0 Introduction
Meeting held on 8th Oct to clarify following subjects:
1. Basement 1 - monthly tank,
2. Basement 1 – separator elevator missing beams,
3. Basement 1 - chiller room,
4. Basement 1 - elevator secondary beams requirement
from KONE
5. Ground Floor clash issues.
1 Escalator Beam
1. Escalator B2 to B1, shift beam B1B42 to support the AECOM 10 Oct 2019
Escalator approved by TTW.
2. Escalator B1-GF, BAM already submitted SD with B1B44
bend to accommodate height of escalator.
3. The ceiling below escalator will modificated ceiling
Bulkhead.
2 Travelator Beam
1. Cantilever beam which support Traveletor is adjust lower TTW – AECOM 10 Oct 2019
and approve by TTW.
2. GFB26 & GFB27 will review by TTW, GFB4 dimension rebar
beam will maintain and shifted 1.2 meter following the
location beam on B1 and L1. TTW will provide beam on
Thursday Oct 10th 2019.
3. Architect : Ceiling SD will follows.
4. MEP : Conduit position for travelator power approved by
TTW.
3 Monthly Tank
Keep the structure as it is until AECOM give instruction for BAM Cwk 34
further. BAM already submitted SD following the structure IFC.
Advance info from APD, genset will relocate to inside building.
Page 1
BMS-STC-T-001 of 2
Version {_UIVersionString} uncontrolled when printed
Template
Next meeting:
When required
Page 2
BMS-STC-T-001 of 2
Version {_UIVersionString} uncontrolled when printed