Vertical Moment

Node L/C Fy kN Mx kNm Mz kNm


1 10 (DL+LL) 624.378 -1.107 -6.366
11 (DL+LL+ 694.461 16.525 122.878
12 (DL+LL+ 857.897 52.855 29.94
13 (DL+LL- 554.294 -18.738 -135.609
14 (DL+LL- 390.858 -55.068 -42.671
3 10 (DL+LL) 632.689 -2.753 9.095
11 (DL+LL+ 779.02 2.025 144.102
12 (DL+LL+ 961.893 63.278 46.903
13 (DL+LL- 486.358 -7.53 -125.912
14 (DL+LL- 303.485 -68.783 -28.714
4 10 (DL+LL) 288.206 -3.364 6.684
11 (DL+LL+ 511.818 8.156 130.274
12 (DL+LL+ 596.112 62.518 41.321
13 (DL+LL- 64.594 -14.885 -116.907
14 (DL+LL- -19.7 -69.246 -27.954
5 10 (DL+LL) 1667.783 -251.53 -0.781
11 (DL+LL+ 1678.539 -129.779 242.345
12 (DL+LL+ 1700.951 129.399 43.879
13 (DL+LL- 1657.028 -373.28 -243.907
14 (DL+LL- 1634.616 -632.458 -45.441
7 10 (DL+LL) 1857.393 -273.424 12.269
11 (DL+LL+ 2050.487 -246.197 262.722
12 (DL+LL+ 1899.88 189.029 58.297
13 (DL+LL- 1664.299 -300.652 -238.184
14 (DL+LL- 1814.905 -735.877 -33.759
8 10 (DL+LL) 1255.318 -184.971 4.043
11 (DL+LL+ 1571.581 -92.338 241.136
12 (DL+LL+ 1320.677 281.372 47.71
13 (DL+LL- 939.054 -277.604 -233.05
14 (DL+LL- 1189.958 -651.314 -39.624
9 10 (DL+LL) 1514.109 209.759 -3.291
11 (DL+LL+ 1574.723 317.814 311.506
12 (DL+LL+ 1714.478 548.007 76.849
13 (DL+LL- 1453.495 101.704 -318.087
14 (DL+LL- 1313.741 -128.489 -83.431
11 10 (DL+LL) 1755.012 229.617 6.537
11 (DL+LL+ 1987.44 285.541 330.092
12 (DL+LL+ 2078.631 631.195 90.015
13 (DL+LL- 1522.583 173.693 -317.018
14 (DL+LL- 1431.393 -171.961 -76.941
12 10 (DL+LL) 1219.945 143.347 3.967
11 (DL+LL+ 1612.523 243.424 308.499
12 (DL+LL+ 1494.846 555.465 84.028
13 (DL+LL- 827.367 43.271 -300.565
14 (DL+LL- 945.044 -268.771 -76.094
13 10 (DL+LL) 273.63 0.091 -0.295
11 (DL+LL+ 415.128 25.654 116.963
12 (DL+LL+ 451.219 38.245 32.735
13 (DL+LL- 132.133 -25.471 -117.553
14 (DL+LL- 96.041 -38.063 -33.325
14 10 (DL+LL) 1039.098 -147.069 -13.318
11 (DL+LL+ 1167.233 33.596 216.146
12 (DL+LL+ 1076.202 128.564 28.912
13 (DL+LL- 910.963 -327.733 -242.782
14 (DL+LL- 1001.994 -422.701 -55.548
15 10 (DL+LL) 962.301 132.98 -16.17
11 (DL+LL+ 1132.837 297.182 278.956
12 (DL+LL+ 1118.027 376.201 60.567
13 (DL+LL- 791.765 -31.222 -311.296
14 (DL+LL- 806.575 -110.241 -92.907
SIZE OF FOOTING SIZE OF COLUMN
ALONG X-AXIS 2.10 m ALONG X-AXIS 600 mm
ALONG Z-AXIS 2.10 m ALONG Z-AZIS 300 mm
depth 850 mm 790 mm
SBC 200 kN/sq. m
Depth below GL 3.50 m
Grade of Concrete M25
BOTTOM STEEL 16 mm @ 125 c/c along both directions

LOADING FROM STAAD

Node L/C Fy kN Mx kNm Mz kNm P/A Mx/Zx Mz/Zz C1 C2 C3 C4


13 10 (DL+LL) 281.966 0.108 0.034 63.937868 0.0699708455 0.0220279 64.029867 63.985811 63.889925 63.84587
11 (DL+LL+EQX) 437.265 30.464 144.641 99.153061 19.736961451 93.709751 170.07982 20.144218 138.50068 -11.43492
12 (DL+LL+EQZ) 480.889 43.545 38.295 109.04512 28.211856171 24.810496 129.65398 89.957188 84.515011 44.818218
13 (DL+LL-EQX) 126.667 -30.248 -144.574 28.722676 -19.59701976 -93.66634 -67.63255 82.233599 -36.27732 113.58883
14 (DL+LL-EQZ) 83.043 -43.329 -38.228 18.830612 -28.07191448 -24.76709 -27.20671 12.420628 17.708351 57.335692
Max: 480.889 170.07982 89.957188 138.50068 113.58883
Min -67.63255 12.420628 -36.27732 -11.43492
25% increase in SBC assumed for Dead + Live ± Eartquake Load

Critical Case
Maximum: 170.079819 kM/sq m Footing Size Ok
Minimum: -67.632549 kM/sq m Footing Size Ok

Two Way Shear Check

Vu = 721.3335 kN ( Factored Load)

