Вы находитесь на странице: 1из 4

FD3/14 p39-42 29/3/04 7:27 am Page 39

GOTHENBURG, SWEDEN

Sealing by Pregrouting at
Trollhattan
Making Safe and Dry
The Oslo-Gothenburg high speed rail-
way is currently under construction
in sections for client Banverket, the
Swedish national railway authority,
with a view to completion by 2015.
When fully commissioned, the new
railway will reduce the journey time
between Oslo and Gothenburg from
the current 4 h to just 2.5 h.
Meantime, individual sections are
being opened as and when they
are completed. The 7 km-long
Trollhattan to Vanersborg section
skirts the southern end of Lake
Vanern, the largest lake in Sweden. A
long loop in the existing single track
is being bypassed by a new twin-
track railway, which includes the
3.5 km-long Trollhattan tunnel. The
tunnel has to be dry, so is being pre- Long Shifts Atlas Copco Rocket Boomer XL3 C at
the face in Trollhattan centre section.
grouted at the face using cement in
18 m-long holes drilled accurately The site operates from 07.00 to 22.00,
around its periphery by a fully- during which time a single blasting cycle is
computerized Atlas Copco Rocket achieved at each working face. Two crews
Boomer XL3 C drillrig.
work alternate weeks, changing over
halfway through the Wednesday shift. The
New Section first crew works a 7.2 h shift on Wednesday,
and 14.4 h shifts on Thursday and Friday.
The new twin-track section connects The weekend is free, and the crew resumes
into the existing single line at both ends, with 14.4 h shifts on Monday and Tuesday,
but follows a straighter alignment, reduc- and a 7.2 h shift on Wednesday. Once
ing the distance travelled. It is currently relieved by the second crew, the first crew Loading a rod into the RAS from the
under construction by contractor NCC takes the following week off. Rocket Boomer XL3 C basket.
International.
The 108 sq m single-tube, twin-track
running tunnel is being excavated by
drill/blast on a north-south alignment in
granite gneiss, which is hard at the north
end and softens progressively towards the
south. Some faulting occurs along the
tunnel alignment, but generally the rock is
sparsely to moderately jointed.
A 2.2 km-long, 27 sq m rescue tunnel
will parallel the main tunnel over much of
its length, and this is being excavated
simultaneously by the same contractor.
The safety regulations require that no one
shall be more than 300 m from an exit into
the rescue tunnel, or into open air, when a
train has to be evacuated in the main
tunnel.

