Академический Документы
Профессиональный Документы
Культура Документы
1. GENERAL
1.1 Description
Provide complete compressed air system to include, but not be limited to, the
following:
1.2 Standards
Unless otherwise agreed by the SO/Engineer, ensure all of the Works comply with
the relevant requirements of the Standards and Codes listed below or referenced in
the body of the Specification. Alternative Standards and Codes may be proposed for
approval by the SO/Engineer, provided it can be demonstrated that the alternative
Standards and Codes comply with the requirements of the standards specified. All
Standards and Codes quoted are current version, unless specific year references are
noted.
Ensure the compressed air installation and testing, in particular comply with the
following:
e. BS 1123 - Safety valves, gauges and fusible plugs for compressed air or inert
gas installations: code of practice for installation
f. BS EN 1092-1 - Flanges and their joints – Circular flanges for pipes valves
and fittings. Part 18 - Steel flanges
l. BS 6759 - Part 2 Specification for safety valves for compressed air or inert
gases.
2. MATERIALS
Use all new materials throughout and which are approved by the relevant controlling
Authorities and comply with the standards and codes listed.
2.1 Piping
a. Use galvanised steel pipes or stainless steel 304 or copper welded pipe as
specified from the compressors to the terminal device.
a. Ensure all isolating valves up to DN 50 for compressed air are ball-type with
screwed connections and DN 65 and above are butterfly type with flanged
connection.
d. Ensure air compressors, dryers and all auxiliary equipment are suitable for
continuous full load duty, and for the operating conditions specified on the
Design drawings.
e. Ensure compressors are designed and arranged for ease of accessibility for
maintenance and removal, without the need for major disassembly and
without disturbing the air piping or compressor alignment.
f. Provide suitable soft starting or star delta starters as shown on the Project
Specific Data Sheet for the compressor set.
g. Ensure the equipment is designed and arranged to “fail- safe” in the event of
controls or power failure.
h. Ensure all moving parts of the machine are totally enclosed or adequately
guarded.
i. Provide sealed inspection and maintenance covers, secured to the main body
by bolting.
k. Ensure major parts such as casing components and bearing housings are
designed and manufactured to ensure accurate alignment on re-assembly.
l. Ensure shaft seals and bearings are accessible for inspection and
replacement with minimum disassembly.
m. Provide each compressor package with a local control panel to contain all
instrumentation and controls required for the safe and reliable control,
regulation and protection of the individual compressor and all ancillaries,
including:
i. Compressor control
ii. Motor protection and starter of star-delta or soft start type
iii. Alarms, trips and indication.
p. Ensure the design permits ease of safe operation and maintenance of the
compressor unit, whilst minimizing the risk of physical injury.
q. Ensure that compressor unit components in excess of 25kg are fitted with
suitable devices to attach them to lifting gear
d. Provide flanged branches suitably sized for system pipeline sizes for inlet
and outlet.
f. Fit safety valves, 100 mm dial pressure gauge with siphon and cock and
an automatic drain valve to vessels. Pass drain lines through an
interceptor before discharging to drain.
g. Ensure the interiors of vessels are painted with corrosion resistance paint.
Paint the vessels externally to the manufacturers standard specification.
Provide vessels with lifting lugs and pressure relief valves.
h. Provide air receivers with a total cubic capacity as detailed on the Design
drawings.
2.5 Dryers
d. Ensure dryers are complete with all ancillary items necessary for
continuous automatic operation unattended with one vessel or modular
cells drying while the other vessel or cells regenerates.
f. Ensure that all hot surfaces are thermally insulated for personnel
protection to limit surface temperatures to 40°C.
h. Provide each dryer with an integral local control panel including dew point
detector indicator for faults, generating (in service), drying/regenerating,
temperature, dew point and moisture. Control the cycle of
drying/regeneration to maximise the capacity of the desiccant.
i. Provide all instrumentation and controls required for the safe and reliable
control, regulation and protection of the individual dryer and ancillaries.
2.6 Filters
a. Fit drain trap assemblies at the base of each vertical branch main,
moisture separators and at air receivers and comprise isolating valve,
strainer, compressed air trap and liquid discharge pipe extended to the
nearest gulley.
b. Fit a pressure balance pipe between the branch main, separator inlet or
air receiver where shown to be required
c. Ensure the complete assembly has a full-bore by-pass with globe valve.
e. Install a valve pressure control pipe between the pressure reducing valve
and the low pressure side, close to the pressure gauge
3. ASSOCIATED WORKS
3.1.1 General
Ensure the compressed air system controls are fully automatic and capable of
running unattended.
Ensure the Controls and Instrumentation and Electrical work include but are not
limited to the following:
a. Each Compressor:
i. Running
ii. Stopped
iii. Fault
iv. Discharge Pressure
Ensure the Control Panels include facilities for the following input and output
signals:
a. Outputs:
i. Running
ii. Stopped
iii. Fault
iv. Discharge Pressure
b. Inputs:
i. Start
ii. Stop
Monitor each air filter for dirty condition by a differential pressure switch. Ensure
that, on reaching the set point, an alarm will be raised at the Control Panel.
Include the following in the Electrical Works associated with this system:
a. A Motor Control Centre for the system containing motor starters for all
drive motors on the system except those on packaged equipment having
motor starters provided in the Control Panel (CP) and moulded case
circuit breaker protected feeds to all CPs
b. Power cabling and containment between the MCC and all motors/CPs.