STRAIGHT LINE DIAGRAM

Construction of Kay Tialo Bridge


Brgy. Sto. Cristo, Del Monte – Norzagaray Road, San Jose Del Monte Bulacan
Contract Package 12 under Bridge Construction Replacement Program II
Effectivity Date:
March 23, 2018

Year
jan feb mar apr may jun jul aug sep oct nov dec 2018

A B C D

Original Expiry Date: Revised Expiry Date:


March 22, 2019 October 30, 2019

Year
jan feb mar apr may jun jul aug sep oct nov dec 2019

E F G

Note:
A- Work Suspension Order no. 1 (May 03, 2018) E - Work Suspension Order no. 2 (January 3, 2019)
B- Continuation of Work Suspension Order no. 1a (June 02, 2018) F - Work Resumption Order no. 2 (March 20, 2019)
C- Continuation of Work Suspension Order no. 1b (July 02, 2018) G - Proposed Work Suspension no. 3 (July 10, 2019)
D- Work Resumption Order no. 1 (December 10, 2018)

Prepared by: Noted by:

MARK T. CUYA LUISITO B. IBE ROBERTO C. IGOT


Project Manager DPWH Project Engineer Resident Engineer
M.E. Sicat Const. Inc/Algon Engineering Corp. (JV) UPMO – Bridges Management Cluster DSI Engineering Services, Inc /
Woodfields Consultants, Inc. (JV)