Академический Документы
Профессиональный Документы
Культура Документы
GOTHENBURG, SWEDEN
Sealing by Pregrouting at
Trollhattan
Making Safe and Dry
The Oslo-Gothenburg high speed rail-
way is currently under construction
in sections for client Banverket, the
Swedish national railway authority,
with a view to completion by 2015.
When fully commissioned, the new
railway will reduce the journey time
between Oslo and Gothenburg from
the current 4 h to just 2.5 h.
Meantime, individual sections are
being opened as and when they
are completed. The 7 km-long
Trollhattan to Vanersborg section
skirts the southern end of Lake
Vanern, the largest lake in Sweden. A
long loop in the existing single track
is being bypassed by a new twin-
track railway, which includes the
3.5 km-long Trollhattan tunnel. The
tunnel has to be dry, so is being pre- Long Shifts Atlas Copco Rocket Boomer XL3 C at
the face in Trollhattan centre section.
grouted at the face using cement in
18 m-long holes drilled accurately The site operates from 07.00 to 22.00,
around its periphery by a fully- during which time a single blasting cycle is
computerized Atlas Copco Rocket achieved at each working face. Two crews
Boomer XL3 C drillrig.
work alternate weeks, changing over
halfway through the Wednesday shift. The
New Section first crew works a 7.2 h shift on Wednesday,
and 14.4 h shifts on Thursday and Friday.
The new twin-track section connects The weekend is free, and the crew resumes
into the existing single line at both ends, with 14.4 h shifts on Monday and Tuesday,
but follows a straighter alignment, reduc- and a 7.2 h shift on Wednesday. Once
ing the distance travelled. It is currently relieved by the second crew, the first crew Loading a rod into the RAS from the
under construction by contractor NCC takes the following week off. Rocket Boomer XL3 C basket.
International.
The 108 sq m single-tube, twin-track
running tunnel is being excavated by
drill/blast on a north-south alignment in
granite gneiss, which is hard at the north
end and softens progressively towards the
south. Some faulting occurs along the
tunnel alignment, but generally the rock is
sparsely to moderately jointed.
A 2.2 km-long, 27 sq m rescue tunnel
will parallel the main tunnel over much of
its length, and this is being excavated
simultaneously by the same contractor.
The safety regulations require that no one
shall be more than 300 m from an exit into
the rescue tunnel, or into open air, when a
train has to be evacuated in the main
tunnel.
FACE DRILLING 39
FD3/14 p39-42 29/3/04 7:27 am Page 40
GOTHENBURG, SWEDEN
Grouting
TO VANERSBORG AND OSLO
40 FACE DRILLING
FD3/14 p39-42 29/3/04 7:27 am Page 41
GOTHENBURG, SWEDEN
FACE DRILLING 41
FD3/14 p39-42 29/3/04 7:27 am Page 42
GOTHENBURG, SWEDEN
42 FACE DRILLING