Therefore, ζv= 0.18408879 N/sq. mm = Vu/ (d*(perimeter at d/2 from column face))
ζc= 1.25 N/sq. mm = (.25 x √fck)
Hence, Footing Safe in Two Way Shear

One Way Shear Check


Overhang along X-axis= 0.75 m
Overhang along Z-axis= 0.9 m

Critical section is taken distace d from face of column, thus


Shear force along X-axis, Vu= -20 kN (Upward force x Area of Contact)
(for 1m Strip)

Shear force along Z-axis, Vu= 10 kN (Upward force x Area of Contact)


(for 1m Strip)

Max force = 10 kN
Therefore, ζv= 0.01265823 N/sq. mm
ζc= 0.19 N/sq. mm from Table 23, IS 456:2000
Hence, Footing Safe in One Way Shear

Bending Moment

X-axis Mu= 84.375 kN m per m


Mu/bd2 = 0.11678201 N/sq. mm

Pt= 0.03223183 (as per Table 3, SP-16)


Minimum Steel i.e. .12% to be provided

Z-axis Mu= 121.5 kN m per m


Mu/bd2 = 0.16816609 N/sq. mm

Pt= 0.04641384 (as per Table 3, SP-16)


Minimum Steel i.e. .12% to be provided

:. Provide 1020 sq mm of steel per m of footing


= 10.2 sq cm of steel per m of footing
Bar dia spacing
Steel provided= 16 @ 125 mm c/c

Provided Footing:
Length = 2.10 m along X-axis
Width = 2.10 m along Z-axis
Depth = 850 mm
Bottom steel: 16 mm @ 125 mm c/c along both directions
SIZE OF FOOTING SIZE OF COLUMN
ALONG X-AXIS 2.30 m ALONG X-AXIS 600 mm
ALONG Z-AXIS 2.30 m ALONG Z-AZIS 300 mm
depth 850 mm 790 mm
SBC 185 kN/sq. m
Depth below GL 3.50 m
Grade of Concrete M25
BOTTOM STEEL 16 mm @ 125 c/c along both directions

LOADING FROM STAAD

Node L/C Fy kN Mx kNm Mz kNm P/A Mx/Zx Mz/Zz C1 C2 C3 C4


12 10 (DL+LL) 630.806 -1.179 -5.292 119.24499 -0.5814087285 -2.609682 116.0539 121.27326 117.21672 122.43608
11 (DL+LL+EQX) 703.781 17.945 155.415 133.03989 8.8493465932 76.640914 174.82412 52.198655 160.66516 38.039701
12 (DL+LL+EQZ) 887.66 59.734 37.093 167.79962 29.457055971 18.291937 172.43889 143.17179 125.3076 96.040503
13 (DL+LL-EQX) 557.832 -20.303 -165.999 105.45028 -10.01216405 -81.86028 10.862273 141.83872 26.881736 157.85818
14 (DL+LL-EQZ) 373.953 -62.092 -47.677 70.690548 -30.61987343 -23.5113 13.247499 50.865581 62.239296 99.857378
Max: 887.66 174.82412 143.17179 160.66516 157.85818
Min 10.862273 50.865581 26.881736 38.039701
25% increase in SBC assumed for Dead + Live ± Eartquake Load

Critical Case
Maximum: 174.824118 kM/sq m Footing Size Ok
Minimum: 10.8622734 kM/sq m Footing Size Ok

Two Way Shear Check

Vu = 1331.49 kN ( Factored Load)

Therefore, ζv= 0.33980451 N/sq. mm = Vu/ (d*(perimeter at d/2 from column face))
ζc= 1.25 N/sq. mm = (.25 x √fck)
Hence, Footing Safe in Two Way Shear

One Way Shear Check


Overhang along X-axis= 0.85 m
Overhang along Z-axis= 1m

Critical section is taken distace d from face of column, thus


Shear force along X-axis, Vu= -2.05E-14 kN (Upward force x Area of Contact)
(for 1m Strip)

Shear force along Z-axis, Vu= 27.75 kN (Upward force x Area of Contact)
(for 1m Strip)

Max force = 27.75 kN


Therefore, ζv= 0.03512658 N/sq. mm
ζc= 0.19 N/sq. mm from Table 23, IS 456:2000
Hence, Footing Safe in One Way Shear

Bending Moment

X-axis Mu= 100.246875 kN m per m


Mu/bd2 = 0.13875 N/sq. mm

Pt= 0.038295 (as per Table 3, SP-16)


Minimum Steel i.e. .12% to be provided

Z-axis Mu= 138.75 kN m per m


Mu/bd2 = 0.19204152 N/sq. mm

Pt= 0.05300346 (as per Table 3, SP-16)


Minimum Steel i.e. .12% to be provided

:. Provide 1020 sq mm of steel per m of footing


= 10.2 sq cm of steel per m of footing
Bar dia spacing
Steel provided= 16 @ 125 mm c/c

Provided Footing:
Length = 2.30 m along X-axis
Width = 2.30 m along Z-axis
Depth = 850 mm
Bottom steel: 16 mm @ 125 mm c/c along both directions
SIZE OF FOOTING SIZE OF COLUMN
ALONG X-AXIS 2.30 m ALONG X-AXIS 600 mm
ALONG Z-AXIS 2.30 m ALONG Z-AZIS 300 mm
depth 850 mm 790 mm
SBC 185 kN/sq. m
Depth below GL 3.50 m
Grade of Concrete M25
BOTTOM STEEL 16 mm @ 125 c/c along both directions

