Академический Документы
Профессиональный Документы
Культура Документы
ASSIGNMENT
ON
COST MANAGEMENT
Submitted To-
Dr. Teena Bagga
Submitted By-
Cost Management includes processes required to complete the project within the approved
budget. With its processes, this knowledge area aims to determine the required budget to
complete the project and then aims to monitor and control the project costs to meet the
determined budget.
The major output of this knowledge area is Project Budget. After the project scope is clear and
project activities are determined, each project deliverable and each project activity will have
an associated cost. Because, project resources will perform activities, and they have some costs
to projects such as expenses, salary etc. And there will be tools, materials or equipment that
need to be used during the project as well. These will require a budget as well.
Cost management knowledge area primarily concerns with the cost of resources needed to
complete the project activities. After the budget is determined, cost management will keep on
measuring and monitoring the cost performance of the project to meet the agreed budget.
Cost Management has 4 processes, three of these processes belong to planning process group,
and on of them belongs to monitoring and controlling process group. These processes are:
For instance, office rent for a project is a fixed cost. Regardless of how many project
resources will work, you need an office, and this cost will be in your project budget.
On the other hand, material costs, expenses for project personnel etc. will be variable
depending on the number of people or materials.
Earned Value Analysis (EVA) is one of the key tools and techniques used in Project
management , to have an understanding of how the project is progressing. EVA implies
gauging the progress based on earnings or money. Both, schedule and cost are calculated on
the basis of EVA.
Features of EVA
• Planned Value (PV) – The approved cost baseline for the work package. It was earlier
known as Budgeted Cost of Work Scheduled (BCWS).
• Earned Value (EV) – The budgeted value of the completed work packages. It used
to be known as Budgeted Cost of Work Performance at a specified point (BCWP).
• Actual Cost (AC) – The actual cost incurred during the execution of work packages
up to a specified point in time. It was previously called Actual Cost of Work Performed
(ACWP).
• Cost Performance Index (CPI) = EV / AC
• Schedule Performance Index (SPI) = EV / PV
EXAMPLE
Suppose you are managing a software development project. The project is expected to be
completed in 8 months at a cost of Rs 10,000 per month. After 2 months, you realize that the
project is 30 percent completed at a cost of Rs40,000. You need to determine whether the
project is on-time and on-budget after 2 months.
• Step 1: Calculate the Planned Value (PV) and Earned Value (EV)
Therefore,
Interpretation: Since Cost Performance Index (CPI) is less than one, this means the project is
over budget. For every Rupee spent we are getting 60 paisa worth of performance. Since
Schedule Performance Index (SPI) is more than one, the project is ahead of schedule. However,
this has come at a cost of going over budget. If work is continued at this rate, the project will
be delivered ahead of schedule and over budget. Therefore, corrective action should be taken.
EVA provides different measures of progress for different types of tasks. It is the single way
for measuring everything in a project.
Provides an ‘Early Warning’ signal for prompt corrective action. The types of signals can be
the following:
a) Bad news does not age well – Holding on to the bad news does not help. The project
manager needs to take an immediate action.
b) Still time to recover – In case, the project is not going as per schedule and may get
delayed, the situation is needed to be taken care of by finding out the reasons that are causing
delay and taking the required corrective action.
c)Timely request for additional funds – While there is time to recover, the need for
additional resources or funds can be escalated with an early warning.