Proyecto: MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE DEL SECTOR 80: A. H. FORTIN CAYCHO Y A. H.

H. MORADORES DEL PASAJE VENUS, DISTRITO DE


Fecha : 30-11-2015
CRONOGRAMA VALORIZADO DE EJECUCION DE OBRA
Costo
Item Descripción MES 1 MES 2 MES 3 MES 4 MES 5
Directo

01 OBRAS CIVILES

01.01 OBRAS PROVISIONALES Y TRABAJOS PRELIMINARES 15,492.49 15,492.49


PLANES Y MITIGACION DE IMPACTO AMBIENTAL, SEGURIDAD Y SALUD
01.02 169,583.62 33,916.72 33,916.72 33,916.72 33,916.72 33,916.72
OCUPACIONAL
01.03 DEMOLICION DE RESERVORIO EXISTENTE V=450m3 59,609.46 59,609.46
01.04 CONSTRUCCION DE RESERVORIO ELEVADO REP- 01 V =100 m3 475,538.31 190,215.32 166,438.41 118,884.58
01.05 CERCO PERIMETRICO RESERVORIO ELEVADO REP-01 108,295.18 54147.59 54147.59
01.06 MEJORAMIENTO DE LA CISTERNA CB-1 16,311.83 16,311.83
02 EQUIPAMIENTO HIDRAULICO Y ELECTRICO
EQUIPAMIENTO HIDRAULICO BYPASS PROVISIONAL - MANTENIMIENTO DEL
11,413.13
02.01 SERVICIO DE AGUA POTABLE 11,413.13
02.02 EQUIPAMIENTO HIDRAULICO REP-01 53,670.78 53,670.78
02.03 EQUIPAMIENTO ELECTRICO REP-01 190,081.69 190,081.69
02.04 MEJORAMIENTO DEL EQUIPAMIENTO HIDRAULICO CISTERNA CB-1 43,920.43 43,920.43
02.05 MEJORAMIENTO DEL EQUIPAMIENTO ELECTRICO CISTERNA CB-1 154,712.62 154,712.62
02.06 SISTEMA DE COMUNICACION LOCAL 59,790.00 59,790.00
03 LINEAS DE AGUA POTABLE
03.01 OBRAS PROVISIONALES 87,567.25 29,189.08 29,189.08 29,189.08
03.02 LINEA DE IMPULSION DE LA CISTERNA CB-1 AL REP-01 58,032.72 29,016.36 29,016.36
03.03 LINEA DE ADUCCION DEL REP-01 (EMPALME 1-2) 105,377.09 52,688.55 52,688.55
03.04 LINEA DE ADUCCION DEL REP-01 (EMPALME 3) 19,097.48 9,548.74 9,548.74
03.05 LINEA DE EMPALME DE LA RED DE AGUA POTABLE A LA CISTERNA CB-1 3,676.76 3,676.76
04 LINEAS DE ALCANTARILLADO
04.01 LINEA DE REBOSE DEL RESERVORIO REP-01 21,871.27 21,871.27
04.02 REBOSE DE CISTERNA A RED DE ALCANTARILLADO 1,187.70 1,187.70

TOTAL COSTO DIRECTO S/. 1,655,229.81 109,018.67 224,132.05 320,797.86 360,676.02 640,605.21
GASTOS GENERALES S/. 281,389.07 18,533.17 38,102.45 54,535.64 61,314.92 108,902.89
UTILIDAD S/. 132,418.38 8,721.49 17,930.56 25,663.83 28,854.08 51,248.42
SUB TOTAL INCL. GASTOS GENERALES Y UTILIDAD S/. 2,069,037.26 136,273.33 280,165.06 400,997.33 450,845.02 800,756.52

SUMINISTRO ELECTRICO S/. 641.00 641.00


MONITOREO ARQUEOLOGICO S/. 29,000.00 9,666.67 9,666.67 9,666.67

PARCIAL S/. 2,098,678.26 136,273.33 289,831.72 410,664.00 461,152.69 800,756.52


I.G.V. (18.00%) S/. 377,762.09 24,529.20 52,169.71 73,919.52 83,007.48 144,136.17

COSTO TOTAL PRESUPUESTO REFERENCIAL S/. 2,476,440.35 160,802.53 342,001.43 484,583.52 544,160.17 944,892.69