CHINA CONSTRUCTION ENGINEERING FOURTH DIVISION

INDONESIA BRANCH
(Decoration engineering work standard)

(Version 1.0)

Editor :

Reviewer :

Approver :

Time Issued :
Decoration engineering work standard

Table of Contents
I. KEY POINTS PROCEDURES AND ACCEPTANCE CHECK...................................... 4
1.1. Main Procedures and Qualified acceptance Check Work Flow ........................... 4
1.1.a. Decoration Fitting Main Procedures ............................................................ 4
1.1.b. Main Check Procedures Work Flow ............................................................ 4
1.1.c. Main Procedures and Qualified Check Management ................................. 5
1.2. Plaster Engineering ................................................................................................... 6
1.2.a. Procedures Description.................................................................................. 6
1.2.b. Project Acceptance Check before Plastering Work .................................... 6
1.2.c. Precautions for Quality Standard ................................................................. 6
1.3. Toilet and Balcony Waterproofing Works .............................................................. 7
1.3.a Procedures Description................................................................................... 7
1.3.b Waterproofing pre-construction Acceptance Check ................................... 7
1.3.c Quality standards and Precautions ............................................................... 7
1.4. Railing Installation.................................................................................................... 8
1.4.a. Railing Pre-installation Acceptance Check Work ....................................... 8
1.4.b Quality Standard and Precautions ................................................................ 8
1.4.c Finished Product Protection ........................................................................... 8
1.5. Ceiling Engineering .................................................................................................. 8
1.5.a Work Procedures Description ........................................................................ 8
1.5.b Pre-ceiling Acceptance Check Works ........................................................... 9
1.5.c Quality Standard ............................................................................................. 9
1.6. Wall Gypsum Board Engineering.......................................................................... 10
1.6.a Procedures Description................................................................................. 10
1.6.b Gypsum Board Pre-construction Acceptance Check Project ................... 10
1.6.c Quality Standard ........................................................................................... 11
1.7. Wall Brick Construction......................................................................................... 11
1.7.a Pre –laying Wall Brick Acceptance Check Work ....................................... 11
1.7.b Quality Standards and Precautions ............................................................ 11
1.8. Aluminum Alloy Door and Window Installation ................................................. 12
1.8.a. Door And Window Pre-Installation Acceptance Check Works ............... 12
1.8.b Quality standards and precautions ............................................................. 12
1.8.c Finished Product Protection ......................................................................... 14
1.9. Interior Door, Entrance Door ................................................................................ 14
1.9.a Door Pre-Installation Acceptance Check Work ......................................... 14
1.9.b Quality Standards And Precautions ............................................................ 14
1.10. Wooden Skirtboard Installation .......................................................................... 16
1.10.a Skirtboard Pre-Installation Acceptance Check Works ........................... 16
1.10.b Quality Standard and Precautions ............................................................ 16
1.11. Emulsion Paint Construction ............................................................................... 16
1.11.a Emulsion Paint Preconstruction Acceptance Check Works .................... 16
1.11.b Quality Standard and Precautions ............................................................ 16
1.12. Floor Tile Construction ........................................................................................ 17
1.12.a Floor tile Pre-pave Acceptance Check Works .......................................... 17
1.12.b Quality Standard and Precautions ............................................................ 17
II. DETAILED CONSTRUCTION REQUIREMENTS AND PRECAUTIONS ............. 18
2.1. Requirements and Precautions .............................................................................. 18
2.2. On-Site Common Problems and Treatment Measures ........................................ 19
III. ANNEX ............................................................................................................................. 27
I. KEY POINTS PROCEDURES AND ACCEPTANCE CHECK

1.1. Main Procedures and Qualified acceptance Check Work Flow

1.1.a. Decoration Fitting Main Procedures


Measure structural main parts real quantity and qualified acceptance check  clean up the
floor  measuring boundaries line  build brickwork  Quantity measure and qualified
acceptance check of the brickwork  set the pipeline and power line embedded slot/notch (the
exposed riser of the balcony must be installed after all wall processes are completed). 
Qualified acceptance check the wire line notch in plastering area in time  toilets and
waterproofed balcony (qualified closed water test)  install the balcony and stairs
handrail/railing  ceilings  wall surface plasterboard  mount the door case and window
frame (close edges and openings)  ceiling and wall putty  ceiling and wall paint  floor
tile  Entry doors, metals, and sanitary, etc installation Owner Handover Qualified
acceptance Check.