LOADING FROM STAAD

Node L/C Fy kN Mx kNm Mz kNm P/A Mx/Zx Mz/Zz C1 C2 C3 C4


3 10 (DL+LL) 297.959 -2.344 6.724 56.324953 -1.1559135366 3.3158544 58.484894 51.853185 60.796721 54.165012
11 (DL+LL) 538.909 11.995 159.88 101.87316 5.915180406 78.842771 149.30489 23.156453 139.8406 13.692164
12 (DL+LL) 628.855 71.854 47.068 118.87618 35.433878524 23.210981 142.01683 104.87926 85.322627 48.185058
13 (DL+LL) 57.009 -16.682 -146.432 10.776749 -8.2265143421 -72.21106 -55.72866 59.809038 -42.56624 72.971461
14 (DL+LL) -32.937 -76.541 -33.62 -6.226276 -37.74521246 -16.57927 -48.44061 -21.91377 11.951732 38.478567
Max: 628.855 149.30489 104.87926 139.8406 72.971461
Min -55.72866 -21.91377 -42.56624 13.692164
25% increase in SBC assumed for Dead + Live ± Eartquake Load

Critical Case
Maximum: 149.304887 kM/sq m Footing Size Ok
Minimum: -55.728663 kM/sq m Footing Size Ok

Two Way Shear Check

Vu = 943.2825 kN ( Factored Load)

Therefore, ζv= 0.24073155 N/sq. mm = Vu/ (d*(perimeter at d/2 from column face))
ζc= 1.25 N/sq. mm = (.25 x √fck)
Hence, Footing Safe in Two Way Shear

One Way Shear Check


Overhang along X-axis= 0.85 m
Overhang along Z-axis= 1m

Critical section is taken distace d from face of column, thus


Shear force along X-axis, Vu= -2.05E-14 kN (Upward force x Area of Contact)
(for 1m Strip)

Shear force along Z-axis, Vu= 27.75 kN (Upward force x Area of Contact)
(for 1m Strip)

Max force = 27.75 kN


Therefore, ζv= 0.03512658 N/sq. mm
ζc= 0.19 N/sq. mm from Table 23, IS 456:2000
Hence, Footing Safe in One Way Shear

Bending Moment

X-axis Mu= 100.246875 kN m per m


Mu/bd2 = 0.13875 N/sq. mm

Pt= 0.038295 (as per Table 3, SP-16)


Minimum Steel i.e. .12% to be provided

Z-axis Mu= 138.75 kN m per m


Mu/bd2 = 0.19204152 N/sq. mm

Pt= 0.05300346 (as per Table 3, SP-16)


Minimum Steel i.e. .12% to be provided

:. Provide 1020 sq mm of steel per m of footing


= 10.2 sq cm of steel per m of footing
Bar dia spacing
Steel provided= 16 @ 125 mm c/c

Provided Footing:
Length = 2.30 m along X-axis
Width = 2.30 m along Z-axis
Depth = 850 mm
Bottom steel: 16 mm @ 125 mm c/c along both directions
SIZE OF FOOTING SIZE OF COLUMN
ALONG X-AXIS 2.50 m ALONG X-AXIS 600 mm
ALONG Z-AXIS 2.50 m ALONG Z-AZIS 300 mm
depth 850 mm 790 mm
SBC 185 kN/sq. m
Depth below GL 3.50 m
Grade of Concrete M25
BOTTOM STEEL 16 mm @ 125 c/c along both directions

LOADING FROM STAAD

Node L/C Fy kN Mx kNm Mz kNm P/A Mx/Zx Mz/Zz C1 C2 C3 C4


4 10 (DL+LL) 637.531 -1.755 8.727 102.00496 -0.67392 3.351168 104.68221 97.979872 106.03005 99.327712
11 (DL+LL+EQX) 794.975 3.821 176.704 127.196 1.467264 67.854336 157.21408 48.647142 154.86646 46.29952
12 (DL+LL+EQZ) 990.337 71.444 52.904 158.45392 27.434496 20.315136 164.96284 132.45862 121.06765 88.56343
13 (DL+LL-EQX) 480.088 -7.33 -159.25 76.81408 -2.81472 -61.152 10.277888 108.12109 14.78144 112.62464
14 (DL+LL-EQZ) 284.726 -74.953 -35.45 45.55616 -28.781952 -13.6128 2.5291264 24.309606 48.58025 70.36073
Max: 990.337 164.96284 132.45862 154.86646 112.62464
Min 2.5291264 24.309606 14.78144 46.29952
25% increase in SBC assumed for Dead + Live ± Eartquake Load

Critical Case
Maximum: 164.962842 kM/sq m Footing Size Ok
Minimum: 2.5291264 kM/sq m Footing Size Ok

Two Way Shear Check

Vu = 1485.5055 kN ( Factored Load)

Therefore, ζv= 0.37911022 N/sq. mm = Vu/ (d*(perimeter at d/2 from column face))
ζc= 1.25 N/sq. mm = (.25 x √fck)
Hence, Footing Safe in Two Way Shear

One Way Shear Check


Overhang along X-axis= 0.95 m
Overhang along Z-axis= 1.1 m

Critical section is taken distace d from face of column, thus


Shear force along X-axis, Vu= 18.5 kN (Upward force x Area of Contact)
(for 1m Strip)

Shear force along Z-axis, Vu= 46.25 kN (Upward force x Area of Contact)
(for 1m Strip)

Max force = 46.25 kN


Therefore, ζv= 0.0585443 N/sq. mm
ζc= 0.19 N/sq. mm from Table 23, IS 456:2000
Hence, Footing Safe in One Way Shear

Bending Moment

X-axis Mu= 125.221875 kN m per m


Mu/bd2 = 0.17331747 N/sq. mm

Pt= 0.04783562 (as per Table 3, SP-16)


