Академический Документы
Профессиональный Документы
Культура Документы
Hospital - Fitout
Mechanical Specification
Builder, Building Trades The entity specifically responsible for the Works;
Give notice, submit, supply, furnish, and Give notice, submit, supply, furnish and the like to the
similar expressions entity specifically responsible as the Principal’s
Equipment procurement
The procurement methods for equipment are identified based on the three main Groups –
Group 1 – Equipment supplied and installed by the Contractor.
Group 2 – Items supplied by the Principle and installed by the Contractor.
Group 3 – Equipment supplied and installed by the Client.
The contractor to confirm with the client prior to submission of tender to ensure prices are provided per
requirement.
Design Requirements
The Contractor shall allow for completion of the services designs, co-ordination, documentation (drawings
and information as required), including but not limited to:
> Detailed design calculations using latest architectural and other information to determine true
requirements of the development. The current D&C services drawings, specifications, and equipment
schedules are for design intent and information purposes only.
> Provide equipment schedules in PDF and Excel format. All final equipment schedules shall be prepared
based on the Contractor’s own detailed design calculations and co-ordination works.
> Coordinate fitout design with base building designs prior to construction.
> Coordinate with the relevant parties for services provisions to Group 2 and Group 3 equipment. Allow to
provide all connection points required to ensure correct operation of the equipment.
> Coordinate and incorporate all requirements outlined in the following documents into the services
design documentation. It is the responsibility of the contractor to obtain these documents from the
Principal as they become available.
> Penrith City Council Development Application Conditions of Consent
> Base building BCA Assessment Report, by City Plan Services
> Base building Fire Engineering Report, by Olsson Fire & Risk (including all performance-based
alternative solutions)
> Acoustic Report: Acoustic Logic
> Principal Project Requirements
> Architectural documentation (Base Building): Bureau SRH
> Hospital planning design documentation: Kelling Projects
> All other sub-consultants’ documentation
> Provide specialist expertise necessary to complete the works in accordance with the documentation
including:
> To certify compliance with contract documents;
> To certify compliance with Authority requirements;
> To certify the installation as required and to all authority requirements;
> To pay all fees applicable to progress and complete the works, including authority fees and charges;
> To obtain all Authority permits and certificates to allow the progress of the work;
Staging Sequence
Refer to architectural documentation for project staging and works sequencing requirement. The contractor
shall provide installation program to suit. Refer to the Project Principal’s Sequencing Requirements for
staging works and provide construction program, identifying the following -
> Sequence of work to suit architect staging integrated fitout intent;
> Critical paths of activities related to the work;
> Allowance for holidays;
> Activity inter-relationships;
> External dependencies including provision of access, document approvals and work by others;
> Periods within which various stages or parts of the work are to be executed;
> Revise these submission requirements as necessary;
> Where updating of program is required, identify changes since the previous version, and show the
estimated percentage of completion for each item of work.
Hold Points
The contractor shall allow to hold all works at certain points for review by relevant parties. As a minimum, the
following hold points shall be allowed for:
Services equipment shall not be purchased without the following approvals:
Review of contractor completed detailed design calculations, layouts, and equipment schedules by the
Principal, or Principal’s representative.
Review of contractor completed detailed design calculations, layouts, and equipment schedules by base
building.
Contractor shall confirm:
All slab penetration requirements, including but not limited to all risers, masonry shafts, ductwork, pipework,
conduit, cabling, etc. to be suitable for the fitout.
All in-slab services. For example: conduits, pipework, etc. to be suitable for the fitout.
Submissions
General
All submissions must be in electronic PDF format as a minimum and with unrestricted, unsecured, indexed
and hyperlinked, text searchable file content.
Provide all information required for approvals including:
> Design drawings;
> Calculations;
> Copies of correspondence with authorities;
> Schedules for all plant and equipment, prior to placing orders;
> Construction drawings;
> Factory test results where applicable;
> Product data, performance test and commissioning results required;
> Shop drawings for fabrication and installation of all equipment and items;
> Inspection, test and commissioning plan for every section of the work;
> handover and training proposals;
> Installation drawings which show all equipment and services layouts, wiring and any other items during
the construction period incorporated into the works;
> Operating and Maintenance manuals;
> Maintenance and service records during the defects liability period;
Technical Data
Submit prior to ordering a full schedule of equipment proposed for the project, including all technical
aspects of the piece of equipment. Identify any changes or non-compliances to the specification in a matrix
schedule nominating all specified parameters and all proposed parameters.
Certification
Submit certification for all plant and equipment and installation carried out in accordance with Authority and
contract requirements.
Provide certificates of design and installation compliance as required by the Principal Certifying Authority,
manufacturers and other Authorities.
Certifying that those sections of the work which are essential services or are services requiring certificates of
compliance with any other ordinance, Regulation or Act, are installed and have been tested and proved to be
in conformity with the relevant requirements.
Carry out tests to prove compliance prior to Practical Completion. The test programme and task of proving
that the system conforms with Authority requirements shall be the responsibility of the Contractor.
Certify that the design is in accordance with the design intent of the documents.
Data to Be Submitted
Include manufacturers’ technical literature and the following information:
> Model name, designation and number;
> Capacity of all system elements;
> Country of origin and manufacture;
> Materials used in the construction;
> Size, including required clearances for installation;
> Technical data schedules corresponding to the equipment specified in documentation. Provide a matrix
schedule nominating all specified parameters and all proposed parameters, and a comparison analysis;
> Type-test reports.
Alternatives
Alternatives may be proposed for consideration. Any alternatives proposal must be submitted, in line with
the requirements above, for approval complete with a fully scheduled comparison between specified and
alternative option, with design calculations and coordination documentation of all direct and associated
works to demonstrate suitability, and statement outlining the options suitability, fit for purpose, and
coordination.
Acceptance of alternatives will be at the discretion of the client.
Shop Drawings
Submit shop drawings in electronic PDF format as required by submissions, in accordance with the
programme and specific requirements outlined herein. Drawings must be prepared in AutoCAD. Incorporate
all shop drawings in operation and maintenance manuals.
The shop drawings shall indicate as a minimum:
Title block with all Contractor’s details;
Nominated coordination details and confirmation from all trades;
Dimensions, types and location of all equipment in relation to permanent site features and other services in
plan, elevation and section detail;
Equipment layouts and sections. Show the location of all fire rated building elements;
Riser layouts and sections;
Fixings and seismic restraint details;
Wiring and schematic diagram for all electrical equipment and control circuits including switchboard layout
and construction details.
Ensure coordination with other building and service elements. Show adjusted positions on the shop and
record drawings.
Check space requirements of equipment and services indicated diagrammatically in the contract documents
and submit a report on consequent variations to the design.
Identify on a separate set of shop drawings the proposed maintenance strategy for all plant and equipment.
This shall include but not limited to the following:
Appliance access and maintenance zones;
Equipment access and maintenance zones;
Authority metering equipment access and maintenance zones;
Fire and smoke seal inspection access.
Quality
Quality Assurance
Provide a Quality Assurance (QA) plan in order to establish, monitor and document a quality assurance
system covering all aspects of the Works. The plan must be in accordance with ISO 9001 or ISO 9002 as
appropriate.
The plan shall include processes and monitoring checklists for checking of all documentation including
drawings, schedules, installation procedures, commissioning and testing procedures, handover
documentation etcetera, for completion prior to submission.
Submit the following documentation before starting work on site:
Quality System third party certification, if any, to the Standards specified by the Joint Accreditation System of
Australia and New Zealand;
Quality Manual detailing the corporate QA policy statement, system element description, registers of
procedures and project specific Inspection and Test Plans.
Content
Include the following:
> Table of contents;
> Drawings and technical data or the operation and maintenance of the installation;
> Directory of names and contact details of all responsible parties;
> General description of the whole installation;
> Technical description and graphic representation of each system installed that fully describes the scope,
performance and facilities provided. Identify function, operating characteristics and limiting conditions;
> Photo of every fire stopped penetration installation;
> Asset register with full equipment descriptions:
> Unique identification tagging suitable for site conditions where applicable;
> Name, contact numbers and email address of the manufacturer and supplier of items of equipment
installed together with all identifying markings and numbers including catalogue and serial numbers;
> Schedules of equipment stating locations, duties, performance figures and dates of manufacture. Cross
reference equipment to the record and diagrammatic drawings and schedules;
> Manufacturer’s technical literature for equipment installed. Exclude irrelevant material. Clearly identify
specific products and component parts used in the installation and shall exclude any irrelevant
information;
> Each item shall be clearly identified on the As-Built Drawings and cross-referenced to the Operation and
Maintenance Manual;
> Supplements to the product data to illustrate relations of component parts;
> Operation Procedures:
Samples
Provide a sample for each item of equipment which is visible to the occupants of the building and additional
samples of items where required.
