Академический Документы
Профессиональный Документы
Культура Документы
SINOPSIS
Modelle van koniese vergruisers en vibreersiwwe word beskrywe. Hierdie modelle was gekonstrueer van
informaBle verkry van werklike aanlegte deur die gebruikmaking van 'n sistematiese mode,l-bou tegniek. Die
modelle was gebruik om volledige vergruisings aanlegte na te boots en sodoende 'n kontrole sisteem vir ver-
gruisings aanlegte te ontwerp en die waarde daarvan te bepaal.
JOURNAL OF THE SOUTH AFRICAN INSTITUTE OF MINING AND METALLURGY MAY1972 257
~
X W
t
yx yx
B Bar Seran.
C t.a'2 Crusher.
S Wire Screen.
W Weigher.
X Sample Point. ~~B
W
that the plant be operating steadily during the collection THE CONE CRUSHER MODEL
of data. The presence of two lOO-ton surge bins in the
closed circuit meant that the plant could run for an A simple model has been used for the cone crusher as it
hour or more under conditions significantly different was felt that more complex models, which could easily be
from steady state. This, together with frequent minor proposed, would contain more parameters than could be
stoppages, meant that the plant seldom ran under calculated using the small amount of available data
steady-state conditions. In addition to these variations, which were, of course, of limited accuracy.
the discharge rate from the crushers contained con-
siderable short-term variations. The basis of the cone crusher model is the assumption
At the start of the data collection, tests of the be- that particles can either be broken or dropped through
haviour of the entire plant were attempted. The later the crusher unbroken. The broken particles then have
test work concentrated on the individual units as a the same choice of dropping through the crusher or of
wider range of operating conditions could be obtained for being broken further. Thus, the cone crusher is simplified
these by using the surge bins to provide feed during the to a single breakage zone and a probability of entering or
sampling. The data collected consisted of size distri- re-entering this breakage zone. Figure 2 shows sym-
butions, ore tonnages, crusher current, crusher gap and bolically the parts of this cone crusher model and the
screen sizes. Figure I shows the sample points. These internal flows between them. The vectors f, x and p give
data were obtained in tests on the individual units for the flow rates in each size fraction. The lower triangular
the purpose of model building. matrix B gives the relative distribution of each size
fraction after it is broken and the diagonal matrix C
gives the proportion of particles entering the breakage
The primary section
region.
It was not possible to obtain samples to separate the
behaviour of the primary screen and crusher but the The mass balances at the nodes in Fig. 2 give the
data provide five tests of the behaviour of this equations
complete section at tonnages ranging between 380 and
f+BCx=x . . . . . . . . . . . . . . (I)
820 tons per hour. Due to experimental difficulties, an and
average feed sizing was assumed for all these tests.
The secondary screens x=Cx+p . . . . . . . . . . . . . . (2)
Ten tests were conducted on the screen behaviour. The
Eliminating x gives the equation
screen sizes used were 0,5,0,625 and 0,75 inches. The feed
tonnages ranged from 219 to 420 tons per hour. p=[I-C] [1-BC]-lf,
The secondary crushers which expresses the crusher product in terms of the feed.
Thirteen tests of secondary crusher behaviour were The matrix 1- BC is always non-singular as a unit
obtained. The crusher gap ranged from 0,2 to 0,5 in. and element on the diagonal of BC implies both no breakage
the feed tonnages from 120 to 360 tons per hour. and no discharge of that size fraction.
258 MAY 1972 JOURNAL OF THE SOUTH AFRICAN INSTITUTE OF MINING AND METALLURGY
f below a certain size k1 are not broken in the crusher,
that is,
c(s)=O,O for s<k1.
Also, there exists a size k2 above which particles are
Cx always broken, that is,
c(s)=1,0 for s>k2.
B Between these sizes c(s) is assumed to be a parabola with
BCx zero gradient at k2, thus,
2
c(s)=1- ( ;1-=-~2) k1<s<k2.
