TransGulf ElectroMechanical (L.L.

C)

Labour Manday Comparison

Estimation Sheet (Labour Man Days)- Electrical L-Rate


Project : Typical Hotel / Office Towers/ Shopping Mall (average) 130.00

Sl. Description Rate

A Main Distribution Boards


Board with incoming upto 1000 Amps ACB and upto 6 nos. out going rating between
1 2,600.00
100 Amps to 800 Amps MCCBs
Board with incoming above1000 Amps ACB and upto 6 nos. out going rating
2 3,250.00
between 100 Amps to 2000 Amps MCCBs
Boards with Two incomers and bus couplers for rating upto 1000 Amps ACB and
3 3,250.00
upto 12 nos. outgoing rating between 100 Amps to 800 Amps MCCBs

Boards with Two incomers and bus couplers for rating above 1200 Amps ACB and
4 3,250.00
upto 12 nos. outgoing rating between 100 Amps to 2000 Amps MCCBs
B ACB Panels
1 ACB Panel upto 1000 Amps 1,300.00
2 ACB Panel above 2000 Amps
C Sub Main Distribution Boards / Motor Control Centres
Board with incoming upto 600 1000 Amps MCCB and upto 8 nos. outgoing of rating
1 1,040.00
between 100 to 800 Amps. MCCBs
Board with incoming upto450 3000 Amps MCCBs and upto 8 nos. outgoing of rating
2 1,040.00
between 100 to 2000 Amps. MCCBs
D Final Distribution Boards
1 4 way MCB board 2 Row 390.00
2 6 way MCB board 3 Row 390.00
3 8 way MCB board 4 Row 390.00
4 10 way MCB board 5 Row 520.00
5 12 way MCB board 5 Row 520.00
6 14 way MCB board 5 Row 520.00
7 16 way MCB board 6 Row 520.00
8 18 way MCB board 5 R 24 1,040.00
9 24 way MCB board 6 R 24 (Enclosure) 1,300.00
E Capacitor Banks
1 50 KVAR to 200 KVAR 1,040.00
2 200 KVAR to 400 KVAR 1,040.00

ELECTRICAL WORKS
Project: Typical Hotel / Office Towers/ Shopping Mall (average) Dtd. 28.10.12 1 OF 24
TransGulf ElectroMechanical (L.L.C)

Labour Manday Comparison

Estimation Sheet (Labour Man Days)- Electrical L-Rate


Project : Typical Hotel / Office Towers/ Shopping Mall (average) 130.00

Sl. Description Rate

3 400 KVAR to 600 KVAR and above 1,040.00

ELECTRICAL WORKS
Project: Typical Hotel / Office Towers/ Shopping Mall (average) Dtd. 28.10.12 2 OF 24
TransGulf ElectroMechanical (L.L.C)

Labour Manday Comparison

Estimation Sheet (Labour Man Days)- Electrical L-Rate


Project : Typical Hotel / Office Towers/ Shopping Mall (average) 130.00

Sl. Description Rate

F Control Panels

1 Panel with single DOL starter 260.00

2 Panel with single Star-Delta starter 260.00

3 Panel with single Star-Delta starter above 20 KW 260.00

4 VFD / Soft starter panel upto 20 KW 390.00

5 VFD / Soft starter panel upto 40 KW 390.00

6 VFD / Soft starter panel above 40 KW 520.00

G Feeder Pillars

1 Feeder Pillar with single incoming MCCB and upto 4 nos. outgoing 1,040.00

2 Feeder Pillar with single incoming MCCB and upto 8 nos. outgoing 1,040.00

H Meter Cabinets

1 Meter cabinet with single phase KWHR meter, incoming and outgoing breakers 260.00

2 Meter cabinet with three phase KWHR meter, incoming and outgoing breakers 260.00

I Bus Ducts
1 2500A TPNE Bus Riser 130.00

2 2000A TPNE Bus Riser 130.00

3 1600A TPNE Bus Riser 130.00

4 1000A TPNE Bus Riser 195.00

5 600A TPNE Bus Riser 260.00

6 Lighting Bus Bar - 63 / 45 A SPNE / TPNE 260.00

7 Tap Off units 1000A TP 390.00

ELECTRICAL WORKS
Project: Typical Hotel / Office Towers/ Shopping Mall (average) Dtd. 28.10.12 3 OF 24
TransGulf ElectroMechanical (L.L.C)