Minimum Steel i.e. .12% to be provided

Z-axis Mu= 167.8875 kN m per m


Mu/bd2 = 0.23237024 N/sq. mm

Pt= 0.06413419 (as per Table 3, SP-16)


Minimum Steel i.e. .12% to be provided

:. Provide 1020 sq mm of steel per m of footing


= 10.2 sq cm of steel per m of footing
Bar dia spacing
Steel provided= 16 @ 125 mm c/c

Provided Footing:
Length = 2.50 m along X-axis
Width = 2.50 m along Z-axis
Depth = 850 mm
Bottom steel: 16 mm @ 125 mm c/c along both directions
SIZE OF FOOTING SIZE OF COLUMN
ALONG X-AXIS 3.10 m ALONG X-AXIS 600 mm
ALONG Z-AXIS 3.10 m ALONG Z-AZIS 600 mm
depth 850 mm 790 mm
SBC 185 kN/sq. m
Depth below GL 3.50 m
Grade of Concrete M25
BOTTOM STEEL 16 mm @ 125 c/c along both directions

LOADING FROM STAAD

Node L/C Fy kN Mx kNm Mz kNm P/A Mx/Zx Mz/Zz C1 C2 C3 C4


14 10 (DL+LL) 1050.506 -149.805 -11.124 109.31384 -30.17119264 -2.240408 76.902239 81.383055 137.24462 141.72544
11 (DL+LL+EQX) 1190.134 63.176 251.326 123.84329 12.723842771 50.617838 149.74797 68.759435 129.38983 48.401286
12 (DL+LL+EQZ) 1088.259 162.622 35.363 113.24235 32.752576281 7.1222181 122.49372 111.09817 70.089595 58.694046
13 (DL+LL-EQX) 910.878 -362.786 -273.573 94.784391 -73.06622806 -55.09845 -26.70423 61.453293 90.201733 178.35926
14 (DL+LL-EQZ) 1012.754 -462.232 -57.61 105.38543 -93.09496157 -11.60283 0.5501098 19.114643 149.50205 168.06658
Max: 1190.134 149.74797 111.09817 149.50205 178.35926
Min -26.70423 19.114643 70.089595 48.401286
25% increase in SBC assumed for Dead + Live ± Eartquake Load

Critical Case
Maximum: 178.359257 kM/sq m Footing Size Ok
Minimum: -26.704231 kM/sq m Footing Size Ok

Two Way Shear Check

Vu = 1785.201 kN ( Factored Load)

Therefore, ζv= 0.40642951 N/sq. mm = Vu/ (d*(perimeter at d/2 from column face))
ζc= 1.25 N/sq. mm = (.25 x √fck)
Hence, Footing Safe in Two Way Shear

One Way Shear Check


Overhang along X-axis= 1.25 m
Overhang along Z-axis= 1.25 m

Critical section is taken distace d from face of column, thus


Shear force along X-axis, Vu= 74 kN (Upward force x Area of Contact)
(for 1m Strip)

Shear force along Z-axis, Vu= 74 kN (Upward force x Area of Contact)


(for 1m Strip)

Max force = 74 kN
Therefore, ζv= 0.09367089 N/sq. mm
ζc= 0.19 N/sq. mm from Table 23, IS 456:2000
Hence, Footing Safe in One Way Shear

Bending Moment

X-axis Mu= 216.796875 kN m per m


Mu/bd2 = 0.30006488 N/sq. mm

Pt= 0.08281791 (as per Table 3, SP-16)


Minimum Steel i.e. .12% to be provided

Z-axis Mu= 216.796875 kN m per m


Mu/bd2 = 0.30006488 N/sq. mm

Pt= 0.08281791 (as per Table 3, SP-16)


Minimum Steel i.e. .12% to be provided

:. Provide 1020 sq mm of steel per m of footing


= 10.2 sq cm of steel per m of footing
Bar dia spacing
Steel provided= 16 @ 125 mm c/c

Provided Footing:
Length = 3.10 m along X-axis
Width = 3.10 m along Z-axis
Depth = 850 mm
Bottom steel: 16 mm @ 125 mm c/c along both directions
SIZE OF FOOTING SIZE OF COLUMN
ALONG X-AXIS 3.60 m ALONG X-AXIS 600 mm
ALONG Z-AXIS 3.60 m ALONG Z-AZIS 600 mm
depth 850 mm 790 mm
SBC 185 kN/sq. m
Depth below GL 3.50 m
Grade of Concrete M25
BOTTOM STEEL 16 mm @ 125 c/c along both directions

LOADING FROM STAAD

Node L/C Fy kN Mx kNm Mz kNm P/A Mx/Zx Mz/Zz C1 C2 C3 C4


5 10 (DL+LL) 1678.212 -254.3 -0.602 129.49167 -32.7031893 -0.077418 96.71106 96.865895 162.11744 162.27227
11 (DL+LL+EQX) 1688.929 -122.279 281.957 130.3186 -15.72518004 36.259902 120.68265 62.666811 145.84294 87.827099
12 (DL+LL+EQZ) 1712.746 175.463 49.404 132.15633 22.564686214 6.3533951 128.85953 118.69409 92.756029 82.590597
13 (DL+LL-EQX) 1667.495 -386.321 -283.161 128.66474 -49.68119856 -36.41474 34.055041 92.318621 113.54496 171.80854
14 (DL+LL-EQZ) 1643.678 -684.063 -50.609 126.82701 -87.97106481 -6.508359 25.878066 36.29144 166.63177 177.04514
Max: 1712.746 128.85953 118.69409 166.63177 177.04514
Min 25.878066 36.29144 92.756029 82.590597
25% increase in SBC assumed for Dead + Live ± Eartquake Load