1.1.b. Main Check Procedures Work Flow

Specific appendix details: (CSJ Meikarta Project residence hand over operation standard rule book)
Decoration engineering work standard

1.1.c. Main Procedures and Qualified Check Management


Decoration engineering work standard

1.2. Plaster Engineering

1.2.a. Procedures Description


Basic cleaning  water moist  vertical hanging, square case, plastering cake  do corner
guard  smearing cement to windowsill  pour wall vein  swing starch, hanging net, skirt
to flat layer (levelling)  repair reserved holes, electric box notch, boxes, etc  Put floor
surface cover  maintaining.

1.2.b. Project Acceptance Check before Plastering Work


Whether the wall verticality, flatness, and mortar filling level meets the requirements;
whether the water and electricity notch has completed.

1.2.c. Precautions for Quality Standard


i. The variety and quality of the materials used must meet the design requirements. The
plaster layer must be firmly bonded collectively, without delamination, empty space, no
defects such as burst mortar and cracks in the surface layer.
ii. The surface is smooth and clean, the joint is level, the corner line is straight and distinct.
iii. Openings, slots, and boxes are the correct size, upright, neat, smooth, and plastering at
the back of the pipeline is smooth.
iv. The width and depth of gutter bead is not less than 10mm, neat and uniform
v. The scaffolding tube hole on the brick wall must be blocked with hard mortar; the water
and electricity duct line on the wall pass in/out are installed in the line boxes and the line
pipe, and the pipe hole is sealed tightly.
vi. The base layer should be clean, free from dust and oil. Before construction, the wall
surface must be brushed from the dust and be moistened with water and the interface
chemical agent should be applied.
vii. When making mortar cake on the wall, you must measure the clearance size of the room
then carry out the square case to ensure that the size of the room does not appear bigger
or smaller after the room is finished.
viii. The thickness of one plaster should not be too thick to avoid the mortar falling and
cracking due to excessive plastering.
ix. It is strictly forbidden to sand emerging and crack in the surface layer of the plastering
works. The plaster layer should be firmly bonded between the plaster layer and the
substrate, and there is no defect such as empty space, delamination, etc.
x. The internal and external corner of the plastering wall are straight and upright, inspect
focus on the ceiling to the corner formed by two walls of are checked straight. The
inspection method is visual inspection and tie line survey. The parts that are not straight
to the corner must be reworked. The plastering wall must be level (flat) and smooth, the
wall surface is free of smears, and focus check the plastering surface is flat: limit 150mm
from the ground (check with two meters guiding ruler, check the verticality is 2mm)
Allowable
Number Project Testing Method
deviation (mm)

1 Facade Verticality 4 Use 2 m verticality ruler test


2 Surface Flatness 4 Use 2 m verticality ruler test
3 Corner Uprightness 4 Use right corner tester

1.3. Toilet and Balcony Waterproofing Works

1.3.a Procedures Description


i. Waterproof material 1st party assign the brand, 2nd party procurement and construction
ii. Work procedures: first clean the ground, remove all mortar on the ground, clean the surface
dust, brush a layer on the ground with plain cement slurry, waterproof twice, total thickness
2mm, bathroom shower height 1.8 m, the other 1.2 m, all around the balcony is 30 cm.
iii. A 24-hour water closed test is required after the completion of the pipe hanging tunnel and
after the waterproof construction is completed.
1.3.b Waterproofing pre-construction Acceptance Check
i. Acceptance check whether the hanging tunnel qualified, conduct the first closed water test
ii. Whether the substrate is cleaned and sorted out, whether the wall surface is flat/level, and
whether the wall feet are rounded as required
iii. Whether it is cleaned from cement mortar
iv. After the completion of the 24-hour water closed test, whether the repair of the leaking
point is completed and tested again
1.3.c Quality standards and Precautions
i. The performance of waterproof materials should meet the design requirements and the
relevant local standards, and should have a product certificate.
ii. The surface of the base layer should be flat and free of defects such as empty drums,
sanding, cracking, etc.
iii. Smear the waterproof layer coating evenly, the thickness meets not less than 2mm, and it
is simultaneously applied by brushing all over.
iv. Smear the coating on surface without bubble, no flow, flat without bumps, the pipe joints,
sanitary ware foundation, floor drains, and drain joints are tightly closed and not leaking.
v. Partial waterproof coating layer must be completely covered fiberglass reinforcing mesh.
No bubbles or adhesion to the wall surface after completion.
vi. After the waterproofing is completed, the water closed test run without leak for 24 hours.