Fig. 2-Symbolic representation of crusher model
The elements in the C matrix are obtained as the mean
values of c(s) in the appropriate size range. For the
The breakage matrix
range Si to S2 the matrix element is:
The observed data on the cone crusher appear to be
explained best by a breakage matrix consisting of two
parts. The first part is a step matrix B1 which gives the I S2
Si
c(s)dS/(S2-S1)'
product sizes relative to the size of the original particle. The two parameters k1 and k2 are predicted by the
This is calculated from equations
k1=0,67g::l::0,77,
p(S)=(1-e -(S/S')U)/(1-e -1), k2= 1,121g+2,31q+T(t)::I::0,071,
where g is the crusher gap in inches, q is the fraction plus
where s' is the size of the original particle and p(s) is the one inch in the crusher feed and t is the feed tonnage to
fraction less than size s. This distribution is a modification the crusher. The function T(t) is a natural spline function
of the Rosin-Rammler distribution given by Broadbent, of degree 3 (Ahlberg, et al, 1967) through the points
et al, (1956). The value of u has been calculated to be (100,0, -0,0486), (250,0, -0,085), (400,0, -0,259),
6,0::1::0,9 for the cone crusher. which is drawn in Fig. 3.
The second part of the breakage matrix, B2, describes This relation for k1 is as would be expected. The
the production of fines. The sizing of this portion of the relation between k2 and gap size is reasonable and the re-
product is not dependent on the size of the original maining terms in this equation appear to relate to the
particle. A Rosin-Rammler distribution is used to ease of flow through the crusher, that is, large particles
describe this material, that is, and low tonnages flow through the crusher more rapidly.
The crusher current
-(s/s")V, This is calculated from the vector Cx which contains
p(x)=1-e
no fine particles and is related to the amount of breakage
where s" is a fixed size. In the calculations, this distri-
by
bution is altered so that the material predicted above the
f-p=[l-B]Cx,
size of the original particle appears after breakage at
obtained by adding equations (1) and (2).
the original particle size. This amount is generally very
A number a is defined by
small. The values calculated for the parameters in this
a=Eti/(Si+Si+1)
distribution are
where tt is the i-th element of Cx and Si, SiH are the
s"=0,12::1::0,025 inches,
upper and lower limits of the i-th size fraction. No
v =1,25::1::0,145.
problems arise in defining an average size of the fine
Finally, to get the total breakage matrix, B, the two
component matrices are added,
0.0
B=aBl+(1-a)B2'
where a is calculated from the gap size in inches, g, as
follows:
a=0,872+0,115g::l::0,0l4. -0.1
The standard deviations of the coefficients in this Effect
equation are 0,15 and 0,039. This equation shows, as onk2
would be expected, that more fine material is produced
-0.2
as the crusher gap is decreased.
The calculated breakage function indicates that when a
particle is caught by the closing crusher gap it tends to
produce a small number of large particles plus a few per -0.3
cent of fines.
JOURNAL OF THE SOUTH AFRICAN INSTITUTE OF MINING AND METALLURGY MAY 1972 259
size fractions as ti=O there. The crusher current IS
s - It
y=V m (h+d )
predicted by
A = 14,2+0,0822a+0,000 305a2:::!::
1,8
The complete cone crusher algorithm is given in gives
Appendix A. h+d Y2 -y 2
The accuracy of the model
The predictions of the cone crusher model have been
./
v m f
Yl
e dY/(S2-S1)'
260 MAY 1972 JOURNAL OF THE SOUTH AFRICAN INSTITUTE OF MINING AND METALLURGY
or primary !'!ection. As wa,s expected, the difference!'! be-
(b) Calculate parameters over all tests by non- tween the data, a,nd the model were more scattered,
linear least-squares estimation and then giving errors in the percentage sizing with a mean of
proceed to step (vii). 2,0 and a standard deviation of 3,5.