Critical Case
Maximum: 177.045144 kM/sq m Footing Size Ok
Minimum: 25.8780658 kM/sq m Footing Size Ok

Two Way Shear Check

Vu = 2569.119 kN ( Factored Load)

Therefore, ζv= 0.58490097 N/sq. mm = Vu/ (d*(perimeter at d/2 from column face))
ζc= 1.25 N/sq. mm = (.25 x √fck)
Hence, Footing Safe in Two Way Shear

One Way Shear Check


Overhang along X-axis= 1.5 m
Overhang along Z-axis= 1.5 m

Critical section is taken distace d from face of column, thus


Shear force along X-axis, Vu= 120.25 kN (Upward force x Area of Contact)
(for 1m Strip)

Shear force along Z-axis, Vu= 120.25 kN (Upward force x Area of Contact)
(for 1m Strip)

Max force = 120.25 kN


Therefore, ζv= 0.15221519 N/sq. mm
ζc= 0.19 N/sq. mm from Table 23, IS 456:2000
Hence, Footing Safe in One Way Shear

Bending Moment

X-axis Mu= 312.1875 kN m per m


Mu/bd2 = 0.43209343 N/sq. mm

Pt= 0.11925779 (as per Table 3, SP-16)


Minimum Steel i.e. .12% to be provided

Z-axis Mu= 312.1875 kN m per m


Mu/bd2 = 0.43209343 N/sq. mm

Pt= 0.11925779 (as per Table 3, SP-16)


Minimum Steel i.e. .12% to be provided

:. Provide 1020 sq mm of steel per m of footing


= 10.2 sq cm of steel per m of footing
Bar dia spacing
Steel provided= 16 @ 125 mm c/c

Provided Footing:
Length = 3.60 m along X-axis
Width = 3.60 m along Z-axis
Depth = 850 mm
Bottom steel: 16 mm @ 125 mm c/c along both directions
SIZE OF FOOTING SIZE OF COLUMN
ALONG X-AXIS 3.70 m ALONG X-AXIS 600 mm
ALONG Z-AXIS 3.70 m ALONG Z-AZIS 600 mm
depth 850 mm 790 mm
SBC 185 kN/sq. m
Depth below GL 3.50 m
Grade of Concrete M25
BOTTOM STEEL 16 mm @ 125 c/c along both directions

LOADING FROM STAAD

Node L/C Fy kN Mx kNm Mz kNm P/A Mx/Zx Mz/Zz C1 C2 C3 C4


7 10 (DL+LL) 1864.443 -269.929 10.8 136.19014 -31.97390085 1.2792924 105.49553 102.93695 169.44333 166.88475
11 (DL+LL+EQX) 2069.285 -236.893 303.702 151.15303 -28.06068742 35.974414 127.25341 69.694344 172.15051 114.59144
12 (DL+LL+EQZ) 1907.324 242.268 62.73 139.32243 28.697372318 7.4305569 140.36028 128.47139 94.444488 82.555597
13 (DL+LL-EQX) 1659.602 -302.965 -282.103 121.22732 -35.88711429 -33.41595 41.539406 95.004922 98.958789 152.4243
14 (DL+LL-EQZ) 1821.563 -782.126 -41.13 133.05793 -92.64517403 -4.871972 28.432624 36.227779 176.6649 184.46006
Max: 2069.285 140.36028 128.47139 176.6649 184.46006
Min 28.432624 36.227779 94.444488 82.555597
25% increase in SBC assumed for Dead + Live ± Eartquake Load

Critical Case
Maximum: 184.460057 kM/sq m Footing Size Ok
Minimum: 28.4326235 kM/sq m Footing Size Ok

Two Way Shear Check

Vu = 3103.9275 kN ( Factored Load)

Therefore, ζv= 0.70665866 N/sq. mm = Vu/ (d*(perimeter at d/2 from column face))
ζc= 1.25 N/sq. mm = (.25 x √fck)
Hence, Footing Safe in Two Way Shear

One Way Shear Check


Overhang along X-axis= 1.55 m
Overhang along Z-axis= 1.55 m

Critical section is taken distace d from face of column, thus


Shear force along X-axis, Vu= 129.5 kN (Upward force x Area of Contact)
(for 1m Strip)

Shear force along Z-axis, Vu= 129.5 kN (Upward force x Area of Contact)
(for 1m Strip)

Max force = 129.5 kN


Therefore, ζv= 0.16392405 N/sq. mm
ζc= 0.19 N/sq. mm from Table 23, IS 456:2000
Hence, Footing Safe in One Way Shear

Bending Moment

X-axis Mu= 333.346875 kN m per m


Mu/bd2 = 0.46137976 N/sq. mm

Pt= 0.12734081 (as per Table 3, SP-16)

Z-axis Mu= 333.346875 kN m per m


Mu/bd2 = 0.46137976 N/sq. mm

Pt= 0.12734081 (as per Table 3, SP-16)

:. Provide 1082.39691 sq mm of steel per m of footing


= 10.8239691 sq cm of steel per m of footing
Bar dia spacing
Steel provided= 16 @ 125 mm c/c

Provided Footing:
Length = 3.70 m along X-axis
Width = 3.70 m along Z-axis
Depth = 850 mm
Bottom steel: 16 mm @ 125 mm c/c along both directions
SIZE OF FOOTING SIZE OF COLUMN
ALONG X-AXIS 3.35 m ALONG X-AXIS 600 mm
ALONG Z-AXIS 3.35 m ALONG Z-AZIS 600 mm
depth 850 mm 790 mm
SBC 185 kN/sq. m
Depth below GL 3.50 m
Grade of Concrete M25
BOTTOM STEEL 16 mm @ 125 c/c along both directions

