Project Title: Slaughterhouse Water Treatment Facility

Clearing the site


width total length

anaerobic pond 8.42 8.42


Falcutative pond 15.46 15.46
maturation pond 12.00 12.00
wetland 9.00 9.00
holding pond 6.00 6.00
TOTAL
Activity: Bush Clearing
Productivity: 200 sq/man-day
Bush Type: Light bush
Laborer: 2 men

No. Of Days: (809.92𝑆𝑞.𝑚)/


((200𝑠𝑞.𝑚/𝑚𝑎𝑛−𝑑𝑎𝑦)(2𝑚𝑒𝑛)) =
Labor 2 days
Desciption Qty Days
Foreman 1.00 2.00
Laborer 2.00 2.00
Total

Project Billboard
Materials
Desciption Qty Unit
Good lumber 168.00 bd.ft
Marine Plywood 4.00 pcs
Tarpauline(8'x8') 2.00 unit
CWN 3.00 kgs
Total
Labor
Desciption Qty Days
Foreman 1.00 2.00
Carpenter 1.00 2.00
Laborer 1.00 2.00
Total

scope of work width total length


EXCAVATION
1.00 anaerobic pond 8.42 8.42
2.00 Falcutative pond 15.46 15.46
1.00 maturation pond 12.00 12.00
1.00 wetland 9.00 9.00
1.00 holding pond 6.00 6.00
TOTAL
LABOR
QUANTITY EQUIPMENT

1.00 BACKHOE
1.00 foreman
2.00 laborer

Excavation Description QUANTITY

Back Hoe 52.80


Foreman 6.60
Laborer 13.20
Sub. Total

Wall Footing and Column Excavation


w l total perimeter
anaerobic pond 6.42 6.42 25.68
Falcutative pond 13.56 13.56 54.24
maturation pond 10.00 10.00 40
wetland 7.00 7.00 28
holding pond 5.00 5.00 20
Total

Activity: Wall Excavation


Productivity: 4 cu.m/man-day
Soil type Firm soil
Laborer: 5.00
Required volume: 111.08

No. Of Days: 111.08/(4(5)) = 5.5


days
Description qty days
foreman 1 5.5
laborer 5 5.5
Total

Gravel Bedding
w l Area
anaerobic pond 7.42 7.42 55.06
Falcutative pond 14.56 14.56 211.99
maturation pond 11.00 11.00 121.00
wetland 8.00 8.00 64.00
holding pond 6.00 6.00 36.00
total

aggregate base course

productivity:
1. loading 8.5cu.m/man-day
2. Spreading 10cu.m/man-day
3. Compacting 10cu.m/man-day

Laborers: 5 men
volume Required: 48.81cu.m

No. of Days =48.81/(5∗8.5) +48.81/(10∗8.5) +48.81/


(10∗8.5) = 2.3 days
=48.81/(5∗8.5) +48.81/(10∗8.5) +48.81/
(10∗8.5) = 2.3 days
Material:

Description qty. unit


Gravel 48.81 cu.m
Labor
Description qty. days
1.00 Foreman 2.30
5.00 laborers 2.30
Total

Total

Backfilling and Tamping


w l total perimeter
anaerobic pond 7.42 6.42 27.68
Falcutative pond 14.56 13.56 56.24
maturation pond 11.00 10.00 42
wetland 8.00 7.00 30
holding pond 6.00 5.00 22
Total

Backfilling and Tamping

Productivity: 3cu.m/day-man
laborers: 12 men
Required Volume: 449.16

No. Of days 449.16/(3∗12) = 12.5 days

Labor
Description qty. days
1.00 Foreman 12.50
12.00 laborers 12.50
Total

B. MOBILIZATION & DEMOBILIZATION


I-EQUIPMENT TO BE HAULED:
BACKHOE
II- LOADING/HAULING/DISPOSING
EQUIPMENT USED
HAULING SITE
HAULING DISTANCE
SPEED OF TRALER W/ LOAD
SPEED OF TRALER W/O LOAD
CYCLE TIME