Labour Manday Comparison

Estimation Sheet (Labour Man Days)- Electrical L-Rate


Project : Typical Hotel / Office Towers/ Shopping Mall (average) 130.00

Sl. Description Rate

8 Tap Off units 800A TP 390.00

9 Tap Off units 600A TP 390.00

10 Tap Off units 250A TP 130.00

11 Tap Off units160A TP 130.00

12 Tap Off units 100A TP 97.50

13 Tap Off units upto 100A TP 97.50

14 Tee Pieces, extra bends & end covers 390.00

ELECTRICAL WORKS
Project: Typical Hotel / Office Towers/ Shopping Mall (average) Dtd. 28.10.12 4 OF 24
TransGulf ElectroMechanical (L.L.C)

Labour Manday Comparison

Estimation Sheet (Labour Man Days)- Electrical L-Rate


Project : Typical Hotel / Office Towers/ Shopping Mall (average) 130.00

Sl. Description Rate

J CABLES AND TERMINATION (Laying only) Average in trench & trays


XLPE/SWA/PVC CABLES
1 1C, 630MM² 21.67
2 4C,300MM2 32.50
3 4C,240MM2 32.50
4 4C,185MM2 26.00
5 4C,150MM2 26.00
6 4C,120MM2 26.00
7 4C,95MM2 13.00
8 4C,70MM2 13.00
9 4C,50MM2 10.00
10 4C,35MM2 8.67
11 4C,25MM2 8.67
12 4C,16MM2 6.50
13 4C,10MM2 6.50
14 4C,4MM2 5.20
15 4C,2.5MM2 5.20
ECC(mm2)
16 1C, 300 6.50
17 1C, 240 6.50
18 1C, 185 5.42
19 1C, 150 5.42
20 1C,120 5.42
21 1C,95 4.33
22 1C,50 4.33
23 1C,35 4.33
24 1C,25 2.17
25 1C,16 1.63

ELECTRICAL WORKS
Project: Typical Hotel / Office Towers/ Shopping Mall (average) Dtd. 28.10.12 5 OF 24
TransGulf ElectroMechanical (L.L.C)

Labour Manday Comparison

Estimation Sheet (Labour Man Days)- Electrical L-Rate


Project : Typical Hotel / Office Towers/ Shopping Mall (average) 130.00

Sl. Description Rate

26 1C,10 1.30
27 1C,4 1.30
FR Cables
28 4C,300MM2 FR 32.50
29 4C, 240MM2FR 32.50
30 4C, 185MM2 FR 26.00
31 4C, 150 MM2FR 26.00
32 4C, 120 MM2FR 21.67
33 4C, 95 MM2FR 13.00
34 4C, 70 MM2FR 13.00
35 4C, 50 MM2FR 10.00
36 4C, 35MM2 FR 8.67
37 4C, 25 MM2 FR 8.67
38 4C, 16 MM2FR 6.50
39 4C, 10MM2FR 6.50
40 4C, 4 MM2FR 5.20
FR 1C Cables
41 1C, 300 ECC-FR 6.50
42 1C, 240 ECC-FR 6.50
43 1C, 185 ECC-FR 6.50
44 1C, 150 ECC-FR 5.42
45 1C, 120 ECC-FR 5.42
46 1C, 95 ECC-FR 4.33
47 1C, 70 ECC- FR 4.33
48 1C, 50 ECC- FR 4.33
49 1C, 35 ECC- FR 4.33
50 1C, 25 ECC- FR 4.33
51 1C, 16 ECC- FR 1.63
52 1C, 10 ECC- FR 1.30

