Engineering Procedure

SAEP-352 1 January 2018


Welding Procedures Review and Approval
Document Responsibility: Welding Standards Committee

Contents
1 Scope ................................................................ 2
2 Conflicts and Deviations ................................... 2
3 Applicable Documents ...................................... 2
4 Definitions and Acronyms ................................. 6
5 Instructions and Approval Responsibility .......... 8
Revision Summary................................................... 9

Appendix I – Welding Master Set


Preparation and Approval ............................... 13
Appendix II – Welding Package Review and
Approval Process for Company Projects ........ 14
Appendix III – Welding Package Review and
Approval Process for
Repair/Maintenance/Alterations ...................... 15

Previous Issue: 24 September 2014 Next Planned Update: 24 September 2019


Revised paragraphs are indicated in the right margin Page 1 of 15
Contact: Al-Ghamdi, Tariq Abdulwahed (ghamta0e) on phone +966-13-8809561

©Saudi Aramco 2018. All rights reserved.


Document Responsibility: Welding Standards Committee SAEP-352
Issue Date: 1 January 2018
Next Planned Update: 24 September 2019 Welding Procedures Review and Approval

1 Scope

1.1 This procedure specifies the responsibilities for welding procedure review and
approval. This procedure applies to pressure vessels, process equipment or
components, piping, pipelines, and structures fabricated to a variety of
standards, such as but not limited to ASME SEC I, IV, VIII, B31.1, B31.3,
B31.4, B31.8 and API STD 510, 570, 560, 620, 650, 653 and 1104, AWS D1.1
and D1.8.

1.2 Additional requirements may be contained in Scopes of Work, Drawings, or


other Instructions or Specifications pertaining to specific items of work.

2 Conflicts and Deviations

Any conflicts between this document and other applicable Mandatory Saudi Aramco
Engineering Requirements (MSAERs) shall be addressed to the EK&RD Coordinator.

Any deviation from the requirements herein shall follow internal company procedure
SAEP-302.

3 Applicable Documents

Unless stated otherwise, all standards, specifications, and codes referenced in this
procedure shall be of the latest issue (including revisions, addenda, and supplements)
and are considered a part of this procedure.

3.1 Saudi Aramco References

Saudi Aramco Engineering Procedures


SAEP-302 Waiver of a Mandatory Saudi Aramco Engineering
Requirement
SAEP-310 Piping and Pipeline Repair

Saudi Aramco Engineering Standards


SAES-D-008 Repairs, Alterations, and Rerating of Pressured
Equipment
SAES-D-108 Storage Tank Integrity
SAES-D-116 Underground Storage Tank System
SAES-K-001 Heating, Ventilating and Air Conditioning (HVAC)
SAES-L-350 Construction Requirements for Metallic Plant Piping

Saudi Aramco: Company General Use


Page 2 of 15
Document Responsibility: Welding Standards Committee SAEP-352
Issue Date: 1 January 2018
Next Planned Update: 24 September 2019 Welding Procedures Review and Approval

SAES-L-450 Construction Requirements for Cross-Country


Pipelines
SAES-L-460 Pipelines Crossing Under Roads and Railroads
SAES-L-850 Design of Submarine Pipelines and Risers
SAES-M-001 Structural Design Criteria for Non-building
Structures
SAES-M-005 Design and Construction of Fixed Offshore Platforms
SAES-M-009 Design Criteria for Blast Resistant Buildings
SAES-T-744 Design Criteria/Installation of Communication
Towers
SAES-W-010 Welding Requirements for Pressure Vessels
SAES-W-011 Welding Requirements for On-Plot Piping
SAES-W-012 Welding Requirements for Pipelines
SAES-W-013 Welding Requirements for Offshore Structures
SAES-W-014 Weld Overlays and Welding of Clad Materials
SAES-W-015 Strip Lining Application
SAES-W-016 Welding of Special Corrosion-Resistant Materials
SAES-W-017 Welding Requirements for API Tanks
SAES-W-019 Girth Welding Requirements for Clad Pipes

