Академический Документы
Профессиональный Документы
Культура Документы
1. Tremie method
2. Pumping technique
3. Hydro valve method
5. Skip method
Tremie pipe, which upper end connected to a hopper and lower end continuously
submerged in fresh concrete, is used to place concrete at the exact location from
a hopper at the surface. The reason to immerse the tremie pipe lower end is to
prevent intermixing of both concrete and water. Tremie pipe typical arrangement
is shown in Figure-1.
Figure-1: Typical Arrangement of Tremie Method of Underwater Concreting
Process of Underwater Concreting using Tremie Method
There number of factors that should be considered during Tremie pipe technique
of underwater concreting:
Tremie Equipment
The tremie pipe might be configured in three different ways such as constant
length that is raised during concreting, pipe with different sections which
dismantled during concreting and telescope pipe.
An aluminum alloy pipe can adversely affect the concrete due to chemical
reactions between them therefore it should be avoided. The pipe should have an
adequate diameter to prevent blockage because of aggregate size.
The usual diameter is between 200- 300 mm and occasionally 150 mm and 450
mm could be used but aggregate size should be considered for example 19 mm
and 40 mm aggregate size is lower limit for 150 mm 200 mm pipe diameter
respectively.
Tremie seal
To avoid intermixing water and concrete in the pipe, a wooden plug of plat is
used to seal the end of the pipe. This prevents entering water in to the pipe and
keeps it dry.
After the pipe reach the intended position the concrete is poured and break the
seal. Then concrete flow out of the pipe and creating a seal by accumulating
around the lower end of the pipe
Placing the concrete
As soon as concreting began the pipe mouth should be submerged up to 1- 1.5
m into fresh concrete to prevent water entering the pipe. The concrete flow rate is
controlled by lowering and raising the pipe and either decrease or increase in
concrete discharge indicates the loss of the seal, therefore flow of concrete
should be continuous and carefully monitored.
Flow pattern
Two types of flow pattern are recognized namely, layered and bulging. The
bulging flow is desired because it displaced the concrete uniformly which leads to
lesser laitance deformation and flatter slopes.
2. Underwater Concreting using Pumping Technique
Underwater concreting using pumping technique is a developed version of
Tremie pipe and it is quicker method for concreting in areas that is difficult to
access such as under piers.
Pumping provide several advantages that Tremie pipe is lacking for example,
pouring concrete from mixer to formworks directly, solve blockages in the pipe
because concreting is through pumping instead of using gravitational force, and
risk of segregation is decreased. Figure 2 show typical pipeline configuration.
As soon as concrete placed in the upper of the pipe, both friction inside the pipe
and hydrostatic pressure is overcame by concrete weight. This leads to move
concrete slowly in the pipe and avoid segregation. A rigid tubular section is used
to seal the end of the hose. This method is not costly and quite simple. Figure 3
shows typical hydro valve arrangement.
Another type of valve is available which can be used to pour concrete at a depth
of 52m without immersing end of the pipe. The function of the valves is to permit,
restrict, stop the discharge of concrete and this method is the useful technique.
Figure 4 show Abetong-Sabema valve.
The Skip technique of underwater concreting is suitable for cases where a large
mass of concrete is required for stabilizing foundations and small amount of
concrete is needed for different locations. Shows opened and closed skips.
Figure-5: Skips for Underwater Concreting (a) Closed and (b) Opened
6. Underwater Concreting using Tilting Pallet Barge
This technique is useful for shallow water and the concrete is poured in thin
layers. Along the deck of the barge a tilting pallet is constructed upon which
concrete is spread uniformly and then fell into the water freely.
7. Underwater Concreting using Preplaced Aggregate
Concrete
Preplaced aggregate concrete method is quite good for cases where pouring
ordinary concrete is difficult or improbable. It includes placing aggregate in the
forms then injecting concrete into the bottom and filled the forms to the top.
To prevent trapping water and air, concreting is beginning from the bottom. That
is why it is necessary to position the tubes in the forms before placing the
aggregate.
Read More:
Inspection of Underwater Concrete Structures -Methods, Types and Purpose
Visual Inspection of Underwater RCC Structures -Tools and Limitations
Methods and Procedure for Repair of Underwater Concrete Structures