FACE DRILLING 39
FD3/14 p39-42 29/3/04 7:27 am Page 40

GOTHENBURG, SWEDEN

Grouting
TO VANERSBORG AND OSLO

Before the running tunnel face can be


advanced, a circular pattern of 30 off
18 m-long holes must be drilled around the
full perimeter using the face drillrig. These
are pregrouted with cement to form a
watertight envelope ahead of the face,
within which three 5 m rounds can be
drilled and blasted.
The drilling and grouting exercise takes
a full working day to complete in the run-
ning tunnels. On the following day, six
control holes are drilled to test the effec-
tiveness of the grouting, and these are
pumped up to 4-5 bar using water. Water
loss is then measured, and, if less than
0.2 lit/min/m/bar is lost for each 18 m
hole, the umbrella is certified as ready for
advance. If one hole fails, it is grouted and
another two holes are drilled and grouted,
and the tunnel carries on regardless.
Each grouted umbrella overlaps the pre-
vious one by 5 m as an extra insurance
against water seepage. Experience has
proved that it is better to pregrout rather
than postgrout, and there are a number of
notable and costly postgrouting failures on
the record.
At Trollhattan, there is an imposed water
ingress limit of 3.5-2.5 lit/min/100 m of
tunnel, required to satisfy the demands of
Banverket for its electric railway system.
Only one water pressure test can be
conducted on any particular hole. To
date, only 50% of grouted rings have
passed the water pressure test first time, so
some face advance is usually lost on a
second day while remedial measures are
undertaken.
Plan of the Trollhattan tunnel. This regime originated at the recently
completed Sodra Lanken project in Drilling and Blasting
Stockholm, to enable the crews to spend as
much time as possible at home, without All blasting is carried out using site sensi-
impacting upon progress. The crews, who tized emulsion, with dynamite primers and
invariably live a long distance from site, Nonel detonators. A Dyno 2 t-capacity
are happy with this compromise, but the mixer truck is used for the north faces,
same cannot be said of the authorities, who operated by NCC under Dyno supervision.
monitor it very closely for obvious rea- The advantage with SSE is that the compo-
sons. However, it must be said that work- nents are not themselves classified as
ing conditions at Swedish tunnelling explosives, and, as such, can be stored and
projects are amongst the best in the world, transported under the less-onerous flam-
and job rotation during each shift keeps mable materials rules. At the south face, a
tiredness at bay and helps avoid boredom. mini SSE truck carrying a 1 t-capacity con-
There is also a major case to be made for tainer docks with the drillrig, which is then
keeping crews together, especially in an used as a charging platform.
environment in which sophisticated mech- The standard blasting pattern in the
anization is the norm. running tunnel comprises 170 holes drilled

40 FACE DRILLING
FD3/14 p39-42 29/3/04 7:27 am Page 41

GOTHENBURG, SWEDEN

to 5.2 m depth using Secoroc Magnum


Section: 400/723
SR35 drilling equipment. 48 mm ballistic
button bits are used with 5.5 m-long round
Magnum SR35 drifter rods. A smooth
blasting technique is applied, using two
rows with reduced charges. At the periph-
ery, 80 gram pentyl cord is used, and in the
second row located 0.6 m inside the
periphery, 0.9 kg of emulsion is measured
into each hole.
+73 m +73 m
The breaking face is formed by four
102 mm holes drilled using Magnum SR35
Dome reaming bits. Drilling and blasting
takes around 3 h, mucking around 7 h, and
scaling 3 h. Very little rock reinforcement
is necessary, with just the occasional rock-
bolt being installed.
Under normal circumstances, one com-
plete cycle of drilling and blasting is
undertaken at each face on three or four
days of the week. Overbreak is measured South Section Typical overbreak recorded in the main
every metre on advance. There is a 50 cm tunnel.
free zone around the perimeter of the Work from the south portal has progressed
drive, and average overbreak is 4% outside past the 600 m point, leaving less than 400 m
the theoretical tunnel line. to go to breakthrough into the completed
The Secoroc bits are reground every 10 valley section. The first 20 m was pregrouted
holes, and have a life of 500-700 m. There with micro cement injected into 18 m-long
are two purpose-built workshop containers holes using a Craelius Unigrout system.
at site housing regrinding facilities, which The tunnel is carried forward on full
include Grind Matic BQ2 semi-automatic face excavation using a refurbished and
button bit grinders. A third container is upgraded Atlas Copco Robot Boomer
used for Boomer maintenance. 185 ES drillrig, which previously saw ser-
vice at another Banverket site at Hallandsas.
False Tunnel The average depth of cover is 20 m, and
the alignment is mainly under forested
Some 1.2 km from the south portal, the ground, except where it passes beneath a
crown of the running tunnel alignment is corner of Bjorndalen, a small housing area
revealed in the base of a valley known as situated some 400 m from the south portal.
Bjornsravinen. Early in the project, NCC At the half dozen houses most affected,
obtained access at this point, diverted the vibration sensors were installed, and these
stream into a pipeline, and excavated the were linked to the Internet, from where Entrance to the rescue tunnel and
base of the valley to tunnel invert level. they could be monitored daily. The blasting centre section faces.
They then established temporary portals,
and drove the running tunnel at full section
for 250 m in each direction.
NCC Sweden, a regional company in
the same contracting group will construct a
short false tunnel across the valley to con-
nect the two temporary portals, and the
area will then be backfilled and the stream
reinstated.
Early excavation of this section
removed a bottleneck on the critical path
of the project, and opened the way to con-
structing the reinforced concrete false
tunnel during the Spring and Summer
months, rather than under the much harsher
winter conditions.