Saudi Aramco Materials System Specifications


01-SAMSS-010 Fabricated Carbon Steel Piping
01-SAMSS-017 Auxiliary Piping for Mechanical Equipment
01-SAMSS-035 API Line Pipe
01-SAMSS-038 Small Direct Charge Purchases of Pipe
01-SAMSS-043 Carbon Steel Pipes for On-Plot Piping
01-SAMSS-046 Stainless Steel Pipe
01-SAMSS-333 High Frequency Welded Line Pipe
02-SAMSS-005 Butt Welding Pipe Fittings
02-SAMSS-006 Hot Tap and Stopple Fittings
02-SAMSS-008 Insulating Joints/Spools for Cathodic Protection
02-SAMSS-009 Design and Fabrication of Scraper Traps

Saudi Aramco: Company General Use


Page 3 of 15
Document Responsibility: Welding Standards Committee SAEP-352
Issue Date: 1 January 2018
Next Planned Update: 24 September 2019 Welding Procedures Review and Approval

02-SAMSS-010 Flanged Insulating Joints/Spools for Cathodic


Protection
02-SAMSS-011 Forged Steel Weld Neck Flanges for Low,
Intermediate and High Temperature Service
04-SAMSS-035 General Requirements for Valves
04-SAMSS-053 Steel Lubricated Plug Valves - Flanged and Welding
End
12-SAMSS-007 Fabrication of Structural and Miscellaneous Steel
12-SAMSS-014 Pre-Engineered Metal Building
27-SAMSS-001 Packaged Water Cooled Centrifugal Chillers for
Utility Services
27-SAMSS-002 Direct Expansion Air Conditioning Systems for
Offshore Facilities
27-SAMSS-003 Manufacture of Non-industrial Cooling Towers
30-SAMSS-001 Diesel Engines
31-SAMSS-001 Centrifugal Compressor
31-SAMSS-002 Packaged Reciprocating Plant and Instrument Air
Compressors
31-SAMSS-003 Reciprocating Compressors for Process Air or Gas
Service
31-SAMSS-004 Centrifugal Pumps
31-SAMSS-005 Centrifugal Fluorocarbon Refrigeration Units for
Industrial/Process Services
31-SAMSS-006 Packaged, Integrally Geared Centrifugal Air
Compressors
31-SAMSS-009 Positive Displacement Pumps - Controlled Volume
31-SAMSS-010 Submersible Pumps and Motors for Water Well and
Offshore Service
31-SAMSS-012 Shaft Sealing Systems for Centrifugal and Rotary
Pumps
32-SAMSS-001 Special Purpose Steam Turbines for Generator Sets
32-SAMSS-004 Manufacture of Pressure Vessels
32-SAMSS-005 Manufacture of Atmospheric Tanks
32-SAMSS-006 Manufacture of Low Pressure Tanks
Saudi Aramco: Company General Use
Page 4 of 15
Document Responsibility: Welding Standards Committee SAEP-352
Issue Date: 1 January 2018
Next Planned Update: 24 September 2019 Welding Procedures Review and Approval

32-SAMSS-007 Manufacture of Shell and Tube Heat Exchangers


32-SAMSS-008 Inlet Air Filtration Systems for Combustion Gas
Turbines
32-SAMSS-009 General Purpose Steam Turbines
32-SAMSS-010 Special Purpose Steam Turbines
32-SAMSS-011 Manufacture of Air-cooled Heat Exchangers
32-SAMSS-013 Lubrication, Shaft Sealing, and Control Oil Systems
32-SAMSS-016 Inlet Air Filtration Systems for Centrifugal Air
Compressors
32-SAMSS-017 Side-Entry Mixers
32-SAMSS-019 Manufacture of Plate and Frame Heat Exchangers
32-SAMSS-020 Manufacture of Trays and Packing
32-SAMSS-021 Manufacture of Industrial Boilers
32-SAMSS-022 Manufacture of Components for Flare Systems
32-SAMSS-027 Manufacture of Electric Heat Exchangers
32-SAMSS-028 Manufacture of Double Pipe Heat Exchangers
32-SAMSS-029 Manufacture of Fire Heaters
32-SAMSS-030 Manufacture of Small Tanks
32-SAMSS-031 Manufacture of Clad Vessels and Exchangers
32-SAMSS-033 Reverse Osmosis Systems
32-SAMSS-035 Manufacture of Heat Recovery Steam Generator
32-SAMSS-036 Manufacture of Small Pressure Vessels
32-SAMSS-100 Combustion Gas Turbines
34-SAMSS-611 Safety Relief Valves Conventional and Balanced
Types
34-SAMSS-612 Safety Relief Valves Pilot Operated Types
34-SAMSS-711 Control Valves
45-SAMSS-005 Valves and Wellhead Equipment Requirements per
API SPEC 6A