Special note: The project department is required to give priority to the bathroom and
balcony waterproof. The upper layer of the bathroom and balcony waterproof coating
construction is completed, and all the leaking points are processed before the ceiling of
the next layer can be worked.

1.4. Railing Installation

1.4.a. Railing Pre-installation Acceptance Check Work


Whether there is a concrete retaining ridge under the railing, Whether the fixed point has a
concrete structure or a structural column as a fixed point, the water retaining ridge must not
have a large height difference.
1.4.b Quality Standard and Precautions
i. The cutting of all components should be accurate and the allowable deviation of the
components length is 1mm.
ii. The component must be checked for straightness before it is unloaded, otherwise it must
be straightened.
iii. Welding rod or wire should be used varieties suitable for welding materials, and should
have factory certification
iv. The position of the component must be placed accurately during welding
v. The welding points between the components during welding shall be firm, the welds shall
be full, the welding waves on the surface of the weld shall be uniform, and there shall be
no undercuts, unwelded, cracks, dross, welds, burn through, arc abrasions, craters. Defects
such as needle-shaped pores, no spatters in the weld zone.
vi. After the welding is completed, the welding slag should be knocked clean
vii. After the components are welded and assembled, they should be smoothed and polished
with grind hand tools gently to make the appearance smooth and clean.
viii. The deviation of each layer level of railings shall not exceed 4mm, and the deviation of
the height difference of adjacent railings shall not exceed 3mm.
1.4.c Finished Product Protection
i. When installing banisters, protect the hand railings, stair steps, and finished items within
the operating range
ii. Do not smear mortar and release debris the installed railings.
iii. After the banisters is installed, it should be wrapped and protected in time.
iv. In order to prevent pollution, the finished railings should be covered with a protective film
during the cross-operation process.

1.5. Ceiling Engineering


1.5.a Work Procedures Description
i. Provide the gypsum board material;
ii. Purchase materials: 40*40 square light steel keel, nails, gypsum board self-tapping screws,
metal edge strips, corner guards, seam joints, putty, various construction tools, etc.
iii. Construction work flow: Define the reference axis, determine the elevation of the ceiling,
put the line, fix the keel around the wall, first make a level of ceiling, then do the primary
keel of the ceiling, the secondary keel, the primary and secondary keel must avoid the
lamps, fire pipes, fire sprinklers. After the installation of the main keel, the level of the
main keel is fully leveled, the elevation is verified, and the relevant personnel are asked
to do the concealed works acceptance check.
iv. Install the gypsum board: first install the gypsum board of the first-level ceiling, and
process it into a 90° gypsum board according to the site size. Fix the bottom first, make
sure that the upper part is fixed after flattening, and install the gypsum board of the first-
level ceiling gypsum board before installing the top gypsum board. The top of the top
gypsum board is left with 1cm side seam and metal partitioning joint is installed. The
distance between the self-tapping screws of the upper gypsum board is 200*200 in the
vertical direction and 600*600 in the horizontal direction. After the installation of the
gypsum board is completed, the inspection is completed.
v. Ceiling board joints and scrape of putty, all the cut in of gypsum board must be connected
with 10cm wide wave fiber mesh cloth. This works only scrape cut in, leftovers, and the
gypsum board does not scrape putty. After the project is completed, the sandpaper is used
first. Then polish with fine sandpaper, sweep away the surface dust, and the ceiling is
finished.
1.5.b Pre-ceiling Acceptance Check Works
i. Before installing the keel: whether the flatness of the first floor, the elevation of the beam
base and the flatness meet the requirements, if it is not qualified it needs to be polished.
ii. Whether the acceptance check of the water and electricity lines are completed, whether
the pipeline pressure test is completed.
iii. Before sealing the gypsum board ceiling: Accepting the flatness of the keel and whether
the elevation meets the requirements
1.5.c Quality Standard
A. Master Control Items
i. The ceiling elevation, size and shape should meet the design requirements (detailed master
drawing)
ii. The material quality, variety, style and specifications of the veneer material should meet
the design requirements (detailed master drawing)
iii. Suspenders, keels and plasterboard must be installed securely
iv. The material quality, specification, installation spacing and connection method of the
boom and keel shall meet the design requirements. The metal hanger and keel shall be
treated with surface anti-corrosion treatment.
B. General Items
i. The surface of the gypsum board should be clean, the color should be consistent, and there
should be no bend, cracks and defects.
ii. The position of the lamps, smoke detectors, sprinklers, tuyere and other equipment on the
gypsum board should be reasonable and beautiful, and should be consistent with the veneer
interface.
iii. The joints of the gypsum board should be uniform, the corner joints should be consistent,
the surface should be flat, no bending, hammer marks.
C. Allowable Works Deviation
Allowable
Entry Works Item Deviation Testing Method
Gypsum Board

