Академический Документы
Профессиональный Документы
Культура Документы
ŝƐƚƌŝĐƚ:ƵĚŐĞ
.$5$13853$5*$1$&(175$/'221+$5,':$552$'7(+6,/ &21&(378$/3/$1
ĞŚƌĂĚƵŶ
',675,&7'(+5$'81877$5$.+$1'
1. INTRODUCTION
The objective of the study is to carry out Environmental Impact Assessment (EIA) for the
proposed project to meet the environmental compliance laid down by the Ministry of
Environment and Forest (MoEF), Govt. of India. The scope of the study would be as per
the EIA guidelines outlined by the MoEF for new construction project.
3.0 CONNECTIVITY
The Project site is well connected to the Major National highways NH-72 and NH-
72A, which is at the distance of about 150 m, N and 1.4 km, W from the project site.
Almost all the surrounding and nearby areas are connected with network of roads.
Dehradun Railway Station is around 750 meter in West direction. Google image
showing location and connectivity of project site is as given below (Ref, fig.2).
The total population of the project will be approx. 3678 persons and floating in nature.
Details of population are given below in Table -3.
POPULATION
The water supply for the propsoed project during operation phase will be sourced
from water supply department of Dehradun. The total water demand works out to
approximately 298 KLD. After recycling and reuse of 236 KLD treated water, the net
fresh water requirement will be 62 KLD, which works out to 21.34% of estimated total
water demand. Details of daily water requirement, waste water generation & reuse of
treated water are given below in Table 4 & 4.1 and water balance diagram is given in
Figure-5. below.
TOTAL
POPULATION/ RATE IN
QTY IN
AREA/UNIT LTS
KL
NON RESIDENTIAL (Working Population )
DOMESTIC 3343 15 50.15
FLUSHING 3343 30 100.30
VISITORS
DOMESTIC 334 6 2.01
FLUSHING 334 9 3.01
TOTAL POPULATION 3678
GARDENING 4554.0 1 4.55
CAPACITY OF STP
WATER FLOW TO STP (DOMESTIC) 80% 49.92
WATER FLOW TO STP (FLUSHING) 100% 103.31
TOTAL WASTE WATER GENERATION 153.23
REQUIRED CAPACITY OF STP - 120% 183.88
SAY 180
Construction phase:
Quantity of sewage generated during the construction phase will be negligible and
proper management will be done by providing mobile toilets. Septic tank & soak pit
will be provided on site for treatment.
Operational Phase:
Sewage generated during operation phase would be approx. 153 KLD. Capacity of
onsite STP is 180 KLD.
Solid waste would be generated both during the construction as well as during the
operation phase. The solid waste expected to be generated during the construction
phase will comprise of excavated materials, used bags, bricks, concrete, MS roads,
(Source: The solid waste generation has been calculated @ 0.2 kg per capita per
day basis ad per guideline of (CPHEEO) manual.)
The power supply shall be supplied by Uttarakhand Power Corporation Ltd. The
estimated electrical demand load & proposed power back to be used during power
failure shall be as per details given in Table:6 below.
POWER
Electrical - Demand Load 2000 KW
Power Back Up - DG Sets 3030 KVA
DG Stack Height (6M above Tallest Tower) 26.10 M
There is provision of 3030 KVA of DG sets for power back up in the Project. The DG
sets will be equipped with acoustic enclosure to minimize noise generation and
adequate stack height for proper dispersion.
The storm water will pass through the desilting chamber/oil& grease separator before
finally discharging to percolation tank. Design details of Rain Water Harvesting
structure are given in the table 7 & Figure 8 below
For basement parking, the rainwater from ramps will be collected in the basement
storm water storage tank. This water will be pumped out to the nearest external
storm water drain
Total of 07 Rain Water Harvesting pits are proposed within the project premises.
Total green area measures 4554 m2 i.e. 17.3% of the total plot area. Approx 50% of
area would be used for peripheral tree plantation, road side plantation & remaining
area would be used for plantation of shrubs, lawn, and ground cover. There are
several trees which will be planted along the sides of the Project boundary. For tree
plantation preference will be given to local tree with large leafs & dense foliage for
shading & reduction of air & noise pollution. The plant species would be selected
from the list given below:
For smooth circulation & reduction of pollution separate entry & exits with gates of
adequate sizes are planned for the vehicles & also for the movement of fire engine.
Provision for car/vehicle parking is planned in the basements. Apart from peripheral
roads for vehicular movement internal roads/pavements are planned for traffic free
movement of pedestrians. Details of parking provision are given in table:8
13.1 Seismicity
Based on the tectonic features and records of earthquake, a Seismic Zoning map
has been developed for the country by Bureau of Indian Standard (BIS). The area
under study falls in Seismic Zone-IV. Suitable seismic coefficients in horizontal and
vertical directions respectively, will be adopted while designing the structures. The
structural design shall be vetted by the agency nominated by local body.
Earthquake resistant construction techniques will also be used.
Increased traffic generation due to project (no. of parking space proposed for the
project is 867) is not going to cause significant increase in atmospheric
concentration of gases and will not result in heat island formation as adequate
landscaping has been provided.
17.0 PROJECTCOST
The total construction cost of the proposed project is approximately Rs. 182 Crore.