support us in the specification and selection of
innovative products and technology.

In the world of electrical power on the UK railway, Amey


Consulting has successfully designed and commissioned
several signalling power upgrades for reliability, resilience and
enhancements. As part of this success, and the present work
bank we have, we work very closely with ATL Transformer’s rail
segment.
ATL has been very supportive in providing Amey Consulting
with product solutions to support its energy management
targets and global sustainability goals, in particular ‘Goal 9’ and
‘Goal 13’, which are ‘Industry, Innovation and Infrastructure’ and
‘Climate Action’ respectively. The design work Amey Consulting
E&P has produced for signalling power projects include the use
of ATL’s Rail Signal Transformers and PSP/ASP Transformers.
The new generation of eco-rail® transformers, that have
been made available to us from ATL, have characteristics that
West Hampstead Principal Supply Point.
contribute to the safeguarding of the environment as they
are ultra-high efficiency, reducing the carbon emissions and
environmental impact. These transformers also present low
standby losses which support the reduction in wasted energy.
The latest aluminium range not only supports copper Amey Consulting has been one of the first E&P design
elimination, a major sustainability target, but it also offers a 30 consultants in the UK to design and implement a signalling
per cent reduction in cost and weight, making the transformers power distribution system using the new ATL slim, aluminium,
easier to transport and install on projects being designed by lightweight supply transformers located inside principal supply
Amey Consulting. points, resulting in a reduced footprint.
ATL has worked with Amey Consulting, manufacturing bespoke
solutions to provide a ‘plug and play’ system, as required by the
client. It has been a pleasure to work with such a knowledgeable
supplier that gives the time and effort to ensure they meet their
customer’s requirements.
As the rail industry has a history of lengthy processes when
seeking product approvals for newly innovated solutions, this did
not deter the collaboration between Amey Consulting and ATL
as both organisations have built a reputation and trust within the
industry and approvals was the least of our concerns.
Amey Consulting has several objectives, one of which is a
sustainable growth of the business. This objective is related
to employee development. In addition to all of the CPD and
technical support we have had from ATL, we are also looking
at the ATL Training Academy for our apprentices, trainees,
graduates and experienced engineers.

Abdul Rehman Savant CEng MIET is a senior electrical engineer


(E&P Design CRE) with Amey Consulting.

Rail Engineer | Issue 177 | Aug/Sept 2019


ELECTRIFICATION/POWER 71

Furrer+Frey — Your Specialist Electrification Partner.


From mainline high speed systems to urban light rail
transport and everything in between.

GB@FurrerFrey.ch @FurrerFreyGB www.FurrerFrey.ch

Rail Engineer | Issue 177 | Aug/Sept 2019


72 ELECTRIFICATION/POWER

Bits
It’s the and that

Pieces
MAKE IT ALL WORK
An assortment of suspension components.
MALCOM
DOBELL

OLEMI (Overhead Line Equipment Master


Index), series 1 or series 2. This involves
compliance with international standards
and having been through Network Rail’s
rigorous product acceptance process.

Droppers
Paul explained that
simple compliance is often
not enough, using as an
example the TF5 dropper
(the vertical cable that
supports the contact wire
from the catenary wire
(pictured)). EN 50119
- Railway applications -