1 Surface Flatness 2mm Check with 2m ruler and feeler

2 Seam Straightness 3mm Pull 5m line check

3 Seam height difference 1mm Check with steel ruler and feeler

1.6. Wall Gypsum Board Engineering

1.6.a Procedures Description


i. Primary Material, Gypsum Board
ii. Secondary materials: finished bonding powder, blended with water in the field to form a
paste.
iii. Construction process: put the line, find the reference line, clean the wall, use the adjusted
adhesive to make the mortar (1m vertical and horizontal spacing), the thickness is 6mm,
check the flatness of the mortar, and Install the gypsum board, apply the adhesive on the
back of the cut gypsum board, the vertical and horizontal spacing is not more than 30cm,
and apply the adhesive around the gypsum board. After the wall of the gypsum board
completed, tap the 2m ruler.
iv. Wall joints, scrape putty, all joints must be connected with a 10cm wide box grid, this
engineering only scrape cut in, corner side, gypsum board does not scrape putty, after the
end of the work, first polish with sandpaper, After polish with fine sandpaper, after
smoothing, the surface dust is removed and the gypsum board construction is completed.
v. 6 cm of wall gypsum board lower part is plastered, this process is completed by the
masonry team. The wooden floor skirting and joint is completed by the skirting board
construction unit.

1.6.b Gypsum Board Pre-construction Acceptance Check Project

i. Before installing the keel: whether the wall verticality, flatness, clearance size, wall
internal and external corners meet the requirements, if it is not qualified, it needs to be
polished.
ii. Whether the pre-embed of water and electricity acceptance check is completed.
iii. Before sealing the gypsum board: whether the mortar level acceptance check meets the
requirements

1.6.c Quality Standard


i. Bonding materials need to provide product certification
ii. Gypsum board brand meets design requirements, product certification is required
iii. Gypsum board bonding is reliable
iv. Acceptance Check Criteria:
Allowable Deviation
Entry Works Item Testing Method
Gypsum Board