Where the building fabric exists, fix the sample in an agreed position. Following approval, remove from
position and submit as above.
Samples to be labelled and stored in a nominated area and schedule maintained.
Coordinate submissions of related samples. Samples shall be provided for approval with sufficient time
allowance to prevent any delays in programme.
Noise
Provide acoustic treatment throughout the installation to ensure the functioning operation of the Works
meets the specified noise levels. Submit details of the proposed equipment noise levels and sound insulation
proposed.
Refer to the relevant acoustic report for specified acoustic performance requirements.
Completion
Commissioning
Carry out tests, verifications and checks to ensure that all systems and items of equipment are ready for
commissioning. Carry out all fault-finding and other operational tests to ensure that all control systems
operate as intended. Provide documentation of completion of testing.
Submit a detailed commissioning programme and pro-forma commissioning sheets for every system or item
of equipment to be commissioned. Provide experienced, qualified commissioning engineers to carry out the
commissioning. Detail:
The procedure to be used to complete the task;
The skill or competency of the person undertaking the work;
The review or testing procedure to assure satisfactory completion of the task;
The person authorised/accredited to sign off the task as accepted.
Training
Provide training in the correct operation and maintenance of the installation. Include in the instruction the
purpose, function, operation and maintenance of the installation. Allow a minimum of 24 hours of face to
face training across all systems and operations at a time and location to Approval, and additional where
nominated.
Use items and procedures listed in the Operation and Maintenance manuals as the basis for instruction.
Conduct training at agreed time at the system or equipment location. For equipment requiring seasonal
operation, demonstrate operation during the appropriate season.
Spares
Submit a schedule of spare parts necessary for maintenance of the installation. State against each item the
recommended quantity and the manufacturer’s current price, including for:
Packaging and delivery to site;
Checking receipt, marking and numbering in accordance with the spare parts schedule;
Referencing equipment schedules in the operation and maintenance manuals;
Painting, sealing and packing to prevent deterioration during storage.
Tools
Provide all tools required to conduct routine maintenance. Include instructions for use.
Maintenance
During the maintenance period, carry out regular inspections and maintenance work as required by statutory
regulations and recommended by equipment manufacturers. Maintenance shall be carried out at times and
in a manner that will have the least impact on the facility. Comply with all access procedures established on
the site of the works.
At each service visit record comments on the functioning of the systems, work carried out, items requiring
corrective action, adjustments made and name of service operator.
Submit details of maintenance procedures and programme, relating to installed plant and equipment.
Nominate dates of service visits. State contact details of service operators and describe arrangements for
emergency calls.
Submit details, including test and approval certificates, recording activities including operational and
maintenance procedures. Such information shall include materials used, test results, comments for future
maintenance actions and notes covering the condition of the installation. Include completed log book pages
recording the operational and maintenance activities performed up to the time of practical completion and
again at the end of defects liability period.
Obvious Work
The services documents show the design intent and general arrangement of equipment. They do not show
minor works or obvious works and items that are necessary to provide fully functioning systems in full
compliance with the design intent and the technical requirements of the documents. Provide such obvious
work.
Make all necessary alterations to the general arrangement and system design to accommodate any
equipment offered and accepted as an alternative to the specified equipment.
Supply air
Main duct in celling space – 6.0 m/s
Branch duct with diffusers connected – 6.0 m/s
Plantroom and riser ducts – 8.0 m/s maximum
Return air
Main duct in ceiling space – 6 m/s
Ventilation System
General Supply or Exhaust – 8 m/s
Project specific advise from the users re the types of surgery in operating theatres and their specific humidity
and temp0erature needs should be sought to confirm the operating theatre room requirements.
Separate localised air conditioning plant should be provided for rooms with unusually high heat gains or
intermittent operation. Separate clinical departments will generally have separate air handling plants.
Zoning of all air conditioning systems will acknowledge different dynamic loads and conditions likely to
occur due to:
> External glazing and wall materials
> Roofs and suspended floors
Outside air economy cycles will be included on all significantly sized air handling plant as per NCC
requirements, unless detrimental to pressure regimes or humidity control.
Mechanical ventilation and air conditioning systems will be fully ducted or be provided with air paths that are
contained, not subject to contamination, accessible and cleanable. Air handling duct systems will be designed
to be accessible for duct cleaning, generally by the provision of access panels. Access panels will be fitted at
each coil, fire and smoke damper and each turn in direction to allow annual essential services inspection, as
well as in locations as per mechanical equipment manufacturers requirements for access and maintenance.
Local exhaust ventilation will be localised as close as practicable to the sources of contamination. Exhausts
will be suitably filtered and discharged in a manner that will not contaminate any adjacent area or system.
The throw of air diffusers should be selected such that there is no splash on walls above patients in beds or
on trolleys. For patient spaces where privacy curtains are used, care is to be taken in the selection and
placement of supply air grilles and pathways for return and relief air.
Operating Theatre 1 + 20
Operating Theatre 2 + 20
Operating Theatre 3 + 20
Operating Theatre 4 + 20
Sterilising and Packaging + 20
Sterile Store + 20
Setup 2 + 30
Airlock + 10
Corridor 2 + 10
Corridor 3 + 10
Utility Corridor - 10
Clean Up - 10
Instrument Washing - 20
Dirty Utility RM 1041 - 10
WC RM1012 - 10
Rooms with specific pressure differentials which are to be maintained must be well sealed including all
service penetrations.
All hospital areas are to have filtration efficiencies as listed in NSW Health Guidelines - Engineering Services
Guidelines. The first filter listed in the matrix of specific requirements is the pre-filter if 2 filters are listed,
second is the main filter and the HEPA if listed is the final terminal filter. Filtration efficiencies to comply with
AS1324. Manometers or differential pressure monitoring devices will be installed across filter banks with
efficiencies greater than grade F6. Air filters shall be adequately sized according to the supply air rate of the
room, air velocity in the room, and the manufacturers recommended face velocity.
> Provision of acoustic enclosures to air conditioning and ventilation plant where required by the acoustic
report.
2.2.3 Sleeves
General: If piping or conduit penetrates building elements, provide metal or PVC sleeves formed from pipe
sections as follows:
> Movement: Arrange to permit normal pipe or conduit movement.
> Diameter (for non fire-rated building elements): Sufficient to provide an annular space around the pipe
or pipe insulation of at least 12 mm.
> Prime paint ferrous surfaces.
> Terminations:
– If cover plates are fitted: Flush with the finished building surface.
– In fire-rated and acoustic-rated building elements: 50 mm beyond finished building surface.
– In floors draining to floor wastes: 50 mm above finished floor.
Elsewhere: 5 mm beyond finished building surface.
> Termite management: To AS 3660.1.
> See, for example, AS 3660.1 Table 1 and clause 7.4.3. Additional state requirements may also apply
under BCA.
> Thickness:
– Metal: 1 mm.
– PVC: 3 mm.
2.3.2.1 General
General: Minimise the transmission of vibration from rotating or reciprocating equipment to other building
elements.
2.3.2.2 Connections
General: Provide flexible connections to rotating machinery and assemblies containing rotating machinery.
> Isolate ducts by flexible connections.
> Isolate pipes by incorporating sufficient flexibility into the pipework or by use of proprietary flexible pipe
connections installed so that no stress is placed on pipes due to end reaction.
2.3.2.3 Speeds
General: If no maximum speed is prescribed do not exceed 1500 r/min for direct driven equipment.
2.5.2 Standard
General: Conform to the recommendations of AS/NZS 2311 Sections 3, 6 and 7 or AS/NZS 2312 Sections 5, 8
and 10, as applicable.
2.8 Training
2.8.1 Maintenance
General: Explain and demonstrate to the principal’s staff the purpose, function and maintenance of the
installations.
2.8.2 Operation
General: Explain and demonstrate to the principal’s staff the purpose, function and operation of the
installations.
2.9 Co-ordination
The Contractor shall be responsible for the detailed setting out of the Building Service of Contract Work so as
to:
> Coordinate with other Trades, particularly with respect to other Building Services and other Contractor's
Contractors.
> The set out of ceilings, floors, etc., including area discussions with all appropriate trade and/or
Contractor's Contractors.
> Locate the relevant Building Service's Works in the spaces as shown on the drawings with suitable access
and clearances for normal and long-term operation and maintenance requirements also in accordance
with the manufacturer's recommendations.
> Alignment of all Building Service’s work, i.e.; light fittings, air registers, smoke detectors, speakers, access
panels, etc., to ensure the Architectural aesthetic requirements are met.