T
ake a look at a typical section of overhead line equipment (OLE) and you Fixed installations - Electric
will see a mass of wires, masts and crossbeams. But, look a little closer, traction overhead contact
and you will see all the other pieces that actually bind it all together. They lines - requires that
reinforce this mechanical engineer’s view that electrification is simply manufacturers must do a
mechanical engineering, but with more copper than usual! type test demonstrating
that the dropper must
What do you do when you need to For someone not familiar with the survive for two million
terminate one end of a 25kV conductor components of OLE, it was a surprise flexing cycles without
wire? You connect it to conical coupling or to see how substantial some of the damage or breakage.
a forked collar socket, of course. You want components are. Simple devices such as What the standard
to support the wire? Use cable dropper clamps to splice two wires together can doesn’t specify is the
clamps with one of a variety of cable easily weigh over a kilogramme, since the dropper length that
dropper solutions using straps or wire. mass of contact wire, catenary wire and all has to be used and, in
Your writer learned all about this and a the components to connect and support a mechanical test such
lot more when talking to Paul Culnane, them is significant. as this, the longer the
who has been managing director of Paul explained that the component dropper, the lower
Arthur Flury (UK) for the last nine years. parts his company supplies are, largely, the strains will be. The
Arthur Flury AG is a Swiss company conservatively designed and many length of droppers varies
that is 99 years old, based in Deitingen, customers have been installing the same significantly and, to ensure
roughly halfway between Bern and Zurich. reliable products on jobs for decades compliance to low system
It manufactures and supplies precision against these trusted specifications; heights, the TF5 has been
OLE components for railways, metros confidence and dependability is successfully tested with
and trams to over 40 countries around everything. a short length of only
the world. The UK subsidiary is based Arthur Flury’s main customer in the UK, 350mm.
in Milton Keynes, a convenient location Network Rail (and contractors working Paul also described the requirement
to access the majority of the country; on its behalf) has specified these parts in for a pull-off force of the dropper wire
something your writer can confirm. all the OLE designs it uses, be it from the from its clamp of 3kN. In the real world,

Rail Engineer | Issue 177 | Aug/Sept 2019


ELECTRIFICATION/POWER 73

Structural design & CAD services available, along with a


FREE FEA Report (including design and component
Queen’s Award Winning
drawings) upon request. Composite Product Supplier
GRP End of Platform
Gates and Fencing
Solutions

Modular Rapid Available Non


Design Install from Stock Conductive

www.duracomposites.com
+44 (0)1255 440291
LOAD
PERFORMANCE
Tested to 3kN crowd loading
(as per BS 1722), resulting in
a deflection of less than
15mm, exceeding the
allowable 25mm industry
standard set ...designed for the future
for fencing.
Industrial Rail Marine Decking Cladding

Structural Precast
for Railways

Rail Engineer | Issue 177 | Aug/Sept 2019


74 ELECTRIFICATION/POWER

(Right) HI25 section however, the vertical force on


insulator. the clamp is only one of the
forces at play, and the design
illustrated shows how strain is
minimised on the clamps.

Materials
The conversation turned
to materials. OLE, couplers
and clamps all need to have
strength and good electrical
conductivity, and Arthur Flury
specialises in copper-nickel-
silicon (CuNiSi) alloy; the
detailed composition and
manufacturing process of which
is a closely guarded secret. This components and can impede referenced to the part numbers
material allows appropriate pantograph movement. for the various OLE series
clamping forces whilst Consider a pantograph and the Network Rail Product
conductivity is a little different moving along a plain contact Acceptance Numbers.
to copper. wire. The upward force of the As is normal for manufacturers
Of course, it’s not just the pantograph is balanced by of specialised but standard
manufacture of the alloy that the resisting force of the wire, components, a significant
needs to be considered, generated partly by its mass pre-sales task is to advise
but the right choice of and partly by its tension. A clients - usually designers - on
manufacturing process for section insulator is many times which of many options is best
the component. For example, the mass of plain wire and for a particular application; for
(Below) A CuNiSi conical components required to the pantograph sees this as a example - is a forked collar
coupler used to connect have good tensile strength significant and sudden increase socket or an eyelet collar socket
two catenary wires. The are not good candidates for in resisting force. This is also best for “this” task?
wire of the correct size is casting, even though the true of neutral sections. This leads to orders that
pushed in from each side manufacturing process is fairly Arthur Flury has developed typically have six to eight week
and cannot be pulled out. inexpensive. Cold forming solutions that are both lighter turnaround, although Paul
- as perfected by Arthur and use spring droppers to did say that the company will
Flury - offers much better minimise the impact of these always make its best efforts
manufacturing tolerances and devices on the passage of when faced with a genuine
product performance, but also pantographs. The newest emergency.
requires a greater investment in version of a neutral section uses There are weekly shipments
manufacturing equipment and in-line insulators on which the from Switzerland to the various
a more highly skilled workforce. pantograph bears, which are sites around the country.
(Below) A stainless steel Clamps, splices, couplers and significantly lighter than the This prompted the inevitable
forked collar used to droppers are comparatively more traditional designs. question about Brexit, even
connect a contact wire inexpensive components, Paul mentioned that the design though Switzerland is not in
or catenary wire to a bought in the hundreds or of the neutral sections and the European Union. Paul
structure or insulator. thousands. However, at the section isolators was iterative, as explained that there is a
other end of the scale, section accurate vertical forces imparted bilateral agreement between
insulators and neutral sections by the pantographs could only Switzerland and the UK to
can cost many thousands of be obtained from prototype maintain tariff free trade and
pounds. These components trials and were found to be that international freight
have been the subject of some significantly higher than the forwarders have identified the
considerable innovation. original estimate. use of alternative ports, to
mitigate any possible risk of
Section insulators and Logistics delays at the France/UK border.
neutral sections The conversation turned The final word goes to Paul:
Section insulators to the process of obtaining “From product specification,
and neutral the right parts. As a matter through component selection
sections have of course, Arthur Flury has and finally to delivery, Arthur
traditionally accreditation to ISO 9001, Flury is here to support
been 14001 and 18001, for quality, our clients’ needs and
environment and occupational offer maximum customer
comparatively safety respectively, and satisfaction.”
heavy maintains a list of its parts cross Enough said!

