JISIMAS SDN. BHD.

PROJECT TITLE: CADANGAN MEMBINA DAN MELABUH TUKUN TIRUAN DASAR LEMBUT PENGHALANG PUKAT TUNDA DI PERAIRAN DARO, MUKAH DI
NEGERI SARAWAK
CONTRACT NO.: PWD/HO/B076/2019
ID Task Task Name Duration Start Finish September 2009 October 2009 November 2009 December 2009
Mode 29 1 4 7 10 13 16 19 22 25 28 1 4 7 10 13 16 19 22 25 28 31 3 6 9 12 15 18 21 24 27 30 3 6 9 12
1 CADANGAN MEMBINA DAN MELABUH 77 days Sat 5/9/09 Fri 4/12/09
TUKUN TIRUAN DASAR LEMBUT
PENGHALANG PUKAT TUNDA DI
PERAIRAN DARO MUKAH DI NEGERI
SARAWAK
2 MILESTONE START 0 days Sat 5/9/09 Sat 5/9/09 5/9

3 PRILIMINARIES & GENERAL 21 days Sat 5/9/09 Tue 29/9/09


4 SUBMISSION OF DOCUMENT 7 days Sat 5/9/09 Sat 12/9/09
5 CONTRACTUAL& SAFTEY & HEALTH 7 days Mon 14/9/09 Mon 21/9/09
REQUIREMENT

6 CONSTRUCTION OF SITE OFFICE 7 days Mon 14/9/09 Mon 21/9/09


7 SITE PREPARATION AND CLEARING 7 days Tue 22/9/09 Tue 29/9/09
8 CONSTRUCTION OF ARTIFICIAL REEFS 57 days Fri 25/9/09 Mon 30/11/09
9 50 UNITS OF ARTIFICIAL REEFS& TESTING
56 days Fri 25/9/09 Sat 28/11/09
10 REEFS MARKING (NUMBERING) 1 day Mon 30/11/09Mon 30/11/09
11 TRANSPORTATION & DEPLOYMENT OF 3 days Tue 1/12/09 Thu 3/12/09
ARTIFICIAL REEFS

12 BARGE TRANSPORTATION, CRAWLER, 3 days Tue 1/12/09 Thu 3/12/09


CRANE& MOBILE CRANE

13 PROVIDE 2 NOS OF SPEEDBOAT 1 day Tue 1/12/09 Tue 1/12/09


14 PROVIDE 2 LICENSED DIVERS 1 day Tue 1/12/09 Tue 1/12/09
15 PPE, TOOLS& EQUIPMENT 1 day Tue 1/12/09 Tue 1/12/09
16 MOLESTONE FINISH 0 days Fri 4/12/09 Fri 4/12/09 4/12

Task External Milestone Manual Summary Rollup Critical Split


Split Inactive Task Manual Summary Progress
Milestone Inactive Milestone Start-only Manual Progress
Summary Inactive Summary Finish-only
Project Summary Manual Task Deadline
External Tasks Duration-only Critical

Page 1