1 Surface Flatness 2mm Check with 2m ruler and feeler

2 Seam Straightness 2mm Pull 5m line check

3 Seam height difference 1mm Check with steel ruler and feeler
Wall thickness after
4 2mm
completion

1.7. Wall Brick Construction

1.7.a Pre –laying Wall Brick Acceptance Check Work


i. The substrate must be cleaned and free of dust, paint, loose residue and other attachments.
ii. Wall flatness and verticality meet the requirements
iii. Whether is there a large area of hollow cracking on the wall.
iv. Waterproof construction completed and passed acceptance check
v. Whether the water and electricity reserved hole is completed
1.7.b Quality Standards and Precautions
i. Brick wall laying is strictly arranged according to the drawings (detailed master drawing)
ii. The flatness of the wall tiles is checked with a 2 meter level. The fault cannot exceed 1
mm. The height difference between adjacent bricks must not exceed 0.5 mm, and the gap
straightness is 1 mm.
iii. The wall brick cracks are 1mm wide and must not exceed 2mm. The joints are even and
straight. Joint with special grout
iv. Control the wall brick empty hollow appearance less than 3%, 3% corner side single point
single lump empty hollow. The repairing lump is not empty hollow.
v. Wall brick bonding material needs to be firmly connected with the waterproof layer.
vi. External corner do wedge opening, putty is added with glue for joint
1.8. Aluminum Alloy Door and Window Installation
1.8.a. Door And Window Pre-Installation Acceptance Check Works
Retain the headroom size, uprightness of the opening, the verticality of the structural column
of the opening, and whether the flatness meets the requirements; whether the concrete
prefabricated block fixing point is set at the window reserved hole.
1.8.b Quality standards and precautions
A. Master Control Items
i. The variety, specification, size, performance, opening direction, installation position,
connection method and wall thickness of aluminum alloy doors and windows should meet
the design requirements. The anti-corrosion treatment and filling, sealing treatment should
meet the design requirements, anti-corrosion treatment and filling, sealing procedures
should meet design requirements.
ii. The installation of the alloy window frame and the sub-frame must be firm, the number
of the embedded parts, the position, the way of embedding, and the connection of the
frame should meet the design requirements.
iii. The sash must be installed firmly, it should be opened flexibly, tightly and without tilting,
and the sliding window sash must be protected against falling off.
iv. Between the aluminum alloy door and window frame and the non-stainless steel fastener
contact surface, it must be treated with anti-corrosion treatment; it is strictly forbidden to
use cement mortar as the blocking material between the door and window frame and the
wall.
v. The model, specification and quantity of door and window fittings should meet the design
requirements, the installation is firm, the position is correct, and the function meets the
requirements for use.
B. General Items
i. Aluminum alloy door and window sash installation should meet the following
requirements.
ii. The swing door and window sash is closed tightly, the gap is even, and the switch is
flexible. Push-pull sash switch force is not more than 60N.
iii. The sliding door sash is closed tightly, the gap is even, and the amount of overlap between
the hinge and the frame should meet the design requirements. The rubber sealing strip or
felt strip of the sash should be installed properly and must not be grooved.
iv. The automatic position of the spring door leaf is accurate, the opening angle is 90°±
1.5°, and the closing time is within the range of 6~10s.
v. Aluminum alloy door and window accessories are complete, the installation position is
correct, firm, flexible and applicable, to achieve their respective functions, correct and
beautiful.
vi. The gap between the aluminum alloy door and window frame and the wall is filled and
compact, the surface is level, smooth and free of cracks. The filling materials and methods
meet the design requirements.
vii. The surface of aluminum alloy doors and windows is clean, no scratches, bumps, no rust;
smooth surface, level, uniform thickness, no air holes
viii. Allowable deviation items: the difference between the length of the two opposite angle of
the door and window frame, the straightness of the door and window frame, the verticality
of the side, the horizontality, the horizontal frame elevation, etc., shall not exceed the
values specified in the following table.

Allowable
No Work Items Deviation Testing Method
(mm)
Door and window frame two ≤2000mm 2 Check with a steel tape
1 opposite angle line length measure, angle
>2000mm 3
difference measure tools
Window sill and frame overlap Check with a depth
2 1
width difference gauge or a steel ruler
Casement
The height difference of the
window Check with wire and
3 transverse end angle of the adjacent 2
steel ruler
hinge of the same door and window
Hinge area Hook with a 100N
≤40N
Door and window ≤1.5m2 spring balance
4 hinge opening 5 times average
Push-pull Hinge area
force limit ≤60N opening and closing at
hinge >1.5m2
the hand
Door and window sash parallel to Check with 1m steel
5 2
frame or adjacent hinge ruler
Door and window frame (including splicing Use 1 set of measure
6 2
materials) straightness and side verticality board
Door and window frame (including splicing Check with 1m level
7 1.5
materials) level ruler and wedge feeler
Check with steel ruler
8 Door and window frame elevation 5 and compare with the
reference axis
Center distance of double-layer door and window,
9 outer and inner frame (including splicing 4 Check with steel ruler
materials)
1.8.c Finished Product Protection
i. Covering the outer surface of the profile and glass with a plastic film
ii. Prevent some destructive behaviors and repair damaged plastic film in time
iii. Place it tightly and neatly without leaving gaps to prevent it from moving during shipping
iv. The frame material that has been mounted on the wall must be covered with a protective
film to prevent the cement from splashing on the frame surface, causing the surface of the
profile to be corroded.

