Академический Документы
Профессиональный Документы
Культура Документы
FMEA
1
What is FMEA?
FMEA is an acronym that stands for
Failure Modes and Effects Analysis
QS 9000
2
FMEA
3
FMEA - Methodology
y
define the system ,;
to be evaluated,;
Failure Analysis
identify failure modes, causes and consequences
as well as design and operating provisions against
such failures
Reporting
4
FMEA – Level of Analysis
premature operation
failure to operate when required
intermittent operation
failure to cease operation when required
loss of output or failure during operation
degraded output
etc
5
FMEA – Analysis of Failures
FMEA - Reporting
6
FMEA - Reporting
p g format;; typically
No standard reporting yp y covers
The unit/system
Failure mode
Consequence of failure
Symptoms
safeguards
Corrective action
Example 1
Household Water Supply system
7
FMEA – Household water supply system
W t Supply
Water S l System
S t FMEA
No Component Safe
Failure mode Failure effect(s) Symtoms Actions
Description Guards
Water
Install flow
1 Kitchen Tap Fails open Kitchen Flooded continuously
- control valve
flowing out
Install water
Inlet pipe No water at filter
2 Blocked Water Tank Dry
(2 in PVC) kitchen tap - Clean filter
periodically
Example 1
Household Water Supply system
8
Failure Mode Effect Analysis
(FMEA)
CRITICALITY ANALYSIS
Criticality is defined in the same way as risk - that
is, a combination of the severity of an effect and
the probability or expected frequency
9
Failure Mode Effect Analysis
(FMEA)
quantification of frequency
q q y depends
p on the
data available and may again be a simple
ranking, such as one depending on failure
probability during the operating time interval
extremely unlikely
remote
Occasional
O i l
reasonably frequent
frequent
10
Failure Mode Effect Analysis
(FMEA)
Example
extremely unlikely - 0.001
CRITICALITY MATRIX
5 A C C D D
4 A B C C D
3 A B B C C
2 A A B B C
1 A A A A A
1 2 3 4 5
A B C D
ACCEPTABLE UNACCEPTABLE
Threshold value = 10
11
FMEA
HAZOP
12
HAZOP
HAZOP is an acronym for HAZard and
OPerability studies
HAZOP
Skelton, B, 1997
formal systematic,
a formal, systematic critical,
critical rigorous examination to
the process and engineering intentions of new and
existing facilities to assess the hazard potential of mal-
operation or mal-function of individual items of
equipment and the consequential effects
W ll G,
Wells, G 1996
HAZOP is formal, systematic examination of a
processing plant in order to identify hazards, failures
and operability problems, and assess the
consequences from such mal-operation
13
WHY DO HAZOP??
Generates a list of identified p
problems,,
usually with some suggestions for
improvement of the system
HAZOP
Basic philosophy
if a process operates within its intended
design philosophy then undesired
hazardous events should not occur
The objective
j of a HAZOP
mainly to identify how process deviations
can be prevented or mitigated to minimize
process hazards
14
Basic Ideas of HAZOP
to stimulate the imagination of a review
team, including designers and operators, in a
systematic way so that they can identify
potential hazards in a design
HAZOP
Outcomes
recommend necessary changes to a
system to meet company risk guidelines
15
HAZOP
application at the correct stage in a
project means that problems are
identified and can be rectified during
detailed design.
HAZOP Terminology
Design intent
the way in which the plant is intended to operate.
Deviation
any perceived deviations in operation from the
design intent. Cause - the causes of the perceived
deviations.
Consequence
the consequences of the perceived deviations
16
Hazop Terminology
Safeguards
existing provisions to mitigate the likelihood or
consequences of the perceived deviations and to inform
operators of their occurrence
Actions
the recommendations or requests for information made by
the study team in order to improve the safety and/or
operability of the plant.
G id words
Guide d
simple words used to qualify the intent and hence discover
deviations.
Parameters
basic process requirements such as 'flow', 'temperature',
'pres-sure' and so on.
