INDONESIA BRANCH
(Decoration engineering work standard)
(Version 1.0)
Editor :
Reviewer :
Approver :
Time Issued :
Decoration engineering work standard
Table of Contents
I. KEY POINTS PROCEDURES AND ACCEPTANCE CHECK...................................... 4
1.1. Main Procedures and Qualified acceptance Check Work Flow ........................... 4
1.1.a. Decoration Fitting Main Procedures ............................................................ 4
1.1.b. Main Check Procedures Work Flow ............................................................ 4
1.1.c. Main Procedures and Qualified Check Management ................................. 5
1.2. Plaster Engineering ................................................................................................... 6
1.2.a. Procedures Description.................................................................................. 6
1.2.b. Project Acceptance Check before Plastering Work .................................... 6
1.2.c. Precautions for Quality Standard ................................................................. 6
1.3. Toilet and Balcony Waterproofing Works .............................................................. 7
1.3.a Procedures Description................................................................................... 7
1.3.b Waterproofing pre-construction Acceptance Check ................................... 7
1.3.c Quality standards and Precautions ............................................................... 7
1.4. Railing Installation.................................................................................................... 8
1.4.a. Railing Pre-installation Acceptance Check Work ....................................... 8
1.4.b Quality Standard and Precautions ................................................................ 8
1.4.c Finished Product Protection ........................................................................... 8
1.5. Ceiling Engineering .................................................................................................. 8
1.5.a Work Procedures Description ........................................................................ 8
1.5.b Pre-ceiling Acceptance Check Works ........................................................... 9
1.5.c Quality Standard ............................................................................................. 9
1.6. Wall Gypsum Board Engineering.......................................................................... 10
1.6.a Procedures Description................................................................................. 10
1.6.b Gypsum Board Pre-construction Acceptance Check Project ................... 10
1.6.c Quality Standard ........................................................................................... 11
1.7. Wall Brick Construction......................................................................................... 11
1.7.a Pre –laying Wall Brick Acceptance Check Work ....................................... 11
1.7.b Quality Standards and Precautions ............................................................ 11
1.8. Aluminum Alloy Door and Window Installation ................................................. 12
1.8.a. Door And Window Pre-Installation Acceptance Check Works ............... 12
1.8.b Quality standards and precautions ............................................................. 12
1.8.c Finished Product Protection ......................................................................... 14
1.9. Interior Door, Entrance Door ................................................................................ 14
1.9.a Door Pre-Installation Acceptance Check Work ......................................... 14
1.9.b Quality Standards And Precautions ............................................................ 14
1.10. Wooden Skirtboard Installation .......................................................................... 16
1.10.a Skirtboard Pre-Installation Acceptance Check Works ........................... 16
1.10.b Quality Standard and Precautions ............................................................ 16
1.11. Emulsion Paint Construction ............................................................................... 16
1.11.a Emulsion Paint Preconstruction Acceptance Check Works .................... 16
1.11.b Quality Standard and Precautions ............................................................ 16
1.12. Floor Tile Construction ........................................................................................ 17
1.12.a Floor tile Pre-pave Acceptance Check Works .......................................... 17
1.12.b Quality Standard and Precautions ............................................................ 17
II. DETAILED CONSTRUCTION REQUIREMENTS AND PRECAUTIONS ............. 18
2.1. Requirements and Precautions .............................................................................. 18
2.2. On-Site Common Problems and Treatment Measures ........................................ 19
III. ANNEX ............................................................................................................................. 27
I. KEY POINTS PROCEDURES AND ACCEPTANCE CHECK
Specific appendix details: (CSJ Meikarta Project residence hand over operation standard rule book)
Decoration engineering work standard
Special note: The project department is required to give priority to the bathroom and
balcony waterproof. The upper layer of the bathroom and balcony waterproof coating
construction is completed, and all the leaking points are processed before the ceiling of
the next layer can be worked.
