Академический Документы
Профессиональный Документы
Культура Документы
: PLP-HTF-P001
and
Flushing procedure Rev. No. : 0
TITLE:
Hydro test
and
Flushing procedure
DISCIPLINE : PIPING
Mr.Ramin
0 QA / QC
24-8-2019
TABLE OF CONTENTS
1.0 PURPOSE 3
2.0 SCOPE 3
3.0 REFERENCES 3
4.0 DEFINITIONS 3
5.0 PROCEDURE 3
5.1 GENERAL 3
7.0 RECORDS 9
APPENDICES
1.0 PURPOSE
This procedure outlines the flushing process and hydro testing requirements, to ensure that
the piping system are clean from debris or unwanted items and the integrity of the system is
proven.
2.0 SCOPE
This procedure is applicable for flushing and hydro testing of prefabricated piping spools and
completed piping in a system.
3.0 REFERENCES
ANSI B31.3 – Chemical Plant and Petroleum Refinery Piping
ANSI B31.4 – Liquid Petroleum Transportation Piping System
4.0 DEFINITIONS
Nil
5.0 PROCEDURE
5.1 General
5.1.1 Each hydro test procedure shall consist of the following :
a) Hydrostatic test flow sheet.
b) Testing details indicating the test pressure, testing medium and other test related details
i.e. filling points, vent, drain points and test limit points.
c) A copy of the hydro test flow chart (Refer to figure II) shall be extended to Client. This shall
be done at least two (2) days advance notice shall be given prior to the scheduled test date.
5.1.2 Hydro testing shall only be performed after the following activities are completed i.e.
a) Visual Inspection.
b) Post Weld Heat Treatment (PWHT).
c) NDT
5.1.3 The pipe support shall be completely installed.
5.1.4 All piping joints and surfaces shall be dry before the commencement of the hydro test.
5.1.5 All hydro testing activities shall be inspected by PILIN Site Supervisor and shall also be
witnessed by PILIN QC inspector and Client’s Representative.
5.2.2 The pressure recorder will be calibrated, and checked for accuracy prior to test. The calibration
certificate for the pressure test recorder shall be submitted to the QC inspector together with
5.2.3 The acceptable accuracy for the pressure recorder shall be ± 0.5% over the full range.
5.2.4 The range of the pressure gauge and pressure recorder to be used shall not be greater than four
5.2.5 Pressure release setting on the pressure relief valve shall be adjusted 10% higher than the
5.3.1 All pipe work should be cleaned internally before testing. All valves, gasket, flanges, bolting,
fitting and other components shall be of the required specifications. All joints shall be exposed
5.3.2 All high points shall be provided with a valve which shall ensure all air removed from the line,
the low points shall be also fitted with a valve to facilities the draining of the line.
5.3.3 Prior to hydro test, all lines shall be flushed with clean water, from the high to the low point.
Prior to flushing, the pipe internal shall be visually inspected where practical to ensure that no
foreign materials which cannot be removed by flushing are left in the line. All ball valves shall
be in the open position and non-return valves defeated, all instrument accessories shall be
5.3.4 All block valves to instrument impulse line connections shall be closed prior to flushing.
5.3.5 Prior to flushing, all instruments exposed to damage by debris, i.e. control valves, orifice fittings,
PD meters, capacitance probes, etc. shall be removed and dummy spools to be installed until
the duration of the test is completed. Spools used shall be ANSI flanged and pipe of correct
5.3.6 At least one (1) day before flushing commences, PILIN Site Supervisor shall inform the QC
inspector of the line inspection. All details for lines inspections are to be highlight in the
5.3.7 Visual inspection shall be conducted by PILIN Site Supervisor, and to be witnessed by the QC
inspector to ensure the system installation is completed. The Visual Inspection Report shall be
5.3.8 Flushing shall be done in the presence of Site Supervisor and to be witnessed by QC inspector
5.3.9 Piping system shall be flushed with clean water with a velocity of 3 m/s for pipe diameter 2
inches and below, and lower velocity for pipe diameter greater than 2 inches.
5.3.10 After flushing, checks shall be carried out to ensure all non-return valves are still defeated.
Swing checks valves are opened and set all ball valve at half open position.
5.3.11 The Flushing Report (Appendix III) shall be prepared by PILIN QC inspector upon completion
of the flushing.
5.4.1 All piping system shall be tested in accordance with Client’s specifications and the latest edition
of ANSI B31.3 Refer to figure I for the Hydro test Schematic Diagram.
