Академический Документы
Профессиональный Документы
Культура Документы
Table of Contents
1.0-INTRODUCTION
This Environmental Assessment (EA) has been prepared to disclose the potential environmental
consequences associated with Washington County Water Conservancy District’s (WCWCD) proposed Ash
Creek Project and Toquer Reservoir Recreation Area in Washington County, Utah (Figure 1). This EA is
a site-specific analysis of potential impacts that could result with the implementation of the Proposed
Actions or alternatives to the Proposed Actions. This EA assists the Bureau of Land Management (BLM)
in project planning and ensuring compliance with the National Environmental Policy Act (NEPA), and in
making a determination as to whether any “significant” impacts could result from the analyzed actions.
1.1 SUMMARY OF THE PROPOSED PROJECT
The Washington County Water Conservancy District (WCWCD) filed an application with the Bureau of
Land Management (BLM) St. George Field Office for a right-of-way (ROW) and a Recreation and Public
Purposes (R&PP) Act lease on BLM-managed lands in Washington County, Utah for the construction,
operation, and maintenance of the proposed Ash Creek Project and Toquer Reservoir Recreation Area
(Project).
The WCWCD’s proposes to construct a new water system that would provide an alternate source of water
for the Toquerville Secondary Water System (TSWS) and, through exchange, allow Toquerville Springs
water, the current TSWS source, to be delivered as municipal drinking water in Toquerville, LaVerkin and
Hurricane. From the base of the existing dam on Ash Creek Reservoir, the Project would install 18.8 miles
of pipeline and associated facilities, continuing in a southerly direction to the proposed new reservoir and
public recreation area at Anderson Junction. The Project would be developed on lands administered
primarily by the BLM St. George Field Office, with additional areas of state lands administered by the Utah
School and Institutional Trust Lands Administration (SITLA) and private land also included.
The sources of water for the Project would be surface flows from Ash Creek that are impounded in the Ash
Creek Reservoir and in the Ash Creek watershed below the reservoir. The WCWCD has a water right
(Water Right # 81-351, priority date 1956) to 10,000 acre-feet from the Ash Creek Reservoir but does not
have a pipeline system in place to convey water from this reservoir. Surface flows in the tributary streams
of Leap Creek, South Ash Creek, and Wet Sandy are fully appropriated water rights held by multiple
entities. See Appendix F for a detailed list and analysis of water rights. Each of these tributaries has an
existing diversion structure that has historically diverted water into open, unlined ditches for agricultural
use. To conserve water, the WCWCD installed a pipeline from the diversion on Leap Creek to replace an
open ditch in 2003 and upgraded the diversion structure on Wet Sandy and piped the open ditch in 2010.
The proposed R&PP lease and subsequent patent area is for approximately 13 acres of BLM-administered
lands for development of the Toquer Reservoir Recreation Area. The recreation area is located within the
municipal boundary of Toquerville City, Washington County, Utah. The recreation area would provide an
additional outdoor venue including camping, picnicking, and hiking as well as interpretive kiosk and
overlook area.
The Project’s area is defined as Sections 23, 26, 27, 28, 29 and 32, Township 42 South, Range 14 West;
Sections 5, 6 and 7, Township 43 South, Range 14 West; and Sections 1, 2, 3 and 12, Township 43 South,
Range 15 West. Refer to Figure 1.
1
DRAFT Environmental Assessment
Ash Creek Pipeline and Toquer Reservoir
1.2 PURPOSE AND NEED OF THE BLM
The BLM’s purpose is to respond to WCWCD’s application for the ROW grant and R&PP lease to patent
on BLM-administered lands for the proposed Ash Creek Project and Toquer Reservoir Recreation Area.
The need is established by the BLM’s statutory and regulatory responsibilities regarding ROWs under
FLPMA (43 USC 1761) and regarding the leasing/patenting of public lands for recreational and public
purposes under the R&PP Act of 1954 (43 USC 869).
