STANDARD EQUIPMENT CAPABILITY ESTIMATES

ITEM NO. TYPE OF WORK EQUIPMENT USED CAPABILITY ADOPTED


100 Clearing and Grubbing Bulldozer 3200 - 4000 sq.m./day

102 Excavation Bulldozer 200 cu.m./day


Compaction Road Roller 240 - 320 cu.m./day

104 Embankment Payloader 240 - 320 cu.m./day


Compaction Road Roller 240 - 320 cu.m./day
Quarrying Bulldozer 400 cu.m./day

105 Sub-grade Preparation Grader 2400 sq.m./day


Compaction Road Roller 240 - 320 cu.m./day

200 Aggregate Sub-Base Course Grader 2400 sq.m./day


Road Roller 240 - 320 cu.m./day
Water Truck 8000 sq.m./day

STANDARD MANUAL CAPABILITY ESTIMATES


ITEM NO. TYPE OF WORK MANPOWER REQT. CAPABILITY ADOPTED

100 Canal Excavation 3.00 cu.m./day


Backfilling 2.00 cu.m./MD

103 Structure Excavation 1.5 cu.m./MD

200 Agg. Sub-Base Course


Spreading 2.50 cu.m./MD

500 RC Pipe Culverts


12" Crew Foreman 16 pcs/day
18 Mason 14 pcs/day
24 Carpenter/Steelman 12 pcs/day
30 12 Laborers 10 pcs/day
36 1 bagger mixer 8 pcs/day
10 mins/bag

504 Grouted Riprap Crew Foreman 7.50 cu.m./day


2 - mason
10 - Laborers
1 bagger mixer

5 Stone Masonry
Laying of Materials Boulders 1.50 cu.m./day
Concreting Crew Foreman 6.00 cu.m./day
2 - Mason
10 - Laboreres
1 bagger mixer
STANDARD SPECIFICATIONS FOR HIGHWAYS, BRIDGES AND AIRPORTS

PART I EARTHWORKS:
Item 100 - Clearing and Grubbing
Item 101 - Removal of Structures and Construction
Item 102 - Excavation
Item 103 - Structure Excavation
Item 104 - Embankment
Item 105 - Sub-grade Preparation
Item 106 - Compaction Equipment and Density Control Strips
Item 107 - Overhaul

PART II SUB-BASE & BASE COURSE:


Item 200 - Aggregate Sub-base Course
Item 201 - Aggregate Base Course
Item 202 - Crushed Aggregate Base Course
Item 203 - Portland Cement Stabilized Road Mix Base Course
Item 204 - Asphalt Stabilized Road Mix Base
Item 205 - Portland Cement Treated Plant Mix Base Course
Item 206 - Aggregate Stockpile

PART III SURFACE COURSE:


Item 300 - Aggregate Surface Course
Item 301 - Bituminous Prime Coat
Item 302 - Bituminous Tack Coat
Item 303 - Bituminous Seal Coat
Item 304 - Bituminous Surface Treatment
Item 305 - Bituminous Penetration Macadam Pavement
Item 306 - Bituminous Road Mix Surface
Item 307 - Bituminous Plant Mix Surface Course-General
Item 308 - Bituminous Plant Mix Surface Course-Cold Land
Item 309 - Bituminous Plant Mix (Stocking Maintenance Mix)
Item 310 - Bituminous Concrete Surface Course, Hot Land
Item 311 - Portland Cement Concrete Pavement

PART IV BRIDGE CONSTRUCTION:


Item 400 - Piling
Item 401 - Railing
Item 402 - Timber Structures
Item 403 - Metal Structures
Item 404 - Reinforcing Steel
Item 405 - Structural Concrete
Item 406 - Pre-Stressed Concrete Structure
Item 407 - Concrete Structure
Item 408 - Steel Bridges
Item 409 - Welded Structural Steel
Item 410 - Treated and Untreated Timber
Item 411 - Paint
PART V DRAINAGE AND SLOPE PROTECTIONS STRUCTURES:
Item 500 - Pipe Culverts and Storm Drains
Item 501 - Under Drains
Item 502 - Manholes, Inlets, and Catch Basin
Item 503 - Metal Structures
Item 504 - Riprap and Grouted Riprap
Item 505 - Stone Masonry
Item 506 - Hand Laid Rock Embankment
Item 507 - Sheet Piles
Item 508 - Concrete Slope Protection
Item 509 - Gabions

PART VI MISCELLANEOUS:
Item 600 - Curb & Gutter
Item 601 - Side Walk
Item 602 - Monuments Marker and Guide Posts
Item 603 - Guard Rail
Item 604 - Fencing
Item 605 - Road Sign
Item 606 - Pavement Markings
Item 607 - Reflecting Pavement Stud
Item 608 - Top Soil
Item 609 - Springing
Item 610 - Sodding
Item 611 - Tree Plant

PART VII MATERIAL DETAILS:


Item 700 - Hydraulic Cement
Item 701 - Construction Lime
Item 702 - Bituminous Materials
Item 703 - Aggregates
Item 703-A - Mineral Filler
Item 704 - Masonry Limit
Item 705 - Joint Minerals
Item 706 - Concrete Clay, Plastic & Fiber
Item 707 - Metal Pipe
Item 708 - Concrete Curing Materials & Admixture
Item 719 - Paints
Item 710 - Reinforcing Steel & Wide
Item 711 - Fence and Guard Rail
Item 712 - Structural Metal
Item 713 - Treated & Untreated Timber
Item 714 - Water
MANPOWER REQUIREMENT AND MINIMUM QUANTITY SURVEY

1. Formworks

Team: 1 Senior Carpenter


3 Junior Carpenter

• for every 10 Teams provide 1 Supervisor

MQS: 20.16 sq. m./day/team for Fabrication


8.29 sq. m./day/team for Installation

2. Steelwork

Team: 1 Lead man


4 Helpers (Benders and Cutters)

MQS: 25 mm. Dia. = 5 to 6 m. length/day


10 mm. Dia. = 10 to 16 m length/day

3. Tileworks

Team: 1 Senior Mason (Places Tiles)


1 Laborer/Jr. Mason (Mixer/Placer)

MQS: 2 sq.m./day/team

4. Welding Works (structural steel/penetration)

Team 1 Senior Welder


2 Junior Welder

MQS: 200 kg. Or 0.20 metric tons/day/team


MANPOWER AND EQUIPMENT CAPABILITY/PROJECT PARAMETERS

• Compaction of Existing Ground After Stripping

Production: 350 cu. m. hr

Equipment: 1 DG Cat Dozer


1 GT Dyna CC-20 Vibro Roller
Water Truck (3000 Gals.)
1 3” dia. Water Pump

crew : 1 Operator
2 Drivers
2 Helpers

• Excavation and Earthmoving

A. Excavation along Earth cuts

Production: 20 cu. m./hr

Equipment: 1 DG Dozer

Crew : 1 Operator
6 – 10 Helper

Manual Labor: 2.50/cu.m./manday (soft)


1.50/cu.m./mandy (rock)

B. Filling with Compaction

Production: 120 cu. m./hr

Equipment: 1 Grader (120 G Cat)


1 GT Dyna CC-20 Vibro Roller
1 Water Truck (3000 gals.)
1 2” dia. Water Pump

Crew : 5 Operators
2 Drivers

C. Hauling/Disposal of Stripped Earth

1) Distance: 320 – 300m

Production: 57 cu. m./hr

Equipment: 1 – 2 ½ cu. yd. 950 Loader


2 – 6 to 8 cu. yd. Dump Trucks
2) Distance: 1 km

Production: 45 cu. m./hr

Equipment: 1 – 2 ½ cu. yd. 950 Loader


2 – 6 to 8 cu. yd. Dump trucks

3) Distance: 2 km

Production: 35 cu. m./hr

Equipment: 1 – 2 ½ cu. yd. 950 Loader


2 – 6 to 8 cu. yd. Dump Trucks

4) Distance: 3 km.

