Operation and maintenance manuals shall contain the functional description of the system and “As Built” status of
the equipment.
System description shall have the complete details of the equipment provided and interface details of the
current/existing system with its tag numbering.
Provide details of the equipment supplied/installed with all the technical specification data sheets and other relevant
information.
PEL, MEL & RSPL – Please add TAG numbers of the equipment and location details as a minimum.
Provide Soft Copy in PDF searchable format.
Provide Contract Scope and Technical specification.
Provide complete package for review.
Send it to the end user.
Line Item
As Built Title blocks are missing from the drawing. (01369-PD-A0-0002,PD-A2-151) – SASEC SCOPE 1,2,3,4,7,8 – To be
Breaking line connection are found in the drawing. (2-ME-A0-653,) – SASEC SCOPE
Drawings updated by SASEC
Most of the drawing content is not visible. (01369-PD-A0-0002 , PD-A2-151) – SASEC SCOPE
It is unclear from the status of the drawing weather it is As-Built or under demolition. (01369-IN-A2-2712,2713) –
SASEC SCOPE
Incorrect representation of section is found in the drawing. (27719-EE-A1-002) – BBSA Already incorporated
Incorrect section references are found in the drawing. (27719-EE-A1-002,003) – BBSA Already incorporated
A consolidated list of all the drawings shall be provided in the attached excel format. (Below) – SASEC SCOPE
All of the above comments are based on random check only. Contractor shall check, verify and correct all the
drawings based RC CAD standards and RCGDCTG. – SASEC SCOPE
Disclaimer: Review and any comments or omissions, errors/discrepancies in the comments by Marafiq on this submittal shall not relieve Contractor from the responsibility of verifying and checking the design with respect to the
Contract Specification and Requirements prior to Approval.