1. Whether to approve or deny the WCWCD’s application for the proposed pipeline and reservoir
ROW for the construction, operation, and maintenance of water pipelines, Toquer reservoir and
appurtenant facilities related to the Ash Creek Project, and if so, under what terms and conditions;
and
2. Whether to approve or deny the WCWCD’s R&PP Act lease application and subsequent patent
under the R&PP Act for construction, operation, and maintenance of the proposed recreation area
at the proposed Toquer Reservoir, and if so, under what terms and conditions.
LD-01 (pg 2.1): Lease or transfer of land under the R&PP Act shall occur where such is determined to be
the most appropriate method for achieving desired public and municipal purposes.
LD-06 (pg 2.2): Over the life of the Plan, it is expected that up to 18,000 acres of public lands may be
transferred out of public ownership in Washington County. Most of these transfers will occur as a
result of land exchanges needed to complete acquisition of state and private lands within the
Washington County HCP Reserve or to support the statewide inholdings exchange with the Utah
School and Institutional Trust Lands Administration.
Generally, public lands within the designated transfer areas shown on Map 2.1 constitute a pool
of lands which may be transferred through sale, exchange, or lease and conveyance under the
Recreation and Public Purposes Act or other applicable authority. Lands not contained in this pool
may be transferred (other than under land sale authority) if subsequent analysis determines that
such transfer will meet the land transfer criteria established above. (BLM 1999:2.2)
LD-12 (pg 2.3): Applications for new rights-of-way on public lands will be considered and analyzed on a
case-by-case basis. Proposals would be reviewed for consistency with planning decisions and
evaluated under requirements of the National Environmental Policy Act and other applicable laws
for resource protection. Mitigation needed to avoid adverse impacts will be integrated into project
proposals and, where appropriate, alternatives identified to further reduce environmental impacts
to lands, resources or adjacent land uses.
LD-13 (pg 2.3): All new rights-of-way will be subject to applicable standards listed in Appendix 1 for
surface disturbing activities. Where needed, wildlife seasonal use restrictions will apply to right-
of-way construction. Rights-of-way will generally remain open to other public uses that do not
2
DRAFT Environmental Assessment
Ash Creek Pipeline and Toquer Reservoir
conflict with the purposes for which the rights-of-way are established.
Objectives (pgs 2.11-2.12): BLM’s objectives for soil and water resources will be to work with
municipalities, state, and local agencies, and other interested parties to:
d) promote water conservation;
f) ensure water availability for the maintenance of key natural systems and human enjoyment;
g) where necessary to meet essential community needs, identify environmentally suitable sites for
water storage and routes for water transport.
SW-15 (pg 2.17): The [Anderson Junction reservoir site], identified by the State of Utah’s Division of
Water Resources and the Washington County Water Conservancy District on public lands in
Washington County, is recognized as a special resource warranting federal awareness and
attention in future land management planning and decision making processes. In evaluating land
use proposals and management options for the site, BLM will give full consideration to the unique
values associated with the potential for water storage and related purposes prior to making
decisions which would preempt the use of such sites for future reservoir development. Where
preemption is considered, the State of Utah and local affected agencies will be consulted and given
sufficient opportunity to respond to the proposal before decisions are made. Development of the
site for reservoir purposes will require complete environmental and engineering analysis and
public participation prior to consideration for approval.
1.4.5 Recreation
Objectives (pg 2.37): BLM’s objective for recreation management will be to provide an array of quality
recreation experiences within the agency’s capability and logical recreation niche to meet the reasonable
needs and expectations of local residents and visitors from outside the area.
1.4.4 Visual Resources
Objectives (pg 2.51): BLM’s objective will be to manage the public lands in such a way as to preserve those
scenic vistas, which are deemed most important:
a) in their impact on the quality of life for residents and communities in the area;
b) in their contribution to the quality of recreational visitor experiences; and
c) in supporting the regional tourism industry and segments of the local economy dependent on public
land resources.