ELECTRICAL WORKS
Project: Typical Hotel / Office Towers/ Shopping Mall (average) Dtd. 28.10.12 6 OF 24
TransGulf ElectroMechanical (L.L.C)

Labour Manday Comparison

Estimation Sheet (Labour Man Days)- Electrical L-Rate


Project : Typical Hotel / Office Towers/ Shopping Mall (average) 130.00

Sl. Description Rate

53 1C, 4 ECC- FR 1.30

ELECTRICAL WORKS
Project: Typical Hotel / Office Towers/ Shopping Mall (average) Dtd. 28.10.12 7 OF 24
TransGulf ElectroMechanical (L.L.C)

Labour Manday Comparison

Estimation Sheet (Labour Man Days)- Electrical L-Rate


Project : Typical Hotel / Office Towers/ Shopping Mall (average) 130.00

Sl. Description Rate

1000 V Termination for 3, 3-1/2 and 4 core cables

54 upto 70 sq.mm. 42.90


55 70 sq.mm. to 150 sq.mm. 65.00
56 150 sq.mm. to 400 sq.mm. 97.50

1000 V termination for single core cables ECC

57 upto 70 sq.mm. 26.00


58 70 sq.mm. to 150 sq.mm. 45.50
59 150 sq.mm. to 400 sq.mm. 65.00
60 400 sq.mm. to 1000 sq.mm. 97.50
1000 V Straight Through Joints for 3, 3-1/2 and 4 core cables
61 upto 70 sq.mm. 91.00
62 70 sq.mm. to 150 sq.mm. 195.00
63 150 sq.mm. to 400 sq.mm. 520.00
1000 V Straight Through Joints for single core cables
64 upto 50 sq.mm. 26.00
65 50 sq.mm. to 150 sq.mm. 42.90
66 150 sq.mm. to 400 sq.mm. 130.00
67 400 sq.mm. to 1000 sq.mm. 260.00
1000 V Termination for 3, 3-1/2 and 4 core cables - FR
68 upto 70 sq.mm. 42.90
69 70 sq.mm. to 150 sq.mm. 65.00
70 150 sq.mm. to 400 sq.mm. 97.50

ELECTRICAL WORKS
Project: Typical Hotel / Office Towers/ Shopping Mall (average) Dtd. 28.10.12 8 OF 24
TransGulf ElectroMechanical (L.L.C)

Labour Manday Comparison

Estimation Sheet (Labour Man Days)- Electrical L-Rate


Project : Typical Hotel / Office Towers/ Shopping Mall (average) 130.00

Sl. Description Rate

1000 V termination for single core cables - FR


71 upto 70 sq.mm. 26.00
72 70 sq.mm. to 150 sq.mm. 42.90
73 150 sq.mm. to 400 sq.mm. 130.00
74 400 sq.mm. to 1000 sq.mm. 260.00
1000 V Straight Through Joints for 3, 3-1/2 and 4 core cables - FR
75 upto 70 sq.mm. 91.00
76 70 sq.mm. to 150 sq.mm. 195.00
77 150 sq.mm. to 400 sq.mm. 520.00
1000 V Straight Through Joints for single core cables - FR
78 upto 70 sq.mm. 26.00
79 70 sq.mm. to 150 sq.mm. 42.90
80 150 sq.mm. to 400 sq.mm. 130.00
81 400 sq.mm. to 1000 sq.mm. 260.00

FP 200 Cables
82 1C 1.5MM² 1.86
83 Terminations (MD / Unit Qty) 8.67
84 1C 2.5MM² 9,100.00
85 Terminations (MD / Unit Qty) 8.67
K CABLE TRAYS / LADDERS / COVERS
1 75mm Cable Tray 21.67
2 100mm Cable Tray 21.67