LOADING FROM STAAD

Node L/C Fy kN Mx kNm Mz kNm P/A Mx/Zx Mz/Zz C1 C2 C3 C4


8 10 (DL+LL) 1267.837 -182.278 3.534 112.97278 -29.090493179 0.5640055 84.44629 83.318279 142.62728 141.49927
11 (DL+LL+EQX) 1607.05 -70.187 277.728 143.19893 -11.20143103 44.32375 141.057 70.139 158.97929 88.061289
12 (DL+LL+EQZ) 1334.904 340.362 52.194 118.9489 54.319766727 8.3298544 145.27881 131.95105 58.367188 45.039421
13 (DL+LL-EQX) 928.624 -294.369 -270.66 82.746625 -46.97955533 -43.19574 -5.942935 63.170247 69.224353 138.33754
14 (DL+LL-EQZ) 1200.77 -704.918 -45.127 106.99666 -112.5007531 -7.202003 -10.16488 1.3583267 169.83633 181.35953
Max: 1607.05 145.27881 131.95105 169.83633 181.35953
Min -10.16488 1.3583267 58.367188 45.039421
25% increase in SBC assumed for Dead + Live ± Eartquake Load

Critical Case
Maximum: 181.359532 kM/sq m Footing Size Ok
Minimum: -10.164878 kM/sq m Footing Size Ok

Two Way Shear Check

Vu = 2410.575 kN ( Factored Load)

Therefore, ζv= 0.54880589 N/sq. mm = Vu/ (d*(perimeter at d/2 from column face))
ζc= 1.25 N/sq. mm = (.25 x √fck)
Hence, Footing Safe in Two Way Shear

One Way Shear Check


Overhang along X-axis= 1.375 m
Overhang along Z-axis= 1.375 m

Critical section is taken distace d from face of column, thus


Shear force along X-axis, Vu= 97.125 kN (Upward force x Area of Contact)
(for 1m Strip)

Shear force along Z-axis, Vu= 97.125 kN (Upward force x Area of Contact)
(for 1m Strip)

Max force = 97.125 kN


Therefore, ζv= 0.12294304 N/sq. mm
ζc= 0.19 N/sq. mm from Table 23, IS 456:2000
Hence, Footing Safe in One Way Shear

Bending Moment

X-axis Mu= 262.324219 kN m per m


Mu/bd2 = 0.3630785 N/sq. mm

Pt= 0.10020967 (as per Table 3, SP-16)


Minimum Steel i.e. .12% to be provided

Z-axis Mu= 262.324219 kN m per m


Mu/bd2 = 0.3630785 N/sq. mm

Pt= 0.10020967 (as per Table 3, SP-16)


Minimum Steel i.e. .12% to be provided

:. Provide 1020 sq mm of steel per m of footing


= 10.2 sq cm of steel per m of footing
Bar dia spacing
Steel provided= 16 @ 125 mm c/c

Provided Footing:
Length = 3.35 m along X-axis
Width = 3.35 m along Z-axis
Depth = 850 mm
Bottom steel: 16 mm @ 125 mm c/c along both directions
SIZE OF FOOTING SIZE OF COLUMN
ALONG X-AXIS 3.20 m ALONG X-AXIS 600 mm
ALONG Z-AXIS 3.20 m ALONG Z-AZIS 600 mm
depth 850 mm 790 mm
SBC 185 kN/sq. m
Depth below GL 3.50 m
Grade of Concrete M25
BOTTOM STEEL 16 mm @ 125 c/c along both directions

LOADING FROM STAAD

Node L/C Fy kN Mx kNm Mz kNm P/A Mx/Zx Mz/Zz C1 C2 C3 C4


15 10 (DL+LL) 976.571 134.956 -15.106 95.368262 24.711181641 -2.765991 117.31345 122.84543 67.891089 73.423071
11 (DL+LL+EQX) 1157.553 327.622 313.115 113.04229 59.989379883 57.333069 184.29179 92.558877 88.308779 -3.424131
12 (DL+LL+EQZ) 1153.068 408.529 70.241 112.6043 74.803894043 12.861511 160.21576 139.63734 40.529531 19.951113
13 (DL+LL-EQX) 795.588 -57.71 -343.327 77.694141 -10.5670166 -62.86505 3.4096582 103.99374 20.316885 120.90097
14 (DL+LL-EQZ) 800.073 -138.616 -100.453 78.132129 -25.38134766 -18.39349 27.48583 56.91542 68.095986 97.525576
Max: 1157.553 184.29179 139.63734 88.308779 120.90097
Min 3.4096582 56.91542 20.316885 -3.424131
25% increase in SBC assumed for Dead + Live ± Eartquake Load

Critical Case
Maximum: 184.291787 kM/sq m Footing Size Ok
Minimum: -3.4241309 kM/sq m Footing Size Ok

Two Way Shear Check

Vu = 1736.3295 kN ( Factored Load)

Therefore, ζv= 0.39530314 N/sq. mm = Vu/ (d*(perimeter at d/2 from column face))
ζc= 1.25 N/sq. mm = (.25 x √fck)
Hence, Footing Safe in Two Way Shear

One Way Shear Check


Overhang along X-axis= 1.3 m
Overhang along Z-axis= 1.3 m

Critical section is taken distace d from face of column, thus


Shear force along X-axis, Vu= 83.25 kN (Upward force x Area of Contact)
(for 1m Strip)

Shear force along Z-axis, Vu= 83.25 kN (Upward force x Area of Contact)
(for 1m Strip)

