Академический Документы
Профессиональный Документы
Культура Документы
INTEGRATED ASSIGNMENT:
MEASUREMENT I (QSB60104)
CONSTRUCTION TECHNOLOGY I (BLD60104)
BUILDING MATERIALS (BLD62003)
1
NAME: NUR FIRZANA BINTI MUHAMMAD HASMI
CONTENTS
PAGE NO.
3
- INTRODUCTION & OBJECTIVES
4
- INTRODUCTION TO SITE
- PROJECT SUMMARY 5
2
INTRODUCTION
on a technical site visit to a construction site. The site visit was organised
by the programme director, Sr Ang Fuey Lin on the 23rd November 2016
to give students the ability to apply their learning skills learnt from within
the lecture theatres into the working world by observing and exploring
OBJECTIVES
3
PROJECT SUMMARY
Murni (Lot 3607),Tanjung Balai (Lorong Haji Yusof), 30/236, bersama satu
unit pencawang elektrik padat di atas Lot 3607 (GM2726), Seksyen 30,
4
Contractor : Pembinaan Purcon Sdn. Bhd.
The location of the site is at Jalan Tanjung Balai (Lorong Haji Yusof),
Shah Alam. Students were required to find their own transportation to the
site by carpooling or getting there on their own and gather at the site
itself before 9:00 am. After arriving at the location, we met with our
lecturers, Sr. Ang Fuey Lin, Dr. Myzatul Aishah Binti Hj Kamarazaly and
construction project by our guide and received safety helmets each before
5
TECHNICAL OBSERVATION
Our guide informed us on the foundations that all units were built
designed with the piles but without the pile caps and instead they use a
raft foundation on top which subsequently, acts as a beam for the ground
6
beam. The type of load transfer would be friction pile due to softness of
the land.
Extra floor
ground beam.
act as a backbone for support so the building can be erected and hold up
the load without collapsing. However, on the day of our site visit, it was
thirty percent completed with the construction. The foundation has already
7
been covered with concrete. So, the only thing visible for us to see were
Suspended beam
Column
Malaysia.
8
Afterwards, he moved on to talking about the columns and beams and
how the process comes together. It begins with the formwork which are
Column formwork
rk
When formworks are put up, the falsework will be needed as well
because they act as a temporary support for the formwork to hold the
9
Falsework
reinforcements.
10
Next, the reinforcement bars will be assembled and ready to be put up
within the formwork. The use of reinforcement bars in concrete is partly due
to its cost and also for the added support. Concrete is strong in compression
but very brittle when it comes to tensile strength. Despite that, steel
using steel bars for the construction will strengthen the structure to hold the
bars within the concrete consequently, the columns and beams will show
Not visible within the photo as it was covered by a piece of wood but there is a
bar bending machine on site where straight reinforcement bars are bend on site.
11
Once everything is put into place, everything comes down to the
For this construction project, there are
concrete mix. The concreting for all the structures were in-situ concrete in
bars coming out of the column. The
grade 25. Before concrete is poured into the formwork, it must be tested
purpose of these are bars is due to
using the slump test to determine the workability and consistency of the
prevent the columns from cracking caused
concrete mix until it comes to a true slump. Casting will then take up at least
by the vibration of moving machinery
a week for it to solidifies before removing the formwork.
plants.
12
We were then given the chance to look around
before it distributes to the strip piling and onto the piles. The ground floor
Most of the housing units had the bricks laid out for the walls on the
ground floor. The brick materials used were cement sand bricks and also
clay bricks. Cement sand bricks have the same function as the clay bricks.
Even so, clay bricks were used between party walls for safety purposes to
13
When it comes down to cost, cement sand bricks(right) are
workers.
14
Independent scaffolding is
ready to be used.
objects.
15
Cement mixer for mixing
the site.
16
Materials like door frames and cement are stored at
the site.
17
Cement mixing truck to
concrete.
CONCLUSION
From this site visit alone, I feel that I have acquired a more in depth
opener that I can apply from what I have learnt in lectures and tutorials
taught by my mentors and be able to apply it and see the procedure take
place before me from paper into reality. Not to mention, that this trip has
18
also given me a more rational understanding on the unforeseeable
mishaps and conditions that can occur like safety hazards and
project.
19