3 150mm Cable Tray 26.00

4 225mm Cable Tray 26.00

5 300mm Cable Tray 26.00

6 450mm Cable Tray 43.33

ELECTRICAL WORKS
Project: Typical Hotel / Office Towers/ Shopping Mall (average) Dtd. 28.10.12 9 OF 24
TransGulf ElectroMechanical (L.L.C)

Labour Manday Comparison

Estimation Sheet (Labour Man Days)- Electrical L-Rate


Project : Typical Hotel / Office Towers/ Shopping Mall (average) 130.00

Sl. Description Rate

7 600mm Cable Tray 43.33


8 750mm Cable Tray 43.33

9 900mm Cable Tray 54.17

10 1000mm Cable Tray 54.17

11 1200mm Cable Tray 86.67

12 100mm Cable tray cover 10.83

13 300mm Cable Tray Cover 14.44

14 750mm Cable Tray Cover 21.67

ELECTRICAL WORKS
Project: Typical Hotel / Office Towers/ Shopping Mall (average) Dtd. 28.10.12 10 OF 24
TransGulf ElectroMechanical (L.L.C)

Labour Manday Comparison

Estimation Sheet (Labour Man Days)- Electrical L-Rate


Project : Typical Hotel / Office Towers/ Shopping Mall (average) 130.00

Sl. Description Rate

CABLE LADDERS -
15 100mm Cable Ladder 21.67

16 150mm Cable Ladder 26.00

17 225mm Cable Ladder 26.00

18 300mm Cable Ladder 26.00

19 450mm Cable Ladder 43.33

20 600mm Cable Ladder 43.33

21 750mm Cable Ladder 43.33

22 900mm Cable Ladder 54.17

BASKET TRAYS

23 100X100mm Wire basket 21.67

24 150X100mm Wire basket 26.00

25 225X100mm Wire basket 26.00

26 300X100mm Wire basket 26.00

27 450X100mm Wire basket 43.33

28 600X100mm Wire basket 43.33

L TRUNKING

1 150X 150mm GI Trunking 13.00

2 100X 100mm GI Trunking 13.00

3 75X 75mm GI Trunking 10.83

4 2Comp. 300X 100mm GI Trunking 21.67

5 2Comp. 200X 100mm GI Trunking 21.67

ELECTRICAL WORKS
Project: Typical Hotel / Office Towers/ Shopping Mall (average) Dtd. 28.10.12 11 OF 24
TransGulf ElectroMechanical (L.L.C)

Labour Manday Comparison

Estimation Sheet (Labour Man Days)- Electrical L-Rate


Project : Typical Hotel / Office Towers/ Shopping Mall (average) 130.00

Sl. Description Rate

Fixing of Metal underfloor trunking


6 Upto 150 m width 10.83
7 Above 150mm upto 300 mm width 16.25
8 Above 300mm width 21.67

9 Junction boxes & service boxes (MD / Unit Qty) 42.90

Fixing of PVC trunking


10 Upto 18mm width 5.78
11 Above 38mm and upto 100mm width 8.67
12 Above 100 mm width 13.00

13 Junction boxes & service boxes (MD / Unit Qty) 26.00

14 Skirting Trunking 21.67


15 Dado Trunking 21.67

ELECTRICAL WORKS
Project: Typical Hotel / Office Towers/ Shopping Mall (average) Dtd. 28.10.12 12 OF 24
TransGulf ElectroMechanical (L.L.C)