Rail Engineer | Issue 177 | Aug/Sept 2019


Request a free subscription
at www.railsubs.com

Call 01530 816 444


or visit www.railstaff.co.uk
for more information

RailStaff
magazine
RailStaff has been championing the rail industry’s
workforce since 1997.
As well as getting to the heart of ‘what you need to
know’ each month, its team of writers focus on the
latest developments in:
• Health
• Safety
• Wellbeing
• Careers and training
We also cover stories that celebrate the great
achievements of staff.
Such is the freely-distributed magazine’s success that
the only industry-wide people recognition scheme,
the RailStaff Awards, was launched in 2007, and has
been held ever since.

Download for free all issues on the


Rail Media App for iOS and Android
76 ELECTRIFICATION/POWER

Transformers
Aluminium or Copper?

PAUL
WALKER

T
here is a drive
on the rail
infrastructure
to reduce the overall cost of
signalling power and other installations
and increase electrical efficiency. One
of the main tenants of this philosophy
is the use of aluminium due to its
low cost. As such there is also a drive
to use transformers with aluminium
windings to reduce costs further.

FT Power Transformers have taken on


the challenge of producing aluminium
transformers for trackside infrastructure in
the 500VA to 100kVA range.
But is aluminium (Al) really so much
better than the traditional copper (Cu)?
Below is a base table of the pro and
cons of both aluminium and copper
transformers, based on both experience Conclusions
and research. These studies have led FT Transformers to believe that large
aluminium power transformers have advantages over similarly
sized copper units when it comes to cost and weight. The
efficiency of the units is about the same.
However, small trackside units that are rarely maintained will,
over the life of the installation, suffer from increasing levels of
Transforming the Market resistance due to aluminium oxide. This will be a future issue for
by Turning Our Customers’ Wishes Into Reality current trackside transformers, particularly for signalling power
units, and will show up as an insulation fault at the permanent
Approved Replacements for
insulation monitors (Bender units located with the Principle Power
Legacy Rectifiers & Transformers
Supply buildings) for the signalling power class II IT feeders.
• Zero Inrush & Insulated to 3kV Regular inspection and maintenance will be required. However,
• Full Certification Class II once a signalling power feeder is commissioned, it is often not
• Hybrid Rectifiers & Transformers maintained until there is an issue.
• Eco friendly and High Efficiency Therefore, it is FT Transformers’ opinion that the life of
CLASS II HYBRID RATINGS signalling power feeders will be greatly reduced using aluminium,
250va 500va 1kva increasing the whole life cost.
Economy Range 1.4kva 2kva 3kva

• Zero Inrush & Insulated to 20kV Paul Walker is a mechanical design engineer with FT Power
• Patented Insulated Coating Transformers.
(GB2496062)
• Full Certification Class II Further Reading:
• Hybrid Rectifiers & Transformers Edvard Csanyi - Aluminium vs. Copper: Conductors in Low Voltage Dry Type

CLASS II HYBRID RATINGS Transformers (Electrical Engineering Portal, October 2010)

2 x 5ADC 2 x 8ADC Hans De Keulenaer - Reliability of Terminations: Copper vs Aluminium