3.2 Industry Codes and Standards

American Petroleum Institute

Saudi Aramco: Company General Use


Page 5 of 15
Document Responsibility: Welding Standards Committee SAEP-352
Issue Date: 1 January 2018
Next Planned Update: 24 September 2019 Welding Procedures Review and Approval

API STD 510 Pressure Vessel Inspection Code: In-service


Inspection, Rating, Repair, and Alteration
API STD 560 Fired Heaters for General Refinery Services
API STD 570 Piping Inspection Code: In-service Inspection,
Rating, Repair, and Alteration of Piping Systems
API STD 620 Design and Construction of Large, Welded,
Low-pressure Storage Tanks
API STD 650 Welded Steel Tanks for Oil Storage
API STD 653 Tank Inspection, Repair, Alteration, and
Reconstruction
API STD 1104 Welding of Pipelines and Related Facilities

American Society of Mechanical Engineers


ASME B31.1 Power Piping
ASME B31.3 Process Piping
ASME B31.4 Pipeline Transportation Systems for Liquid
Hydrocarbons and other Liquids
ASME B31.8 Gas Transmission and Distribution Piping Systems
ASME SEC I Rules for Construction of Power Boilers
ASME SEC IV Rules for Construction of Heating Boilers
ASME SEC VIII Rules for Construction of Pressure Vessels
ASME SEC IX Welding and Brazing Qualifications

American Welding Society


AWS D1.1 Structural Welding Code-Steel
AWS D1.8 Structural Welding Code - Seismic Supplement

International Standardization Organization


ISO 17025 General Requirements for the Competence of
Testing and Calibration Laboratories

4 Definitions and Acronyms

Application Approval: Approval acquired from Inspection Department to apply


technically approved welding procedure. ID generally verifies that the intended
application of previously approved welding procedures is within the welding
procedure's variables (e.g., diameter, thickness, materials, service, etc.) approval range.
Saudi Aramco: Company General Use
Page 6 of 15
Document Responsibility: Welding Standards Committee SAEP-352
Issue Date: 1 January 2018
Next Planned Update: 24 September 2019 Welding Procedures Review and Approval

CRM: Customer Relationship Management system

CSD: Consulting Services Department Welding Specialist/Engineer or CSD's Appointed


Representative (e.g., Aramco Services Company Welding Specialist/Engineer).

ESR: Engineering Service Request

ID: Inspection Department Vendor, Operations or Project Inspector or Inspection


Representative.

OCSD: Operations Consulting Services Division

PMC: A Program Management Contractor.

SAPMT: Saudi Aramco Project Management Team or someone acting on their behalf
such as PMC.

PCSD: Projects Consulting Services Division

PMT Designated Welding Representative (PMT DWR): A welding engineer /


inspector assigned to and contracted by SAPMT who has the approval authority for
project(s) associated welding procedures.

PQR: Procedure Qualification Record

Technical Approval: Approval of welding procedures acquired from CSD or PMT


Designated Welding Representative. This approval indicates that the welding
procedure was qualified to Saudi Aramco and/or industry standards or codes and it is
acceptable for the intended application. Every page of the welding procedure
specifications should include the reviewer signature and/or approval stamp.

Weld and Line Designation Table: A table that lists the applicable welding procedures,
approval conditions (e.g., low temperature, sour service, etc.), welding process, and any
general welding information pertinent to those applicable welding procedures.

Weld Map: A schematic one line diagram of pressure containing equipment


(e.g., pressure vessel or tank). The map should indicate where each approved welding
procedure will be applied.

Welding Master Set (WMS): It is compilation of welding procedures prepared by


vendor/fabricator. It is a standardized set of welding procedures that is used with a
generic Weld and Line Designation Table and/or generic Weld Map, which include the
material and service application information.