As part of the operation and maintenance manuals required post completion of the project, the contractor is
to contribute towards compiling a comprehensive building user’s guide in association with other services.
> Prior to Practical Completion test, balance and commission the systems to ensure they operate as per
the specified requirements.
> The Subcontractor in cooperation with the builder shall agree on a programme and provide adequate
notice for the consultant to check any areas that are complete and available. Consultant checking will
not commence until the Subcontractor has fully commissioned the system and has ensured that the
system is performing as required.
> The Basis of Design section of this specification defines the base design conditions that relate to this
project.
> The final commissioned air conditioning and mechanical ventilation installation and works undertaken as
part of this specification shall as a minimum meet the design conditions and flow rates specified in the
basis of design section of this specification and associated drawings.
Labour and Equipment: Supply the necessary facilities, labour, apparatus and instruments, properly
calibrated, required for carrying out the tests, and give the Managing Contractor five working days' notice in
writing of tests. All instrumentation used for the testing shall have a current calibration test certificate.
Energising
2.12 Commissioning
Give sufficient notice for inspections to witness commissioning of the installation. Minimum notice required
is 5 working days.
For commissioning ensure all systems are fully operational and meet the specification performance
requirements and are suitable for building users to operate.
Allow to adjust equipment and systems to suit the training operational requirements with the Principles
representatives.
3.2 Aims
3.2.1 Responsibilities
General: Provide fans. As documented.
3.2.2 Design
Axial flow fans: Provide fans selected so the air flow can be increased 5% above the rate in Fan schedules
as follows:
> Against the corresponding increased system resistance as installed.
> Without unstable operation.
> By pitch angle change alone.
Variable volume systems: Provide fans for variable volume systems selected for:
> Maximum fan efficiency at 70% to 80% of design air flow rate.
> Operation from 30% to 110% of design air flow without going into a surge condition.
Fans with variable speed drives:
> All fans: Provide fans selected to operate at 50 Hz under all conditions.
> Fans with belt drives: Adjust fan speed during commissioning for motor to operate at 50 Hz under all
conditions.
Fans with multi-speed motors:
> Two speed fans: Provide fans selected to perform both duties given in the Fan schedules.
> Fans with 3 speeds and single phase fans with adjustable speed control: Provide fans selected to
achieve the duty stated in the Fan schedules at a speed 80% of highest speed.
3.5 Products
3.5.1 Materials
3.6.2 General
Provide fans with non-overloading power characteristics.
3.6.3 Casings
Tubular, flanged at each end, constructed from mild steel, fully welded, hot dip galvanized after fabrication.
3.6.4 Impellers
General: Provide aerofoil section blades constructed from cast aluminium alloy or glass reinforced plastic to
the Axial flow fan schedule.
Pitch angle: Manually adjustable.
Balancing: Balance impellers, statically and/or dynamically.
3.6.6 Motors
General: Direct mount to impellers with minimum Thermal class 155 (F) insulation to IEC 60085.
For smoke spill fans, Class 180 (or higher) insulation is required.
Bearings: Provide sealed for life bearings or grease packed bearings fitted with lubrication lines extending
through the casing. Provide bearings with a minimum rating fatigue life of 17,500 hours, suitable for
horizontal or vertical mounting as appropriate.
3.7 Marking
3.7.1 Labels
Show the following:
> Manufacturer’s name.
> Model.
> Serial number.
> Size.
> Direction of rotation, marked on casing.
3.8.1.1 Access
Arrange fans and accessories to allow service access for maintenance, removal or replacement of assemblies
and component parts, without disturbance of other items of plant, fire rating material and/or the building
structure.
3.8.1.3 Drains
Where moisture is likely to enter or condense inside a fan provide a trapped drain in accordance with
AS/NZS 3666.1.
4.2 Aims
4.2.1 Responsibilities
General: Provide air filters to all supply air systems as required by NSW Health Guideline – Engineering
Services Guidelines Table 7.1.
Selections: As documented.
4.4 Standard
4.4.1 Air Filters
Performance and construction: To AS 1324.1.
Microbial control: To AS/NZS 3666.1 and the recommendations of SAA/SNZ HB 32.
4.5 Interpretations
4.5.1 Abbreviations
General: For the purposes of this work section the abbreviations given below apply.
DOP: Dioctylpthalate.
HEPA: High efficiency particulate arrestance.
4.5.2 Definitions
General: For the purposes of this work section the definitions given below apply.
Class: Filter class to AS 1324.1.
Type: Filter type to AS 1324.1.
4.7 Submissions
4.7.1 Filter Type Tests
Particulate filters: For each type of filter, submit evidence of filter type tests conducted by a Registered
testing authority within the past 5 years.
Standards:
> HEPA and MEPA filters: To AS 4260.
> Other particulate filters: To AS 1324.2.
Filter size for test: 610 x 610 mm face dimension.
4.8 Products
4.9 Materials
4.9.1 General
Sealant performance: Resistant to air, entrained water and oil, and microbial growth.
Adhesive performance:
> Characteristics under environmental conditions: Odourless and non toxic. Non-migrating, non-
evaporating and non-hardening, and resistant to microbial growth.
> Environmental conditions: Normal temperature, sustained temperatures up to 60C, and operating air
velocities.
4.10 Components
4.10.1 Component Sizes
General: Standardised throughout the installation as far as practicable.
4.10.2 Filters
Consistency: For filters of the same type provide filters from only one manufacturer.
4.13 Execution
4.14.5 Manometers
General: Provide a manometer on each filter bank with more than one cell or handling more than 600 L/s.
Type: Minimum 75 mm diameter non-liquid, diaphragm type marked to show differential pressure across
each filter bank.
Differential pressure gauge unit: Include pipework, termination and fittings necessary for correct operation
and maintenance.
Indicator scale: Mark in 10 Pa divisions with full scale deflection no more than twice the maximum dirty filter
condition.
Location: Outside unit casing in a readily readable location.
Marking: Mark clean and maximum dirty pressure drops on manometer scale.
4.14.9 Cleaning
4.14.10 Cleaning
General: Before start-up, ensure that the installation is free from debris and dirt, and check the integrity of
the filter bank and plenum installation.
5.2 Aims
5.2.1 Responsibilities
General: Provide ductwork as documented.
Selections: All ductwork shall be galvanised steel.
5.4 Standard
5.4.1 General
Ductwork: AS 4254 Part 1 and Part 2.
5.5 Interpretations
5.5.1 Abbreviations
General: For the purposes of this work section the abbreviations given below apply.
FRL: Fire-resistance level.
5.7 Submissions
5.7.1 Fire Hazard Properties
General: Submit evidence of conformance with the following:
> Fire hazard indices for all materials when tested in conformance with AS/NZS 1530.3:
– Spread of flame index: 0.
– Smoke developed index: 3.
> Facing materials when tested to AS 1530.2: Flammability index: 5.
> Assembled duct systems: Pass the UL 181 burning test.
> Fire protection of duct systems: Achieves the required FRL to AS 1530.4.
Situation:
> External situation includes:
– Ductwork outside the building.
– Fire, smoke and motorised dampers in ductwork outside the building.
– Fire, smoke and motorised dampers located in the discharge air path within 3 m of the point of
discharge from the building.
– Fire, smoke and motorised dampers located in the outside air or mixed air/recycle air path up to
the filters.
> Internal situation includes:
– Ductwork inside the building not included in external situation.
5.10.2 Fasteners
Rivets: Expanding solid end type, aluminium base alloy for galvanized duct, stainless steel for stainless steel
duct, minimum size as follows:
> For sheet metal to sheet metal: 3 mm.
> For sheet metal to supports, brackets and rolled steel angles: 4.8 mm.
Self tapping screws: Zinc-plated for galvanized duct, stainless steel for stainless steel duct.
Self drilling and tapping screws: Zinc-plated for galvanized duct, stainless steel for stainless steel duct.
Provide only if base material into which they screw is thicker than 1.5 mm and they are unlikely to be
removed or replaced.
Bolts, nuts, washers and drop rods: Zinc-plated steel, service condition number 2 for galvanized duct,
stainless steel for stainless steel duct. Parts on stainless steel duct not in contact with air stream or corrosive
conditions may be zinc-plated as for galvanized duct. Provide washers under nuts and bolt heads.
Outdoors A A A A
Unconditioned B A B B
spaces
Conditioned C B B B
spaces (concealed
ductwork)
Conditioned spaces A A B B
(exposed ductwork)
- Office-type
spaces
5.14.2 Blades
Material: Metallic-coated steel, aluminium or stainless steel.