Labour Manday Comparison

Estimation Sheet (Labour Man Days)- Electrical L-Rate


Project : Typical Hotel / Office Towers/ Shopping Mall (average) 130.00

Sl. Description Rate

M CONDUITING AND WIRING


Pulling of wires in conduits
1 1.5 sq.mm. to 6 sq. mm. 1.30
Pulling of wires in Trunking
2 1.5 sq.mm. to 6 sq. mm. 1.30
3 6 sq.mm. to 25 sq. mm. 2.60
Encasing of PVC conduits in floors
4 Upto 25 mm dia 5.42
5 Above 25mm dia. and upto 50 mm dia 8.67
Fixing of PVC conduits in Slab
6 Upto 25 mm dia 5.42
7 Above 25mm dia. and upto 75 mm dia 8.67

Laying of PVC conduits / pipes in Ground

8 Upto 25 mm dia 5.42


9 Above 25mm dia. And upto 75 mm dia 8.67
10 Above 75mm dia 10.83
Encasing of Metal Conduits in floors
11 Upto 25 mm dia 21.67
12 Above 25mm dia. And upto 75 mm dia 43.33

Fixing of Metal conduit in slab (Surface)

13 Upto 25 mm dia 21.67


14 Above 25mm dia. And upto 75 mm dia 43.33

N Isolators
1 16A SP Isolators 32.50
2 20A SP Isolators 32.50
3 16A TP Isolators 32.50
4 20A TP Isolators 32.50
ELECTRICAL WORKS
Project: Typical Hotel / Office Towers/ Shopping Mall (average) Dtd. 28.10.12 13 OF 24
TransGulf ElectroMechanical (L.L.C)

Labour Manday Comparison

Estimation Sheet (Labour Man Days)- Electrical L-Rate


Project : Typical Hotel / Office Towers/ Shopping Mall (average) 130.00

Sl. Description Rate

5 25A TP Isolators 32.50


6 40A TP Isolators 42.90
7 60A TP Isolators 42.90
8 80A TP Isolators 65.00
9 100A TP Isolators 65.00
10 125A TP Isolators 65.00
11 160A TP Isolators 85.80
12 200A TP Isolators 85.80
13 400A TP Isolators 130.00
14 600A TP Isolators 260.00
15 800A TP Isolators 260.00
16 1000A TP Isolators 390.00
17 1250A TP Isolators 390.00
18 1500A TP Isolators 520.00
19 Stop lock push button 42.90
O Wiring Accessories
1 13A, SSO with neon 13.00
2 13A, twin SSO with neon 13.00
3 13A, switched fused spur outlet 13.00
13A, unswitched fused
4 13.00
spur outlet
5 20A DP switch with neon indicator (W/H) 16.25
6 Flex outlet 13.00
7 45A DP switch Cooker 32.50
8 Connection unit for Cooker 16.25
9 Shaver socket 32.50
10 5A, SSO for table lamps 13.00
11 1 & 2 way switches upto 4 gangs 13.00
12 1 & 2 way switches upto 8 gangs 26.00
13 13A, SSO with neon - W.P 32.50
ELECTRICAL WORKS
Project: Typical Hotel / Office Towers/ Shopping Mall (average) Dtd. 28.10.12 14 OF 24
TransGulf ElectroMechanical (L.L.C)

Labour Manday Comparison

Estimation Sheet (Labour Man Days)- Electrical L-Rate


Project : Typical Hotel / Office Towers/ Shopping Mall (average) 130.00

Sl. Description Rate

14 13A, twin SSO with neon - W.P 32.50


15 16A 3pin SSO with plug top - W.P 42.90
16 16A 5pin SSO with plug top - W.P 42.90
17 32A 5pin SSO with plug top - W.P 42.90
18 Hand Dryer 42.90
19 Bell push 13.00
20 Door bell 32.50
21 TV Outlet 13.00
22 Twin RJ 45 outlet 13.00
23 Twin RJ 45 outlet (W/P) 32.50

P CONDUITS AND ACCESSORIES


Pvc conduits
1 20mm 5.42
2 25mm 5.42
3 32mm 8.67
4 50mm 13.00
GI conduits
5 20mm 21.67
6 25mm 21.67
7 32mm 43.33