HAZOP COMPONENTS
Team
Procedure
Guide words
17
Hazop Team
normallyy comprises
p g
between four and eight
members,
each of whom can provide knowledge and
experience appropriate to the project to be
studied
Hazop Team
Two types of person are required in a
Hazop team:
those with detailed technical knowledge of
the process;
those with knowledge and experience of
the HAZOP technique and the ability to
chair and report upon technical meetings
18
Hazop Team
typical member of a Hazop team
chairman or team leader
secretary
process design engineer
control engineer
operations specialist
project engineer
Other specialists may be consulted or be
available for specific points
Hazop Team
chairman or team leader
selected for his or her ability to effectively
lead the study
should have sufficient seniority to give the
study recommendations the proper level of
authority
knowledge and experience of the Hazop
technique
19
Hazop Team
Secretary
should have a technical appreciation of the
project and be familiar with the HAZOP
technique
technical members
usually part of the project design team
Hazop PROCEDURE
1. Begin with a detailed flow sheet. Break the flow
sheet into a number of process units.
eg the reactor area might be one unit, and the storage
tank another. Select a unit for study.
20
Hazop PROCEDURE
4. Pick a process parameter:
flow,
flow
level,
temperature,
pressure,
concentration,
pH,
viscosity,
power,
Inert
etc
Hazop PROCEDURE
5. Apply a guide word to the process parameter to
suggest possible deviations.
deviations
NO
MORE
LESS
REVERSE
etc
21
Hazop PROCEDURE
7. Evaluate the consequences of the
deviation (if any).
any)
8. Recommend action
what?
by whom?
by when?
Hazop PROCEDURE
9. Record all information.
22
Hazop PROCEDURE
11. Repeat
p steps
p 4 through
g 10 until all applicable
pp
process parameters have been considered for
the given study node.
Hazop PROCEDURE
23
Hazop GUIDE WORDS
Guide words Meaning Comments
NO, NOT, The complete negation of the No part of the design intention is achieved, but
NONE intention Quantitative decrease nothing else happens.
MORE, HIGHER, Applies to quantities such as flow rate and
GREATER Quantitative increase temperature and toiattivities such as heating and
LESS, LOWER reaction.
All the design and operating intentions e achieved
AS WELL AS Qualitative increase along with some additional activity, such as
contamination of process streams.
Only some of the design intentions are achieved,
PART OF Qualitative decrease
some are not.
Most applicable to activities such as flow or chemical
REVERSE The logical opposite of reaction. Also applicable to substances, for example,
poison
i instead
i d off antidote.
id
No part of the original intention is achieved - the
OTHER THAN Complete substitution
original intention is replaced by something else
SOONER THAN Too early or in the wrong order Applies to process steps or actions.
LATER THAN Too late or in the wrong order Applies to process steps or actions.
Applies to process locations, or locations in operating
WHERE ELSE In additional locations
procedures.
Hazop Worksheet
HAZARD AND OPERABILITY STUDY REPORT
P j Title:
Project Ti l
Project Number; Date:
P&ID Number: Chairman:
Line Number: Study Team:
Action
Guide
Deviation Cause Consequences Safeguards Reply
word Number By Details
Accepted
24
Hazop Worksheet
HAZOP ACTION SHEET
Project: Project no: Action no:
P&ID no: Date: ref:
Action on: Date for reply:
Description:
Reply:
Signed: Date:
Review comments:
Example 3
Household Water Supply system
25
Example 3
Household Water Supply system
HAZARD AND OPERABILITY STUDY REPORT
Project Title: household water supply system
Project Number; 2008-101 Date: 25 Oct 2008
Drawing Number: Myhome-101 Chairman: Mywife
Line Number: Line No 1 ( pipe from water tank Study Team: MyHusband, Maid, eldest son
and kitchen tap)
Item: Kitchen Tap Paramter: Flow
GUIDE
DEVIATIONS CAUSES CONSEQUENCES SAFEGUARDS ACTION REQUIRED
WORDS
Water flow Valve (kitchen tap) Install flow control
REVERSE Kitchen flooded none
continuously fails open valve
MORE
Example 3
Household Water Supply system
HAZARD AND OPERABILITY STUDY REPORT
Project Title: household water supply system
P j t Number:
Project N b 2008 2008-101
101 D t 25 O
Date:25 Octt 2008
Drawing Number: Myhome-101 Chairman: Myhusband
Line Number: Line No 2 (main valve, pipe & Study Team: Mywife, Maid, eldest son
tank)
Item: Water Tank Paramter: Water Supply
GUIDE
DEVIATIONS CAUSES CONSEQUENCES SAFEGUARDS ACTION REQUIRED
WORDS
House owner forgot Water tank
More water than
MORE to close water overflow, house none Install level controller
tanks capacity
supply valve flooded
Low water
Low water level Pipe partially pressure to
Less none Install water filter
in tank blocked bathroom and
kitchen
26
Example 3
Household Water Supply system
27