State Finished
Completed on Monday, April 15, 2019, 1:36 PM
Time taken 4 mins 47 secs
Points 5.00/5.00
Grade 10.00 out of 10.00 (100%)
Question 1
Correct
1.00 points out of 1.00
Flag question
Question text
Monitoring and control processes should occur _________ while the project work is being
executed.
Select one:
a. weekly or bi-weekly
b. continuously and continually
c. monthly
d. at each milestone
Question 2
Correct
1.00 points out of 1.00
Flag question
Question text
Except in extreme cases, the evaluation of success or failure is ________ because time and cost
to complete the project are _________.
Select one:
a. Subjective; estimates
b. Done by the project manager; fixed
c. Objective; inflexible
d. Done by the project team; set by them
Question 3
Correct
1.00 points out of 1.00
Flag question
Question text
Question 4
Correct
1.00 points out of 1.00
Flag question
Question text
During the system investigation stage, __________ studies are done to determine if the
hardware, software, and communications components can be developed and/or acquired to
solve the business problem.
Select one:
a. Economic feasibility
b. Technical feasibility
c. ROI
d. NPV
Question 5
Correct
1.00 points out of 1.00
Flag question
Question text
The ________ identifies all work or activities that need to be performed, the schedule of work,
and who will perform the work.
Select one:
a. Business case
b. Project plan review
c. Statement of work
d. Work breakdown structure