1.9. Interior Door, Entrance Door

1.9.a Door Pre-Installation Acceptance Check Work


The clearance size of the door opening, the uprightness, the verticality of the structural
column of the opening, and the flatness meet the requirements; the threshold of the two sides
must be kept at the same level; after the decoration is completed, the thickness of the entrance
door must not exceed 13cm, and the thickness of the door threshold of the bathroom must not
exceed 12cm, the thickness of the bedroom doorsill must not exceed 10cm.
1.9.b Quality Standards And Precautions
A. Wooden door product acceptance check standard
i. No scratches, bumps, etc. on the surface of the entire door
ii. The color is consistent with the customer's requirements and there is no obvious color
difference, bright colors and clear wood grain
iii. The whole batch of doors has the same color and no obvious color difference. Meet
customer's gloss requirements.
iv. The surface of the paint has no sag, shrinkage, rising edge, wrinkled skin, and the line
corner is basically the same as the surface, without defects such as accumulation of
paint and abrasion.
v. The size of the door is consistent with the size of the opening.
vi. Wooden doors are uniformly colored on both sides, no significant difference
vii. No obvious processing marks on the surface of the coating, no coloring defects
viii. Produced according to drawings and processing techniques, real materials
ix. The wooden door should be flat, square, and warped.
x. The combination of product parts to parts should be tight, firm, seamless, steady
xi. The hinge installation is not skewed, the hole is drilled according to the mold, and the
position of the keyhole is accurate.
xii. Uniform linear shape, uniform groove depth, no buckling.
xiii. The door panel is evenly installed and meets the requirements. The door sills is installed
correctly and is not skewed.
xiv. The door is opened and flexible, no abnormal sound.
xv. The door sills and the wall are sealed with double-sided sealant, and then cut and
flattened after drying.
xvi. Set screws between the door sills and the wall, not less than 3 per meter
xvii. The same side sills should be on a flat surface, and the gap should be filled with sealant.
xviii. The threaded cut in must be flat and the set line bend is allowed to be 1 mm.
xix. After the door is closed, it is tightly combined with the sealing strip and does not sway.
B. Wooden Door Installation Acceptance Check Standard
Door sills installation:
i. The door set should be tightly connected, flat and without black seams; the fixed parts
should be locked; the diagonal of the door sills should be accurate, the tolerance is less
than 1 mm within 2 meters, and ≤1.5 mm for more than 2 meters;
ii. After the door is set, it should be three-dimensional horizontal and vertical, the tolerance
of verticality is +2 mm, and the horizontal straightness tolerance is +1 mm; the joint
between the door sills and the wall should have fixing screws (not less than 3 per length);
Socket installation:
The wire installation should be evenly coated with the door sills and the wall. The socket
interface should be flat, tight and seamless. After installation, the same side line cover is in one
level; when the wall is not flat, the sills interface must be flat. The line cover allows a tolerance
of 1 mm cambers. Apply fluid sealant to fill seam chink to handle the wire line cracks on the
wall.
Door installation
i. After the door leaf is installed, it should be flat and vertical, and the door leaf and the
exposed surface of the door sills are level; the door leaf is opened without abnormal noise,
and the switch is flexible and free.
ii. The gap between the door sills and the door leaf is 6 mm for the lower seam and 2 mm
for the other three sides; the tolerance is +0.5 mm for all the slits.
iii. After the door is closed, it is tightly combined with the sealing strip and does not sway.
Hardware:
i. The door hinge should be vertical and flat. The flat hinge should be slotted on the door
leaf and doorsills. The notch should be standardized. The size is the same as the hinge.
The tolerance of the three sides is +0.5. After assembly, flat and no chink. The hinge
should be opened. The hinge opening should be flexible. The hinge opening should be
flexible. The trigeminal hinge is mounted in the mold and the latch should be inserted
into place. Hinge fixing screws should be fully and straight, hidden in the hinge plane.
ii. The door lock slot should be accurate and standardized, and the size should be consistent
with the lock body and the lock piece; the door lock should be tightened and unlocked
without any abnormal noise; the accessories are fully installed, and the fixing screws
should be fully and straight.
iii. Suction, door closers, handles, etc. should be installed in the designated position, the
installation is firm, the fixing screws should be installed fully and straight, and the fittings
are good after installation.
Exterior:
i. The gap between the sills, the door line and the ground should be less than 3 mm, and
the gap is sealed with a waterproof sealant.
ii. After the whole door is installed, it should be leveled, open and flexible, the overall
result is good, no scratches.

1.10. Wooden Skirtboard Installation


1.10.a Skirtboard Pre-Installation Acceptance Check Works
Whether the skirting line position to be plastered and flatten, whether the corner is upright.
1.10.b Quality Standard and Precautions
i. The material quality, variety, specifications and color of the installed baseboard meet
the design requirements and current relevant standards.
ii. The wooden base skin must be tightly stick to the plywood, and no air bubbles should
appear.
iii. The gap between the baseboard and the door frame is ≤ 2 mm; the spacing between the
baseboard seams is ≤ 1 mm; the gap between the baseboard and the floor surface should
be in the range of 3 mm to 5 mm; the height difference of the baseboard buckle should
be ≤ 1 mm
iv. The skirtboard is installed with flat seams, the height is consistent, firm and no loose,
yin and yang angles are upright, the thickness of the wall is the same, straight up,
accurate-cutting angle.
v. The appearance quality of the baseboard must not be scratched, deformed, bumped, etc.,
the surface color is consistent, clean and tidy
vi. For good installed skirtboard, for gap with the wall over 1 mm must apply putty and
glue to close it.