Production: 57 cu. m./hr.

Equipment: 1 – 2 ½ cu. yd. 950 Loader


3 – 6 to 8 cu. yd. Dump Trucks

5) Distance: 4 km.

Production: 35 cu. m./hr.

Equipment: 1 - 6 to 8 cu. yd. 950 Loader


3 – 6 to 8 cu. yd. Dump Trucks

6) Distance: 5 km.

Production: 57 cu. m./hr.

Equipment: 1 – 2 ½ cu. yd. 950 Loader


4 – 6 to 8 cu. yd Dump Trucks
CAPABILITIES OF EQUIPMENT

ITEM TYPE OF WORK CAPABILITY

1. Dozer a) Clearing 500 sm/hr


b) Stripping 200 sm/hr
c) Quarrying 50 sm/hr
d) Excavation 25 sm/hr
e) Pushing 3 cm/hr

2. Grader a) sub-grading 300 sm/hr


b) spreading 50 cm/hr

3. Pay Loader a) loading 30 cm/hr

4. Crane Shovel a) loading 35 cm/hr

5. Sheep foot a) static rolling (12 passes-15 cm lift) 45 cm/hr


Roller b) vibratory rolling (4 passes-15 cm lift) 135 cm/hr

6. No. 3 Road a) static rolling (6 passes-15 cm lift) 24 cm/hr


Roller

7. Tractor-drawn a) vibratory rolling (6 passes – 2 cm lift) 240 cm/hr


Roller (1-D)

8. Tander Roller a) static rolling 96 passes-20 cm lift) 24 cm/hr

9. 5-T Dump truck a) Hauling Common Borrow 3.5 cm /hr


b) Hauling SEBC (Selected borrow, 5 cm/trip
basecourse)
c) Hauling Concrete batch class “A” 3 batch/trip

10. 2 ½ DT a) Hauling Common Borrow 2.5 cm/trip


b) Hauling SEBC (Selected borrow, 2 cm/trip
basecourse
c) Hauling concrete batch class “A” 2 batch/trip

11. Buggy a) Hauling concrete mix 6 cm/trip

12. Wheel Borrow a) Hauling aggregate 2.5 cm/trip


b) Hauling concrete mix 1.7 cm/trip

13. Water Truck a) Watering 1000 sm/hr

14. Asphalt a) Spraying asphalt prime coat 300 sm/hr


Distributor
15. 165 Conc. Mixer a) Mixing concrete 9 cm/hr

16. Rock Crusher a) Crushing mixed sand and gravel 30 cm/hr

17. Conc. Vibrator a) Vibrating concrete mix 40 cm/hr

18. Conc. Floor a) Finishing concrete floor 140 sm/hr


Finisher

19. Scraper lowed a) Hauling heap capacity 11 cm/trip

20. Percussion a) Drilling hard rock 0.75 f/hr


b) Drilling loose rock 1 f/hr
c) Drilling lime stone 1.25 f/hr
d) Drilling sticky clay 1.60 f/hr
e) Drilling loose clay 2.50 f/hr
CONSTRUCTION WORK CAPACITIES IN MANHOUR

ITEM TYPE OF WORK CAPABILITIES

1. Earth works a) Excavation 3.13 – 4.10 manhours/cm


b) Backfill 2.29 manhours/cm

2. Formworks a) Footings, gradeboams & columns 22 manhours/100 sf


b) Beams, bond beams & floor slabs 26 manhours/100 sf
c) Roof beams and bond beams 28 manhours/100 sf
d) Roof slab 31 manhours/100 sf
e) Edging (100”) for roof 16 manhours/100 sf
f) Grade slab edging (4”) 14 manhours/100 sf
g) Retaining walls 28 manhours/100 sf
h) Stairs and landings 23 manhours/100 sf
i) Form oil application 0.60 manhours/100 sf

