Академический Документы
Профессиональный Документы
Культура Документы
on structural design of
foundation bored piles
4
What need to be submitted WITHIN
28 days of completion ?
• BC Act Section 9(4)(e) & BC Regulation 23(1)(c) require QP to
submit as-built piling plan, within 28 days of completion of piling
works.
Failure to do so is a contravention !
5
Why need to submit
within 28 days ?
6
Is it possible to do it
within 28 days ?
Total = 21 days
7
Diagnose Cause of
delayed submission
8
This non-compliance must NOT
be continued.
10
QP to visit piling site frequently to
be fully aware of site status
• Frequent site visits by QP
• Early detection of piles constructed
significantly shorter than what have been
designed
• Take timely remedial action to address piles
constructed with major deviation, before
pilecap and superstructure are constructed.
11
(B)
Guidelines to Identify
Rock During Piling
Drafted by a joint industry
workgroup chaired by
GeoSS and BCA
Objective of the guidelines
Design stage
• To specify the Point load Index tests requirement on the drawings
for every pile
• To specify minimum Is(50) value to be achieved in order to be
classified as rock
(C)
Structural design of
bored piles based
on EC2
Contents
1. Structural design of bored pile based on Eurocode 2
24
(1) Structural design of
bored pile based on
Eurocode 2
Structural design of bored pile (Lightly reinforced)
Eurocode 2 & BS EN1536
• EN 1992-1-1:2004 Cl 12.3.1(1)
Length of reinforcement
2) Length of reinforcement to go beyond soft or loose soil as
recommended in EN1536, subject to a minimum of 10m from
pile cut-off-level
Minimum longitudinal reinforcement
SS EN 1992-1-1 Clause 9.8.5 (Eurocode 2)
Øp
≤0.798m 0.5%Ac
0.5%-0.25%Ac
>1.13m 0.25%Ac
• The minimum diameter for the longitudinal bars should not be less than 16 mm. Piles should
have at least 6 longitudinal bars. The clear distance between bars should not exceed 200
mm measured along the periphery of the pile. 28
Minimum length of reinforcement
EN 1536:2010
7.1.2 Bored piles design shall take into
account the construction tolerances given in
8.1 and the execution conditions as set in
Clause 8.
Soft clay
7.1.7 A bored pile should be
reinforced over any length of soft or
loose soil.
Competent soil
layer or
7.5.2.8 Concentric layers of longitudinal bars bedrock
should be avoided where possible.
This means that the reduction factor may ranges from 4% to 10%,
depending on the pile diameters.
Is this reduction factor adequate ?
31
Comparison on pile
design between
Eurocode and CP4
Wind loading
CP4 Eurocode
• CP4 Clause 2..3.2.4.3 allows wind • No such allowance for
load to be ignored in foundation load wind load in Eurocode
if it is less than 25% of (dead load +
live load) • BS EN 1990:2002 Cl
4.1.1 (1)P Wind
• If wind load exceeds 25%, only the loading is classified as
excess over 25% need to be a variable action (Q)
considered in foundation load
CP4
Comparison between EC2 with CP4 (nominally reinforced pile)
f cd,pile = 0.3636 f ck
EC2 f cd,pile ≈ 1.35G k + 1.5Q k ≈ 1.4 Q a
f ck ≈ 0.8 f cu
0.3636 × 0.9025 × 0.8f cu
Qa ≈ ≈ 0.187 f cu
1.4
Above is based on 1m dia pile. For 2.5m dia pile, Qa ≈ 0.20 fcu .
CP4
Qa = 0.25 fcu, subject to maximum of 7.5 MPa
Comparison of EC2 and CP4
fcd,pile = 0.3636 fck for lightly einforced bored pile using EC2
Caution on the use of fcu more than 40 MPa in design as they may
NOT be achievable due to adverse casting condition underground.
Verification of in-situ
concrete strength through
testing
Concrete core tests
Using higher concrete grade fcu > 40 MPa in
design in EC2 will result in much larger structural
capacity as compared to CP4.
• For bored piles using concrete grade fcu > 40 MPa in design
resulting in working compressive stress exceeding 7.5 MPa,
minimum 5% of piles to be subject to concrete core test.
Test method:
BS EN12504-1:2009 taking and
preparation of cored specimens
38
Requirement on pile profile test
• For bored piles supporting buildings of 10-storeys or more,
Quality Control Test Recommended test schedule
CP4
Qa = 0.25 fcu, subject to maximum of 7.5 MPa
Lightly reinforced vs fully reinforced
• By changing from lightly reinforced to fully reinforced in design,
there is a sharp increase of 42% in pile structural capacity (as αcc has
increased sharply from 0.6 to 0.85).
fcu (MPa) 30 35 40 45
Lightly reinforced (0.3636fck) 5.6 6.5 7.5 8.4
0.187 fcu 1m dia
Fully reinforced (0.515fck) 0.265 fcu 1m dia 7.9 9.3 10.6 11.9
Fully reinforced (0.515fck) 0.282 fcu 2.5m 8.5 9.9 11.3 12.7
dia
Eg. If adopt 0.265 to 0.282 fcu for fcu= 45 MPa fully reinforced pile
design, adopted stress of 11.9–12.7 MPa will be 59%- 69% over 7.5 MPa.
53
Allowable settlements for pile
working load test
• Working load test should be carried out to a
minimum 1.5 times or 2 times characteristic load
acting on the pile, with allowable maximum
settlement at pile top generally not exceeding 15
mm or 25 mm respectively.
• When you design your pile to take higher compressive
stress, check that the settlement criteria is still fulfilled.
• Pile settlement is also affected by workmanship and
execution conditions. Consider them in design !
54
Model factor has been revised
• Enterprise Singapore has made
amendment to Singapore National Annex
to SS EN 1997-1:2010 (2018)
• Model factor 1.2 – 1.4 has been revised
to 1.35 – 1.55.
• Please use revised model factor in your
geotechnical design of foundation pile.
55
Implementation date
56
Concluding remarks
QP to take into account adverse execution condition
1 underground when designing bored pile for its
structural and geotechnical capacity.