(iv) Examine the closeness of fit in (iii) for un-
satisfactory behaviour. SIMULATION OF THE COMPLETE CRUSHING
(v) Attempt prediction of the model parameters PLANT
from (iii) (a) from the operating parameters
For the simulation of the complete plant, the closed-
using regression techniques.
circuit operation of the secondary section must be
(vi) Programme the prediction equations found in
(v) into the model and test them for correct simulated. This is done by assuming a crusher discharge
(initially, zero is adequate) and then simulating the units
implementation.
around the closed loop following the direction of ore
(vii) Compare the model predictions with all the
flow so that an improved estimate of the crusher dis-
available data and test the error terms for any
charge is obtained. This improved estimate of the crusher
significant non-random behaviour.
discharge is used to enable the units around the loop to
(viii) Incorporate random number generators into the
be simulated again and this process is repeated until it
model to simulate the random behaviour of the
converges. A relaxation factor may be used to improve
difference between the model and the data.
the rate of convergence. Normally 15 to 20 iterations are
Test these additions again for correct imple-
required to find the steady-state behaviour. As the
mentation.
simulation is quite fast, this presents no problems on a
(ix) Compare the predicted errors with the actual
digital computer.
errors for each test.
(x) Use other tests such as behaviour in con- The test data for the tests on the complete plant were
simulated. An acceptable reproduction of the test data
junction with other models or predictions from
was obtained. The secondary crusher current had a
internal sections of the model to increase the
mean error of 2,3 amperes and a standard deviation of
confidence in the model.
3,2 amperes, and the crusher load a mean error of
Should the results of any of the above comparisons be
1,3 tons/h and a standard error of 25 tons/h. The per-
unsatisfactory, the model is revised at some level, and
centage sizings of the plant product had a standard
the above procedure continued from that level. The
error of 3,5. The data error prediction (by perturbing the
details of each step in the above procedure are given in
parameters) of the model provided a reasonable recon-
Whiten (1971 a).
construction of the distribution of these errors.
The regression technique used was multiple spline
regression. This uses natural cubic spline functions,
which are very smooth interpolation curves (Ahlberg, DEDUCTIONS FROM THE SIMULATION OF THE
et al, 1967), to predict the dependent variable. In this
COMPLETE CRUSHING PLANT
technique, restraints on the amount of detail replace The simulation of the complete plant allows a precisely
assumptions on the analytic form of the regression controlled series of simulated tests to be run. Such a
equation and the emphasis is on the response surface or series of tests on the actual plant would be very time-
its component response surfaces, rather than the coeffi- consuming and usually spoilt by random variations in
cient in an analytic expression. Ordinary linear re- the test conditions and data values. A series of tests
gression is obtained as the simplest case of the multiple involving a total of 21 plant simulations, which cost less
spline regression which is generally more flexible and than $10 for computer time, was run. The following
provides a more easily controlled tool than stepwise variables were varied individually over their operating
multiple regression analysis (Efroymson, 1960) when range:
the analytic form of the relation being sought is not (i) secondary crusher gap,
known. Multiple spline regression provides more infor- (ii) secondary screen size,
mation on the nature of the data and is less likely to (iii) primary screen size,
impose an improper form onto the data. Details of this (iv) primary crusher gap, and
technique are given in Whiten (1971 b). (v) tons per hour of new feed.
In the case of the screen and cone crusher models, it Of these simulations, the last was of particular interest,
was found necessary to use only one one-dimensional as it showed that an increase of three amperes on the
non-linear response and hence the prediction equation;; secondary crushers corresponded to an increase of
for the model parameters contain only one spline 50 tons/h in plant throughput, with a slight decrease in
function, the remaining terms being linear. product size at the higher feed rates. To take advantage
of this, a control system was designed to remove some of
the variations in the crusher current so that a smaller
SIMULATION OF THE PRIMARY SECTION
safety margin would be required, and hence a higher
The data obtained for the primary section were not throughput could be obtained. This control system was
considered extensive or reliable enough to build inde- also designed to ensure that either the primary section
pendent models for this section. The models of the or the secondary section would run at a set maximum
screen and crusher constructed for the secondary current. The balance between primary and secondary
section were found to give adequate prediction for the sections is controlled from the surge bin levels.
