Вы находитесь на странице: 1из 6

Light Metals 2009 Edited by

TMS (The Minerals, Metals & Materials Society), 2009

Increased availability and optimization of calciner performance due to automation


Michael Missalla, Dr. Jan Jarzembowski, Roger Bligh, Dr. Hans Werner Schmidt
Outotec GmbH, Oberursel / Germany

Keywords: Alumina Calciner, CFB calciner, Operation, Automation

Abstract similar design and layout. This improvement in operability is


mainly due to an increased level of automated protective measures
In the last 30 years, Outotec has installed more than 50 calciners which lead to fewer operator mistakes and therefore higher
worldwide. Over the years the operation was improved availability and improved safety[5].
significantly and thus also availability was raised. Real costs for
instrumentation and control systems have also reduced over this Further examples are the two recently commissioned 3500 tpd
period, thus encouraging the installation of more instrumentation, calciners at the Rio Tinto/Alcan refinery in Gove, where a number
data analysis and better process monitoring. of advances in automation were implemented, especially in the
area of preheat burner and fuel control. As a result, these calciners
More recently, the trend has been towards full automation of have proved to be significantly easier to operate than their
activities like capacity load changes while maintaining other predecessor, despite their larger capacity.
performance and product quality related parameters within
specification. Other examples of improved automation are the use The target and goals for automation can be formulated as:
of advanced control loops with multiple input, while preheating
and shut down of the calcination plant can be achieved with just  Reduced operational risk
the push of a button.  Reduced operator pre-occupation with standard tasks
 Improved operational stability and product quality
The benefits of improved automation include improved  Reduced operating cost
availability through avoidance of operator error, reduction in
manpower for process control related tasks and reduced Risk to personnel, equipment and plant productivity resulting
requirement for field adjustment in potentially hazardous areas. from incorrect/inappropriate operation of the plant can be reduced
regardless of the individual operator skills by the implementation
The implementation of multivariable control strategies in recently of pre-defined and approved procedures. Automation of operating
commissioned plants and comprehensively engineered control and control functions plays an important part in achieving this
concepts are described. Furnace temperature feed forward control, target by taking predetermined actions directly, and providing
automated pre-heating, start-up, gas and solids purge, equipment diagnostic information to the operator. The introduction of
protection monitoring, and automated protective measures for automated procedures to prevent plant trips leads to an increased
operational stability and plant trip prevention are presented. availability and throughput of the calciner [6].

Introduction Automation also helps operators to focus on overall site


performance by reducing their pre-occupation with standard tasks
In line with the trend towards larger alumina refinery size, like following a pre-heating curve according to a set profile or
Outotec’s customers have also requested calciners with steadily load change the load of a calciner.
larger unit capacities[1],[2]. For example, Outotec has recently
commissioned two large CFB calciners with a design capacity of
3300 tonnes per day (tpd) at the alumina refinery in Alunorte, Moreover, the improved operational stability resulting from
Brazil which design was based on the existing plants D and E. advanced automation techniques leads to a more stable product
quality, even under conditions where the process is being
With the start up of the calciners D and E in 2006, the team of disturbed by external upset conditions.
Alunorte and Outotec set a new benchmark in terms of short
duration until the plant could operate with full production [3]. The Automation can be further divided into pre-operational,
start up of the new calciners F and G in 2008 made this former operational and post-operational activities. Pre-operational
record a routine. With these calciners Alunorte now operates in activities consist of preheating, purging and preparation activities.
total seven alumina calciners based on Outotec’s Circulating While post-operational activities deal with all the stop activities to
fluidized Bed (CFB) technology [4]. The overall production bring the equipment into a defined status as required by the user.
capacity of 6.3 million tons per year (tpy) makes Alunorte the Operational activities are for example start up and production.
world’s single biggest alumina refinery.
In the operational part protective measures for operational
Importantly for the customer, calciners F and G have proven to be stability and plant trip preventions are implemented. For example,
easier to operate and control than their predecessors despite the trip prevention measures prevent operators from entering data
which would lead to a major upset or trip of the calciner. Besides The conveying air cleaned in the airlift cyclone is delivered via
trip conditions are monitored and pro-active measures are taken ducts to the secondary air cyclone and serves finally as
from the control system, e.g. the limitation of fuel with respect to combustion air. The hydrate entering the venturi preheater of the
a safe fuel/air ratio [7]. second preheating stage is mixed with the hot waste gas leaving
the recycling cyclone and is dehydrated by the heat contained in
Process Description the hot gas