3. Reinforcement a) Reinforcement of footing up to


roofing____take an ave. of_____ 4 manhours/100 lbs
b) floor slab 1.2 manhours/100 sf
c) floor membrane 1.4 manhours/100 sf

4. Concrete Work a) Column, footings, wall footings,


grade beams, grade slabs 1.31 manhour/cm
b) Floor beam & bond beams 2.84 manhour/cm
c) Floor slabs (suspended) 2.62 manhour/cm
d) Roof beam & bond beams 2.41 manhour/cm
e) Stairs 2.62 manhour/cm
f) Roof slabs 2.93 manhour/cm
g) Curing (water) 2 manhour/day for 7 days
h) Equipment
1. Vibrator 15 manhour/cm
2. Crane 3 cm/manhour
CAPABILITIES OF MANUAL LABOR

UNIT TYPE OF WORK CAPABILITY

1. One Man a) Excavation loam or sand 0.76 cm/hr


b) Excavation clay or heavy soil 0.61 cm/hr
c) Excavation of rock 0.33 cm/hr
d) Backfilling 1.22 cm/hr
e) Spreading, tampering & grading 2.09 cm/hr
f) Placing scramble fill 4.78 cm/hr
g) Placing binders 9.56 cm/hr
h) Clearing undergrowth and small brush 40 sm/hr
i) Clearing undergrowth and truss 20 sm/hr

2. One Mason & One a) Laying CHB and Adobe 2 sm/hr


helper b) Cement finish 2.80 sm/hr

3. One Carpenter & a) Erecting forms 1.86 sm/hr


One helper b) Removing forms 1.86 sm/hr

4. One Mechanic & a) Operational maintenance and repair of 3 equipments


One helper engineering equipments

EMPIRICAL REQUIREMENTS FOR VARIOUS STRUCTURES

I. Box Culverts

Forms = 60 bf/cm of concrete


Bars = 80 kg/cm of concrete
Nails = 1.5 kg/cm of concrete
Tie Wire = 0.80 kg/cm of concrete

II. Bridges

Forms = 60 bf/cm of concrete


Bars = 120-150 kg/cm of concrete
Nails = 2 kg/cm of concrete
Tie Wire = 1.1 kg/cm of concrete

III. Grouted Riprap

4 bags cement/cm of riprap


0.68 cm of sand/cm of riprap
DIESEL
EQUIPMENT ENGINE OIL GREASE GEAR OIL GASOLINE
FUEL
1. Payloader 10 liters/hr 3 liters/day 1 lb./day 1 liter/day

2. Bulldozer 12 liters/hr 3 liters/day 1 lb./day 1 liter/day

3. Road Grader 10 liters/hr 3 liters/day 1 lb./day 1 liter/day

4. Road Roller 2 liters/day 2 lbs./week 6 liters/hr


(5 tons)

5. Road Roller 5 liters/hr 2 liters/day 2 lbs./week 1 liter/week


(5-8 tons)

6. Road Roller 5 liters/hr 2 liters/day 1 1 liter/week


(10-12 tons) liters/week

7. Crane Truck 4 liters/day 1 liter/day 12 liters/hr


2 lbs./day

8. Pneumatic 1 liter/day 1 liter/week 6 liters/hr


Tractor ½ lb./day

9. Truck Tractor 2 kms./liter 1 liter/day


with trailer 1 lb./week

10. Water Truck 1 .5 liters/day 1 liter/week 8 liters/hr


with Pump 1 lb./day brake fluid-
1pint/week

11. Pave 6 liters/day 2 litters/day


1 lb./day
12. Dump truck 3 kms./liter 1 liter/day 2 liter/week
1 lb./week brake fluid-
1 pint/week

13. Tractor 80 liters/day 2 liters/day 1 liter/day


Crawler (D-7) 2 lbs./day

14. Stake Truck 8 1 liter/km 1 liter/day ½ liter/day


tons 1 lb./day

15. Conc. Mixer 4 ½ liter/day 60 liters/day


Bagger ½ lb./day

16. Jeep 4 wheel 1 liter/day ½ lb./day 1 liter/day 30 liters/day


drive
AVERAGE POL CONSTRUCTON FOR VARIOUS CONSTRUCTION EQUIPMENT/DAY
ACCOUNT & CONTRACT WORKS GUIDELINE

I. MECHANIZED ASPECT:
A. Clearing & Grubbing

PRODUCTION ( SQ. M. /HR.