JOURNAL OF THE SOUTH AFRICAN INSTITUTE OF MINING AND METALLURGY MAY 1972 261
This control system has been installed at Mount Isa and crushing plant at Broken Hill hit!! been reproduced
has increased crushing capacity by 15 to 20 per cent. successfully by these simulation models and the effect of
The effect of size of crusher gap, which increases conversion of the plant to clmled circuit calculated.
slowly during operation, was examined in another 36 Hence, it appears that these models can be applied to
simulations of the entire plant. The actual tonnage at most crushing plants consisting of cone crushers and
which the plant would run under the control system was screens.
determined by interpolation in tables of the plant Once a suitable simulation is achieved, many tests on
operation at various tonnages and fixed crusher gaps. the simulated plant can be carried out at a very low
Hence a table of the variations in product size and cost. Further, the results of these simulations do not
plant tonnage with primary and secondary crusher gaps display the large amount of random variation that is
for the control system was obtained (Fig. 4). These typical of data from actual crushing plants. Hence the
results also showed that optimum crushing plant interpretation of the simulation results is much easier,
operation occurs when both primary and secondary and provides more definite conclusions than can be
crusher currents are at their maximum values. This obtained from direct experiments on a crushing plant.
optimum is at the corners on the constant crusher gap
lines on Fig. 4.
ACKNOWLEDGEMENTS
The support of Mount Isa Mines throughout the
duration of this project is acknowledged. New Broken
55 Hill Consolidated provided further data. Dr A. J. Lynch
.,. . provided many helpful discussions during the develop-
+1/4
In ment of these models.
product.
50
5=.2 REFERENCES
APPENDIX A
A cone crusher algorithm
Notation
A amperage
bl b2 ba scaling factors
b't coarse breakage function
262 MAY 1972 JOURNAL OF THE SOUTH AFRICAN INSTITUTE OF MINING AND METALLURGY
Si upper size)imit of i-th fraction
t tons per hour of feed
ti a temporary vector
SPNV interpolating spline function
1. Calculation of breakage function
a. Relative size (coarse) breakage
2.3 V2=Vl
b. Fines production
l.l V2=1
1,25
2.1 vl=exp (-si+1/0,12)
2.3 V2=Vl
2. Model parameters
l.l k1=0,67g
1.2 k2=1,121g+2,31q b1+b1 SPNV ([100.,250.,400.],[ -0,0477, -0,0849, -0,2593], t/b1)
1.3 a =0,8723+0,115g
3. Calculation of product
Define function F(s) as
1
F(s) =k1+3 (k1-k2) k1>s
I (s-k2)3
=s+3(k1 -k2)2 k2>s>k1
=s s>k2
l.l e = [F(sj) -F(Sf+l)]/(Sj-Sj+1)
!i-/l/ [abJ'-i+1+(I-a)b"]ti
1.2 x- .
J for j=1 to n-l
1-[ab{+(I-a) b/]e
i£1
1.3 tj = ex
1.4 pj =x-tj
n n-l
2.1 Pn=i£1 !i-i£1 Pi
4. Calculation of amperage
n
l.l a =£.ti/(Si+Si+1)
~
1.2 A =b2+ba (0,082 2a+0,000 305a2/b1)
JOURNAL OF THE SOUTH AFRICAN INSTITUTE OF MINING AND METALLURGY MAY 1972 263
APPENDIX B
Tht vibrating 8Crttn algorithm
Nota.tion
Ct coa.rse product vector components
d wire diameter
fi feed vector components
h hole size
k1 kg ka model parameters
l length of screen
n number of size fractions
Pt fine product vector components
8t upper size limit of i-th fraction
v volumetric feed rate
w width of screen
1.1 Z =klJ
1+(k:V/Wh)2 / (h+d)
0,124734
Define g(x) -
Z / {[(x - 0,437 880 5)x+0,266 982]x+0,138 375}
2.1 Ct =ft
for i such that SiH>h
2.2 Pt =0
si-h
3.1 r -
Si-StH
)U,89/Z-g[Z(h-SiH)])
3.2 Ct = f i (+(1
r -r
>: h -Si+l for i such that St>h>SiH
3.3 Pt =fi-Ci
g[Z(h-st)] -g[Z(h-SiH)]
4.1 Ci = for i such that h>Si and i ~ n
Si - SiH
4.2 Pt =ft-Ci
J
5.1 Cn=0,1fn
5.2 pn=fn-cn
264 MAY 1\)72 JOURNAL OF THE SOUTH AFRICAN INSTITUTE OF MINING AND METALLURGY