In the cyclone, which is arranged downstream of the venturi


preheater, the flow of gas and solids will be separated. From the
cyclone, the pre-calcined alumina is delivered into the fluid bed
furnace through the material feeding line. The waste gas leaving
the cyclone of the second preheating stage is conveyed to the
venturi preheater or the first preheating stage where it assumes the
above mentioned function.

Calcining Stage

The final calcination of the preheated and partly dehydrated


hydrate takes place in the fluid bed furnace. The required heat for
calcination is generated by direct combustion of fuel in the fluid
bed. For that purpose, dedicated retractable oil lances for heavy
fuel oil will be installed. Part of the air quantity required for
combustion is introduced through the nozzle grate as primary air,
Figure 1: Typical flowsheet of a Circulating Fluid Bed (CFB) and the remaining air is added above the grate as secondary air.
calciner. Due to the intensive mixing and heat exchange that takes place in
the fluidised bed, the furnace temperature adjusts itself as a mixed
In the flowsheet (Figure1) the central piece of equipment is the temperature between the combustion temperature and the solids
furnace group in the form of a CFB which is the core process for temperature, and is kept steady at a pre-set level. In the lower
the calcination. Upstream the furnace group, heat is recovered by furnace zone, between the grate and the secondary air inlet, a fluid
the feed hydrate from the off-gases in the two preheating stages. bed of high solids concentration is adjusted. It favors the
Downstream of the calcination, the alumina solids are cooled combustion of the fuel and increases the mean retention time in
down in the cooling stages before being discharged to the alumina the calcining furnace. In the upper furnace zone the internal
storage. recirculation of the solids causes a continuous reduction of solids
concentration until a relatively low concentration is reached. With
Preheating Stage I this solids concentration, the hot gases enter the recycling cyclone
where they are separated from the solids. The hot alumina, which
From the hydrate feed bin, the hydrate is discharged by a screw is separated in the recycling cyclone passes through the seal pot
feeder. The screw feeder delivers the material into the venturi and re-enters the fluid bed furnace.
preheater of the first preheating stage. There the solids are mixed
with the waste gas, which leaves the cyclone of the second The recirculation of the solids leads to uniform and practically
preheating stage. The heat contained in the waste gas evaporates identical product - and gas temperatures in the entire calcination
the entire surface moisture of the hydrate. stage, which consists of the fluid bed furnace, recycling cyclone
and seal pot. The fluidisation of the solids in the seal pot, which is
The preheated hydrate entrained with the waste gas is conveyed required for re-circulation is done by means of the seal-pot
into the two-stage electrostatic precipitator (ESP). In a first blower. A partial product stream is taken from the circulation
mechanical stage of the ESP parts of the entrained solids are system and discharged to the cooling stage by the water-cooled
precipitated. The rest of the solids enters the second stage of the discharge lance.
ESP together with the waste gas. The waste gas is finally cleaned
by means of electrostatic precipitation before it leaves the process The alumina, which is discharged from the calcining stage is
to the atmosphere. cooled in two direct cooling stages each of which consists of a
liftduct and a secondary air cyclone. The third cooling stage is
The solids precipitated in the second stage by electrostatic designed as a fluid bed cooler and mainly relies on indirect heat
precipitation are conveyed to the bottom of the mechanical stage transfer.
by means of screw conveyors. The solids are then fed into an air
slide. Cooling Stage I