Total Travel Time :


Mobilization and Demobilization
Qty Unit
1.00 l.s
C. Layout
I-BATTER BOARD
Layout Parameters
pond type
width(m) length(m) perimeter(ft)
anaerobic pond 7.42 7.42 97.35
Falcutative pond 14.56 14.56 382.05
maturation pond 11.00 11.00 144.32
wetland 8.00 8.00 104.96
holding pond 6.00 6.00 78.72
TOTAL
II-STAKING
Layout Parameters
pond type
width(m) length(m) perimeter(ft)
anaerobic pond 7.42 7.42 97.35
Falcutative pond 14.56 14.56 382.05
maturation pond 11.00 11.00 144.32
wetland 8.00 8.00 104.96
holding pond 6.00 6.00 78.72
TOTAL
GRAND TOTAL:

Materials
Description qty unit
2x3x12' coco lumber 696.39 bd.ft
Assorted CWN 14 kg
Nylon 1.5 kg
Total
labor
Description qty days
foreman 1 3
skilled worker 5 3
Total

D. FORMWORKS AND SCAFFOLDINGS

I. FORMWORKS
pond type Layout Parameters
hieght(m) perimeter(ft) area(sq.ft)
anaerobic pond 2.70 84.23 745.94
Falcutative pond 2.10 353.19 2432.77
maturation pond 1.50 131.20 645.50
wetland 0.70 91.84 210.86
holding pond 1.50 65.60 322.75
TOTAL 4357.83
Il-vertical and longitudinal stud
pond type Layout Parameters
width(m) length(m) perimeter(ft)
anaerobic pond 6.42 6.42 84.23
Falcutative pond 13.46 13.46 353.19
maturation pond 10.00 10.00 131.20
wetland 7.00 7.00 91.84
holding pond 5.00 5.00 65.60
TOTAL

Labor type: wall covering


Given Capability
1.00 Foreman 30 sq.m/man-day
15.00 skilled workers
Area 4035.08 sq.m

No. of Days =((2𝑥4357.83 /3.28)𝑆𝑞.𝑚)/


((30𝑠𝑞.𝑚/𝑚𝑎𝑛−𝑑𝑎𝑦)(15𝑚𝑒𝑛)) = 6 days

Labor type: Stud/Framing


Given Capability
1.00 Foreman 12 sq.m/man-day
15.00 Skilled Worker
Area 4357.83

No. of Days =(4357.83∗2/3.28) 𝑆𝑞.𝑚)/


(12𝑠𝑞.𝑚/𝑚𝑎𝑛−𝑑𝑎𝑦)(15𝑚𝑒𝑛)) = 14 days
Materials
Description qty unit
2x2x12' coco lumber 3475.05 bd.ft
Ordinary Plywood 150.00 pcs
Assorted CWN 70 kg
Nylon 3 kg
Total
labor
Description qty days
foreman 1 10
skilled worker 30 10
Total

E. Scaffolding(movable Scaffolding)
Parts: Wood Size qty
1. Flatform 2x10x8' Good 1 unit
2. Braces 2X3x10' Good 9 pcs
3. Column 2x2x8' 4 pcs
4. Cleats use waste
Total

Provide 10 Scaffolding; 10x69 = 690

Materials
Description qty unit
2x2x12' coco lumber 690.00 bd.ft
Assorted CWN 14 kg
Nylon 3 kg
Total
labor
Description qty days
foreman 1 3
skilled worker 5 3
Total
total area

70.90
478.02
144.00
81.00
36.00
809.92

𝑎𝑦)(2𝑚𝑒𝑛)) =
Unit Cost Amount
570.64 1141.28
317.00 1268.00
2,409.28

ct Billboard

Unit Cost Amount


40.00 6720.00
850.00 3400.00
980.00 1960.00
65.00 195.00
12,275.00

Unit Cost Amount


570.64 1141.28
412.80 825.60
317.00 634.00
2,600.88

total area thickness/hight volume

70.90 2.80 198.51


478.02 2.20 1051.65
144.00 1.60 230.40
81.00 0.80 64.80
36.00 1.50 54.00
809.92 1599.36