Form: No sharp edges. Sufficiently rigid to eliminate movement when locked.
Minimum thickness:
> Metallic-coated sheet steel and stainless steel:
– Single thickness blades: 1.6 mm.
– Double thickness blades: 1.2 mm.
> Aluminium:
– Single thickness blades: 2.4 mm.
– Double thickness blades: 1.8 mm.
Maximum length: 1200 mm. If necessary provide intermediate mullions.
Single blade dampers:
> For single thickness blades: 600 mm maximum length, 600 mm maximum width or 600 mm maximum
diameter.
5.14.3 Bearings
Type: Oil impregnated sintered bronze bearings, sealed-for-life ball bearings or engineering plastic sleeve
bearings. If the operating temperature is > 50C, do not provide nylon.
Lubrication: Provide access for lubrication.
Housings: Rivet to damper frames.
5.14.4 Spindles
Material: Stainless steel in stainless steel dampers, zinc-plated steel or stainless steel otherwise.
Construction: Securely fix to damper blades.
Minimum diameter:
> Blade lengths 600 mm: 10 mm.
> Blade lengths > 600, 1200 mm: 12 mm.
5.14.5 Linkages
Fix securely to blades so that the blades rotate equally and close tightly without slip.
5.16.2 Links
Mechanical fire dampers: Provide frangible bulb or fusible links.
Smoke dampers: Provide fusible links activated by either local heat or a low power external electrical
impulse.
Installation: Mount for easy replacement.
5.18.2 Construction
Type: Double panel, deep formed, zinc-coated steel construction, insulated to match the duct, or filled with at
least 25 mm glass wool or rock wool insulation.
Cold bridging: Arrange to prevent condensation on cold surfaces.
Frames: Provide rigid matching galvanized steel frames securely attached to the duct. Do not protrude any
part of the panel or frame into the airstream.
5.19 Execution
5.20.2 Spacing
Provide minimum clear spacing, additional to duct insulation, as follows:
> 25 mm between adjacent ducts.
> 25 mm between duct flanges or upper surfaces of ducts and undersides of beams and slabs.
> 50 mm between ducts and electric cables.
> 150 mm between ducts and ground, below suspended floors.
5.20.5 Cleaning
During installation progressively remove construction debris and foreign material from inside ducts.
5.20.6 Drainage
Provide drainage to AS/NZS 3666.1 at locations in ductwork where moisture may accumulate including at
outside air intakes.
6.2 Aims
6.2.1 Responsibilities
General: Provide insulation of ductwork and related items.
Selections: As documented.
6.4 Standards
6.4.1 General
Ductwork insulation: To BCA 2016 Volume 1 Specification J5.2b Table 3.
6.6 Submissions
6.6.1 Fire Hazard Properties
General: Submit evidence of conformance with the following:
> Fire hazard indices for all materials when tested in conformance with AS/NZS 1530.3, including, if the
material has a reflective facing, scoring and blackening to AS/NZS 1530.3 clause A6:
– Spread of flame index: 0.
– Smoke developed index: 3.
> Facing materials when tested in conformance with AS 1530.2: Flammability index: ≤ 5.
> Assembled duct systems: Pass the UL 181 burning test.
6.6.3 Samples
Samples: Submit samples of the following:
> Each type of insulation, applied to a sample 1.5 m long section of ductwork, including a site applied
insulated transverse joint.
6.7 Products
6.8.5 Insulation
Type: In batt, board or blanket form.
Polyester: Thermally bonded polyester fibres.
Polyolefin: Closed cell cross-linked polyolefin foam produced using non-CFC blowing agent.
Flexible type: Blanket form.
2.0 75
1.2 50
6.8.10 Adhesives
Type: Suitable for bonding facing to the insulation. Apply in an even coat.
Fire hazard properties:
> Smoke developed index: 0.
6.9 Execution
6.10 General
6.10.1 Fixing Devices
Standard: To AS 4254.2 clause 2.7.
Pins: Stud welded fully annealed metallic-coated steel.
Speed clips: Bevel edged metallic-coated steel with an area not less than that of a 25 mm circle. Secure speed
clips flush to the face of the insulation.
6.10.3 Joints
Joints: Install insulation with the least number of joints practicable.
Use of multiple layers: If insulation is applied in more than one layer, stagger longitudinal and end joints.
6.11.2 Application
General: Cover parts of ducts designated to be insulated, with individual pieces of insulation for each side of
the duct. Where this is not possible, butt join edges of adjacent pieces. Where multi-layers are used (round or
oval ducts) stagger all joints.
6.12.2 Application
General: Cover parts of ducts designated to be insulated with individual pieces of insulation for each side of
the duct. Where this is not possible, butt join edges of adjacent pieces. Overlap adjacent sides at corners.
650 0.6
6.12.5 Location
General: Apply metal facing to internal insulation in the following locations:
> 300 mm each side of fire, smoke and volume control dampers.
> Air handling plant casings and plenums.
> All other locations where insulation may be subject to mechanical damage.
6.13.2 Application
General: Wrap insulation around the outside of ducts, covering the parts designated to be insulated.
Minimise the number of joints.
Joints: Square cut and butt together the edges of adjacent pieces of insulation.
Insulation of bends: Apply a single piece of insulation to each face of a bend or transition. Insulate bends and
transitions on round and flat oval ducts with individually mitred gores cut to fit the fitting.
Vapour sealing: Seal the vapour barrier at joints with 100 mm wide aluminium foil laminate tape, applied
centrally over the joint. Where the insulation is impaled over pins, seal the vapour barrier by covering pins
with water-based mastic vapour barrier or reinforced aluminium foil faced tape at least 100 x 100 mm.
6.14.2 Application
General: Comply with External – laminate faced.
Support: Support insulation against the duct surfaces with 0.55 mm metallic-coated steel cut and folded to
the outside dimensions of the insulated duct.
6.15.2 Dampers
Internal: Leave clearance between insulation and edges of the splitter or manually operated damper blades.
External: For manual and motorised dampers, provide removable insulated sheet metal top hat sections to
encase dampers. Ensure the actuator is in a serviceable position.
6.16.2 Method
General: If the insulation of the connecting ductwork is:
> External laminate faced on one or both sides of the flexible connection: Insulate duct flexible connection
as required in the External laminate faced clause.
> Any other insulation system: Insulate duct flexible connection with elastomeric foam as required in the
Elastomeric foam insulation clause.
7.2 Aims
7.2.1 Responsibilities
Obtain approval from architect, submit sample
7.4 Standards
7.4.1 General
General: AS 4254 Part 1 and Part 2.
7.5 Interpretations
7.5.1 Abbreviations
VAV: Variable air volume.
7.5.2 Definitions
General: For the purposes of this work section the definitions given below apply.
> Air grille: A general term referring to a grille of metal or other material fitted to the inlet or outlet end of
an air duct or within walls, floors ceilings or doors.
> Diffuser: A supply air grille mounted in a ceiling or on the underside of a duct through which air is
supplied and distributed within a room or interior space of a building.
> Register: A supply air grille mounted in a wall or on the side of duct.
> Grille: A grille fixed over the aperture from which air is removed from an enclosed space.
7.6 Submissions
7.6.1 Samples
General: Submit a sample of each type of air grille and diffuser. Include plenum box and blanking plates as
documented.
7.7 Products
7.7.1 Manufacture
General: Provide proprietary grilles:
> Free from distortion, bends, surface defects, irregular joints, exposed fastenings and operation vibration.
> Mounted with secure and concealed fixings.
> With flange corners neatly mitred, butted and buffed, with no joint gaps.
Material: Steel or aluminium.
Finish:
> Exposed surfaces: Powder coated to nominated colour.
> Visible internal elements: Matt black enamel.
Fixings: Provide concealed fixings which allow removal without damage to surrounds or grilles.
7.11.2 Mounting
General: Provide a matching escutcheon to close gaps between the grille and its surrounds. Provide grilles
with flanges to cover penetrations and irregularities in surrounds.
Tiled ceilings: Locate grilles and diffusers to minimise cut tiles. Otherwise, locate grille symmetrically in the
tile.
Appearance: Install square.
8.1.2 Design
General: Base design pressures on the following:
> The maximum hydrostatic head at the location.
> The pump shut off head at the maximum impeller size for the pump casing.
System: Provide piping systems complete with all necessary piping, valves, supports, guides, drains, vents,
expansion compensation and all fittings necessary for their safe and efficient operation.
Installation: Follow the line of walls, ceilings, etc., and include all necessary offsets and arrange to avoid
interference with the building or other services regardless of whether or not these aspects are shown on the
drawings.