WP: Welding Package.

WPS: Welding Procedure Specifications.


Saudi Aramco: Company General Use
Page 7 of 15
Document Responsibility: Welding Standards Committee SAEP-352
Issue Date: 1 January 2018
Next Planned Update: 24 September 2019 Welding Procedures Review and Approval

5 Instructions and Approval Responsibility

5.1 CSD shall be the technical approval authority for the followings:
a) All Saudi Aramco Project welding procedures for applications listed in
Table 1 from either in-kingdom or out of kingdom fabricators and
construction contractors. Appendix II is a flowchart that indicates the
review process for Saudi Aramco projects.
b) “Welding Master Set” submissions for the applications listed in Table 1
from in-Kingdom and Gulf Cooperation Council fabricators.
See Appendix I for details on welding master set's preparation and
approval. Appendix II is a flowchart that indicates the review process for
Saudi Aramco projects.
c) The WMS for maintenance/repair/alteration applications in operations
shall be submitted to Operations Consulting Services Division (OCSD) in
CSD. Appendix III is a flow chart that indicates the review process.
d) All welding procedures and WMSs needing CSD approval shall be
submitted to PMT or Engineering/Maintenance Division, as appropriate, in
clear and legible scanned pdf format for onward transmittal to CSD
through the Engineering Service Request (ESR) using Customer
Relationship Management (CRM) system. Hard copy may be requested by
CSD for the large volume of documents.
e) WPS must be signed by contractor’s welding engineer before submission
to PMT or engineering/maintenance division for approval. In case of EPC
contract, WPS must be signed by fabricator’s welding engineer as well as
by EPC contractor’s welding engineer before submission to PMT.
f) All procedure qualification (PQR) mechanical tests and examinations shall
be performed by ISO 17025 certified test laboratory for OOK fabrication
and SA approved 3rd party test laboratory for IK fabrication and
construction. Updated list of SA approved 3rd party test laboratories will
be asked to Welding Standards Committee.
Note: For all PQR testing, the ISO 17025 document shall be submitted along with
welding submittal as a mandatory requirement prior review and approval.

5.2 A PMT designated welding representative assigned to and contracted by


SAPMT may be the approval authority for project(s) associated welding
procedures. He must review the welding procedures for all applications listed in
Table 1, and as requested by PMT

CSD will interview and approve the PMT designated welding representative.
Written examinations may be requested and prepared by CSD, this will depend
Saudi Aramco: Company General Use
Page 8 of 15
Document Responsibility: Welding Standards Committee SAEP-352
Issue Date: 1 January 2018
Next Planned Update: 24 September 2019 Welding Procedures Review and Approval

on the project scope. With coordination with SAPMT, CSD will periodically
audit some of his welding procedures review.

5.3 For applications not listed or not requiring CSD/PMT DWR review in Table 1
the qualified welding procedures shall be available at the fabrication/welding
site (e.g., vendor shop, field fabrication, etc.) for review by the Inspector, if
requested. The procedures shall be included in the project or shop
documentation record books.

5.4 If the welding procedure is approved to the latest edition of the welding
standards, then the fabricator/construction contractor is permitted to use the
welding procedure without CSD/PMT DWR review. The assigned inspector
must verify that the qualification range (e.g., diameter, thickness, material grade,
etc.) of the welding procedure is still applicable to the new work.

5.5 If the welding procedure is approved to a previous edition of the welding


standards, then fabricator/construction contractor is permitted to use it, if it was
not affected by the revisions. The fabricator/construction contractor must write
a formal letter to PMT or Engineering/Maintenance Div. indicating that the
subject welding procedure still complies with the latest edition of Saudi Aramco
Welding Standards. The assigned inspector must verify that the qualification
range (e.g., diameter, thickness, material grade, etc.) of the welding procedure is
still applicable to the new work.

5.6 If the previously approved welding procedure is invalidated by a change in the


welding standard, a revised welding procedure, along with the old approved
copy, must be submitted for CSD/PMT DWR review. The assigned inspector
must verify that the qualification range (e.g., diameter, thickness, material grade,
etc.) of the welding procedure is still applicable to the new work.

