Вы находитесь на странице: 1из 6

Final Bill:Page 1 of 6

Estimate of 400M3 tank foundation in Khoragaon GGS 1


Size
Sl
Structure Location UOM Nos. Bredth Depth/ Quantity
No. Length (m)
(m) Height(m)
Stone Piles:
1 MTR 350 5.000 1750
Total 1750

Prepared By Checked By Approved By

.............................. ..................................... ...................................


(PECOPD)
Final Bill:Page 2 of 6

Remarks

Prepared By Checked By Approved By

.............................. ..................................... ...................................


(PECOPD)
PUNJAB ENGINEERING COMPANY (Project Division)
Name of the Work : Civil & Structural work for U.K. Paints(India) Pvt. Ltd., Bhomoraguri(Assam)
Assam "Site"- General Building Work.
Client : U.K. Paints (India)Pvt. Ltd.(Assam)
Consultant : Engineering and Development Consultants
Name of Contractor : PUNJAB ENGINEERING COMPANY (PROJECT DIVISION)
ABSTRACT
MEASUREMENT OF EXECUTED
QTY
SL SOR
Description UOM Rate (Rs.) Since
NO ITEM No Previous Upto Date
Previous

PILE WORK: Boring, providing and installing


1 A1
cast in situ reinforced cement concrete pile.
RM 1979.00 915.900 915.900

Supplying and fixing in position HYSD for RCC


2 A1a
cast in situ pile work.
MT 50180.00 15.190 15.190

Conducting Routine Load Test on selected vertical


3 A-1b pile Nos 58200.00 1.000 1.000

Filling in plinth and backfilling in foundations with


4 A-5
excavated earth
CUM 150.00 493.160 493.160

5 A-5A Filling with approved earth brought from out side CUM 457.00 1960.736 73.617 2034.353

Filling in plinth & filling in foundations with


6 A-6 approved local sand CUM 1005.00 14.835 14.835

Providing and laying stone soling using 100 × 80 size


7 A-7 stone CUM 2800.00 29.670 29.670

Providing and injecting chemical emulsion for


8 A8
pre-constructional anti-termite treatment
SQM 160.00 2072.345 2072.345

Providing and laying required thickness of


9 B-1
controlled plain cement concrete1:4:8
CUM 4113.00 272.311 42.231 314.542

Providing and laying cast-in-situ reinforced


10 B-2a
cement concrete of grade M25 (00 to -3.9 Lvl)
CUM 6398.00 224.240 1.422 225.663

Providing and laying cast-in-situ reinforced


11 B-2b
cement concrete of grade M25 (00 to +4.5 Lvl)
CUM 8683.00 21.193 36.794 57.987

Providing & fixing plain formwork for centering


12 B-4a and shuttering by using approved quality SQM 411.00 1116.439 7.840 1124.279
plywood panels.a) 0.00 to -3.5
Providing & fixing plain formwork for centering
13 B-4b and shuttering by using approved quality SQM 411.00 36.985 267.974 304.959
plywood panels.b) 0.0 to +4.5M Lvl
Laying & fixing in position reinforcement for
14 B-3 RCC work with straightening, MT 56669.00 29.696 3.549 33.245
cutting,bending,binding etc.
Providing and laying Damp Proof Course 40 MM
15 B-5 Thick in cement concrete 1:2:4 CUM 500.00 26.841 26.841

Labour charges for fixing and alignment of


16 B-7a foundation bolts Nos 250.00 352.000 352.000

Providing and laying first class bricks in cement


17 C-1 mortar 1:5 CUM 6215.00 493.596 6.686 500.282

Providing and laying first class bricks in Super


18 C-2 structure. A) from -0.8M to +4.5M Lvl CUM 6215.00 65.800 26.575 92.375

Providing and laying first class bricks in 115mm thk


19 C-3 wall in cement morter 1:4.A) from -0.0M to +6.0M SQM 1005.00 43.980 39.340 83.320
Lvl
20 C-4 Supply and fabrication and fixing of angle iron… Kg 95.00 9589.914 9589.914

Providing and laying reinforced cement concrete


21 E-1 flooring in Mix- M25 CUM 6596.00 269.454 269.454

Providing and applying vaccum dewatering method


22 E-3 (Termix) SQM 137.00 1256.438 1256.438

Providing & laying IPS (Indian patent Stone) cement


23 E-4 concrete flooring SQM 750.00 9.450 9.450

Providing and laying vertified tiles flooring tiles 600 X


24 E-7 600 mm. SQM 1280.00 0.000 0.000

Providing and fixing aluminium glazed doors


25 F-4a including fixed glazing, high quality extreded SQM 3500.00 3.780 3.780
aluminium section

Providing and fixing aluminium glazed openable


26 F-4b window including fixed glazing, high quality extreded SQM 2800.00 4.590 4.590
aluminium section
27 H-1 Providing cement plaster 1:4 on inside SQM 225.00 53.227 1561.902 1615.129
28 H-2 Providing cement plaster 1:4 on outside SQM 225.00 574.667 1201.999 1776.666
Providing and laying non pressure NP2 class
29 J-4b hume/RCC RM 3769.00 9.000 9.000

30 K-9 Laying of 80 MM thk Paver Blocks of M30 SQM 942.00 148.350 148.350
31 NA Providing and fixing galvalume sheet SQM 853.00 832.320 832.320
Providing and laying Road Metal of 60-40 under RCC
32 NA Floor CUM 3298.00 504.350 86.001 590.351

33 NA Providing & Fixing of 16 Dia Anchor Fastner Nos 295.00 56.000 56.000
Authorized Signatory Total work done value(Rs.)
#NAME?

……………………………………………………..
Punjab Engineering Company(PD)
ANY (Project Division)
moraguri(Assam)
Bill No: PE/UKPIL/RA05

Date09.06.2017
Revised Date: 28.06.2017
T
VALUE OF WORK DONE
Since REMARKS
Previous Upto Date
Previous

1812566.10 0.00 1812566.10

762234.20 0.00 762234.20

58200.00 0.00 58200.00

73974.00 0.00 73974.00

896056.35 33642.97 929699.32

14909.18 0.00 14909.18

83076.00 0.00 83076.00

331575.20 0.00 331575.20

1120015.14 173697.85 1293712.99

1434689.52 9100.84 1443790.36

184018.82 319486.63 503505.45

458856.43 3222.24 462078.67

15200.84 110137.19 125338.03

1682842.62 201118.28 1883960.90

13420.25 0.00 13420.25

88000.00 0.00 88000.00

3067700.69 41551.79 3109252.48

408947.00 165164.45 574111.45

44199.90 39536.40 83736.30


911041.85 0.00 911041.85

1777318.58 0.00 1777318.58

172132.01 0.00 172132.01

7087.50 0.00 7087.50

0.00 0.00 0.00

13230.00 0.00 13230.00

12852.00 0.00 12852.00

11976.08 351427.94 363404.02


129300.08 270449.81 399749.89

33921.00 0.00 33921.00

139745.70 0.00 139745.70


709968.96 0.00 709968.96 PECOPD's Balipara Project

1663346.30 283630.47 1946976.77 Berger Project assigned rate

16520.00 0.00 16520.00


18148922.00 2002167.00 20151089.00

4119857