Plant access: Make provision for plant isolation and maintenance. Locate valves and other components in
ceilings where they are easily accessible and where access or leaks will not cause inconvenience or risks to
occupants, or damage to water sensitive equipment.
Connections: Arrange connections to plant to permit dismantling of the plant without disturbing other pipes
and to permit removal of the plant without removal of the piping. Provide union on at least one side of each
screwed valve and screwed pipeline component requiring removal for inspection or maintenance. Make all
connections to plant by one of the following methods:
> Flare compression joints (up to 20 mm copper and only where there is no vibration).
> Screwed brass unions (up to 50 mm size and for pressures up to 800 kPa).
> Bolted flanges (no limitation).
Contractor to be flush pipework prior to commissioning.
8.4 Interpretations
8.4.1 Definitions
General: For the purposes of this work section the definitions given below apply.
> Accuracy: The closeness of the agreement between the result of a measurement and the true value of
the particular quantity being measured.
> Error: The measured value minus the true value of the particular quantity being measured.
> Resolution: The smallest difference between indications of a displaying device that can be meaningfully
distinguished.
8.5 Submissions
8.5.1 Valves
Calibrated balancing valves: For each type and size of valve, submit a manufacturer’s calibration chart relating
pressure drop to fluid flow across the valve opening range. Submit independent test reports giving accuracy
and repeatability tolerances.
Automatic/dynamic system balancing valves: For each type and size of valve, submit a manufacturer’s report
verifying a flow rate control accuracy of 5% or better is maintained over the selected pressure differential
control range.
8.6 Products
8.7.2 Jointing
General: Select from the following except where a specific jointing method is documented:
> Silver brazed capillary joints.
> Brass flanges with brass nuts and bolts.
> Flare compression joints: 20 DN nominal size and only where no vibration occurs.
> Proprietary grooved joints.
> Crimp
> Victaulic
15, < 20 12
20, < 32 15
32, < 50 25
50, < 80 30
8.8.2 Installation
Standard: To AS 3690.
8.8.4 Jointing
Permanent joints: Solvent cement.
Demountable joints:
> Piping DN 50: Threaded fittings.
8.9.2 Installation
Standard: To AS/NZS 2032.
8.9.3 Jointing
Permanent joints: Solvent cement.
Demountable joints:
> Piping DN 50: Threaded fittings.
> Piping > DN 50: Flanges with backing rings.
8.10.2 Installation
Standard: To AS/NZS 2033.
8.10.3 Jointing
Permanent joints: Solvent cement.
Demountable joints:
> Piping DN 50: Threaded fittings.
> Piping > DN 50: Flanges with backing rings.
8.12 Accessibility
8.12.1 General
General: Provide access and clearance at fittings which require maintenance or servicing, including control
valves and joints intended to permit pipe removal. Arrange piping so that it does not interfere with the
removal or servicing of associated equipment or valves or block access or ventilation openings.
8.12.2 Gauges
General: Locate thermometers, pressure gauges and similar instruments so that they are easily read after
installation.
8.13 Cleaning
8.13.1 External Preparation
General: Remove scale, rust, burrs and grease and ensure that surfaces are clean and dry.
Protection: During construction, prevent the entry of foreign matter into the piping system by temporarily
sealing the open ends of pipes and valves with purpose-made covers of pressed steel or rigid plastic.
8.14 Supports
8.14.1 Support Systems
General: Provide hangers, brackets, saddles, clips, and support system components, incorporating provisions
for adjustment of spacing, alignment, grading and load distribution. Support pipework from associated
equipment or building structure. Support valves, strainers and major line fittings so that no load is placed on
adjacent tubes or transmitted to them during operation and maintenance.
Support type: Proprietary metallic-coated steel channel section with clamps and hangers sized to match
external diameter of pipe being supported.
Vertical pipes: Provide anchors and guides to maintain long pipes in position, and supports to balance the
mass of the pipe and its contents.
Saddles: Do not provide saddle type supports for pipes DN 25.
< 20 6 6
20, < 35 10 10
35, < 65 12 12
8.16 Sleeves
8.16.1 General
Location: Provide sleeves that permit normal pipe movement through all walls, floor slabs, and building
elements.
< 20 65 mm
8.17 Joints
8.17.1 General
Minimise the number of joints. If practicable, provide welded or brazed joints or a proprietary pipe coupling
system.
Nominal size of pipe to be drained, DN Nominal size of drain and valve, DN (minimum)
8.18.3 Grading
Water systems: Grade to rise in the direction of flow to points of air venting, except, if the water piping is
exposed in a run with other services, run the water piping to the same grade as the other services.
> Minimum grade: 1 in 200.
9.2 Aims
9.2.1 Responsibilities
General: Provide insulation to hot and cold piping.
Selections: As documented.
9.4 Standards
9.4.1 Installation of Glass Wool and Rock Wool Insulation
General: Comply with the ICANZ Industry Code of Practice for the Safe Use of Glass Wool and Rock Wool
Insulation.
Marking: Deliver Glass Wool and rock wool products to site in packaging labelled
FBS-1 BIO-SOLUBLE INSULATION including the following label.
9.5 Interpretations
9.5.1 Definitions
General: For the purposes of this work section the definitions given below apply.
> FBS-1 Glass Wool: Spun fibres of molten glass, utilizing up to 80% recycled waste glass, thermally
bonded to form batts, blankets and sheets for thermal and acoustic insulation.
> FBS-1 Rock Wool: Spun fibres of molten rock thermally bonded to form batts and blankets for thermal
and acoustic insulation.
> Polyester insulation: 100% imported polyester fibres thermally bonded to form batts and blankets.
9.6 Submissions
9.6.1 Fire Hazard Properties
General: Submit evidence of conformance with the following:
> Fire hazard indices for all materials when tested in conformance with AS/NZS 1530.3, including, if the
material has a reflective facing, scoring and blackening to AS/NZS 1530.3 clause A6:
– Spread of flame index: 0.
– Smoke developed index: 3.
> Facing materials when tested in conformance with AS 1530.2: Flammability index: ≤ 5.
9.7 Samples
9.7.1 General
General: Submit samples of the following:
> Each type of insulation, including at least one transverse joint, bend and one hanger on a ≥ 1.5 m long
section of pipe. If the piping system to be insulated using the respective type of insulation includes
flanges, provide an insulated flange in the sample.
Cutaway sections: For each sample, provide cutaway sections to permit inspection of application details
including insulation materials, adhesives, mastics, fixings and sheathing.
9.10 General
9.10.1 Insulation
General: Provide piping insulation in conformance with the Minimum piping insulation thickness table.
Condensate drains from air handling plant: If included in the Piping insulation schedule provide 25 mm
thick insulation.
9.11 Materials
9.11.1 General
Prohibited materials: Do not provide materials:
> Containing asbestos, lead, mercury or mercury compounds.
> Containing substances listed as hazardous in the NOHSC Hazardous Substances Information System.
> Which use CFC or HCFC as blowing agents in the manufacturing process.
Materials in contact with stainless steel: To have properties including leachable chloride content that does
not cause corrosion or other deterioration of the stainless steel.
9.12 Execution
9.13 General
General: Do not apply insulation to piping joints until piping pressure testing is complete.
Preparation: Before installing insulation, remove weld slag, rust, grease and other foreign matter from the
surface of the pipe and ensure it is clean and dry. For black steel pipe, apply one of coat water-borne primer
for steel to AS/NZS 3750.19.
Supports: Do not apply insulation at supports until the spacers, vapour barrier (if any) and metal sheathing (if
any) has been installed.
Joints: Install insulation with the least number of joints practicable.
Use of multiple layers: If insulation is applied in more than one layer, stagger longitudinal and end joints.
Glass wool or rock Hot or selected Glass wool or rock Aluminium foil None required
wool sections of cold wool laminate
Polyester fibre Hot piping up to Polyester fibre Aluminium foil None required
100°C laminate
Polyolefin foam Hot piping up to Polyolefin foam Aluminium foil None required
100°C laminate
10.4 General
10.4.1 Standards
General: To Part 2 of AS/NZS 3000 unless otherwise documented.
Electrical systems: To AS/NZS 3008.1.1 and SAA HB 301.
Degrees of protection (IP code): To AS/NZS 60529.
EMC: To AS/NZS 61000.
Telecommunications systems: To AS/ACIF S008, AS/ACIF S009, AS/NZS 3080, SAA HB 243 and SAA HB 29.
10.5 Products
10.5.1 Wiring Systems
Selection: Provide wiring systems appropriate to the installation conditions and the function of the load.
10.6 Execution
10.6.1 Power Cables
Straight-through joints: Unless unavoidable due to length or difficult installation conditions, run cables
without intermediate straight-through joints.