DOZER
BOFSE DENSE OF VEGETATION (NO. OF TREES/HAS.
POWER

0-50 51 – 100 101 - 200 201 - 250 251 & >

120 360 250 190 160 130


140 420 290 220 185 150
160 480 330 255 210 170
180 540 375 285 240 195
200 600 420 310 265 215

B. Excavation : Common Materials


B.1. CRANE

Pro. (cu. m/hr.) Bank Volume


Tonnages
Canal Structure Creek

10 – 15 15 10 10
15 – 20 25 15 15
20 – 25 30 20 20
25 - 30 35 25 25

B. 2. DOZER

Pro. (cu. m/hr.) Bank Volume


Horse Power
Canal Structure

120 30 10
140 40 15
160 50 20
180 60 25
200 70 30
B. 3. BACKHOE

Production (cu. m/hr.) Bank Volume


Bucket
Canal Structure Creek

0.50 20 15 15
0.75 30 20 20
1.00 35 25 25
1.25 40 30 30
1.50 50 35 35

C. Quarrying

Production (cu. m/hr.) Bank Volume Loose


Dozer
Excavated Mat.
( H. P.) Common Aggregate Col/Bol
( cu .m.)

140 40 30 10 70
160 50 40 15 80
18 60 55 20 90
200 75 70 25 100

D. Loading

Production (cu.m/hr.) Bank Volume


Bucket (cu. m.)
Common Aggregate Cobbles/Boulders

1.0-1.5 70 80 30
1.5-2.0 100 110 40
2.0-2.5 130 140 50
2.5-3.0 150 160 60

E. Spreading

Production (cu. m/hr.) Cmp.


Grader (H.P)
Common Aggregate

80 – 100 60 70
100 – 125 70 80
125 – 150 90 100
150 - 175 100 110

F. Side Borrow (Common Mat.)

Production (cu. m/hr.) Compacted Vol.


Dozer (H.P)
80 – 100 35
100 – 125 40
125 – 150 45
150 – 175 55
G. STR. BACKFILL w/Comp.

Production (cu. m/hr)


Dozer (H.P)
Compacted Vol.

