NOVEMBER 2018

1st Month
16 17 18 19 20 21 22 23 24 25 26 27 28

I CONSTRUCTION STAKING AND SITE LAY-OUT


1 Mobilization/Demobilization

2 Site Inspection and Joint Inspection in Aritao and Gapan location

3 Preparation of Inspection Reports

4 DPWH and IRD Meeting Regarding the result of the Joint Inspection

5 Conduct Revalidation of Candidate Sites

6 Confirmation of the Final Sites for Aritao and Gapan from DPWH

7 Coordination with all the Local Utilities

8 Approval of Permits (from Electric Cooperative, Internet and Fiber Optic)


II SUPPLY OF PORTABLE WIM
Manufacturing, Shipping, Custom Clearance and Delivery of Imported Goods for
9
the Portable WIM

10 Inspection and Testing and Training


III SUPPLY OF HIGH-SPEED WIM
Manufacturing, Shipping, Custom Clearance and Delivery of Imported Goods for
11
the High-Speed WIM and HWIM VMS

12 Inspection and Testing and Training

INSTALLATION OF HWIM VMS & HIGH SPEED WIM INCLUDING ALL CIVIL
WORKS (i.e. all cable trenching/HDD/excavation works,
IV footings/foundations/columns for iSINC cabinet, cameras and VMS,
restoration and equipment
installation/assembly/configuration/calibration/testing)

SITE #1: BRGY. CALITLITAN, ARITAO, NUEVA VIZCAYA


13 First mobilization and preparation

14 Second mobilization, delivery and preparation

15 Kick-off Meeting with DPWH Nueva Vizcaya II DEO

16 Excavation Works for Underground conduits crossing the road

17 Laying of underground conduits for communication and power cables

Purchasement of steel bars (16mm & 20mm Ø) for the foundation of camera & VMS
18
mounting poles, pedestal of iSINC cabinet and installation of pullbox (2)

19 Excavation works for the foundation of camera mounting pole #1 (Southbound)

Bending/form works of steel rebars including anchor bots installation for the
20
foundation of camera mounting pole #1 (Southbound)
21 Excavation works for the foundation of camera mounting pole #2 (Northbound)

Bending/form works of steel rebars including anchor bots installation for the
22
foundation of camera mounting pole #2 (Northbound)

23 Excavation works for the foundation of VMS mounting pole (Southbound)

Bending/form works of steel bars including anchor bots installation for the
24
foundation of VMS mounting pole (Southbound)

25 Excavation works for the pedestal of iSINC cabinet (Southbound)

26 Pouring of concrete for the footing of camera and VMS mounting poles

27 Pouring of concrete for the column of camera and VMS mounting poles

28 Pouring of concrete for the pedestal of iSINC cabinet

29 Installation of iSINC cabinet and protective posts (2)

30 Pullbox installation in Southbound

31 Pullbox installation in Northbound

32 Installation of Piezoelectric and loop sensors in the first lane

33 Installation of Piezoelectric, loop and temperature sensors in the second lane

34 Installation of Piezoelectric, loop and temperature sensors in the third lane

35 Installation of Piezoelectric and loop sensors in the forth lane

Trenching and laying of homerun cables on PVC pipes and restoration/backfilling


36
works in Southbound

Trenching and laying of homerun cables on PVC pipes and restoration/backfilling


37
works in Northbound

38 Cable pulling work

39 1km fiber optic cable installation (Microtrenching)

Installation of camera mounting pole #1 including OVCs, ANPRs and illuminators


40
with power box

Installation of camera mounting pole #2 including OVCs, ANPRs and illuminators


41
with power box

42 Installation of VMS mounting pole including 2 VMS and power box

43 Installation of iSINC equipment and termination of all commucation cables


Installation of all AC power with surge protection and distribution panel for cameras,
44
illuminators, VMS and iSINC equipment

Configuration and Testing of iSINC equipment connected to OVCs. ANPRs,


45
illuminators, VMS and laptop in the confirmatory site

46 HSWIM system calibration

47 HSWIM system training and actual on-site demonstration

48 Final acceptance and Commissioning

SITE #2: BRGY. SAN ROQUE, GAPAN, NUEVA ECIJA

49 Mobilization, delivery and preparation

50 Kick-off Meeting with DPWH Nueva Ecija II DEO

51 Excavation Works for Underground conduits crossing the road

52 Laying of underground conduits for communication and power cables

Purchasement of steel bars (16mm & 20mm Ø) for the foundation of camera & VMS
53
mounting poles, pedestal of iSINC cabinet and installation of pullbox (2)

54 Excavation works for the foundation of camera mounting pole #1 (Southbound)

Bending/form works of steel rebars including anchor bots installation for the
55
foundation of camera mounting pole #1 (Southbound)

56 Excavation works for the foundation of camera mounting pole #2 (Northbound)

Bending/form works of steel rebars including anchor bots installation for the
57
foundation of camera mounting pole #2 (Northbound)

58 Excavation works for the foundation of VMS mounting pole (Southbound)

Bending/form works of steel bars including anchor bots installation for the
59
foundation of VMS mounting pole (Southbound)

60 Excavation works for the pedestal of iSINC cabinet (Southbound)

61 Pouring of concrete for the footing of camera and VMS mounting poles

62 Pouring of concrete for the column of camera and VMS mounting poles

63 Pouring of concrete for the pedestal of iSINC cabinet

64 Installation of iSINC cabinet and protective posts (2)

65 Pullbox installation in Southbound


66 Pullbox installation in Northbound

67 Installation of Piezoelectric, loop and temperature sensors in the first lane

68 Installation of Piezoelectric, loop and temperature sensors in the second lane

Trenching and laying of homerun cables on PVC pipes and restoration/backfilling


69
works in Southbound

Trenching and laying of homerun cables on PVC pipes and restoration/backfilling


70
works in Northbound

71 Cable pulling work

72 1km fiber optic cable installation (Horizontal Directional Drilling)

Installation of camera mounting pole #1 including OVCs, ANPRs and illuminators


73
with power box

Installation of camera mounting pole #2 including OVCs, ANPRs and illuminators


74
with power box

75 Installation of VMS mounting pole including VMS and power box

76 Installation of iSINC equipment and termination of all communication cables

Installation of all AC power with surge protection and distribution panel for cameras,
77
illuminators, VMS and iSINC equipment

Configuration and Testing of iSINC equipment connected to OVCs. ANPRs,


78
illuminators, VMS and laptop in the confirmatory site

79 HSWIM system calibration

80 HSWIM system training and actual on-site demonstration

81 Final acceptance and Commissioning


ER 2018 DECEMBER 2018 JANUARY 2019
onth 2nd Month 3rd Month
29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14
JANUARY 2019 FEBRUARY 2019
3rd Month 4th Month
15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 1 2
MARCH 2019 APRIL 2019
5th Month 6th Month
3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18
PRIL 2019 MAY 2019
th Month 7th Month
19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4
JUNE 2019 JULY 2019
8th Month 9th Month
5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
2019 AUGUST 2019
onth 10th Month
22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12