3
DRAFT Environmental Assessment
Ash Creek Pipeline and Toquer Reservoir
Implementation of the Project would also be in compliance with applicable state and local statutes, and
enforceable plans, including:
Utah Code Annotated 9-8-404
State of Utah Code Title 17: Water and Irrigation
State of Utah Administrative Code R655-11: Requirements for the Design, Construction and
Abandonment of Dams
General Plan of Washington County, Utah (WCPC 2010, revised 2012), pg 54:
Other projects are planned to be constructed in the near future to be able to continue efficient water
resource management, including the Ash Creek Project that will involve construction of a new
reservoir near Anderson Junction and the Warner Valley Reservoir Project. The General Plan is
supportive of these efforts to provide for the water needs of county residents. The construction of
reservoirs and wells at strategic locations in the county also helps to improve the underground
water supply.
Cultural Resources
What adverse effects would there be on National Register of Historic Places (NRHP)-eligible
properties within the Project area?
Socio-economics
How would the construction, operation, and maintenance of the Project effect the surrounding
communities and local economy?
Wetlands/Riparian Zones
What would be the impacts on riparian zones related to construction, operation, and maintenance
of the Project?
Fish and Wildlife, Excluding U.S. Fish and Wildlife Service (USFWS)-Designated Species
What effects would the project construction and maintenance have on small mammals, reptiles,
amphibians, and birds, including BLM-sensitive species within the Project area?
What effect would project construction, implementation, and maintenance have on aquatic species
(Bonneville cutthroat trout, desert sucker, flannelmouth sucker, and Virgin spinedace) by water
quality changes (siltation and temperature) and changes to stream flow?
Would permanent roads, the reservoir, and associated facilities cause loss of general terrestrial
species habitat?
How would construction activities affect crucial wintering range for mule deer?
4
DRAFT Environmental Assessment
Ash Creek Pipeline and Toquer Reservoir
Migratory Birds
Would construction and maintenance activities associated with the proposed Project affect
migratory bird species that occupy the action area and adjacent lands seasonally or year-round?
Would potential foraging, nesting, and cover habitat for migratory birds be lost in both the long
term and the short term during project construction and maintenance activities?
Would migratory birds be disturbed or displaced from nests or individuals killed if Project activities
occur during nesting seasons?
Would Project construction, implementation, and maintenance affect aquatic migratory bird species
due to possible changes in water quality (siltation and temperature) and stream flow?
Would terrestrial migratory bird species habitat be lost?
Federally Listed Threatened, Endangered, or Candidate Animal Species
Would construction and maintenance activities result in the loss of Mexican spotted owl (Strix
occidentalis ludica) critical habitat, and southwestern willow flycatcher (Empidonax traillii
extimus), and western yellow billed cuckoo (Coccyzus americanus) potential dispersal and foraging
habitat?
Would the above species be displaced into adjacent habitats during construction and maintenance
activities?
Vegetation, Excluding USFWS-Designated Species
What effect would there be on vegetation in areas where shrubs and trees need to be cleared?
Lands/Access
What effects would the Project have on the maintenance and operation of existing ROW holders
and ancillary facilities (power line, fiber optic, cable, natural gas) in the Project Area?
Would the Project require the exercise of eminent domain related to the private land around the
proposed reservoir site?
Recreation
What effect would the Toquer Reservoir and recreation area have on dispersed casual recreational
uses and opportunities on public lands within Washington County?
Visual Resources
What effect would the Project have on the identified Key Observation Points (KOPs)?
5
DRAFT Environmental Assessment
Ash Creek Pipeline and Toquer Reservoir
In January 1996, the USFWS announced plans to reintroduce California condors into northern Arizona and
designate these birds as non-essential experimental populations, as provided by Section 10j of the ESA
(USFWS 1996). California condors from the experimental population area (USFWS 1996) frequently
forage away from the Vermillion Cliffs of Arizona into southwestern Utah, including Washington County.