Preheating Stage II The alumina coming from the calcining stage is first mixed with
pre-heated air in the liftduct 1 and conveyed into the secondary air
The air slide discharges the hydrate into the sending pot of the cyclone 1. At the same time the air is heated from the temperature
pneumatic elevator where the hydrate is conveyed by air to the of the second cooling stage to the temperature of the first cooling
airlift cyclone. The main portion of the discharged solids is stage. This air is routed from the outlet of the secondary air
delivered via a discharge seal to the lower part of the venturi cyclone 1 to the CFB system as secondary air and used for
preheater of the second preheating stage. combustion.
Cooling Stage II Distributed Control System (DCS) and are also monitored by a
Safety Instrumented System (SIS) with an implemented Burner
The alumina discharged from the bottom of the secondary air Management System (BMS). To put the preheat burner into
cyclone 1 is fed into the liftduct 2 via a pressure seal. In this operation, the operator at the panel can order the BMS via the
liftduct the alumina is mixed and further cooled with secondary DCS to start the burner, which is done then by a fully automated
air coming from the fluid bed cooler and additional air coming sequence. Once the burner is started successfully, the panel
directly from blowers. It is then conveyed into the secondary air operator can modulate the burner load to heat up the calciner. The
cyclone 2 from where it is discharged into the fluid bed cooler. At degree of automation now enables swifter heat up of the calciner
the same time the secondary and additional air are pre-heated to after a trip.
the temperature of the second cooling stage and then routed to the
bottom of the liftduct 1. New calciners equipped with fully automated preheat burners will
be automatically preheated according to a predefined heat up
Cooling Stage III curve (e.g. 70 K/h). Thus no further panel operator action will be
required during preheat of a calciner. After the automated
In order to achieve a low specific heat consumption during the preheating cycle, the operator will be enabled to initiate the
calcining process, there is further heat recovery in the air-cooled automated plant start sequence.
part of the fluid bed cooler. Primary air is pre-heated by indirect
heat exchange in a counter-current flow to the alumina, at the Further, the lances are controlled in a similar way by the BMS.
same time the alumina is cooled. At the outlet of the fluid bed Once the calciner furnace is above the minimum safe ignition
cooler the alumina is discharged to a mechanical or pneumatical temperature the operator starts up the fuel injection system in a
transport system via a pressure seal. similar manner to the preheat burner. When the lances are set in
operation and the fuel demand is increasing or decreasing then the
The primary air delivered by blowers is first pre-heated in the appropriate number of lances are started or stopped automatically.
fluid bed cooler and then introduced into the fluid bed furnace Therefore, an operator is no longer needed for the lances and this
through the nozzle grate of the furnace. consequently speeds up the process of putting sufficient lances in
operation.
Blowers deliver the secondary air for the fluidisation of the fluid
bed cooler. The secondary air is distributed to the compartments This approach was applied in the design of the calciners in Gove
of the fluid bed cooler in such a way that a uniform degree of where the customer wanted the possibility for a dual fuel system
fluidisation is obtained. In the liftduct 2 the preheated air is to be able to change from one fuel to another without reducing the
supplemented with additional air, which is also delivered from production rate of the calciner. When fully implemented, it will be
blowers. possible for the operator to mix the fuel supply according to the
energy demand, but also to the available combustion air
independent from the different air requirements of the fuels. The
Pre-Operational Activities fuel flows will be controlled by the total energy demand to
maintain the calcination temperature. Figure 2 demonstrates the
Fully Automated Gas- and Solids Purge control philosophy. Here the percentage of delivered energy is
plotted versus a control value set by the operator. A control value
Safety standards usually required a gas purge prior to the restart of 0-5% means only heavy fuel oil is supplied and a value of 95-
of a calciner. In addition to the gas purge a solids purge with 100% corresponds with only natural gas supply. Every value
controlled solids discharge from the plant is recommended from between these margins corresponds with a percentage of the total
an operational point of view in order to achieve defined restart energy demand by the furnace temperature control system being
conditions. delivered in the form of heavy fuel oil. The difference represents
the energy demand supplied in the form of natural gas.
All recently commissioned Outotec CFB-calciners provide
automated purge sequences which supervise the gas purge and
100
Percentage of Energy

solids discharge from the entire plant. Relevant equipment will be


NG
Delivered by Fuel

automatically started, valves opened as well as flow and pressure 75


controllers set to designated purge set values. The controlled
solids purge is designed to retain a certain solids inventory in the 50
furnace group in order to achieve better temperature stability HFO
when restarting the hydrate feed. 25