140 50
160 70
180 80
200 90

H. Embankment Compaction

Cap. Cu. m/hr Comp. Volume


Tons
Vibratory Static

3–5 60 40
6 – 10 70 50
11 – 15 80 60

I. Loading, Spot & Maneuver & Delay Time


Used Loader : 1.00 cu. m. Bucket

Cobbles/
Road Surface
Dump Truck Capacity Common Materials Boulders
Materials
4.00 cu. m. 10 min. 12 min. 15 min.
6.00 cu. m. 12 min. 15 min. 17 min.
8.00 cu. m. 17 min. 17 min. 20 min.
J. Average Speed of Dump Truck (Kilometer per hour)
Haul dist. Good Poor Haul dist. Good Poor
Km. Maintained Maintained Km. Maintained Maintained
Road Road Road Road
0.30 18.00 13.00 11.00 46.00 30.50
0.40 19.00 14.00 12.00 47.00 31.00
0.50 20.00 15.00 13.00 48.00 31.50
0.60 21.00 16.00 14.00 49.00 32.00
0.70 22.00 17.00 15.00 50.00 32.50
0.80 23.00 18.00 16.00 51.00 33.00
0.90 24.00 19.00 17.00 52.00 33.50
1.00 25.00 20.00 18.00 53.00 34.00
2.00 27.00 21.00 19.00 54.00 34.50
3.00 30.00 22.00 20.00 55.00 35.00
4.00 32.00 23.00 21.00 55.00 35.00
5.00 35.00 25.00 22.00 55.00 35.00
6.00 37.00 26.00 23.00
7.00 39.00 27.00 24.00 same speed
8.00 41.00 28.00 24.00 to all
9.00 43.00 29.00 26.00 succeeding
10.00 45.00 30.00 27.00 haul distance
NOTE: Free haul dist. is limited to 200m.
H. Demolition of Concrete:
300 CFM Compressor & two (2) Jackhammer
Cap. = 15.00 cu. m. /day for massive concrete
= 20.00 cu. m./day for slab & wall
160 CFM Compressor & two (2) Pavement Breakage
Cap. = 8.00 cu. m. /day for massive concrete
= 12.00 cu. m./day for slab & wall
L. Diving of Piles:
Steel Piles : Crane 25 tons w/ 2-tons drop Hammer: Cap. = 20ml/hr
Conc. Piles : Crane 25 tons w/ 7500 kgs. - m pile hammer
Cap : 2.00 mt/hr. & 4.00 m/hr. for thick & thin concrete piles

M. Fuel & Oil Consumption


Equipment Fuel Oil & Lub Equipment Fuel Liter / Oil & Lub
Liter/hr road hr. Liter /hr.

DOZER GRADER
55 – 84HP 12 0.24 60-75hp 14 0.25
85 – 114HP 15 0.33 110-130hp 15 0.28
132 – 159HP 17 0.40 180-200hp 18 0.50
180 – 200 HP 23 0.50

BACKHOE CRANE
.10 – 45 m 10 0.68 10-15 tons 6 0,25
.70 – 1.0cm 18 0.76 16-20 tons 10 0.40
1.1-1.5cm 32 0.94 21-25 tons 12 0.50
D. TRUCK
4-6 cu.m. 7 0.25
7-8 cu.m. 9 0.30
Wh. Loader MIXER
.75 – 1.0cm 7 0.35 1 Bagger 1 0,05
1.1 - 1.5cm 11 0.38 2 Bagger 2 0.06
1.5 – 2.0cm 16 0.50 C. Vibrat. 1 0.05
Compressor
Compactor (cf m)
Static
5 – 10 tons 5 0.25 350-450 9 0.25
11 – 20TC 7.5 0.40 251-315 8 0.20

Vibrator Water Truck 7 0.25


1 – 3 tons 4 0.30
4 – 6 tons 8 0.50 Cargo Truck
6-7 tons 7 0.25
Water Pump 8-10 tons 8 0.30
2” 1.5 0.05
4” 4.0 0.08 Farm Truck 6 0.20
6” 6.5 0.10
8” 9.0 0.15

II. MANUAL ASPECT


A. EXCAVATION
A.1. Common Material

Cap. (cu.m.) Depth of less Bank Volume excavation


TYPE OF WORK
2m more than 2m

Farmditche 3.50 3.00


Canal 3.00 2.50
Structure 1.5 2.00

A.2 Slight hd. Matl (Ind)