Most California condor use occurs east of the Project area near Zion National Park; no nests, roosts, or
other special use areas for condors have been identified in the Project area.
Under the requirements of NEPA, when a Proposed Action may potentially affect the California condor
10(j) non-essential experimental population, the 10(j) population should be addressed (and their status
defined) and then not carried forward for further analysis within the NEPA document.
2.0-DESCRIPTION OF ALTERNATIVES
2.1 ALTERNATIVE A-NO ACTION
Action 1- Under Alternative A, the No Action Alternative, the BLM would not authorize a ROW to allow
the WCWCD to construct, operate, and maintain a water pipeline and reservoir for the proposed Ash Creek
Project on BLM-managed public lands. If the No Action Alternative were to be selected, the WCWCD
could, nevertheless, undertake actions on SITLA and private lands, including making repairs to the Ash
Creek Reservoir, reconstruction of the diversion on South Ash Creek, and replacing the unlined Pintura
ditch with a pipeline and constructing a regulating pond to serve Pintura water users.
The upgrade of the South Ash Creek diversion and piping the South Ash Creek canal would result in
approximately 26.3 acres of temporary surface disturbance. Post-construction, approximately 19.4 acres
would be revegetated along the pipeline alignment. The Pintura regulating pond would cover approximately
2.8 acres of land. Water diversion would likely be less than the Proposed Action and similar to the existing
amount of diversion for the users in the Pintura area.
Action 2- Under Alternative A, the No Action Alternative, the BLM would not grant to the WCWCD the
R&PP lease for the proposed recreation area at the proposed Toquer reservoir.
6
DRAFT Environmental Assessment
Ash Creek Pipeline and Toquer Reservoir
conditions to determine a reliable yield of the system. A conceptual model of Project water conveyance and
storage components with their expected associated average annual water volumes that would be diverted to
authorized water rights holders and to the proposed Toquer Reservoir is shown in Figure 2-1. A reliable
yield of 1,730 acre-feet per year (af/yr) from the proposed Project has been modeled using available flow
date from Ash Creek and the three tributary streams (Alpha 2019).
Figure 2-1 Conceptual model of Project Water Conveyance and Storage Components (Alpha 2019)
Table 2-1 provides a summary of total acres that would be temporarily and permanently disturbed by
construction, operation, and maintenance of the Project. Individual components of the Project are
summarized below. Refer to the POD in Appendix D for specific design features and dimensions of
pipelines, reservoir, recreation area, associated facilities related to the Project.
Ash Creek Pipeline—A buried water pipeline would be installed from the base of existing Ash
Creek Reservoir Dam along existing roads and trails where possible to the proposed Toquer
7
DRAFT Environmental Assessment
Ash Creek Pipeline and Toquer Reservoir
Reservoir. A 14-foot wide permanent access road would be constructed within the 50-foot wide
permanent ROW on top of the buried pipeline for future maintenance.
South Ash Creek Diversion Structure—The existing diversion structure on South Ash Creek
would be replaced with a buried water pipeline for water diversion.
South Ash Creek Pipeline—The existing, unlined ditch extending from the South Ash Creek
diversion to the new regulating pond near Pintura would be replaced with a buried water pipeline.
Leap Creek Pipeline—A buried pipeline would be installed from the existing Leap Creek
diversion to the new regulating pond in Pintura.
Regulating Pond—A regulating pond near Pintura would be constructed to receive water from the
new South Ash Creek and Leap Creek pipelines. The pond would provide hydraulic pressure for
the South Ash/Leap Creek combined pipeline.
South Ash/Leap Creek Combined Pipeline—A buried water pipeline would be constructed from
the Pintura regulating pond to the Ash Creek pipeline.