3 Seam height difference 1mm Check with steel ruler and feeler
i. Before installing the keel: whether the wall verticality, flatness, clearance size, wall
internal and external corners meet the requirements, if it is not qualified, it needs to be
polished.
ii. Whether the pre-embed of water and electricity acceptance check is completed.
iii. Before sealing the gypsum board: whether the mortar level acceptance check meets the
requirements
3 Seam height difference 1mm Check with steel ruler and feeler
Wall thickness after
4 2mm
completion
Allowable
No Work Items Deviation Testing Method
(mm)
Door and window frame two ≤2000mm 2 Check with a steel tape
1 opposite angle line length measure, angle
>2000mm 3
difference measure tools
Window sill and frame overlap Check with a depth
2 1
width difference gauge or a steel ruler
Casement
The height difference of the
window Check with wire and
3 transverse end angle of the adjacent 2
steel ruler
hinge of the same door and window
Hinge area Hook with a 100N
≤40N
Door and window ≤1.5m2 spring balance
4 hinge opening 5 times average
Push-pull Hinge area
force limit ≤60N opening and closing at
hinge >1.5m2
the hand
Door and window sash parallel to Check with 1m steel
5 2
frame or adjacent hinge ruler
Door and window frame (including splicing Use 1 set of measure
6 2
materials) straightness and side verticality board
Door and window frame (including splicing Check with 1m level
7 1.5
materials) level ruler and wedge feeler
Check with steel ruler
8 Door and window frame elevation 5 and compare with the
reference axis
Center distance of double-layer door and window,
9 outer and inner frame (including splicing 4 Check with steel ruler
materials)
1.8.c Finished Product Protection
i. Covering the outer surface of the profile and glass with a plastic film
ii. Prevent some destructive behaviors and repair damaged plastic film in time
iii. Place it tightly and neatly without leaving gaps to prevent it from moving during shipping
iv. The frame material that has been mounted on the wall must be covered with a protective
film to prevent the cement from splashing on the frame surface, causing the surface of the
profile to be corroded.
masonry plastering。
1 Plastering
2. After the masonry plastering and gypsum board are completed, the
vertical flatness sub-package must be 100% measured on the wall. QC
team of the project department checks and reviews all.
1. The bathroom tile and the painted surface are constructed with a height
difference of 10mm (the tile surface height), and the putty is slanted to
Toilet and
the side.。
2 Balcony
Waterproofing 2. The installation company must distribute the floor string of pipe
hanging hole twice. Cannot use the iron wire to test the water test. The
base should be flat
1. All switch boxes of the installation company must be upright, the
installation height of switches, sockets, bathroom hot and cold water
The ceiling corner gypsum board adopts a 45° corner bending angle
4 Ceilings pattern to ensure that the corner is straight and flat, saving the finished
corner strip
Before the gypsum board is installed, it must be dotted to ensure the
Wall gypsum
5
board verticality of the wall.。
1. The door frame closing edge line is straight, and the skirtboard and the
Interior door
and entrance door sills are neat, level, and artistic.。
8
door
2. The toilets reverse ridge width is widened to be level with the
installation
skirtboard. The door frame falls on the ridge。
Skirtboard
9 Apply putty joints on skirtboard。
installation
Before the wall putty then paint construction, the textured paper must be
Emulsion paint
10 attached to the aluminum alloy door frame, window frame and door
construction
frame.
Floor tile construction is strictly in accordance with the layout drawing
Floor tile If the floor tile is finished, if there is any follow-up maintenance work, it
11
construction is necessary to lay cardboard and membrane cover on the tile surface. The
relevant tools and materials of the maintenance team must be concentrated
Kitchen
Bench
Aluminum
alloy
installation
The ceiling height is 2200, and the Appropriate adjustment of the ceiling
aluminum alloy window is 2260. The elevation, the ceiling must not be lower
ceiling is located under the aluminum than the bottom of the aluminum alloy
window. Difficult to close frame
Indoor door
Riser
Hanging hole
requirements。
Toilet Wall The height difference is retained, and the
tiles putty is glued to the beveled edge.。
Switch box
opening
design requirements.。
Ceiling
gypsum
board
External
corners
Tiles
Paving
Indoor and
outdoor door
area detailed
practice
Metals
Aluminum alloy window positioning is
Window
not uniform
Area
Alloy door
Aluminum alloy door centering installation.
area
Finished
product
Protection
The floor tiles are seriously worn, and The last construction of the floor tiles is
the aluminum alloy windows and covered with paper sheets after the
railings are seriously polluted.。 construction is completed, and the
aluminum alloy windows, wooden doors
and railings are covered with membrane
cover.
III. ANNEX