Individual wiring of extra-low voltage circuits: Tie together at regular intervals.
Tagging: Identify multicore cables and trefoil groups at each end with stamped non-ferrous tags clipped
around each cable or trefoil group.
Marking: Identify the origin of all wiring by means of legible indelible marking.
Cable systems: Provide the following:
> Accessible concealed spaces: Thermoplastic insulated and sheathed cables.
> Inaccessible concealed spaces: Cable in UPVC conduit.
> Plant rooms: Cable in heavy duty UPVC conduit, or on tray or in duct.
> Plastered or rendered surfaces: Cable in UPVC conduit.
> Stud walls without bulk insulation: Thermoplastic insulated and sheathed cables.
> Walls filled with bulk thermal insulation: Cables in PVC conduit.
10.7.2 Standards
Cable trunking systems: To AS/NZS 4296.
Conduits and fittings for electrical installations: AS/NZS 2053 Parts 1, 2, 3, 4, 5, 6, 7 and 8.
Stainless steel cable ties shall be provided to all fire rated cabling, including radox type.
10.7.3 Products
10.7.6 Execution
10.8 Switchboards
10.9 General
10.9.1 Standards
Standards: To AS/NZS 3439.3.
10.10 Products
10.10.1 General
Busbars: Incorporate proprietary busbar systems for the interconnection of isolators, circuit breakers and
other circuit protection devices.
Doors: Provide lockable doors with a circuit card holder unless enclosed in cupboards or in an area which is
not readily accessible to the public.
IP rating:
> Weatherproof: IP56 minimum.
> Variable speed drives: IP54.
> Otherwise: IP42 minimum.
10.12 Products
10.12.1 General
Rated duty: Uninterrupted in non-ventilated enclosure.
Rated making capacity (peak): 2.1 x fault level (RMS) at assembly incoming terminals.
Utilisation category: To AS 60947.1 clause 4.4.
Circuits consisting of motors or other highly inductive loads: At least AC-23.
Coordination: Select and adjust protective devices to discriminate under over-current and earth faults.
10.12.5 Contactors
Standard: To AS 60947.4.1.
Type: Enclosed, block type, air break, electro-magnetic.
Poles: 3.
Rated operational current: The greater of:
> Full load current of the load controlled.
> ≥ 16 A.
Auxiliary contacts: Provide auxiliary contacts with at least one normally-open and one normally-closed
separate contacts with rating of 6 A at 230 V a.c., utilisation category: AC-1.
10.13 Execution
10.13.1 Marking and Labelling
General: Provide labels including control and circuit equipment ratings, functional units, notices for
operational and maintenance personnel, incoming and outgoing circuit rating, sizes and origin of supply and
kW ratings of motor starters. Traffolyte Labels must be used for all labelling.
11.2 Aims
11.2.1 Responsibilities
General:
> Provide electric motors and starters as follows and as documented.
> Variable speed drive to all fans, in-ceiling fan coil units and air handling units.
Selections: As documented.
11.3.3 Abbreviations
LED: Light emitting diode.
VSD: Variable speed drive.
11.4 Submissions
11.4.1 General
Calculations: Submit calculations supporting motor selection in relation to load characteristics.
Technical data: Submit manufacturers technical data for all motors, starters and protection equipment.
Variable speed drives: Submit reports of type tests for variable speed drives.
11.4.2 Calculations
Submit calculated input power factor and harmonic content for variable speed drives.
11.6 Motors
11.6.1 General
General: Provide motors selected in conformance with AS 1359.101, the application load characteristics,
motor manufacturers’ recommendations and the following:
> Motors 0.75 kW: Three phase.
11.6.2 Rating
Standard: To AS 1359.101.
Maximum power rating: The greater of the documented minimum motor size and next preferred standard
frame size above the maximum load of the driven equipment.
Duty: ≥ S1.
Class: 'continuous running’.
Speed: ≤ 1500 r/min.
11.6.4 Efficiency
Motors documented as high efficiency: To AS/NZS 1359.5 Table A3 or Table B3.
All other motors: To AS/NZS 1359.5 Section 2.
11.6.5 Environment
Site operating conditions: To AS 1359.101 Section 5.
Electrical operating conditions: To AS 1359.101 Section 6.
11.6.6 Enclosure
General: Provide enclosures appropriate to the environment in which the motor operates.
Motor enclosure classification: ≥ IP44 to AS 60529.
11.6.7 Cooling
Standard: To AS 1359.106.
Classification: ≥ IC01.
11.6.8 Marking
Terminals: To IEC 60034-8.
11.6.10 Noise
Standard: To AS 1359.109.
11.6.11 Vibration
Standard: To AS 1359.114.
Grade: ≥ N (normal).
11.8 Starters
11.8.1 Standard
General: To AS 60947.1.
Electromechanical motor starters: To AS 60947.4.1.
Semiconductor motor starters: To AS 60947.4.2.
11.8.2 Selection
General: Provide motor starters selected according to the following:
> Electricity distribution network limitations for starting currents and voltage flicker.
> Torque requirements for the motor load.
> Heating effects on the motor.
> Voltage drop during start due to starting currents.
> Time required to accelerate from rest to full speed.
> Number of starts per hour.
11.10.2 Type
General: Microprocessor controlled, solid-state electronic type, providing motor speed control of 3 phase
squirrel cage induction motors by means of stepless variable frequency, variable voltage pulse width
modulated (PWM)output.
Application: Suitable for the documented applications.
11.10.3 Selection
General: Provide variable speed motor drive controllers selected for the following:
> Rating: Continuously rated to suit the full load current stated on the motor nameplate and the length
and type of cable feeding the motor.
> Service conditions: To AS 61800.2 Section 4.
> Speed ranges: Suitable for the load duties.
> Control deviation band: To suit the controls functional specification.
Design: Provide the following:
> Soft start (initially start motors on low speed).
> Adjustable maximum current limit.
> Automatic reset/restart of system after removal of fault or power failure condition. If the number of
reset/restart attempts is limited for safety and equipment protection, provide for safe shut down and
manual restart in the event of an unsuccessful attempt at the reset/restart sequence.
> Ability to immediately restart a motor following momentary interruption of supply, even if the motor is
rotating, or rotating in the reverse direction.
Protection: Provide protection against:
> Instantaneous power failure.
> Instantaneous over current.
> Internal and external overload.
> Under and over voltage.
> Over temperature of the controller.
> Earth fault.
> Contact with live parts without the removal of fixed covers or panels.
Motor protection:
11.10.4 Controls
Provide facilities for local display and control, including the following:
> Indication of run condition, motor speed or output frequency, input control parameters, output current
and voltage, and alarm conditions.
> Indication of power on, zero speed, enable, earth fault, short circuit, over current, under voltage, over
temperature and remote trip.
> Facilities for automatic/off/manual control.
> Local and remote analogue input, to control frequency output of controller when in manual or
automatic mode.
> For BMS remote control, interfaces for analogue input and output associated with speed control,
start/stop, and voltage free contacts for alarm fault indication.
> BACnet HLI to all VSDs providing the full range of available parameters, including energy, Fault, Volts,
Amps, Hertz, etc (basic factory HLI with minimum points not acceptable)
11.10.6 Installation
Switchboard mounting: Install each controller, together with associated equipment, in separate ventilated
subsections of AS 1359.107.
The motor control switchboard with hinged door, meeting the level of separation, ventilation and screening
for the overall enclosure.
Wall mounting: Install in an IP54 rated enclosure.
11.10.7 Testing
Routine tests: Standard separate device and power drive system tests to AS 61800.2 and AS 61800.3.
Site tests: Test input power factor and harmonic content on completed installation.
Preferred Brands are ABB and Danfoss, alternatives will be considered.
12.1.2 Responsibilities
General: Provide automatic control systems to perform the documented control functions.
Performance: Within the documented limitations of the plant capacities, maintain the documented
conditions. Supply and commission control systems that are safe and stable in operation under all
anticipated operating conditions including start up, shut down and fault condition.
Service interruption: Except for documented manual restoration of operation, provide fully automatic
restoration of control system operation after any service interruption of any duration.
Safety: Provide control devices and software to protect personnel from injury and equipment from damage
by either normal or abnormal operation of the control system, including the removal and reapplication of
power whether expected or unexpected.
Compatibility with existing controls: If the documented control systems interface or connect to existing
control systems, provide new control components and software that are either identical to the existing or, if
not identical, compatible. If not identical, provide evidence that the proposed components are compatible.
Operating environment: Provide components that function correctly in their local environment.
Selections: As documented.
12.1.5 General
General: Conform to the General requirements work section.