Pintura Pipeline—A buried water pipeline would be constructed from the new regulating pond in
Pintura parallel with the South Ash/Leap Creek combined pipeline interconnecting into a new
Pintura pressurized irrigation system.
Wet Sandy Connection—Connect the existing Wet Sandy diversion, regulating pond, and pipeline
to the new Ash Creek Pipeline.
Toquer Reservoir—A water storage reservoir would be constructed at Anderson Junction,
impounded by an earth and rock fill dam with a concrete weir and splash pad for an open overflow
channel into the existing ephemeral Anderson Junction Wash below the proposed dam.
Toquerville Secondary Irrigation Pipeline—A buried water pipeline would be installed from the
Toquer Reservoir to the existing Toquerville Secondary Water System (TSWS) regulating pond.
No other changes would be made to the TSWS.
Recovery Wells, Access Roads, and Power Lines—Drill and operate as many at nine
groundwater recharge and production wells within a well field protection zone, south of the
proposed Toquer Reservoir, for future use in the culinary system. Roads would be constructed as
necessary to access the wells. Power lines to operate the wells would be connected to existing
power lines in the area..
Toquer Recreation Area—The recreation area would be developed on a 13-acre parcel at the
southwestern end of the reservoir. Amenities would include campsites, a boat dock and ramp, fee
station, restrooms, parking lots, 20’x40’ covered pavilion, utilities to the recreation area, an
unpaved hiking and mountain biking trail around the reservoir, interpretive kiosk panels and
boundary fencing.
Lift Station—The existing list station for the Ash Creek Special Service District (ACSSD) is
located within the proposed footprint of the reservoir and will need to be relocated to north of the
reservoir high water elevation on 40’x50’ area of already disturbed land owned by the WCWCD.
8
DRAFT Environmental Assessment
Ash Creek Pipeline and Toquer Reservoir
The pipeline portion of the Project would consist of 6 segments totaling 18.8 miles of pipeline being
installed within already disturbed areas where possible. Installation of the pipelines would require a 50-
foot-wide permanent ROW and a 100-foot-wide temporary construction ROW. The permanent ROW could
expand to 300 feet in steep areas to account for cut and fill. The steep areas generally occur from the existing
Ash Creek Reservoir to the Snowfield staging area. A 14-foot-wide permanent access road would be
constructed within the 50-foot ROW and on top of the buried pipeline for future maintenance. During
pipeline construction, approximately 50 feet on either side of the centerline of the ROW would be needed
for vehicle passage and pipeline assemblage. Approximately 36 feet of the permanent ROW and any
disturbed portions of the temporary construction ROW would be re-seeded with native species, using a seed
mix recommended by BLM, after construction.
1. The proposed Ash Creek pipeline would originate at the base of the existing Ash Creek Reservoir
and continue in a southerly direction to the proposed Toquer Reservoir, a distance of approximately
10.87 miles
2. The proposed Leap Creek pipeline would extend from an existing diversion structure and pipeline
to the proposed regulating pond in Pintura (2.12 miles)
3. The proposed South Ash Creek pipeline would originate at the proposed South Ash diversion and
also connect to the proposed Pintura regulating pond (1.32 miles)
a. A new diversion would be installed on the South Ash Creek diversion. The diversion would
include a coarse screen to prevent damage to the diversions and pipelines from transport of
cobbles and boulders during high water events; it would also include a small concrete lined
pond to temporary settle solids from the water.
b. The WCWCD would install two wildlife guzzlers along the South Ash Creek pipeline route
to compensate for water that would be made unavailable to wildlife when the open ditch is
converted to the pipeline.
4. The combined South Ash Creek/Leap Creek pipeline would extend from the proposed Pintura
regulating pond to the proposed Ash Creek pipeline (0.55 miles).
5. A pipeline running parallel to the combined Ash Creek/Leap Creek would connect the new
regulating pond with the Pintura pressurized irrigation system (1.77 miles).