0
Fully Automated Preheat Burner and Burner Management System 0 25 50 75 100
for Fuel Injection Lances
Operator Choice of NG-Ratio on Energy Demand
Each of the new calciners for Rio Tinto Alcan in Gove is Figure 2: Control of fuel mixture for a dual fuel operated calciner
equipped with one preheat burner and four lances for heavy fuel
oil (HFO). Additionally they have a separate set of natural gas
(NG) lances in anticipation of natural gas being available to the
site at a later stage. Operational Activities

To improve the operability of the calciners, the preheat burner and Automated Plant Start Sequence
the fuel injection lances are fully automated through the
Outotec’s recently commissioned calciners provide semi- material from 100 % of design capacity to about 25 %, the furnace
automated plant start sequences and procedures which are guiding temperature was kept stable, thus maintaining a constant product
the operator through the plant start up. In future, new installations quality.
will be equipped with fully automated start up sequences which
will – after being initiated by the panel operator – automatically
introduce fuel, start all relevant equipment, commence hydrate
feed and ramp the plant up to a preselected capacity.

Improved Furnace Temperature Control

The temperature in the furnace is controlled by the fuel oil flow.


However it might be possible that the amount of hydrate been fed
to the furnace is fluctuating. The fluctuation can be caused by an
uneven ESP solid discharge or even an uneven hydrate feed via
the hydrate feed screw. If the feed to the furnace is reduced the
temperature will rise. The velocity of this rise is dependent on the
amount of hydrate missing and on the response time of the thermo
couple. However this could lead to unacceptable high or low
temperatures finally resulting in a plant equipment safety trip.

To improve the furnace stability under the conditions described Figure 4: Rapid load change in a calciner from 235 t/h to 60 t/h
above, Outotec has implemented a furnace temperature feed within 10 minutes.
forward control strategy where the hydrate mass flow is measured
just before it enters the furnace. Fluctuations in this signal are Start-up Performance of Alunorte
used in a feed forward loop to increase or decrease fuel flow as
appropriate. The latest CFB calciners –2 x 3500 tpd at Gove and 4 x 3300 tpd
at Alunorte - have proven to be very easy to operate and fast in
Figure 3 illustrates the re-start procedure of a CFB calciner over a start-up from preheat to full capacity. This is demonstrated in
time period of several hours. The diagram shows the furnace Figure 5, where the capacity is plotted versus the time in minutes.
temperature, the furnace temperature set point, the heavy fuel oil At t = 0 min, preheating is finished and furnace temperature is
flow (HFO) and the hydrate feed during the re-start period up to approx. 830°C, ready for the start of the heavy fuel oil lances. It
nominal load. It can be seen that the fluctuation of the furnace takes only 100 minutes from the start of the heavy fuel oil lances
temperature is even with load changes from almost zero hydrate to 100% of the calciner design capacity.
feed capacity to nominal load in the range of 10 degrees.

120
(Actual Fuel Flow)/(Full Capacity Fuel Flow), -

100

80
Calciner Capacity in

60

40

20

0
0 50 100 150 200 250 300 350 400
Figure 3: Furnace temperature feed forward control. time, min
Max. deviation from set point ~10°C. Figure 5: Calciner capacity over time after re-start.