Max force = 83.25 kN


Therefore, ζv= 0.10537975 N/sq. mm
ζc= 0.19 N/sq. mm from Table 23, IS 456:2000
Hence, Footing Safe in One Way Shear

Bending Moment

X-axis Mu= 234.4875 kN m per m


Mu/bd2 = 0.32455017 N/sq. mm

Pt= 0.08957585 (as per Table 3, SP-16)


Minimum Steel i.e. .12% to be provided

Z-axis Mu= 234.4875 kN m per m


Mu/bd2 = 0.32455017 N/sq. mm

Pt= 0.08957585 (as per Table 3, SP-16)


Minimum Steel i.e. .12% to be provided

:. Provide 1020 sq mm of steel per m of footing


= 10.2 sq cm of steel per m of footing
Bar dia spacing
Steel provided= 16 @ 125 mm c/c

Provided Footing:
Length = 3.20 m along X-axis
Width = 3.20 m along Z-axis
Depth = 850 mm
Bottom steel: 16 mm @ 125 mm c/c along both directions
SIZE OF FOOTING SIZE OF COLUMN
ALONG X-AXIS 3.55 m ALONG X-AXIS 600 mm
ALONG Z-AXIS 3.55 m ALONG Z-AZIS 600 mm
depth 850 mm 790 mm
SBC 185 kN/sq. m
Depth below GL 3.50 m
Grade of Concrete M25
BOTTOM STEEL 16 mm @ 125 c/c along both directions

LOADING FROM STAAD

Node L/C Fy kN Mx kNm Mz kNm P/A Mx/Zx Mz/Zz C1 C2 C3 C4


9 10 (DL+LL) 1527.598 211.402 -4.092 121.21389 28.3514505 -0.548784 149.01655 150.11412 92.313651 93.41122
11 (DL+LL+EQX) 1591.463 327.989 350.44 126.28153 43.987114115 46.998053 173.81336 98.616474 103.43398 28.237092
12 (DL+LL+EQZ) 1749.961 590.652 87.047 138.85824 79.213256927 11.674008 183.79641 165.11799 57.055195 38.376782
13 (DL+LL-EQX) 1463.734 94.814 -358.625 116.14632 12.715652774 -48.09576 64.612974 141.56618 44.267929 121.22114
14 (DL+LL-EQZ) 1305.236 -167.849 -95.231 103.56961 -22.510490038 -12.77158 54.630033 75.064557 90.646818 111.08134
Max: 1749.961 183.79641 165.11799 103.43398 121.22114
Min 54.630033 75.064557 44.267929 28.237092
25% increase in SBC assumed for Dead + Live ± Eartquake Load

Critical Case
Maximum: 183.796406 kM/sq m Footing Size Ok
Minimum: 28.2370918 kM/sq m Footing Size Ok

Two Way Shear Check

Vu = 2624.9415 kN ( Factored Load)

Therefore, ζv= 0.59760985 N/sq. mm = Vu/ (d*(perimeter at d/2 from column face))
ζc= 1.25 N/sq. mm = (.25 x √fck)
Hence, Footing Safe in Two Way Shear

One Way Shear Check


Overhang along X-axis= 1.475 m
Overhang along Z-axis= 1.475 m

Critical section is taken distace d from face of column, thus


Shear force along X-axis, Vu= 115.625 kN (Upward force x Area of Contact)
(for 1m Strip)

Shear force along Z-axis, Vu= 115.625 kN (Upward force x Area of Contact)
(for 1m Strip)

Max force = 115.625 kN


Therefore, ζv= 0.14636076 N/sq. mm
ζc= 0.19 N/sq. mm from Table 23, IS 456:2000
Hence, Footing Safe in One Way Shear

Bending Moment

X-axis Mu= 301.867969 kN m per m


Mu/bd2 = 0.41781034 N/sq. mm

Pt= 0.11531565 (as per Table 3, SP-16)


Minimum Steel i.e. .12% to be provided

Z-axis Mu= 301.867969 kN m per m


Mu/bd2 = 0.41781034 N/sq. mm

Pt= 0.11531565 (as per Table 3, SP-16)


Minimum Steel i.e. .12% to be provided

:. Provide 1020 sq mm of steel per m of footing


= 10.2 sq cm of steel per m of footing
Bar dia spacing
Steel provided= 16 @ 125 mm c/c

Provided Footing:
Length = 3.55 m along X-axis
Width = 3.55 m along Z-axis
Depth = 850 mm
Bottom steel: 16 mm @ 125 mm c/c along both directions
SIZE OF FOOTING SIZE OF COLUMN
ALONG X-AXIS 3.85 m ALONG X-AXIS 600 mm
ALONG Z-AXIS 3.85 m ALONG Z-AZIS 600 mm
depth 850 mm 790 mm
SBC 185 kN/sq. m
Depth below GL 3.50 m
Grade of Concrete M25
BOTTOM STEEL 16 mm @ 125 c/c along both directions

LOADING FROM STAAD

Node L/C Fy kN Mx kNm Mz kNm P/A Mx/Zx Mz/Zz C1 C2 C3 C4


11 10 (DL+LL) 1766.672 237.616 4.691 119.18853 24.983008895 0.493213 144.66475 143.67833 94.698735 93.712309
11 (DL+LL+EQX) 2009.863 296.456 371.655 135.59541 31.16946201 39.075905 164.67262 102.15118 114.80148 52.280037
12 (DL+LL+EQZ) 2113.826 679.856 99.891 142.60928 71.480239106 10.502566 179.67367 162.86956 65.305283 48.501177
13 (DL+LL-EQX) 1523.481 178.777 -362.273 102.78165 18.79666092 -38.08948 66.791065 127.73423 36.716408 97.659574
14 (DL+LL-EQZ) 1419.518 -204.624 -90.509 95.767785 -21.51422132 -9.51614 51.789939 67.015763 86.212693 101.43852
Max: 2113.826 179.67367 162.86956 114.80148 101.43852
Min 51.789939 67.015763 36.716408 48.501177
25% increase in SBC assumed for Dead + Live ± Eartquake Load