TYPE OF WORK CAP. (cu. m/day/man) Bank


Volume

Canal 1.00
Structure 0.75

B. LOADING: Util. five (5) LABORERS

Total time per cubic meter

Sand & gravel Cobles Boulder


15 min. 17 min 20 min
C. UNLOADING: Util. 5 LABORER

Total time per cubic meter

Sand & gravel Cobles Boulder


11 min. 12 min 15 min

D. CUT, BEND & PLACE RSB

Structure 1 Steel man & 1 Helper


with bar cutter

Dam 96 kgs/day
Siphon 112 kgs/day
Bridge 100 kgs/day
Other 80 kgs/day

E. QUARRYING

Cu. m/day/man
Capability

Sand & Gravel Cobles Boulder


3.50 2.50 2.00

F. DEMOLITION OF CONCRETE

Slab & Wall 0.35 cu/day/man


Massive Conc. 0.20 cum/day/man

G. SCREENING OF AGGREGATES

Gravel 4.00 cum/day/man


Sand 6.00 cum/day/man

H. MANUAL BACKFILL
Cap : 2.00 cu.m./day/man

I. LAYING OF MATERIALS (cum/day/man)


Cobbles=2
Boulders=1.50

J. SPREADING OF AGGREGATE (cum/day/man)


Cap : 2.50
K. RUBBLE MASONRY (Concreting)
Crew:1-foreman, 2 mason
10-Laborer & L.E. Operator
Cap. = 6.00 cum/day

L. GROUTED RIPRAP
Crew: 1-Foreman, 2-Mason
10-Lab. & 1-L.E. Operator
Cap.: 7.50 cum./day

M. C.H.B. : Setting Cap. (sqm/d)


Crew: 1-Mason, 2 Laborer
: Fence : Building
4” CHB : 14 : 10 = 125 pcs/day
6” CHB : 10 : 8 = 100 pcs/day

N. CONCRETE LINING:
Crew: 1-foreman, 2 mason, 1
L.E. Operator 10-lab. w/ 1 Bagger mixer
Capability = 4.50 cu. m./day

O. INSTALLATION OF STEEL GATES


Crew 1-manson & 5 - Laborer
16x16 to 24x24 : 2 assy/day
above 24x24 : 1 assy/day

P. CONCRETE WORKS
P – 1. Fabrication, Placing & dismantling of forms
Crew : 2 - carpenter & 4 – laborer : Cap. = 2.00 cu. m./day for 3000psi
:1 – carpenter & 1 – laborer : Cap. = 4.50 cu.m./day Canal lining

P – 2. Concreting & Curing


P – 2a With concrete mixer
Crew : 1 –1 foreman, 2 – mason, 1 - L.E. Operator & 8 – laborer
Cap. = 3.50 cu. m./day for Class “A” : 4.50 cu. m./day for Class “B”.
=3.50 cu. m./day for Class “C” : 4.50 cu. m./day for Lean Concrete

P – 2b. Without concrete mixer


Crew : 1 – foreman, 2 – mason, and 10 – laborer
Cap. = 2.50 cu. m./day for Class “A” : 3.20 cu. m./day for Class “B”
=3.50 cu. m./day for Class “C” : 4.50 cu. m./day for Lean Concrete

Q. PLASTERING OF C.H.B. WALL


Crew : 2 – mason and 2 – laborer
Capability = 12 sq. m./day (one side only) = 150 pcs/day
Both sides = 75 pcs/day
R. Reinforced Concrete Pipes

Capability
DIAMETER
CREW
Installation
In. cm. Fabrication
1 – Foreman 12 30 15 16
1 – Mason 18 46 11 14
1 – Carp./Steel man 24 61 9 12
12 – Laborers 30 76 6 10
with 1 Bagger Mixer 36 91 5 8
48 122 3 6
NOTE:
TIME OF MIXER/DAY=BAGS OF CEMENT /DAY X 10 MIN./BAG
60 MINUTES/HOUR
III. MATERIAL ASPECT

CLASS STRENGTH Max. Cement Sand Gravel Boulder


Aggregate bag/cum Cum/cum Cum/cum Cum/cum
inches

A. CONCRETE
a) 3000 psi 1.50 9.00 0.45 0.90 -
b) 2400 psi 2.00 7.00 0.50 1.00 -
c) 2400 psi 3.00 6.50 0.52 1.04 -

Canal Lining 1.00 7.50 0.48 0.96 -


2400 psi

B. Rubble Masonry 4.25 0.25 0.375 0.95


w/3000 psi
4.00 0.22 0.05 1.00
C. Grouted Riprap

D. Lean Concrete 5.00 0.50 1.00 -


1000 psi
0.20 1.00 -
E. Gravel Blanket -
0.90 0.40 -
F. Filter Drain -

G. Other Materials

C
L
A Strength E. lumb. 1/2pl. wd Tie wr. Nail
S TYPE OF STR
S
Psi Bdft/cum pcs/cum Kgs/cum Kgs/cum