12.2 Standards
12.2.1 General
Building automation system protocol: BACnet® to ANSI/ASHRAE 135, including Annex J. (Referred to in this
work section as BACnet.)
12.3 Interpretations
12.3.1 Abbreviations
General: For the purposes of this work section the abbreviations given below apply.
AAC: Advanced application controller.
ASC: Application specific controller.
BACnet: (Building automation control network) Data communication services and protocols conforming to
ANSI/ASHRAE 135 BACnet.
BC: Building controller.
BMS: Building management system.
FFCP: Fire fan control panel.
FIP: Fire indicator panel.
LAN: Local area network.
LED: Light emitting diode.
OWS: Operator workstation.
PID: Proportional plus integral plus derivative.
RTD: Resistance temperature device.
SA: Smart actuator.
UPS: Uninterruptible power supply.
12.4 Submissions
12.4.1 Software
General: Submit proposed project specific software and documentation in hard copy form. Include:
Fully developed functional descriptions, written in simple sentences, of each system including but not limited
to start up, normal running, shut down, fire mode operation, operation in fault conditions, alarms, safety
controls and manual over-ride provisions.
Logic flow charts.
Provisional values and nomographs for set points and other control parameters.
Control schematics or diagrams illustrating control logic, valve and damper sequences, external interlocks,
and interfaces.
Input, output and software points schedules including corresponding point addresses, short form and full
text labels.
Details of communication standards and protocols.
Details of connections to external interfaces and components outside the automatic control system.
Format of proposed graphics.
When requested, provide manuals, data sheets and other explanatory information needed to interpret the
material submitted.
Test reports: Submit a report showing the test results. Carry out necessary modifications and re-test.
12.4.3 Drawings
Required: Submit the following:
12.4.5 Samples
Submit samples of the following:
Each control component to be mounted within occupied areas.
12.5.1 General
12.6 Software
12.6.1 General
Inclusions: As part of the automatic control installation provide:
Software to perform the required project specific functions.
Facilities to alter time schedules, set points and manually override control functions.
Diagnostic routines within the controller to continuously monitor for faults and to raise alarms.
Time scheduling including provision for weekends, holidays and automatic adjustment to daylight saving
times.
Control algorithms for standard control functions to meet the functional specification including PID loops
and calculate psychrometric properties.
All calculations and data in SI metric units.
Multi-level passwords to limit access to controller functions.
12.7.2 Interface
General: Provide interface to Building Controllers (BC), Advanced Application Controllers (AAC), Application
Specific Controllers (ASC), and Smart Actuators (SA) to achieve the documented performance and
functionality.
Stand-Alone Operation: Provide controllers that perform their control and their energy management
functions as stand-alone units including trends, schedules and alarm functions. Include required
communication hardware in each panel. Provide control for each piece of equipment from only one
12.7.3 Backup
General: Provide automatic backup to the BMS of all data held locally on the controller. Automatically
download backed up data after restoration of power after power failure.
12.7.4 BACnet
General: Provide the following BACnet interface functionality on the controllers:
Building Controllers (BCs): Provide BCs that have demonstrated interoperability during at least one BMA
Interoperability Workshop and that conform to BACnet Building Controller (B-BC) device profile as specified
in ASHRAE/ANSI 135, BACnet Annex L.
Advanced Application Controllers (AAC): Provide AACs that conform to BACnet Advanced Application
Controller. (B-AAC): device profile as specified in ASHRAE/ANSI 135, BACnet Annex L and that are listed as a
certified B-AAC in the BACnet Testing Laboratories (BTL) Product Listing.
Application Specific Controllers (ASCs): Provide ASC that conform to BACnet Application Specific Controller
(B-ASC) device profile as specified in ASHRAE/ANSI 135, BACnet Annex L and that are listed as a certified B-
ASC in the BACnet Testing Laboratories (BTL) Product Listing.
Smart Actuators (SAs): Provide SAs that conform to BACnet Smart Actuator (B-SA) device profile as specified
in ASHRAE/ANSI 135, BACnet Annex L and that are listed as a certified B-SA in the BACnet Testing
Laboratories (BTL) Product Listing.
Connections between BACnet networks and IP internetwork: Via BACnet/IP Broadcast Management Device
(BBMD) capability.
Objects: Each object must be BACnet object if the BACnet specification provides for the object.
12.7.5 Communication.
General: Provide controllers with the following communications functionality:
Each BC to reside on or be connected to a BACnet network using ISO/IEC 8802-3 (Ethernet) Data
Link/Physical layer protocol and BACnet/IP addressing.
BACnet routing to be performed by BCs or other BACnet device routers as necessary to connect BCs to
networks of AACs and ASCs.
Service Port: Provide each controller with a service communication port for connection to a Portable
Operator's Terminal.
Signal Management: Use BC and ASC operating systems to manage input and output communication signals
to allow distributed controllers to share real and virtual object information and to allow for central
monitoring and alarms.
Data Sharing: Arrange each BC and AAC to share data as required with each networked BC and AAC.
Add clauses for any project specific functionality which will be carried out by the BMS server rather than by
stand-alone controllers, eg Energy Management, Maintenance Systems, Alarm processing etc.
12.13.2 Electrical
Current transformers, wattmeters and watt-hour meters: Conform to the Switchboard components work
section.
12.14 Actuators
12.14.1 General
General: Provide actuators designed for the type of location and application in which they are installed and
the required control function.
Type: Electronic, incorporating a disengagement mechanism that permits manual operation in the event of
power failure without disconnecting the actuator. Provide a position indicator on the actuator.
Position feedback: If a position signal is required, provide a potentiometer on the actuator.
Mounting: Provide actuators and mounting selected to provide sufficient torque to allow changes of position
with the fans or pumps operating.
Protection: Minimum IP54 enclosure. If the actuator is located outdoors provide additional weather
protection.
Overload and stall: Protect actuators against overload. Provide electronic or magnetic clutch type stall
protection effective throughout the entire actuator stroke. Do not rely on end switches that require field
adjustment.
Fail safe operation: If fail-safe operation is required, provide integral spring return via clutch only.
Noise: Provide actuators that are inaudible in occupied areas.
12.16 Chilled and Heating Hot Water Fan Coil Units and Air Handling
Units
Start/Stop Control
Start/stop control of fan coil units and air handling units on an individual basis by the Mechanical Control
System time schedule, operator override, after hours control or switchboard auto/off/on switch. Each FCU
and AHU is to be enabled via either the floor occupancy time schedule, after hours request, or optimum start
systems. When any FCU or AHU stops, its associated heating water valve, chilled water valve and outside air
dampers are to be driven closed.
In normal occupancy hours, each FCU and AHU is to be assigned a time schedule. At the scheduled time, the
air conditioning enables points for the respective FCU/AHU, return and supply air shut off dampers, return air
dampers and central plant are to be energized to start.
The associated outdoor air fan shall be interlocked to the fan coil unit operation. The fan shall energise upon
receipt of signal from any one (1) fan coil unit.
Ventilation systems in critical patient care areas such as operating rooms and recovery will operate on
emergency power.
12.28 Metering
All electrical, hydraulic and supplementary mechanical services meters are to incorporate a HLI connection to
the BMS user graphic interface.
Sub metering shall incorporate:
> Location and identifier (meter number)
> Sub-meter reading shall have time and date and corresponding meter and meter reading.
> Minimum monthly reading of energy consumption (electricity/gas)
> Provide a single line diagram to show the associated equipment for the sub meter
Mechanical Services:
Air Handling Units, consider the following points:
> Stop / start of Supply air Fan
> Stop Start of the return Air Fan
> Supply air temperature
> Return Air Temperature
> Return air Humidity
> Cooling Valve Control
> Off Cooling Coil Temperature
> Heating Valve Control
> Off heating Coil temperature
> Economy Damper control
> Run Status of the supply and return air Fan (Air Flow Switch)
> Run Status of the supply and return Variable Speed Drive
> Run Speed of the supply and return Variable Speed Drive
> General Fault status of the Variable Speed drive
> Static supply air duct pressure, every supply zone
> Static Differential pressure across the filters (dirty Filter alarm)
Various HVAC Pumps including, Chilled water, Condenser water, Tenant Condenser water.
> Start / stop
> Run status (at the pump via diff pressure switch)
> Run Status at the Variable Speed Drive
> Run Speed of the variable speed drive
> General Fault status of the Variable Speed drive
Air Handling Units/Fan Coil Units serving rooms with specific pressure requirements
> Supply fan shall be modulated via VSD to maintain constant airflow rate
> Pressure sensor alarms shall be actuated when filters and HEPA terminal unit pressures exceed
manufacturers requirements or specified room pressures.