6. A buried pipeline would extend south from the Toquer Reservoir and connect to the existing TSWS
regulating pond (2.17 miles). For roughly the southern half of this distance, this pipeline segment
would be constructed within the ROW of State Route 17 (SR-17) planned bypass west of
Toquerville. The exact route of the SR-17 bypass is still under design and planning by the city of
Toquerville and the Utah Department of Transportation (UDOT). Water diverted by the proposed
Project that would not be delivered to existing holders of water rights in the three tributaries and to
the TSWS could be used for irrigation purposes in the cities of La Verkin and Hurricane or diverted
into the existing Quail Creek pipeline serving the Quail Creek/Sand Hollow Reservoir system.
9
DRAFT Environmental Assessment
Ash Creek Pipeline and Toquer Reservoir
The diversion structure construction area ROW would be staked and cleared of vegetation. The existing
sandbag and plastic diversion would be removed. During construction of the new diversion dam, water
would be diverted around the construction area and continue down the existing South Ash Creek streambed
by the installation of a temporary coffer dam, pipeline, or diversion. The diversion structure would measure
approximately 40 foot long by 20 feet wide. A concrete-lined settling basin would be included to
complement the diversion. It would be located away from the stream and receive water from the diversion.
The basin would be excavated 6 to 8 feet, formed, and poured with concrete. The overall diversion structure
would require a 350 by 500-foot permanent ROW (4.02 acres) to construct and maintain the diversion. A
CWA 404 or stream alteration permit would be required for the construction of the diversion structure.
Refer to the POD in Appendix D for specific design features and construction methods.
2.2.3 Pintura Regulating Pond
The combined South Ash Creek and the Leap Creek pipeline would flow into the proposed Pintura
regulating pond that would be constructed west of the town of Pintura on SITLA land (Figure 1). This
action could occur regardless of BLM action.
The regulating pond would measure approximately 150 by 250 feet and would require a 550 by 650-foot
permanent ROW (8.2 acres) to construct and maintain. The WCWCD would deliver water to the water right
holders in Pintura through a new pressurized irrigation system that would be regulated from this pond.
Refer to the POD in Appendix D for specific construction and design features.
The pond ROW would be staked and cleared of all vegetation. The pond would be lined with an impervious
material, either clay or an artificial lining, then covered with sand and gravel, with riprap protection on the
side slopes to protect the lining. The pond would have an overflow into an existing ditch or streambed. For
safety purposes, chain-link fencing would be installed around the pond.
2.2.4 Toquer Reservoir Area
Topographical conditions dictate the overall capacity of the proposed Toquer Reservoir. The preliminary
design identifies the reservoir’s maximum storage capacity to be 3,638 acre-feet, with a surface area of
approximately 115 acres. A 372-acre temporary construction area and a 185-acre permanent area would be
required for construction and operation of the reservoir, earthen dam, and spillway. The spillway would
consist of a concrete weir and splash pad and an 1,9721-foot excavated overflow channel (1,602 feet on
BLM and 370 feet on private land) leading to Anderson Wash. The reservoir would be created by the
construction of an earth and rockfill dam with central clay core transitioning to basalt rock fill.
The amount of water available for the reservoir is limited by the amount of water available in the
respective streams; the capacity of the respective pipeline; and the prevailing water rights that must
be satisfied on the streams. Refer to Figure 2-1 above. The remaining streamflow in the four areas of
contribution is conveyed within the piping system into the Toquer Reservoir. This water is diverted and
stored during periods of availability then distributed during the irrigation season to the TSWS. The average
total monthly and average annual amount of water available to the Toquer Reservoir are presented in Figure
2-3 (Alpha 2019). Recreation use is second to consumptive water use and the reservoir will be managed as
such.
