Академический Документы
Профессиональный Документы
Культура Документы
Discharge by Performance
-both parties have fully performed their contractual obligation
Substantial performance
- A court is satisfied by the performance and award the contractually agreed price
and deduct sums to reflect the amount not performed.
- Problem to think about: to what extend/ amounts to substantial performance.
There is no precise limit to set down but is to be determined on the facts of
individual cases.
‘Quantum Meruit’ is a Latin word for ‘as much as he deserved’ (paid for what he had
done)
Condition to apply:
-or Sir Hameed’s example: If Messi was supposed to become ambassador but instead a
gentlemen name Messy arrive. It’s a big No. This Messy doesn’t have the same skills as Messi.
Discharge by Agreement
-Both parties agreed to bring contract to an end, release each other from their contractual
obligations.
-For a contract to be discharged through agreement there must be accord and satisfaction.
-Accord= Agreement
-Satisfaction=Consideration
-both parties must also provide consideration
-If both parties have continuing obligations then generally the consideration will be simply
each of them giving up their rights under the contract.
-The only time consideration become an issue is when one party has fully performed their
part of contract and the other is not.
-the no-performing party must provide consideration to make the agreement binding.
-Also, if agreement is made by deed there is no requirement to provide consideration.
By Sir Hameed’s
‘Condition Subsequent’
-Head v Tatterall (1871)
i)Wholly executory
-The Hannah Blumenthal (1983)
A contract was made for the sale of a ship.
A dispute arose between parties regarding alleged defects.
The dispute was referred to arbitration but the requirement for a third arbitrator
under the contract was not fulfilled and the arbitration was delayed.
The sellers raised proceedings for a declaration that the arbitration agreement was
discharged by repudiation, consensual rescission or frustration.
ISSUE: At first instance, it was held that there had been no agreement to abandon the
arbitration but it had been discharged by frustration. The Court of Appeal agreed that
the agreement had been frustrated because, due to the long period of time that had
passed, it would be impossible for there to be a fair trial of the buyer’s claim. The
buyer further appealed to the House of Lords.
HELD: The House of Lords allowed the appeal. The arbitration agreement was not
frustrated. Both parties were in default of the agreement by not applying to the
arbitral tribunal for direction to prevent delay. Such a default excluded the operation
of the doctrine of frustration. Lord Diplock held that the virtual impossibility of a
satisfactory trial following the delay was incapable of being classified as a frustrating
event; even If it had come about without the default by either party. Furthermore, the
sellers had not proven abandonment of the arbitration as they had not shown that
they believed that the buyers had intended to abandon the action and there were
actions by them which were inconsistent with such a belief.
ii)Partially performed
-by deed-no need consideration
-accord & satisfaction
Agreed termination
-On specified notice period
-Upon occurrence of agreed events
-Upon agreed types of breach e.g material breach
Discharge by breach
Breach condition
-Victim party is entitled to (repudiate)end contract and claim damages (condition)
Poussard v Spiers (1876)
-Madame Poussard entered a contract to perform as an opera singer for 3 months
-She became ill 5 days before the opening night and not able to perform the first 4 nights
-Spiers then replaced her with another opera singer
HELD:
-Madame Poussard was in breach of condition and Spiers were entitled to end the contract
-She missed the opening night which wass the most important performance as all critics and
publicity would be based on this night.
Anticipatory breach
Before the time of performance – where one party informs the other that they will not
fulfil their obligations under the contract
-Right of action given immediately to the innocent party:
Hochster v De La Tour (1853)
-The claimant agreed to be a courier for the defendant for 3 months starting on 1st June 1852.
-on 11th May, the defendant wrote to the claimant stating he no longer wanted his services
and refused to pay compensation.
-The claimant obtained a service contact elsewhere but this was not to start until 4th July
-The claimant brought an action on 22nd May for breach of contract
-The defendant argued that there was no breach of contract on 22nd May as the contract was
not due to start until 1st of June.
HELD:
-Where one party communicates their intention not to perform the contract, the innocent
part need not to wait until the breach has occurred before bringing their claim.
-they may sue immediately or they can choose to continue with the contract and wait for the
breach to occur.
-Where the breach is of a warranty – the aggrieved party may receive damages only – if they
mistakenly treat the contract as repudiated and fail to fulfil their own obligations then they
themselves will have committed a serious breach (Hong Kong Fir) - even if acting in good
faith!
-Warranties are minor terms of a contract which are not central to the existence of the
contract. If a warranty is breached the innocent party may claim damages but cannot end the
contract:
Bettini v Gye (1876)
- Bettini agreed by contract to perform as an opera singer for a three-month period
- He become ill and missed 6 days of rehearsals
- The employer sacked and replace him with another opera
HELD
- Bettini was in breach of warranty and therefore, the employer was not entitled to end
the contract
- Missing the rehearsals did not go to the root of the contract.
Repudiatory Breach
Renunciation: Person who’s obligated to perform but refused to do it.