Insulated Range 1 x 10ADC (Leonardo Energy, August 2018)
Ronaldo Bertoldi - Aluminium vs. copper conductors in transformer
manufacture (EE Publishers, March 2017)
FT TRANSFORMERS LTD Tahir Ayub - Eliminating Copper, the next step (Rail Engineer, July 2017)
+44 (0) 121 451 3204 Powersmiths International Corp - Transformer Inrush Currents and Protection
www.ft-transformers.co.uk (Critical Power Group, June 2013)

Rail Engineer | Issue 177 | Aug/Sept 2019


FT Transformers Advert2.indd 1 06/02/2015 13:16
ELECTRIFICATION/POWER 77

GRP Handrail System,


on track with your
safety expectations

The non-conductive alternative to traditional steel handrails

The GRP system is created on a 50mm tube for strength and durability and joined together using a variety of
specifically developed GRP moulded fittings to make it strong and durable.
DISCUSS YOUR
• Non-conductive • Easy to install • Lightweight
• Non-magnetic • Low maintenance yet strong
PROJECT NOW
• Fire retardant • Warm to the touch
CALL US ON
0117 970 2420

Visit us online today at eziklampsystems.com


RS0001_Adhesion_RailEngineer_190x130mm_AW_V1_Outlined.pdf 1 04/07/2019 14:06

CM

MY

CY

CMY

Rail Engineer | Issue 177 | Aug/Sept 2019


78 ELECTRIFICATION/POWER

PETER
STANTON

OLErt
Overhead Line and Pantograph Monitoring

I
n this digital age, railways are harvesting increasing and the contact wire. Whilst
volumes of data (‘Big Data’) on the performance of their a failure of the wheel/rail
assets but converting raw data into meaningful information interface can result in a very
remains a challenge for many organisations in the industry. serious safety incident, a failure
to maintain the connection
One example of a successful Critical interface between train and power
foray into the processing of Whilst considerable attention supply can be operationally
‘Big Data’ is in the area of is paid to the interface disastrous. There are also
electrification overhead line between wheel and rail, there safety connotations in the case
contact system performance. is another mechanical moving of failure.
The technology application interface between a train For some time, there have
is helped by the introduction and the infrastructure - that been various methods of
of cheap and small sensors, between the pantograph monitoring the electrification
declining computing and data
storage costs, new abilities to
process and analyse data and
ubiquitous connectivity. The
coming together of these key
enablers is driving the adoption
of the Internet of Things in
rail and, with it, demands
for analytic applications to
turn data into operational
intelligence.
Rail Engineer was invited to
the new traction maintenance
depot at Reading to meet the
team that has developed the
OLErt monitoring system and
hear of the advantages it can
bring to the railway.

Rail Engineer | Issue 177 | Aug/Sept 2019


ELECTRIFICATION/POWER 79

overhead contact system relationship, and


processes to avoid that relationship being out of
correspondence have been developed.
One major risk emerges if the extremity of the
pantograph (the ‘horn’) becomes separated from
the lateral position of the contact wire while that
wire is still close to the pantograph. In that case,
the contact wire may then get underneath the
pantograph horn and either severely damage
the pantograph or the contact wire and its
associated overhead line equipment (OLE) may
be torn down - or both.
Traditionally, stagger (the deliberate deviation
of the contact wire from a central position
to spread wear on the pantograph contact
surface) of the contact wire has been monitored At present, the cameras provide useful output
by observation from a train, such as the test but, in reality, they only show the circumstances
car ‘Mentor’. Instrumented processes have of an incident after it has occurred, such as the
been used and the height and stagger of contact system/pantograph interface becoming
the wire may also be checked by patrolling non-compliant with unfortunate results. Using
and suitable equipment. Cameras have been the data to improve performance required
mounted on train roofs for some time, but with a system to identify potential problems and
little recovery of data by technology. More highlight them before an incident occurs.
recent developments have involved bespoke These events have a high impact, with
equipment to monitor the contact system and passenger and electric freight line closure as a
the interface - this has not been a low cost or minimum. They are also expensive, with each
generic option. one costing Network Rail time and money for
The recent development of cameras being infrastructure repair and compensation to train
fitted to the roofs of modern electric trains has operators. Despite receiving this compensation,
generated an opportunity to develop a more the train operators would prefer better reliability
real time and wide-ranging monitoring process. and no disruption for passengers.