Revision Summary
24 September 2014 Major revision to revise the welding procedure approval instructions and gives guidelines
for the methodology of submitting new welding procedures packages through Engineering
Service Request in CRM system.
1 January 2018 Editorial revision to modify paragraph 5.1(b).

Saudi Aramco: Company General Use


Page 9 of 15
Document Responsibility: Welding Standards Committee SAEP-352
Issue Date: 1 January 2018
Next Planned Update: 24 September 2019 Welding Procedures Review and Approval

Table 1 – Welding Procedure Technical Approval Responsibility


Review/Approval
Welding Responsibility
Component Application Specification
Standard
CSD/PMT DWR Not Required (1)
Boiler Manufacture of Boilers 32-SAMSS-021 SAES-W-010 X
Repairs, Alterations, and Re-rating SAES-D-008 SAES-W-010 X
Axial , Centrifugal, & Expander
31-SAMSS-001 NA X
Compressors
Packaged Reciprocating Plant &
31-SAMSS-002 NA X
Instrument Air Compressor
Compressor Reciprocating Compressor 31-SAMSS-003 NA X
Packaged, Integrally Geared
31-SAMSS-006 NA X
Centrifugal Air Compressor
Inlet Air Filtration Systems for
32-SAMSS-016 NA X
Centrifugal Air Compressor
Coils Only 32-SAMSS-029 SAES-W-011 X
Fired Heater Repairs, Alterations, and Re-rating SAES-D-008 SAES-W-010 X
SAES-W-011
Fabricated Carbon Steel Piping 01-SAMSS-010 X
SAES-W-012
High Frequency Welded Pipe 01-SAMSS-333 01-SAMSS-333 X
SAES-W-011
Scraper Traps 02-SAMSS-009 X
SAES-W-012
SAES-W-011
Construction of Plant Piping SAES-L-350 X
SAES-W-016
Construction of Pipelines SAES-L-450 SAES-W-012 X
Pipeline Crossings Under Roads and
SAES-L-460 SAES-W-012 X
Railroads
Submarine Pipelines and Risers SAES-L-850 SAES-W-012 X
SAES-W-011
Piping and Pipeline Repair SAEP-310 X
SAES-W-012
Spectacle Blinds SAES-W-011 X
Fitting Auxiliary Piping 01-SAMSS-017 NA X
Piping Mounted Skids NA X
Pipeline Procurement & Manufacturing of Line
01-SAMSS-035 NA X
Pipe (large quantity)
Procurement & Manufacturing of Line
01-SAMSS-038 NA X
Pipe (small quantity)
Carbon Steel Pipes for On-Plot Piping 01-SAMSS-043 NA X
Manufacturing of Stainless Steel Pipe 01-SAMSS-046 NA X
Manufacturing of Butt Welding Pipe
02-SAMSS-005 NA X
Fittings
Manufacturing of Hot Tap and
02-SAMSS-006 NA X
Stopple Fittings
Manufacturing of Insulating
02-SAMSS-008 NA X
Joints/Spools for Cathodic Protection
Manufacturing of Flanged Insulating
02-SAMSS-010 NA X
Joints/Spools for Cathodic Protection
Power Piping NA X
Manufacture of Components for Flare
Flare System Systems
32-SAMSS-022 NA X

Saudi Aramco: Company General Use


Page 10 of 15
Document Responsibility: Welding Standards Committee SAEP-352
Issue Date: 1 January 2018
Next Planned Update: 24 September 2019 Welding Procedures Review and Approval