Critical Case
Maximum: 179.673665 kM/sq m Footing Size Ok
Minimum: 36.7164079 kM/sq m Footing Size Ok

Two Way Shear Check

Vu = 3170.739 kN ( Factored Load)

Therefore, ζv= 0.72186937 N/sq. mm = Vu/ (d*(perimeter at d/2 from column face))
ζc= 1.25 N/sq. mm = (.25 x √fck)
Hence, Footing Safe in Two Way Shear

One Way Shear Check


Overhang along X-axis= 1.625 m
Overhang along Z-axis= 1.625 m

Critical section is taken distace d from face of column, thus


Shear force along X-axis, Vu= 143.375 kN (Upward force x Area of Contact)
(for 1m Strip)

Shear force along Z-axis, Vu= 143.375 kN (Upward force x Area of Contact)
(for 1m Strip)

Max force = 143.375 kN


Therefore, ζv= 0.18148734 N/sq. mm
ζc= 0.19 N/sq. mm from Table 23, IS 456:2000
Hence, Footing Safe in One Way Shear

Bending Moment

X-axis Mu= 366.386719 kN m per m


Mu/bd2 = 0.50710965 N/sq. mm

Pt= 0.13996226 (as per Table 3, SP-16)

Z-axis Mu= 366.386719 kN m per m


Mu/bd2 = 0.50710965 N/sq. mm

Pt= 0.13996226 (as per Table 3, SP-16)

:. Provide 1189.67923 sq mm of steel per m of footing


= 11.8967923 sq cm of steel per m of footing
Bar dia spacing
Steel provided= 16 @ 125 mm c/c

Provided Footing:
Length = 3.85 m along X-axis
Width = 3.85 m along Z-axis
Depth = 850 mm
Bottom steel: 16 mm @ 125 mm c/c along both directions
SIZE OF FOOTING SIZE OF COLUMN
ALONG X-AXIS 2.30 m ALONG X-AXIS 600 mm
ALONG Z-AXIS 2.30 m ALONG Z-AZIS 300 mm
depth 850 mm 790 mm
SBC 185 kN/sq. m
Depth below GL 3.50 m
Grade of Concrete M25
BOTTOM STEEL 16 mm @ 125 c/c along both directions

LOADING FROM STAAD

Node L/C Fy kN Mx kNm Mz kNm P/A Mx/Zx Mz/Zz C1 C2 C3 C4


12 10 (DL+LL) 630.806 -1.179 -5.292 119.24499 -0.5814087285 -2.609682 116.0539 121.27326 117.21672 122.43608
11 (DL+LL+EQX) 703.781 17.945 155.415 133.03989 8.8493465932 76.640914 174.82412 52.198655 160.66516 38.039701
12 (DL+LL+EQZ) 887.66 59.734 37.093 167.79962 29.457055971 18.291937 172.43889 143.17179 125.3076 96.040503
13 (DL+LL-EQX) 557.832 -20.303 -165.999 105.45028 -10.01216405 -81.86028 10.862273 141.83872 26.881736 157.85818
14 (DL+LL-EQZ) 373.953 -62.092 -47.677 70.690548 -30.61987343 -23.5113 13.247499 50.865581 62.239296 99.857378
Max: 887.66 174.82412 143.17179 160.66516 157.85818
Min 10.862273 50.865581 26.881736 38.039701
25% increase in SBC assumed for Dead + Live ± Eartquake Load

Critical Case
Maximum: 174.824118 kM/sq m Footing Size Ok
Minimum: 10.8622734 kM/sq m Footing Size Ok

Two Way Shear Check

Vu = 1331.49 kN ( Factored Load)

Therefore, ζv= 0.33980451 N/sq. mm = Vu/ (d*(perimeter at d/2 from column face))
ζc= 1.25 N/sq. mm = (.25 x √fck)
Hence, Footing Safe in Two Way Shear

One Way Shear Check


Overhang along X-axis= 0.85 m
Overhang along Z-axis= 1m

Critical section is taken distace d from face of column, thus


Shear force along X-axis, Vu= -2.05E-14 kN (Upward force x Area of Contact)
(for 1m Strip)

Shear force along Z-axis, Vu= 27.75 kN (Upward force x Area of Contact)
(for 1m Strip)

Max force = 27.75 kN


Therefore, ζv= 0.03512658 N/sq. mm
ζc= 0.19 N/sq. mm from Table 23, IS 456:2000
Hence, Footing Safe in One Way Shear

Bending Moment

X-axis Mu= 100.246875 kN m per m


Mu/bd2 = 0.13875 N/sq. mm

Pt= 0.038295 (as per Table 3, SP-16)


Minimum Steel i.e. .12% to be provided

Z-axis Mu= 138.75 kN m per m


Mu/bd2 = 0.19204152 N/sq. mm

Pt= 0.05300346 (as per Table 3, SP-16)


Minimum Steel i.e. .12% to be provided

:. Provide 1020 sq mm of steel per m of footing


= 10.2 sq cm of steel per m of footing
Bar dia spacing
Steel provided= 16 @ 125 mm c/c

Provided Footing:
Length = 2.30 m along X-axis
Width = 2.30 m along Z-axis
Depth = 850 mm
Bottom steel: 16 mm @ 125 mm c/c along both directions