5.4.2 Prior to commencement of hydro testing, PILIN Site Supervisor shall submit an isometric
5.4.3 The piping system shall be subdivided into sub-systems for testing where necessary. The hydro
test flow sheet shall indicate the test limit points i.e. the location of block valves, and blind
5.4.4 Blind flanges shall be installed for equipment excluded from the hydro test. Blind flanges may
be installed with temporary tubing connection where necessary to by-pass the equipment.
The blind flanges shall be installed to the following equipment i.e. pumps, turbines, blowers
and compressors.
5.4.5 Pressure gauges, pressure transmitters and flow meter, along with the secondary piping
connection the instruments to the block valve at the equipment or primary piping shall be
5.4.6 Fresh water shall be used with the high volume low pressure pump to fill the system. The filling
points shall be at lowest point in the system.To prevent trapping of air or vapors in the system,
5.4.7 For stainless steel, the chloride content of the water shall no exceed 200 ppm.
5.4.8 All vent valves and other high point connections which serve as vents shall be opened during
5.4.9 After filling, the pumping system shall be shut off and disconnected from the system.
5.4.10 System under hydro test shall be adequately supported to withstand the test pressure and
5.4.11 External surfaces of the piping system shall remain dry during inspection whilst checking for
leak.
5.4.12 The pressure shall be raised gradually, with stops to allow the pressure to stabilize. The
pressurizing of the system shall continue until the required pressure is reached.
5.4.13 Caution shall be taken during pressurization to avoid surging effects. Pressurization and
depressurization will be done gradually (25% of the test pressure requirement per 15 min) at
all times.
5.4.14 The rate of pressurization shall be reduced when approximately 80 percent of the specified
5.4.15 The pump shall be shut off once the required test pressure is achieved.
5.4.16 Whilst holding the system at test pressure, the system pressure shall be released if it exceeds
the test pressure due to temperature variation. This shall be done by opening the bleed valve
5.4.17 Open the block valve leading to the pressure recorder after the system pressure is stabilized.
5.4.18 Sign the temperature chart and pressure chart before and after hydro test by the QC inspector.
a) The hydro test time shall commence when PILIN and Client Representative agreed the
system pressure is stable. The duration of the test shall be one (1) hour for flanges rated at
b) The test duration for flanges rated at 300 lbs and above, the test duration shall be two (2)
hours.
5.4.19 The pressure test Report (Appendix IV) shall be prepared by PILIN QC inspector upon
Any leak in flange connections, bolting shall be carefully and gradually tightened in proper
sequence to prevent uneven tightening. If leak occurred in the weld joint the water shall be drained
5.6.1 After hydrostatic testing of the system is completed satisfactorily, care should be taken during
depressurization so as to avoid any surging effects. Tested system shall be completely drained
5.6.2 After the system has been depressurized, all vents shall be opened before the system is drained
and shall remain opened during draining to prevent vacuum effect in the system.
5.6.3 The system shall be completely drained. Compressed air shall be used to blow dry the system.
5.6.4 All spades, blind flanges, etc installed for testing shall be removed and pressure relieving
devices replaced.
5.6.5 Upon completion of test, the system shall be reinstated to its designed conditions.
6.1.1 During pressure build-up, shall take suitable precaution to prevent building up of excessive
6.1.2 Pressurization of the system shall be done in an increment of 25% of the required test pressure
per 15 min. to avoid over pressurization of the system and to allow stabilization of the test
6.1.3 The test area shall be cordoned off and provided with warning sign boards “CAUTION!
Hydrostatic Test in Progress”, also warning signs shall indicate the date and duration of test,
6.1.4 PIPIN shall ensure that the correct pressure rating for all ancillary fittings used (i.e. temporary
piping, hoses, blanks, etc) can withstand the flushing and pressure test.
6.1.5 All system testing will be carried out in accordance with the applicable codes, and client’s
specification requirements.
6.1.6 No tightening of bolts/nuts to be carried out during the stabilization of the required pressure in
the system.
7.0 RECORDS
APPENDICES
REQ. NO. :
INSPECTION REQUISITION
REQUEST BY : LOCATION :
REQ. NO. :
PROJECT :
SYSTEM TESTED :
………………………………………………………………
ACCEPTED REJECTED
REMARK :
NAME
DATE
QCP-10 Rev-0
Appendix III
PACKAGE NO. /
REPORT NO.
FLUSHING REPORT
PROJECT
CLIENT
PROJECT NO.
SYSTEM FLUSHED
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
18.
19.
20.
21.
22.
REMARKS :
NAME
DATE
QCP-10 Rev-0
Appendix IV
PRESSURE TEST REPORT
PROJECT NO : REPORT NO :
Start Finish
Others : Time :
Condition :
Date :
The above mentioned items / lines were listed and accepted / rejected by :