FACE DRILLING 41
FD3/14 p39-42 29/3/04 7:27 am Page 42

GOTHENBURG, SWEDEN

shotcrete over its entire length before han-


dover in December, 2005.
NCC employs 35 people at Trollhattan to
cover the three sites in operation. In the
centre section, mucking is subcontracted. In
the north and south sections, NCC uses
Broyt X43 diesel-powered hydraulic loaders
which are not self-propelled, loading into
subcontractors 30 t-capacity semi trailers.

Rocket Boomer XL3 C


The new Rocket Boomer XL3 C working in
the centre section of the tunnel is a fully-
computerized face drilling jumbo, with auto-
Side view of Rocket Boomer XL3 C. sequence was adjusted to lower vibration, matic boom control (ABC), and handles all
as necessary. face and grouthole drilling. It has been well-
received by the operators, who found that it
North Section took just two days to convert fully from their
previous Atlas Copco 353 ES.
The tunnel dips at 1% from the north This machine is equipped with a rod
portal for 2.3 km to the valley position, adding system (RAS) on the two outer
and then flattens out to 0.3% for the booms, which are reloaded alternately by a
remaining 1.2 km to the south portal. single operator using the rig basket. The
The drive from the north portal, which short movement of the rod adding system
is being undertaken using an Atlas Copco speeds up the grouthole drilling process.
Rocket Boomer 353 ES drillrig, passes The rig computer tells the operator how
within 100 m of a local hospital. many rods are in each hole, and indicates
Fortunately, the areas of the hospital that when the hole is complete.
would be sensitive to blasting are 250 m The operators report that the rig
away, and are generally unaffected. achieves 2.6-3 m/min/rockdrill, even with
Nevertheless, blasting times are negotiated all three machines in use.
with the hospital authorities, if need be. In general, the Rocket Boomer XL3 C is
a three-boom and basket hydraulic tun-
Rescue Tunnel nelling rig with high reaching Eagle console
for railway tunnels and underground cav-
At a point some 1.2 km from the north portal erns, suitable for cross sections up to
a 370 m adit has been driven oversize down 179 sq m. It is equipped with COP 1838
to the main tunnel horizon, from which faces rock drills with double reflex dampening for
are being driven in both directions in both high speed drilling and excellent drill steel
the running tunnel and the rescue tunnel. A economy. An integrated diagnostic system
pair of Swedvent 1.2 m-diameter silenced can immediately identify faulty electronic
axial flow fans mounted high above the adit components. The ABC system assists the
entrance provides auxiliary ventilation for operator to achieve accurate drill hole loca-
the faces. The adit is paved with asphalt to tion and improve the quality of drilling by
provide a safe, year-round surface for optimizing the drilling pattern and reducing
mobile equipment and trucks. overbreak. A full specification of this drill-
An Atlas Copco Rocket Boomer XL3 C rig is available at facedrilling.com ■
is drilling the running tunnel faces, while a
rebuilt Boomer H175 is working in the Acknowledgements
5 m-wide x 5.5 m-high rescue tunnels.
Rock produced from the tunnel is the Atlas Copco is grateful to NCC
property of Banverket, and is used for bal- International AB for facilitating the site
lasting tracks or sold into the aggregate visit on which this article is based, and
market. NCC conducts some crushing at particularly thanks Goran Manell, NCC
site on behalf of Banverket. project manager at Trollhattan, for taking
The completed tunnel will be lined with the trouble to explain details of this
50 mm depth of steel fibre reinforced complex project.

42 FACE DRILLING

Вам также может понравиться