1.11. Emulsion Paint Construction


1.11.a Emulsion Paint Preconstruction Acceptance Check Works
Whether the putty wall is polished flat; whether the gypsum board wall surface and the ceiling
joint are finished as required; whether the gypsum board surface is damaged or not repaired;
whether the wall surface is cracked.
1.11.b Quality Standard and Precautions
i. The type and color of materials used meet the design requirements
ii. The putty must be polished before the latex paint is applied. Paint construction can be
carried out after reaching the basic acceptance criteria
iii. The painted surface is the same color, it is not allowed to have quality defects such as seep,
chinking, falling powder, skin soda, peeling, snap color and so on.
iv. No current fall, hand touch smooth paint coating, no drop powder, Doors and windows,
lamps, furniture, etc. are clean, no paint marks.
v. The same room must use the same batch of paint

1.12. Floor Tile Construction


1.12.a Floor tile Pre-pave Acceptance Check Works
The base layer must be cleaned and free of dust, paint, loose residue and other attachments;
whether any unused reserved hole that is not blocked.
1.12.b Quality Standard and Precautions
i. Floor tile paving is strictly arranged according to the drawings
ii. Clean the surface starch, ground dust, etc. on the base layer with a temporary or wire brush,
and then clean the surface dust with a broom.
iii. The flatness of the floor tiles is checked with a 2 meter level. The fault shall not exceed 1
mm. The height difference between adjacent tiles shall not exceed 0.5 mm, and the flatness
of the gap shall be 1 mm.
iv. The width of the floor tile is 1mm, no more than 2mm, and the joint is even and straight.
Fill with special grout.
v. The floor tile empty hollow phenomenon is controlled within 3%, It is necessary to rework
the empty hollow on the primary passage. 3% single finger single lump corner side empty
hollow, the repair block is not empty hollow.
vi. The slope of the floor tiles paving with drainage requirements shall meet the drainage
requirements. Floor tiles paving with floor drains should allow water to drift out (a very
small degree slope) pointing to the floor drain, and the integration with the floor drain
should be tight and firm.
II. DETAILED CONSTRUCTION REQUIREMENTS AND
PRECAUTIONS

2.1. Requirements and Precautions


No Procedures Requirements
1. Balcony riser civil construction can be installed after completion of

masonry plastering。
1 Plastering
2. After the masonry plastering and gypsum board are completed, the
vertical flatness sub-package must be 100% measured on the wall. QC
team of the project department checks and reviews all.
1. The bathroom tile and the painted surface are constructed with a height
difference of 10mm (the tile surface height), and the putty is slanted to
Toilet and
the side.。
2 Balcony
Waterproofing 2. The installation company must distribute the floor string of pipe
hanging hole twice. Cannot use the iron wire to test the water test. The
base should be flat
1. All switch boxes of the installation company must be upright, the
installation height of switches, sockets, bathroom hot and cold water

outlets, sprinklers, etc. meet the design requirements.。


Installation
3
work 2. After the installation of the fire box is completed, the installation
company shall protect itself and determine the uniform height from the

ground after the installation of the fire box is completed.。

The ceiling corner gypsum board adopts a 45° corner bending angle
4 Ceilings pattern to ensure that the corner is straight and flat, saving the finished
corner strip
Before the gypsum board is installed, it must be dotted to ensure the
Wall gypsum
5
board verticality of the wall.。

Wall brick construction is strictly in accordance with the layout drawing

Wall brick (suggested with a grout);


6
construction
Bathroom wall brick and paint surface 10mm height difference (wall brick
height), putty and plastic bevel edge closing。
7 Aluminum The aluminum alloy door of the balcony is installed centrally. The inner
alloy door and side of the aluminum alloy window frame is installed 50mm away from
window the inner wall surface, the inner side of the window is 15mm, and the
installation
outer side is 5mm.。

1. The door frame closing edge line is straight, and the skirtboard and the
Interior door
and entrance door sills are neat, level, and artistic.。
8
door
2. The toilets reverse ridge width is widened to be level with the
installation
skirtboard. The door frame falls on the ridge。
Skirtboard
9 Apply putty joints on skirtboard。
installation
Before the wall putty then paint construction, the textured paper must be
Emulsion paint
10 attached to the aluminum alloy door frame, window frame and door
construction
frame.
Floor tile construction is strictly in accordance with the layout drawing