Review/Approval
Welding Responsibility
Component Application Specification
Standard
CSD/PMT DWR Not Required (1)
Shell and Tube Heat Exchanger 32-SAMSS-007 SAES-W-010 X
Air-Cooled Heat Exchanger 32-SAMSS-011 SAES-W-010 X
Plate and Frame Heat Exchanger 32-SAMSS-019 SAES-W-010 X
Electric Heat Exchanger 32-SAMSS-027 SAES-W-010 X
Heat
Double Pipe Heat Exchanger 32-SAMSS-028 SAES-W-010 X
Exchanger Clad Heat Exchanger 32-SAMSS-031 SAES-W-010 X
SAES-W-010
Repairs, Alterations, and Re-rating SAES-D-008 SAES-W-014 X
SAES-W-015
Heat Recovery
Manufacture of Heat Recovery Steam
Steam Generators
32-SAMSS-035 SAES-W-010 X
Generator
Brazing NA NA X
Centrifugal Fluorocarbon
Refrigeration Units for 31-SAMSS-005 NA X
Industrial/Process Services
Diesel Engines 30-SAMSS-001 NA X
Direct Expansion Air Conditioning
27-SAMSS-002 NA X
Systems for Offshore Facilities
Heating, Ventilating and Air
SAES-K-001 NA X
Miscellaneous Conditioning (HVAC)
Lubrication, Shaft Sealing, and Control
32-SAMSS-013 NA X
Oil Systems
Manufacture of Non-industrial
27-SAMSS-003 NA X
Cooling Towers
Packaged Water Cooled Centrifugal
27-SAMSS-001 NA X
Chillers for Utility Services
Reverse Osmosis System 32-SAMSS-033 NA X
Side-Entry Mixers 32-SAMSS-017 NA X
Centrifugal Pump 31-SAMSS-004 NA X
Positive Displacement Pump 31-SAMSS-009 NA X
Pump Submersible Pump 31-SAMSS-010 NA X
Shaft Sealing System 31-SAMSS-012 NA X
Construction of Fixed Offshore
SAES-M-005 SAES-W-013 X
Platforms
Fabrication of Structural and
12-SAMSS-007 NA X
Miscellaneous Steel
Structural Pre-engineered Metal Buildings 12-SAMSS-014 NA X
steel Non-building Structures SAES-M-001 NA X
Blast Resistant Buildings SAES-M-009 NA X
Communication Towers SAES-T-744 NA X
Fabrication and field welding on AWS D1.1
NA X
Structural Steel in Seismic Condition AWS D1.8
Atmospheric Tank 32-SAMSS-005 SAES-W-017 X
Low Pressure Tank 32-SAMSS-006 SAES-W-017 X
Small Tank 32-SAMSS-030 SAES-W-017 X
Tank Repair, Alteration, and
SAES-D-108 SAES-W-017 X
Reconstruction
Underground Storage Tank SAES-D-116 SAES-W-017 X

Saudi Aramco: Company General Use


Page 11 of 15
Document Responsibility: Welding Standards Committee SAEP-352
Issue Date: 1 January 2018
Next Planned Update: 24 September 2019 Welding Procedures Review and Approval

Review/Approval
Welding Responsibility
Component Application Specification
Standard
CSD/PMT DWR Not Required (1)
Special Purpose Steam Turbine 32-SAMSS-001 NA X
Inlet Air Filtration System for CGT 32-SAMSS-008 NA X
Turbine General Purpose Steam Turbine 32-SAMSS-009 NA X
Special Purpose Steam Turbine 32-SAMSS-010 NA X
Combustion Gas Turbine 32-SAMSS-100 NA X
General Requirement 04-SAMSS-035 NA X
Steel Lubricated Plug Valve 04-SAMSS-053 NA X
Safety Relief Valve Conventional and
34-SAMSS-611 NA X
Balanced Types
Valve Safety Relief Valve Pilot Operated
34-SAMSS-612 NA X
Types
Control Valve 34-SAMSS-711 NA X
Valve and Wellhead Equipment per
45-SAMSS-005 NA X
API SPEC 6A
Manufacture of Pressure Vessel 32-SAMSS-004 SAES-W-010 X
Manufacture of Small Pressure Vessel 32-SAMSS-036 SAES-W-010 X
Manufacture of Clad Vessel 32-SAMSS-031 SAES-W-010 X
Vessel SAES-W-010
Repairs, Alterations, and Re-rating SAES-D-008 SAES-W-014 X
SAES-W-015
Manufacture of Trays and Packing 32-SAMSS-020 NA X

Notes:
(1) Formal approval is not required. However, all WPS/PQR/Weld Map documents must be available for the inspector review
or verification upon his request.
(2) In special cases the PMT or the Engineering/Maintenance Division may request CSD procedure review for any
application. This may be done even though procedure review is not required according to Table 1 or is not listed
in Table 1.

