ID Task Task Name Start Finish Text1 tober 2019 November 2019 December 2019

Mode 4 7 10 13 16 19 22 25 28 31 3 6 9 12 15 18 21 24 27 30 3 6 9 12 15 18 21
1 PEA Las Bambas Fri 11/10/19 Sun 15/12/19 66 días
2 E1: Realidad Cap 1 ‐ 4 Fri 11/10/19 Sun 27/10/19 17 días
3 E2: Aterrizaje Cap 5 y 6 Mon 28/10/19 Fri 15/11/19 19 días
4 E3: Implementación Cap 7 ‐ 9 Sat 16/11/19 Sun 15/12/19 30 días

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Programa de Trabajo P
Summary Manual Summary Rollup Progress
Date: Fri 11/10/19
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 1
January 2020 February 2020 March 2020 April 2020 May 2020 J
21 24 27 30 2 5 8 11 14 17 20 23 26 29 1 4 7 10 13 16 19 22 25 28 2 5 8 11 14 17 20 23 26 29 1 4 7 10 13 16 19 22 25 28 1 4 7 10 13 16 19 22 25 28 3

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Programa de Trabajo P
Summary Manual Summary Rollup Progress
Date: Fri 11/10/19
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 2