Load Change in a Calciner The characteristics of some important temperatures within the
calciner are shown in Figure 6. The furnace temperature increases
In Figure 4 a load change in the calciner from 235 t/h to 60 t/h of rapidly after starting the oil lances. The temperatures in the feed
hydrate feed within 10 minutes is shown. This rapid load change preheating stages are established within seconds of balancing
was necessary due to a failure in the hydrate delivery to the hydrate feed to the heat generation in the furnace. On the other
calciner. It can be seen that fuel oil flow follows the hydrate flow hand, temperatures in the alumina cooling stages increase to
with a certain time delay. Even with this rapid change in feed
nominal values comparatively slowly due to the delay in combined with a controlled shutdown sequence in order to
discharge of alumina from the furnace. achieve a safe and defined plant status and increased reliability
factor [6]

Conclusions
120
Furnace The reduction in real instrumentation costs has encouraged the
Temperature as percentage of value at

100 installation of more instruments leading to a better monitoring of


the process. Using this additional data, several automated
80 procedures were developed. The targets for this automation were
steady state, %

the reduction of operational cost and risks. Besides the pre-


Cooling Stage 1
60
occupation of operators with standard tasks will be significantly
Cooling Stage 2
reduced
40
The automation activities are divided into pre-operational,
operational and post-operational activities and samples from
20
industrial scale plants for each area are given. Even upset
conditions do not lead to a trip of the plant.
0
0 50 100 150 200 250 300 350 400
time, min The new developed furnace temperature feed forward control
assures constant furnace temperatures even at rapid and
Figure 6: Important process temperatures after re-start of calciner. significant load changes. Product quality from the CFB calciner
can therefore be kept consistent not only at constant loads, but
also during the load changes.
When the plant is shut down, all solids are removed from the
vessels to the fluid bed cooler by means of the blowers. This is
done to avoid blockages during restart. The alumina discharge Acknowledgment
from the calcining stage is closed at the beginning of hydrate feed Outotec would like to thank the engineers and operations
and stays closed until enough inventory is built up in the furnace. personnel of Alunorte and Rio Tinto Alcan for their professional
support and appreciates their contributions to the recent
Figure 7 shows two of the latest calciners operating in Gove, developments in CFB technology.
Australia were the above described technology is already applied.

References

[1] D.J. Brodie, H.W. Schmidt, “Custom Design Fluid Bed


Calciner for Nabalco Pty. Ltd.”, Proceeding of 5th International
Alumina Quality Workshop, (1999), Bunbury, Australia

[2] Y.Yetmen, H.W. Schmidt, Large Units for Alumina


Calcination Plants with improved Technology “ Int. Conference
on New development in Metallurgical Process Technology
Proceedings VDEM, pp 369-375 (1999)

[3] Michael Missalla, Cornelis Klett, Roger Bligh, “Design


Developments for Fast Ramp-up and Easy Operation of New
Large Calciners”, TMS Light Metals (2007)

[4] A. Squires, “Origins of the Fast Fluid Bed, Advances in


Chemical Engineering”, Vol. 20, Fast Fluidisation (Ed. Kwauk,
M.), Academic Press (1994), pp 4-35
Figure 7: Two calciners 3500 tpd capacity each. [5] H.W. Schmidt, M. Ströder, G. Singh, M. Sant’ana, J. Ribeiro,
Gove, NT, Australia J. Piestrzeniewicz, M. Cable, “Improved Health and Safety
Conditions and Increased Availability in Large Alumina
Calcining Units”, TMS Light Metals (2005)
Post-Operational Activities [6] P.Hiltunen, R.Bligh, C.Klett, M.Missalla, H.W.Schmidt
“How to Achieve High Availability with Large Calciners and
Automated Plant Shut Down Avoid Unforeseen Downtime”, TMS Light Metals (2008)
Post-operational activities are currently semi-automatically and [7] L.Reh,” New and Efficient High Temperature Process with
include sequences to stop blowers, ESP rectifiers, rappers, Circulating Fluid Bed Reactors”, Chem. Eng.Technol. 18 (1995)
discharge conveyors and other equipment. In future applications page 75-89
the semi automated sequences will be further developed and

Вам также может понравиться