Saudi Aramco: Company General Use


Page 12 of 15
Document Responsibility: Welding Standards Committee SAEP-352
Issue Date: 1 January 2018
Next Planned Update: 24 September 2019 Welding Procedures Review and Approval

Appendix I – Welding Master Set Preparation and Approval

1. Each fabricator/vendor awarded a contract or purchase order will compile all CSD
revised previously approved welding procedures and any welding procedures,
intended to be used in Saudi Aramco projects.
2. Revised previously approved welding procedures must be submitted in new forms,
unsigned, and the approved copy is attached to compare welding parameters
between the two copies.
3. The master set must include typical “Weld Maps”, “Weld Description” sheet,
“Request for Welding Procedure Approval” form and any supporting document
required to be submitted by Saudi Aramco Welding Standard (SAES-W-010,
SAES-W-011, etc.). It is recommended that a distinct identification system is
used for the WPS and the revision number (e.g., WPS # is WMS P1-P8-1 and the
revision # is M0, here both WMS and M indicate that the welding procedure is
part of welding master set).
4. The PQRs must be either the originals, certified/stamped copies, or colored copies of
the originals. PQR welding activities must be carried out in the presence of Saudi
Aramco inspection engineer or third party inspection agency. The qualification tests
must be performed by independent testing agency approved by Saudi Aramco
(Contact CSD Welding Group to get the updated list of the approved independent test
agencies).
5. The time required to review each master set will depend on the number of the
submitted welding procedures and the pertinent technical welding requirements
(e.g., PWHT, hardness test, impact toughness test, etc.). The table below lists the
estimated time to review welding master sets.

Estimated Time to Review Welding Master Sets

Number of MS Welding Procedure Time to Complete Review


Up to 50 6 Weeks
>50 to 100 10 Weeks
> 100 16 Weeks

6. After the initial technical approval, the welding procedures can be applied in
various company projects if ID approves the application.
7. The fabricator/ Construction Contractor must continuously review the approved
welding procedures to ensure their conformance with the latest applicable Saudi
Aramco Welding Standards and Industry Codes.

Saudi Aramco: Company General Use


Page 13 of 15
Document Responsibility: Welding Standards Committee SAEP-352
Issue Date: 1 January 2018
Next Planned Update: 24 September 2019 Welding Procedures Review and Approval

Appendix II – Welding Package Review and


Approval Process for Company Projects

Fabricator/Construction Contractor
prepares WP complying Saudi Aramco
Welding Engineering Standards

PMT screens WP:


No
 Is it IK/GCC fabricator’s WMS?
OR
 Does it need CSD/PMT DWR
formal approval as per Table 1?

Fabricator/Construction Yes
Contractor receive and review
CSD/PMT DWR comments
and correct WP deficiencies CSD welding
specialist/engineer or PMT
DWR reviews WP

WP rejected PMT receives WP review


Results

WP accepted WP rejected

ID reviews and approves


the application of WP

WP accepted

PMT formally accepts the


WP and sends the approval
to Fabricator/Construction
Contractor

Fabricator/Construction Contractor
can use the welding procedure

Saudi Aramco: Company General Use


Page 14 of 15
Document Responsibility: Welding Standards Committee SAEP-352
Issue Date: 1 January 2018
Next Planned Update: 24 September 2019 Welding Procedures Review and Approval

Appendix III – Welding Package Review and


Approval Process for Repair/Maintenance/Alterations

Fabricator/Construction Contractor prepares


repair/maintenance/alterations WP complying
with Saudi Aramco Welding Engineering
Standards and submits it to Proponent

Engineering/Maintenance Div. No
receives the WP and screens if it need
CSD formal approval as per Table 1?

Yes
Fabricator/Construction
Contractor receive and CSD welding
review CSD comments and specialist/engineer reviews
correct WP deficiencies WP

WP rejected Engineering/Maintenance Div.


receives WP review Results

WP accepted WP rejected

Proponent Inspection Unit reviews


and approves the application of WP

WP accepted

Engineering/Maintenance Div.
formally accepts the WP and sends
the approval to
Fabricator/Construction Contractor

Fabricator/Construction Contractor
can use the welding procedure

Saudi Aramco: Company General Use


Page 15 of 15