Eminence Property Developments Ltd v Heaney (2010)
Remedies
- Solution / what you can get as an injured party
Severe breach
- Can terminate contract
- Non-severe: cannot terminate
- If Council considered the breach is not severe, the claimant is considered making a
severe breach
Rule of election
Where there has been a breach of a condition or an innominate term the innocent party has
the right of election – innocent party may choose whether to affirm the contract or to
terminate it (but can always claim damages)
Innocent party must make his decision known to the defaulting party (The Santa Clara)
– must be clear and unequivocal
· Innocent party will only be bound by his decision where he knows of the right of
election (Peyman v Lanjani)
· Innocent party given time to decide (Stoczbia Gdanska v Latvian Shipping Co)
Discharge by Frustration
- A change in circumstances after contract was made
- Not the fault of either of the parties
- Resulted of contract to be impossible to perform
- Outside of control of both parties
- If frustrated, each party is discharged from future obligations under the contract and
neither party may sue for breach
Requirements
- Supervening
- Radically different
- Contracts makes no sufficient/ provision
- Unforeseeable
- At no fault of either party
Supervening Illegality
-contract becomes illegal to perform
Fibrosa Spolka v Fairbairn (1943)
-An English company which manufactured textile machinery agreed by contract
dated 12th July 1939 to supply some machines to a Polish company.
-The machines were to be delivered in 3-4 months.
-£1,600 was payable up front and the balance of £3,200 payable on delivery.
-The Polish company paid £1000 on 18th of July on account of the initial payment
due.
-On 1st Sept Germany invaded Poland and on 3rd Sept Great Britain declared war
on Germany.
-On 23rd of September Orders in Council made Poland an enemy territory making
it illegal for British companies to trade with Poland.
HELD:
-the contract was frustrated as it was no longer possible to perform the contract
because of the supervening illegality.
The defendant hired a flat on Pall Mall for the sole purpose of viewing King
Edward VII's coronation procession. The price agreed was £75 for two days. The
defendant paid £25 deposit. Due to illness of the King the coronation was
cancelled. Consequently, the defendant did not use the flat. The claimant sought
to claim the outstanding £50.
Held:
Davis Contractors agreed to build 78 houses for Fareham Council within 8 months for an
agreed price of £85,000. Due to a shortage in skilled labour and material the contract
took 22 months to complete and was much more expensive than anticipated. Davis
Contractors were paid the contractually agreed price but bought an action arguing for
more money based on the fact that the contract had become frustrated and therefore
they were entitled to further payment based on a quantum meruit basis.
HELD:
The contract was not frustrated. The fact that a contract becomes more difficult to
perform or not so profitable is not sufficient to amount to frustration. It was still possible
to perform the contract.
The defendant agreed to ship some Sudanese peanuts during November or December
1956 to Hamburg for a certain price. On 2nd of Nov the Suez-canal was closed to
shipping. The defendant could still have transported the peanuts within the contractually
agreed time but this would mean going via the Cape of Good Hope which would have
taken four times as long and increased the cost of transport considerably. The defendant
did not carry the goods and argued that the contract had been frustrated.
HELD:
The contract was not frustrated. It was still possible to perform the contract without any
damage to the peanuts. The fact that it was more difficult or costly to perform is not
sufficient to amount to frustration.
The claimant owned five fishing vessels one of which was chartered to the defendants.
The fishing vessels were all fitted with otter trawler nets. New legislation was introduced
requiring licences to be held by those using otter trawl nets. The claimant applied for five
licences but was only granted three. He had to name which vessels the licence would be
used on. He named his own vessels and excluded the vessel which the defendant was
using. This meant that the defendant was unable to use the vessel for fishing. The
claimant sued the defendant for the price of hire and the defendant in his defence stated
the defendant had committed a breach in not providing a license so he was not obliged
to pay for the cost of hire. The claimant argued there was no breach as the failure to
provide a license was a frustrating event in that the decision to grant licenses rested with
the secretary of state.
Held:
The contract was not frustrated since the claimant had chosen to keep the three licenses
granted for himself rather than using one to fulfil his contractual obligation. He had
therefore induced the frustrating event and was therefore in breach of contract.
Held:
The delay had been so long as to put an end to the contractual obligations. It was the
happening of the event and not the fact that the event was the result of a breach by one
party of his contractual obligations that relieved the other party from further performance
of his obligations.
4. Where the frustrating event could be foreseen
A hotel owner entered a contract with an advertising agency enabling them to put
illuminated adverts on the roof of their hotel. The hotel was then compulsorily purchased
by the Local Authority and demolished. The advertising agency sued for breach of
contract and the hotel argued the contract had become frustrated.
Held:
The contract was not frustrated as the hotel owners were aware that the Local Authority
were looking to purchase the hotel at the time, they entered the contract. They should
have foreseen the fact that this could happen in the life time of the contract and made
provision in the contract for such an eventuality. They were therefore liable to pay
damages for breach of contract.
The claimant, an English company, purchased some ant’s eggs from the defendant in Finland.
The ant’s eggs required an export license. The after agreeing to the sale, the defendant was
refused the license. The claimant brought an action for breach of contract. The defendant
argued the contract was frustrated so they were not liable for breach.
Held:
The defendant should have foreseen the possibility of the license being refused and therefore
the contract was not frustrated.