Signalling the future


Henry Williams...at the forefront
of railway innovation since 1883
For all your engineering
and signalling needs.
• Signalling: Fully Wired
Location Cases, REB’s
• Power: FSPs, Switchgear,
DNO’s, SafeBox
• Enclosures: Location Cases,
Dis Boxes, Power Annexes, ELD’s
• Signalling Panels, Control Panels
• PW: Fishplates, Clamps
• Treadles and Treadle Gauges

Contact us today!
T: +44 (0) 1325 462722
E: sales@hwilliams.co.uk
www.hwilliams.co.uk

Rail Engineer | Issue 177 | Aug/Sept 2019


80 ELECTRIFICATION/POWER

Of the other contributors, the


University of Oxford brought
algorithms from its own
research groups and Icomera
contributed its expertise in
wireless connectivity, while
Network Rail and Great
Western Railway integrated the
projects activities. The group
has now successfully completed
the first phases of the project
and, for that, has been voted
‘highly commended’ at the
2019 Rail Partnership Awards
for Driving Efficiencies.
From the group came the
inspiration to take the existing
Understanding the data Team contributions camera output from the train and
So, data was required - Big Incremental Solutions, a high- to digitise it, producing a data
Data in this modern world - to growth and relatively young stream that could continuously
discover how the pantograph company, has been exploiting monitor the performance of the
and contact wire interact and the concept of ‘intelligent pantograph and its movement in
to detect any potential faults mobility’ in the rail industry line with the OLE contact wire.
before they can cause trouble. to improve understanding of That data stream could then be
Network Rail is already vehicle movements and to solve analysed to extract changes in
receiving information from in- critical issues of performance, a normally consistent signature,
service trains on the condition reliability and journey so identifying potential incident
of its track, and the wheel/rail optimisation. sites.
interface, but it did not have a Its core aims are to assist in In order to test the theory,
system for retrieving contact the creation of a connected Great Western Railway made
force data from the pantograph transport network with available a class 387 electric
interface at over 100 mph. a proactive approach to multiple unit to which was fitted
Ideally, a pantograph will predicting and preventing, the pantograph monitoring
exert a constant upward force resulting in improved incident camera. Following a calibration
on the contact wire and a good management, more accurate exercise to eliminate any lens
maintenance regime will keep timetabling and, overall, distortion and ensure the
the carbon strip on the top of operationally more efficient. pantograph was within height
the pantograph - the point of It does this by utilising best- range, a network video recorder
contact between the train and in-class solutions, working with (NVR) was installed into the
the wire - in good condition. other innovators and liaising train roof-space. This was linked
With the Great Western with academia. This creates to the Ethernet backbone to
electrification programme set opportunities for SMEs to enable a secure download of
to increase markedly both the scale up their ideas, promotes the recorded footage via Wi-Fi,
number of trains running under innovation and challenges the removing risks associated with
the wires and the number status quo. access to the train roof.
of pantograph passes, the
possibility of increased failures
had to be taken seriously.
A consortium of interested
parties came together to
meet this challenge under
the auspices of Network Rail.
Software specialist Incremental,
communications specialist
Icomera, Great Western Railway
(GWR) and the University of
Oxford began a development
project using a modern EMU
and capturing data from the
monitoring camera. The aim of
this ‘OLErt’ project was to make
the camera intelligent.

Rail Engineer | Issue 177 | Aug/Sept 2019


ELECTRIFICATION/POWER 81

(Left) A Network Video


Recorder was installed
into the train roof space
and was linked to the
Ethernet backbone to
enable a secure download
of the recorded footage
via Wi-Fi.
(Right) Two different
styles of camera used in
the trials.