(suggested with a grout);

Floor tile If the floor tile is finished, if there is any follow-up maintenance work, it
11
construction is necessary to lay cardboard and membrane cover on the tile surface. The
relevant tools and materials of the maintenance team must be concentrated

in the cardboard area to avoid scratch damage to the tile surface.。

Finished Divide construction unit self-preservation, follow-up unit mutual preserve;


12 product
recount aluminum window, railing。
protection

2.2. On-Site Common Problems and Treatment Measures

Procedures On-site Error Practice Measures and Requirements


Entry door, The doorsills is level with skirting board,
indoor door paste textured paper on closing edge. Do
installation finished product protection

The thickness of the skirtingboard the


doorsill is different. Closing is not
artistic.

Kitchen
Bench

Carefully check the drawings, and make the


Kitchen Bench and piping pack have flatness and verticality of the kitchen bench
different size,tiles is difficult to close wall check during the plastering rebuild.

Aluminum
alloy
installation

The ceiling height is 2200, and the Appropriate adjustment of the ceiling
aluminum alloy window is 2260. The elevation, the ceiling must not be lower
ceiling is located under the aluminum than the bottom of the aluminum alloy
window. Difficult to close frame

Indoor door

Carefully check the drawings, do


construction of the masonry operation by
the door and threshold dimensions
The wall spacing is too small to
checking. Ensure that the subsequent
construct the threshold and cannot be
operations are carried out normally. If the
closed.
wall spacing is too small, the threshold
cannot be constructed. Joint design to solve.

Riser
Hanging hole

The back of water pipe hanging hole


The installation company must distribute
cannot be polished,bottom plate not
the floor string of pipe hanging hole twice.
smooth,Poor sensory quality
Riser,
Installation

After removing the riser, reinstall the riser


The balcony is not plastered,the riser after plastering and latex paint construction,
has been installed, cannot finish the and then install the riser after finishing the
entire area floor decoration. decorative surface in strict accordance with
the process.。

The opening and closing of the switch


socket is directly inside the fire hydrant and
Fire hydrant is not installed. All switch boxes must be
area pipeline upright and highly compliant with design

requirements。
Toilet Wall The height difference is retained, and the
tiles putty is glued to the beveled edge.。

There is a 10mm height difference


between the tiling area and the non-tiling
area

Switch box
opening

The opening of the gypsum board is


uniformly opened by the installation
Switch socket opening is too large,
company, and the decoration unit leaves the
difficult to close, and side-by-side switch
position of the wire. All the switch boxes
sockets are of different heights
must be upright and the height meets the

design requirements.。
Ceiling
gypsum
board
External
corners

Gypsum board cutting is not Gypsum board is cut to a 45 degree corner


standardized, the seam is too large before installation to ensure straight lines

Tiles
Paving

Strictly follow the layout of the


The site was not constructed according
construction drawing, communicate with
to the brickwork drawing, and the seams
the owner whether to use the joint grout。
were black.

Indoor and
outdoor door
area detailed
practice

Reverse ridge width is insufficient


The width of the reverse ridge of the
bathroom is widened to be level with the
skirtingboard。The door frame falls on the
reverse ridge

Metals
Aluminum alloy window positioning is
Window
not uniform
Area

The inner side of the aluminum alloy


window frame is installed 50mm away
from the inner wall surface, and the inner
side of the window is 10mm, and the outer
side is 5mm. (Detail Master Drawing)

Alloy door
Aluminum alloy door centering installation.
area

The aluminum alloy door is installed on


the inner side of the wall, and the height
difference between the door frame and
the wall in the edge area is unsuccessful
control.
Kitchen and
bathroom
waterproofing

The waterproof base layer is cleaned and


Waterproof base layer is not cleaned the cement mortar is R corner

Finished
product
Protection

The floor tiles are seriously worn, and The last construction of the floor tiles is
the aluminum alloy windows and covered with paper sheets after the
railings are seriously polluted.。 construction is completed, and the
aluminum alloy windows, wooden doors
and railings are covered with membrane
cover.
III. ANNEX

1. Attachment: "CSJ Meikarta Project Hardcover Housing Delivery Standard


Operating Regulations"
2. Figure: "CSJ Meikarta Project Fine Decoration Master Drawing"