EQUIPMENT CAPABILITY (cu.m/day)


REQUIRED VOL. DURATION IN DAYS
DURATION IN HOURS

240.00 1599.36 6.66 53.31


6.66 53.28
6.66 53.28

UNIT UNIT PRICE AMOUNT

Hrs. 1537.00 81153.60


day 570.64 3766.22
day 317.04 4184.93
89,104.75

d Column Excavation
thickness width of Excation Volume
0.5 1 12.84
1 1 54.24
0.5 1 20
0.5 1 14
0.5 1 10
111.08

unit price Amount


570.64 3138.52
317.04 8718.6
11,857.12

thickness volume
0.10 5.51
0.10 21.20
0.10 12.10
0.10 6.40
0.10 3.60
48.81
unit price Total cost
500.00 24405.00

unit price Total cost


570.64 1312.47
317.04 3645.96
4958.43

29363.43

g and Tamping
thickness width of Embankment Volume
2.80 1 77.504
4.40 1 247.456
1.60 1 67.2
0.80 1 24
1.50 1 33
449.16

g and Tamping

unit price Total cost


570.64 7133.00
317.04 47556.00
54689.00

:1 UNIT

:1 TRAILER
:MATI
:4kM
25KM/HR
30KM/HR

= 4.0𝑥60/30 min + 4𝑥60/25 min +27 min = 44.


6min
:44.6x2 or 1.5 hrs
Unit price Amount
3812.00 3,812.00
2x3 Coco Lumber
length per lumber(ft) quantity(12') adjusted qty(12') no. of bd. Feet
12.00 8.11 9 55.98
12.00 31.84 37 219.68
12.00 12.03 14 82.98
12.00 8.75 10 60.35
12.00 6.56 8 45.26
464.26

2x3 Coco Lumber s.p @ 8 ft


length per stake(ft) quantity (12') adj. qty. (12') no. of bd. Feet
4.00 4.06 5 27.99
4.00 15.92 18 109.84
4.00 6.01 7 41.49
4.00 4.37 5 30.18
4.00 3.28 4 22.63
232.13
696.39

unit price Amount


15 10445.8164
65 910
120 180
11,535.82

unit price Amount


570.64 1711.92
317.04 4755.6
6,467.52

ordinary plywood
area per piece of plywood quantity adjusted qty.
32.00 23.31 26
32.00 76.02 84
32.00 20.17 22
32.00 6.59 7
32.00 10.09 11
150

2x2x12 Coco Lumber


hight(m) Vertical Stud s.p @ Longitudial s.p @ 2'adj. Qty bd.ft
2.70 1243.24 379.04 149 594.84
2.10 4054.63 1236.17 485 1939.96
1.50 1075.84 328.00 129 514.74
0.70 351.44 107.15 42 168.15
1.50 537.92 164.00 64 257.37
3475.05

357.83 /3.28)𝑆𝑞.𝑚)/
𝑚/𝑚𝑎𝑛−𝑑𝑎𝑦)(15𝑚𝑒𝑛)) = 6 days

∗2/3.28) 𝑆𝑞.𝑚)/
𝑚𝑎𝑛−𝑑𝑎𝑦)(15𝑚𝑒𝑛)) = 14 days

unit price Amount


15 52125.795861333
600 90000
65 4550
120 360
147,035.80

unit price Amount


570.64 5706.4
317.04 95,112
100,818.40

bd. Foot
13.33
45.00
10.67

69 bd.ft

unit price Amount


15 10,350.00
65 910
120 360
11,620.00
unit price Amount
570.64 1711.92
317.04 4755.6
6,467.52
S