ELECTRICAL WORKS
Project: Typical Hotel / Office Towers/ Shopping Mall (average) Dtd. 28.10.12 15 OF 24
TransGulf ElectroMechanical (L.L.C)

Labour Manday Comparison

Estimation Sheet (Labour Man Days)- Electrical L-Rate


Project : Typical Hotel / Office Towers/ Shopping Mall (average) 130.00

Sl. Description Rate

Q LIGHT FITTINGS
1 Fluorescent Light fixtures recessed 26.00
2 Fluorescent light fixtures Surface mounted 22.10
3 Incanderscent type light fixtures recessed 32.50

4 Incanderscent type light fixtures surface mounted 22.10

5 Incanderscent type light fixtures wall type 22.10


6 Pendent Light fittings 32.50

7 Chandliers (500W) 42.90

8 Chandliers (1000W) 65.00

9 Ceiling Fan 65.00

10 Street light fixtures upto 400 watts 65.00

11 Street light fixtures upto 1000 watts 65.00

12 Flood lights upto 400 watts 65.00

13 Flood lights upto 1000 watts 65.00

14 Flood lights above 1000 watts 65.00

STREET LIGHT POLES

15 Upto 5 meters 260.00

16 5 meters to 10 meters 390.00

17 10 meters to 14 meters 520.00

18 14 meters to 25 meters 1,300.00


R Central battery System
1 EM Surface type 26.00
2 EM Recessed type 26.00
3 EXIT Surface type 26.00
4 EXIT Recessed type 26.00

ELECTRICAL WORKS
Project: Typical Hotel / Office Towers/ Shopping Mall (average) Dtd. 28.10.12 16 OF 24
TransGulf ElectroMechanical (L.L.C)

Labour Manday Comparison

Estimation Sheet (Labour Man Days)- Electrical L-Rate


Project : Typical Hotel / Office Towers/ Shopping Mall (average) 130.00

Sl. Description Rate

5 EXIT Double sided type 26.00

6 Signage light 26.00

7 Emergency panels with maintenance free Lead Acid Batteries 1,170.00

S Lighting Conrtol System


1 Lighting Control Panels 520.00
2 Dimmer Racks 1,300.00
3 Wall mounted touch screen 32.50
4 Control Cables 4.33
T Fire Alarm System
1 Photo electric smoke sensor 22.10
2 Ditto, but with sounder 22.10
Photo electric smoke sensor
3 44.20
above F/C with remote indicator below F/C
4 Heat Sensor 22.10
5 Fireman telephone jack 13.00

6 Wall mounted / recessed fire alarm sounder with flasher - W/P 32.50

7 Break glass - intelligent type 16.25


8 Break glass - intelligent type - W/P 16.25
9 Fire alarm ceiling/wall sounder 32.50
10 Fire alarm ceiling/wall sounder - W/P 32.50
11 Ceiling speaker with fire dome 26.00
12 Wall mounted speaker with flasher 26.00
13 Wall mounted speaker with flasher - W/P 26.00
14 Pluggable phone 13.00
15 Short circuit isolators 22.10
16 Duct mounted smoke detector 32.50

ELECTRICAL WORKS
Project: Typical Hotel / Office Towers/ Shopping Mall (average) Dtd. 28.10.12 17 OF 24
TransGulf ElectroMechanical (L.L.C)

Labour Manday Comparison

Estimation Sheet (Labour Man Days)- Electrical L-Rate


Project : Typical Hotel / Office Towers/ Shopping Mall (average) 130.00

Sl. Description Rate

17 MFACP-1 (12 loop panel) 1,560.00


18 MFACP-2 (11 loop panel) 1,560.00
19 MFACP-2 (4 loop panel) 520.00
20 FARP 520.00

ELECTRICAL WORKS
Project: Typical Hotel / Office Towers/ Shopping Mall (average) Dtd. 28.10.12 18 OF 24
TransGulf ElectroMechanical (L.L.C)