Supply and Installation of one fluid energy meter specifically for the Tenant Condenser water with
BACnet High-level Interface. The Fluid Meter must be factory Calibrated (no Calculation in the BMS)
providing an Integer via the HLI. Meter must be Level 1 or similar for Billing Purposes, and NABERS
Assessments. Flow and return temperature sensors to be pipe installed (i.e no Surface mount sensors)
and factory calibrated to the meter and the High Level Interface.
Note: If these monitor points can be measured via HLI within the generator System, this is acceptable
and preferred.
12.35 Execution
12.35.1 General
Marking: Mark each control component.
12.35.16 General
Location: Install controllers within dedicated switchboard enclosures.
Points lists: Provide plasticised fade-free points lists in enclosure door pocket. Include in the list terminal
numbers, point addresses and short and long descriptions.
12.35.18 General
General: Conform to Mechanical piping.
Installation: Install valves with stems vertical.
Mounting: Mount the valves with the actuator above the valve and thermally isolated from the valve body.
12.35.20 General
Standards: Conform to: BCA, AS/NZS 1668.1.
Connections: Provide numbered terminals for connection to the FIP and FFCP.
12.35.22 General
General: Conform to Mechanical commissioning.
12.35.24 Demonstration
General: Demonstrate by software simulation using simulated inputs and outputs that the project specific
software achieves the required functions, operation and safety sequences and accurately computes the
related values. Demonstrate each control loop including all calculations and global functions.
12.35.25 Commissioning
General: Conform to Mechanical commissioning. Commission all parts of the system in detail to verify that the
equipment and systems operate correctly and achieve the required control functions.
Program: Before commissioning starts submit a program description of the proposed work to commission
and test the systems including a time schedule.
Supplier's representative: Use a representative of the controls supplier to coordinate testing, to be present
during all tests and training, and to attend site until the control systems are fully commissioned and
operational.
Minimum requirement: Carry out the following:
Point tests and wiring verification: Test all field wiring from terminals to field interface terminal strips and
attend the testing of all equipment that interfaces to the controllers to confirm the operation of such
equipment from the controller interface terminals.
Component function: Test each component for correct function and operation. Check the operation of
controlled devices to ensure that they operate in the required direction and through the correct range of
physical movement relative to the applied control signal.
Local control loop tests: Test and verify calibration of all controller inputs and outputs, actuators and sensors
for proper response by actual operation of the devices.
12.35.26 Training
12.35.27 General
Operator training: In addition to training documented elsewhere, provide on-site operator training during
the defects liability period.
Number and duration of training sessions: Provide training sessions of at least 4 hours at 3 month intervals (a
total of 4 sessions).
13.1.1.1 Responsibilities
General: Provide commissioning of all mechanical systems.
Selections: As documented.
13.3 Standards
13.3.1 General
Measurement of fan and duct air quantities > 1000 L/s: To ISO 5802.
Testing, balancing and commissioning except fan and duct air quantity measurement: To ASHRAE Standard
111 or CIBSE Commissioning Codes A, B, C, R and W.
Statistical analysis: To ASHRAE Guideline 2 (RA 96) – Engineering Analysis of Experimental Data.
Fire operation of air handling systems: To AS/NZS 1668.1.
Orifice plates and venturi meters: To BS 1042.
Microbial control: To AS/NZS 3666.1.
AS/NZS 3666.1 applies to all air and water systems in buildings. See Clause 4.7 in particular.
Pressure equipment: To AS/NZS 3788.
13.3.2 Interpretations
13.3.3 Definitions
General: For the purposes of this work section the definitions given below apply.
> Accuracy: The closeness of the agreement between the result of a measurement and the true value of
the particular quantity being measured.
13.3.5 General
Submissions: Provide a program consistent with, and forming part of, the construction program. Set out the
proposed program for completion, commissioning, testing and instruction. Identify related works and timing
of the works pre-requisite to successful and timely completion of the works.
Fire safety: Complete testing and certification of all fire safety measures before occupation of the building.
Revisions: Revise the program as the project proceeds.
Running in period: Include time in the program for the running period prior to the date for practical
completion.
13.3.7 Retesting
Failure to meet documented performance: Identify and correct the cause of failure and repeat the test.
14.1.2 Reports
General: Submit reports indicating observations and results of tests and compliance or non-compliance with
requirements.
14.1.3 Notice
General: Give sufficient notice for inspection to be made of the commissioning of the installation.
14.1.4 Starting Up
General: Coordinate schedules for starting up of various systems and equipment. Give 5 working days notice
before starting up each item.
Checks: Before starting, verify that each piece of equipment has been checked for proper lubrication, drive
rotation, belt tension, control sequence, circuit protection or for other conditions which may cause damage.
Tests: Verify that tests, meter readings, and documented electrical characteristics agree with those required
by the manufacturer.
Wiring: Verify wiring and support components for equipment are complete and tested.
Manufacturers' representatives: If individual technical work sections require the attendance of a
manufacturer’s representative, have the manufacturers' representatives present on site to inspect and check
and/or system installation before starting up, and to supervise placing equipment and operation.
Starting up: Execute starting up under supervision of manufacturers' representative (if nominated in the
respective technical work section) and appropriate contractors' personnel, in accordance with manufacturers'
instructions.
Report: Submit a report demonstrating that equipment has been properly installed and is functioning
correctly.
14.2 Instrumentation
14.2.1 Calibration and Certification
General: Use only instruments that have been calibrated by a Registered testing authority. Provide copies of
certification if requested.
Maximum period since last calibration: As recommended by manufacturer but 12 months, except as noted
below.
14.2.6 Temperature
Air temperature instruments specifications:
> Accuracy: ± 0.2 K or better at measured value.
Chilled water and condenser water temperature instrument specification:
> Accuracy: ± 0.2 K or better at measured value.
Instrument specifications for other temperature applications:
> Accuracy: ± 0.5 K or better at measured value.
> Scale divisions (mercury-in-glass): 1.0 K or better.
14.2.7 Humidity
Instruments specifications: Sling psychrometer, aspirated psychrometer or electronic humidity meter.
> Accuracy:
– ± 3% from 10 to 90% relative humidity where measured value tolerance is ± 5% relative humidity.
14.2.9 Electrical
Instrument specifications:
> Voltage < 600 V ac: Accuracy ± 3% of full scale.
> Voltage < 30 V dc: Accuracy ± 3% of full scale.
> Currents < 100 A: Accuracy ± 3% of full scale.
> Maximum period between calibration: As recommended by manufacturer but not more than 6 months.
System type Terminal air quantity Branch air quantity Total air quantity
tolerance tolerance tolerance
14.4.4 Diversity
General: For variable air volume (VAV) and other systems where the sum of the design terminal air quantities
is greater than the design fan air quantity, adjust the system as follows:
> The flow rate at the terminals is within tolerance for all possible load situations.
> The fan flow is within the tolerance limits for total air quantity in the Air quantity tolerance table.
14.5.2.1 General
General: Include the following on the air balance reports:
14.9.3 Motors
Motor-driven equipment performance tests: Test for performance. Adjust thermal overloads for actual
current and record measured current and overload settings.
14.10 Certification
14.10.1 General
Contract documents: Provide certification that the installation complies in all respects with the contract
documents.
Statutory requirements: Provide certification of compliance with the relevant statutory requirements.
UTILITY
CORRIDOR + ROOF EC Fan with
AHU-1.5 890 130 15.6 13.2 5 12 0.553 6 80 60 0.127 26.2 17.9 350 450 F4 3 / 400 / 50
INSTRUMENT MOUNTED Economy Cycle
WASHING
15.3 Fans
All fan static pressure listed are estimated and for information only. Contractor to perform pressure static calculations based on equipment selection and workshop drawings.
Sound
Fan Motor Pressure
No. off Air Flow Ext. Static
Reference Serving Type Level @ 3m Notes
(L/s) (Pa)
Rating Motor
Phases dB
(kW) Drive
OAF-1.1 OUTSIDE AIR FAN INLINE MIXED FLOW 1 330 200 3 0.37 VSD 64 Fantech or approved equal
OAF-1.2 OUTSIDE AIR FAN INLINE MIXED FLOW 1 930 200 3 0.61 VSD 61 Fantech or approved equal
OAF-1.3 OUTSIDE AIR FAN INLINE MIXED FLOW 1 3210 250 3 2.42 VSD 76 Fantech or approved equal
OAF-1.4 OUTSIDE AIR FAN INLINE MIXED FLOW 1 1450 200 3 0.83 VSD 67 Fantech or approved equal
Plant Ref.
MSSB # Description Ø MCA (A) Drive
ID
adpconsulting.com.au