Corporate Engineering PT Holcim Indonesia,Tbk Phone +62 21 8235687

Narogong Plant Fax +62 21 8234057

Report

KEY WORDS

FAT, Capacitor bank, IEC

Number: CE/13/E/1223
Authors: Agus Budiaji
Agus.aji@holcim.com

Date: November, 2013


MV Capacitor bank Factory Acceptance Test (FAT)
Title: at SAMWHA

Company: PT Holcim Indonesia,Tbk-Narogong plant


Project no.: 7000130595
Ordered by: PT Holcim Indonesia,Tbk
Copies to internal: Made Suartika, Reza Priatna, Abdul Kayi
, Raju Goyal, Mulyadi Rafiudin

SUMMARY

As per Supply Contract for MV Capacitor bank ( 2 x 6000 kVAR ) and Installation of
NR4 AFR Project, Samwha will supply 2 units MV Capacitor bank. The MV Capacitor
bank was manufactured according to IEC at their factory in Gyeonggi-do, South Korea.

To ensure a proper working system, SAMWHA conducted Factory Acceptance Test


(FAT) on 27, 28 November 2013 at South Korea together with HIL. The tests are
performed in accordance with contractual requirements and the specific test schedule
for each test. The FAT started with as exhaustive Visual Inspection followed the by a
complete signal test and performance test.

The testing of first capacitor bank has been completed in accordance with procedures
and checklist. The test system was found with deficiencies according deficiency List. It
has been agreed that the Minor Deficiencies will be completed until 10th December
2013. The FAT has been approved by all parties (Samwha and HIL). The second

PT Holcim Indonesia, Tbk MV Cubicle Factory Acceptance Test at Samwha film capacitor in Korea 2/5
Corporate Engineering PT Holcim Indonesia,Tbk Phone +62 21 8235687
Narogong Plant Fax +62 21 8234057

capacitor bank was the chance to make visual only. Afterward, they will make the
internal SAMWHA Factory tests and submit the protocol to Holcim.

OBJECTIVES

The present report is dedicated to inform what we discovered during FAT. Deficiencies
were noted in the Deficiency List, whereby differentiation was made minor deficiencies.
In principle any deficiency shall satisfactorily be rectified in accordance with the terms of
the contract and/or prior to the supplier applying for any subsequent test respectively.

CONCLUSION

In overall the FAT was acceptable but with several recommendation.

RECOMMENDATION

During the FAT following important improvements/rectifications have been identified:

1. The installed fuses should be replace with circuit breaker.


2. Colors of terminal tubes should be as follows :
- Phase R = Red ( Already complied )
- Phase S = Yellow ( existing white not complied )
- Phase T = Black ( existing blue not complied )
3. Color of grounding cable should be replace with Green strip yellow.
4. 6 Heater and thermostat shall be ship and installed later by contractor in the site.
5. The space for the incoming cable should be secured according to the design by
SAMWHA.
6. SAMWHA should be provide complete test report including setting values.
7. SAMWHA should be provide engineer during commissioning test and training.
8. Portable test equipment ( AVO meter ) not calibrated.
9.
Performance test for actual application cannot conduct because existing power source
is 11 kV, but for control stepper, OCR, UVR, Measurement test and Circuit control was
completely tested.

PT Holcim Indonesia, Tbk MV Cubicle Factory Acceptance Test at Samwha film capacitor in Korea 2/5
Corporate Engineering PT Holcim Indonesia,Tbk Phone +62 21 8235687
Narogong Plant Fax +62 21 8234057

PT Holcim Indonesia, Tbk MV Capacitor bank Factory Acceptance Test at Samwha capacitor Korea 5/5

Calibrated

Withstand voltage test ( 20 kV for 60S) Withstand test tools with Korean Calibration

Calibrated

Under voltage relay test Over current relay test

Unbalance load test Grounding continuity test

PT Holcim Indonesia, Tbk MV Cubicle Factory Acceptance Test at Samwha film capacitor in Korea 2/5
Corporate Engineering PT Holcim Indonesia,Tbk Phone +62 21 8235687
Narogong Plant Fax +62 21 8234057

PT Holcim Indonesia, Tbk MV Capacitor bank Factory Acceptance Test at Samwha capacitor Korea 5/6

Fuses-less type
not complied

Overall thickness
plate is 3.8 mm
include coating

Visual inspection of control system Visual inspection of thickness plate

Wrong Color code

Request 100 µm

Visual inspection of bus bar arrangement Visual inspection of thickness painting

Grounding cable
not complied with
HIL standard

Visual inspection of Accessories Visual inspection of name plate

PT Holcim Indonesia, Tbk MV Cubicle Factory Acceptance Test at Samwha film capacitor in Korea 2/5
Corporate Engineering PT Holcim Indonesia,Tbk Phone +62 21 8235687
Narogong Plant Fax +62 21 8234057

FAT Question :

1. Competent, Training & Certificate for Testing operator ? To be clarified


2. Documentation refer to IEC 60871-1 ? To be clarified
3. Test equipment within calibration date, tested and dated? ( Main instrument ) Passed
4. Safety procedure? PPE. Not complied
5. Manufacturer process and name plate ? Passed
6. Visual inspection ( Painting, Hardness, bending, Esthetics, etc) Passed
7. Accessories part ( Heater, Fan, Grounding, discharge reactor, etc ) Passed
8. Insulation test : Phase – Ground & Phase – Phase = 2.2 GΩ. Passed
9. Capacitance test : refer to certificate
10. Measure reactance : refer to certificate
11. High voltage test : Withstand test Phase – Ground & Phase – Phase = 20 kV ( 60s ). Passed
12. Balancing test step procedure ? Passed
13. Load losses test ? refer to Certificate