A Bridge/Flume 3000 40 1.00 1.25% RSB 2.25


A Siphon/box culvert 3000 25 1.00 1.20% RSB 2.00
A Other Struc. MC 3000 20 1.25 1.10% RSB 1.75
A Other Struc. T.Fac. 3000 15 1.15 1.10% RSB 1.50
A Rubble Masonry 3000 5 0.15 - 0.75
C Canal Lining 2400 5 - - 0.25
A Dam 3000 15 0.10 1.00% RSB 1.00
A Dam 2400 5 0.10 1.00% RSB 1.00
F. REINFORCE CONCRETE PIPES

Fabrication Materials
Diameter Cement
G.I.
Inches bag Gravel F. Lumber R.S.B.
Sand cu.m. Sheet
cu.m. bd.ft. kgs.
L.F.

12 0.58 0.02 0.05 0.12 0.24 5.28


18 1.22 0.05 0.10 0.19 0.36 7.72
24 1.82 0.08 0.15 0.24 0.48 9.77
30 2.52 0.11 0.21 0.30 0.60 23.22
36 3.33 0.14 0.28 0.34 0.72 50.43
42 4.28 0.18 0.36 0.40 0.84 60.84

F.a Installation of R.C.PIPES

Diameter Cement Sand Gravel R.S.B. F. Lumber CWN. &


inches bag Cu.m. Cu. m. kgs Bdft. TWIRE
Kgs

12 0.21 0.01 0.02 - 2.00 0.20


18 0.45 0.02 0.04 3.65 2.00 0.20
24 0.72 0.03 0.06 4.52 3.00 0.30
30 0.93 0.04 0.08 5.26 3.00 0.30
36 1.11 0.05 0.10 6.01 4.00 0.40
42 1.32 0.06 0.12 6.79 4.00 0.40

G. PLASTERING C.H. BLOCK

SIZE Materials per sq. m.


(for two side)
Sand Cement
4&6 0.038 0.45

G.1. LAYING OF C.H.B.

SIZE CEMENT SAND


Bag/sqm. Cu/sq.m.

4” 0.55 0.047
6” 1.07 0.091
IV. COSTING ASPECT:

A. Computation of Gross Rates for Agency Manual Labor per Day


G. R. = BRI + COLA + AA + IA + M + TI + EFSA + MA
Where : GR=Gross rate per day BR1 = Basic Current Rate/day
BR2 = Basic Previous Rate per day

COLA : Cost of Living Allo. Per day=(P550/m)/(22d/m)=P25.00/day


AA : Allowance per pay =0.10 BR1/day
A1 : Incentive Allo. Day=(( BRX30 + o.10BR x 30 + 550/Y))/
(12M/Y x 22DAY/MO.)
= P.01875BR1 + P3.125
T1 : Term Insurance/day = (P12.00/y)/(12m/yx22d/m) = P0.05/day
EL : Earned Leaves/day = (BR1/dx30d/m)/ (12/yx22d/m) = P0.11bri1/d
EFSA : Emergency Food Subsidy Allowance per day
= (P200/m – (BR1-BR2) (22d/m) /(22d/m)/(22d/m) = P9.09/day – BR1 + BR2
NA : Medical Allowance per day = (P200/m)/(22d/m) = P9.09/day
M : Medicare (Govt. Share) per day = (P7.50/m)/(22d/m)=P0.34/d
G.R : BR1 + P25 +P0.10BR1 + P0.187BR1 + P3.125 + P0.05+P0.11BR1
+ P9.09 – BR1 + BR2 + P9.09 + P0.34
= P0.3975BR1 + BR2 + P46.695