Processing the data from the camera, utilising by application of a special film ensuring that,
algorithms from the Oxford University research, after four weeks testing, the image obtained was
supplied the proof of concept for the project. It still good.
was noted that the data from the widely fitted In summary, the OLErt system has usefully
cameras on the fleets was encrypted, so special built on existing data acquisition, itself a
arrangements had to be made for the OLErt- recent development, and applied advanced
related measurement camera on the chosen methodology to harvest large amounts of
class 387. data. It has then used algorithms supplied by
In the realm of fixed equipment, a Wi-Fi academia to turn that ‘Big Data’ into a format
network was installed in the East yard of that will allow individual sites with potential
Reading Train Care Depot. This included three problems to be identified so they can be
access points onto the noise abatement wall to investigated before a significant operational or
cover the stabling locations of the unit - plus the safety incident occurs.
necessary network ancillaries. This research will definitely benefit all partners
A number of test sites were chosen as in the operation of the railway and help enhance
examples of differing environments, including a continuing good service to customers.
high-speed running (over 100mph), increased
contact-wire height over level crossings, neutral Thanks to the OLErt team for explaining their
sections, tangential wires crossed at speed and a work and its concepts - Paul Barnes and Dean
complex layout. Shaw (Network Rail), Daniel Lee-Bursnall
(Incremental), Stephen Duncan (Oxford
Results University), Rich Fisher and David Eveleigh
The series of tests, and monitoring and (Great Western Railway).
processing of the outputs, revealed interesting
data and proved the concept of the proposals.
As stated earlier, the potential is for a mass of
data which would not be capable of analysis,
but the results passed through the Oxford
algorithms allowed the ‘signature’ of the OLE
to be observed and potential problem spots
identified. In fact, during the trials, a location
with a serious risk of dewirement was picked up
and attended to as a matter of urgency.
A conclusion emerged that pantograph stress
is more complex than thought - during the trials
51 different signalled patterns were achieved
in the five geographical areas. Pantograph
force assessment did show that the average
pantograph force was compliant with that
expected at speed and in service. Interestingly,
concerns over dirt on the camera lens, which
might have obscured the image, were addressed

Rail Engineer | Issue 177 | Aug/Sept 2019


FREIGHTLINER is a leading rail freight provider with
businesses in the United Kingdom, Continental Europe and
the Middle East. They have established themselves as a
leader within the rail freight industry; setting standards,
introducing new thought processes and industry firsts.

Over: 2,000 employees 250 locomotives 5,500 wagons

All recruitment conversations will be handled confidentially.

Mobile Ground Staff ROLE OVERVIEW


Conducting safe shunting operations

Career Opportunities in accordance to the relevant railway


rules and regulations with the goal of
dispatching trains efficiently
South West & London Load examinations
Safety checks
The role involves shift-based working
which can include, early, late and
FISSION RAIL is working in partnership with weekend working

Freightliner, the market leader in providing You must reside or be prepared to relocate
to within 60 minutes of Wembley, Tilbury
innovative rail freight solutions to bolster their and Mendip Quarries
existing teams of Mobile Ground Staff across 3 COMPANY BENEFITS
depots - Wembley, Tilbury and Mendip Quarries.
Competitive salaries

are you a reliable, committed individual? Industry-wide defined contribution


and/or final salary pension scheme
do you possess the knowledge and experience Freightliner life (which includes
needed to become a member of the Mobile cycle to work, childcare vouchers,
discounted gym membership).
Ground staff team? Employee Assistance Programme

Open day interviews will be taking place at the end of September 2019 in central London.
Successful candidates will be invited to attend interviews. All applications must be made via Fission Rail.
Please email an up to date CV with contact details to rail@fission.co.uk
IN SEARCH OF
ELECTRIFICATION
ENGINEERS
JOIN US IN YOUR
NEXT CAREER MOVE
We develop projects from concept through to
operation, providing integrated services for
multi-year, multimillion-pound programmes for
major rail and transport agencies. Working together,
we can realise our ambitions for the future.

We are looking for Electrical Engineers | Senior


Electrical Engineers | Principal Electrical Engineers |
OLE Engineers | Senior OLE Engineers | Lead OLE
Engineers.

Roles are based in Birmingham, Croydon, Glasgow,


London, Manchester, Swindon and York.

aecom.com/uk/electrification-careers/
S&C South Alliance, UK
Velaro Novo
It’s time to rethink velocity

Discover a train that offers a whole new perspective


on high-speed and intercity transportation. 30% lower
energy consumption,10% more available space and
lower maintenance costs: these and many other
benefits make the Velaro Novo unique when it comes
to increasing value sustainably over the entire lifecycle
and enhanced passenger experience.

siemens.com/velaro-novo

Вам также может понравиться