Labour Manday Comparison

Estimation Sheet (Labour Man Days)- Electrical L-Rate


Project : Typical Hotel / Office Towers/ Shopping Mall (average) 130.00

Sl. Description Rate

21 MIMIC Panel 1,170.00


22 VE Panel (8 channel amplifiers rack) 1,300.00
23 Graphic Commad Centre with printer 520.00
U CCTV System
1 Fixed Type Dome Camera 42.90
2 Fixed wall mounted w.p 42.90
3 PTZ Camera 65.00
4 Wall mounted Dome Camera 65.00

5 Digital Vid. Multplxd. Rec.(DVMR) with DVD Backup,360 GB Hard Disk 780.00

6 Multiplexer 780.00
7 21'' Monitor 65.00
8 17'' Monitor 65.00
9 PC, Software etc. 65.00
10 Rack 260.00
V Access Contrtol System
1 Smart Card Readers 65.00
2 Magnetic Door contacts 65.00
3 Magnetic locks(Single) 65.00
4 Magnetic locks(Double) 65.00
5 Door release Push Buttons 65.00
6 Badge/Card printer 130.00
7 Control panels 520.00
8 Photo ID Badging 780.00
9 PC, Software etc. 780.00
10 Rack 260.00
W MATV System
1 Head End Station (RF/IF) 1,300.00
2 TV Amplifiers 78.00

ELECTRICAL WORKS
Project: Typical Hotel / Office Towers/ Shopping Mall (average) Dtd. 28.10.12 19 OF 24
TransGulf ElectroMechanical (L.L.C)

Labour Manday Comparison

Estimation Sheet (Labour Man Days)- Electrical L-Rate


Project : Typical Hotel / Office Towers/ Shopping Mall (average) 130.00

Sl. Description Rate

3 RF satellite Programs 65.00


4 Analogue Channels-Free channels 65.00
5 IF signal - pay channels 65.00
6 Antenna 195.00
7 Satellite Dish 390.00
8 Splitters 32.50
9 TV Outlets 13.00
10 Coaxial Cable(RG-11,RG-6) 4.33
X PA System
1 Speakers Ceiling mounted 26.00
2 Speakers wall mounted 26.00
3 Speakers W.P 26.00
4 Amplifier 260.00
5 Microphones 26.00
6 Tuners - AM/FM 130.00
7 CD Player+Tape 130.00
8 Volume controls 13.00
9 Music Rack 260.00
10 Rack wiring 1,040.00
Y Generators
1 Generator - Standby Type (1500KVA) 5,200.00
2 Generator - Standby Type (1000KVA) 3,900.00
3 Generator - Standby Type (600KVA) 2,600.00
4 Generator - Standby Type (400KVA) 2,080.00
5 Generator - Standby Type (200KVA) 1,040.00
6 Generator - Standby Type (100KVA) 780.00
7 Generator - Standby Type (50KVA) 780.00
8 ATS With By-pass switch (200A) 520.00
9 ATS With By-pass switch (400A) 780.00

ELECTRICAL WORKS
Project: Typical Hotel / Office Towers/ Shopping Mall (average) Dtd. 28.10.12 20 OF 24
TransGulf ElectroMechanical (L.L.C)

Labour Manday Comparison

Estimation Sheet (Labour Man Days)- Electrical L-Rate


Project : Typical Hotel / Office Towers/ Shopping Mall (average) 130.00

Sl. Description Rate

10 ATS With By-pass switch (600A) 1,040.00


11 ATS With By-pass switch (800A) 1,300.00
12 ATS With By-pass switch (1000A) 1,300.00
13 ATS With By-pass switch (1600A) 1,560.00
14 ATS With By-pass switch (2500A) 2,080.00
15 Accoustic insulation to wall -
16 Sound Attenuators 4 x 4mtr 2,340.00
17 Fuel pump 260.00
18 Fuel piping Mtr/MD
19 Bulk fuel tank 1,560.00
20 Exhaust piping / flue stack (Mtr/MD) 32.50
21 Control Cable Mtr/MD 260.00

