Niagara Falls Construction Project

Syndicate 1 :

Time (Days)
Intermediate
Activity Description Workers Normal (Expected Critical Path
Predecessesors Crash
Time : Days)
A Applied building permit Rikert 21 YES
B Review project A Rikert 2 YES
C Apply for minor variance B Rikert 49 YES
D Reapply for building permit C Rikert 21 YES
Developing project and list
E all of building materials D Rikert 1 YES
F Contact ON1Call E Rikert 5 YES
Ordered steel roofing
panels, garage door, roof
G trusses E Rikert 14 NO
H Excavating stage G Rikert and Dakin 2 YES
I Set the forms H Rikert or Dakin 1 YES
Spreading the layer of
J gravel I Rikert or Dakin 1 YES
K Pick up the set rebar J Rikert 1 YES
L Foundation Inspection K Inspectors 3 YES
Ordered and delivery
M concrete L Rikert 2 YES
N Poured the concrete M Rikert and Dakin 1 YES
O Cured the concrete N Rikert 3 YES
P Removed the forms O Rikert and Dakin 1 YES
Framing and erect the
Q walls P Rikert and Dakin 1 YES
Set and secure the roof
R trusses Q Rikert and Dakin 1 YES
Sheating exterior and
S wrapping air barrier R Rikert and Dakin 1 YES
T Structure Inspection S Inspectors 3 YES
Rikert split his
Install the steel roof and jobs. James for the
attached the pannels also Roof and Dakin for
install the single window, the Door and
U man door and garage door G, T Windows 2 YES
Rikert alone for the
normal days and if
Rikert and Dakin
worked together it
Complete exterior soffit and would be on
V fascia U crashing days 3 2 YES
Rikert alone for the
normal days and if
Rikert and Dakin
worked together it
would be on
W Vinyl siding V crashing days 7 4 YES
X Installing the eaves through W Rikert and Dakin 1 YES
Y Inspection finishing X Inspectors 3 YES
136 132
Reasons for the crashing :
We choose the activities U and V to be crashed because there are a potential days to decrease the work days. As explained in Gantt Chart
the end of our working days will be in August 25, 2019. However it's reached the personal due date that Rikert has been set before August
23, 2019. If we tried to pushed again the date by crashing the activities U and V then the due date will be in August 21, 2019.