ELECTRICAL WORKS
Project: Typical Hotel / Office Towers/ Shopping Mall (average) Dtd. 28.10.12 21 OF 24
TransGulf ElectroMechanical (L.L.C)

Labour Manday Comparison

Estimation Sheet (Labour Man Days)- Electrical L-Rate


Project : Typical Hotel / Office Towers/ Shopping Mall (average) 130.00

Sl. Description Rate

Z UPS System -
1 200KVA 1,560.00
2 100KVA 1,040.00
3 60KVA 780.00
4 40KVA 520.00
5 20KVA 520.00
6 10KVA 390.00
AA Earthing / Lightning protection -
1 25 x 3mm Bare Cu Tape Mtr/MD 17.33
2 25 x 3mm Square Tape clamp 18.20

3 Air Terminal (with taper pointed rod, base and Stem) 260.00

4 Bare Cu Cable for - 95mm² Mtr/MD 18.57


5 50mm Duct 21.67
6 Cad welding points 42.90
7 Mechanical Bonding 42.90
8 Earth Pit 85.80
9 Test link 85.80

10 16mm Cu Bonded Cu steel earth rod(8per pit) 780.00

11 Coupler 18.20
12 Driving Stud 18.20
13 Spike 18.20
14 Rod to Cable clamp 26.00
15 Allow for down conductor welding 42.90
16 Equipotential Earth Bar with Test link 85.80
17 PVC Insualted Cable 70mm² (Mtr / MD) 4.26
BB Miscellaneous items -
Intercom System -

ELECTRICAL WORKS
Project: Typical Hotel / Office Towers/ Shopping Mall (average) Dtd. 28.10.12 22 OF 24
TransGulf ElectroMechanical (L.L.C)

Labour Manday Comparison

Estimation Sheet (Labour Man Days)- Electrical L-Rate


Project : Typical Hotel / Office Towers/ Shopping Mall (average) 130.00

Sl. Description Rate

1 Intercom Outlets 13.00


2 Audio / Video Handsets 42.90
3 Intercom Panel 1,040.00
4 Cable (Mtr / MD) 4.33
Room Management system -
5 Room controllers 520.00
6 Intermediate panels 260.00
7 Workstation 780.00
8 Cables (Mtr / MD) 4.33
-

Cabling or wires in PVC ducts for external works -

10 Single core 4 to 25 sq.mm. 3.71

11 Single core 25 to 150 sq.mm. 8.67


12 Single core 150 to 400 sq.mm. -

ELECTRICAL WORKS
Project: Typical Hotel / Office Towers/ Shopping Mall (average) Dtd. 28.10.12 23 OF 24
TransGulf ElectroMechanical (L.L.C)

Labour Manday Comparison

Estimation Sheet (Labour Man Days)- Electrical L-Rate


Project : Typical Hotel / Office Towers/ Shopping Mall (average) 130.00

Sl. Description Rate

Cabling or multi core cables in PVC ducts for external wroks


13 upto 50 sq.mm. -
14 50 to 150 sq.mm -
15 150 to 400 sq.mm. -
Cabling or Telephone cables in Duct -
16 upto to 25 pairs cable -
17 upto 200 pairs cable -
18 upto 550 pairs cable -
19 upto 1000 pairs cable -
-
High voltage transformer 11/ 415 V -
20 200 to 500 KVA -
21 500 KVA to 1.5 MVA -
22 1.5 MVA and above -

Total Labour Excluding Idle Labour =

Uplift for Idle Labour


No. Of Floors
20
30
40
50
60
70

ELECTRICAL WORKS
Project: Typical Hotel / Office Towers/ Shopping Mall (average) Dtd. 28.10.12 24 OF 24