10
DRAFT Environmental Assessment
Ash Creek Pipeline and Toquer Reservoir
Figure 2-3. Average Total Monthly and Average Annual Amount of Water Available to the Proposed
Toquer Reservoir (Alpha 2019)
11
DRAFT Environmental Assessment
Ash Creek Pipeline and Toquer Reservoir
destinations would conform with BLM requirements.
12
DRAFT Environmental Assessment
Ash Creek Pipeline and Toquer Reservoir
Pipelines would likely need to be cleaned with a poly pig on an annual basis
A grader would be used to grade the pipeline roadways as necessary to ensure that access is
maintained
The pipeline system is estimated to have a 50-year life before major pipeline repair would be
required
The reservoir dam would require regular inspection and maintenance
Water levels in the Pintura regulating pond and Toquer Reservoir would largely be controlled at
the diversions on Leap Creek, South Ash Creek, and Wet Sandy Creek, with direct releases from
the reservoir and pond expected to be infrequent and minimal
The Best Management Practices (BMPs) and Standard Operating Procedures (SOPs), and Applicant
Committed Environmental Protection Measures (EPMs) that are included in Appendix D would be
followed during construction, operation and maintenance of the Proposed Actions and are, therefore,
integral components of this alternative.
2.2.7 Termination and Restoration
If the Project is terminated or abandoned, a joint inspection would be held with the authorized officer(s)
of the BLM prior to termination in order to agree upon an acceptable rehabilitation plan for the area.
13
DRAFT Environmental Assessment
Ash Creek Pipeline and Toquer Reservoir
development density increases with urbanization, water conservation technology improves and water users
are educated and motivated by water conservation plans as they are updated every five years.
Between 1996 and 2010, WCWCD spent $12.6 million on water conservation efforts, and the district
currently budgets about $250,000 per year for water conservation programs directly, in addition to a full-
time water conservation manager and two full-time horticulturists for its demonstration gardens. The goal
of each conservation plan is to conserve more water through the various programs that are improved and
added over time. Appendix E contains a table of the conservation programs incorporated into the recently
adopted 2015 Water Conservation Plan. Seven cities have also adopted water conservation plans: St.
George, Santa Clara, Washington, Hurricane, Ivins, Toquerville and LaVerkin. The conservation efforts of
the individual cities in Washington County are consistent with those of WCWCD, implementing a range of
conservation measures, several in partnership with WCWCD.
Water conservation could not meet the purpose and need of the Project because it would not accomplish
groundwater recharge, preventing losses to evaporation and seepage from open ditches, or replace culinary
quality spring water. Reductions in use from water conservation over time would not occur fast enough nor
would they reduce water use enough to offset reasonably anticipated demand.
3.0 AFFECTED ENVIRONMENT, ENVIRONMENTAL CONSEQUENCES,
AND CUMULATIVE IMPACTS
This chapter describes (1) the affected environment, specifically the existing or baseline conditions relevant
to each issue identified in Section 1.6, followed by (2) a description of the direct, indirect, and cumulative
impacts projected to result from each alternative. Resources that were identified as not present in the Project
Area or that would not be affected to a degree that requires detailed analysis are not described in or analyzed
in this EA. The rationale for not analyzing these resources in presented in the ID Team checklist in
Appendix A.
Impacts are direct or indirect and measured in terms of intensity (scale and concentration) and duration
(short-term or long-term). Direct effects are caused by the action and occur at the same time and place.
Indirect effects are caused by the action and are later in time or farther removed in distance but are still
reasonably foreseeable. Impacts can be positive, seen as benefitting the resource, or negative, seen as a
detriment to the resource. Positive impacts could result from management actions that maintain or enhance
any of the resource values described in the analysis. Negative impacts could result from management
actions that diminish any of the resource values described in the analysis. The intensity and duration of
impacts are defined as follows:
Negligible: The impact is at the lower level of detection; there would be no measurable change.
Minor: The impact is slight but detectable; there would be a small change.
Moderate: The impact is readily apparent; there would be a measurable change.
Major: The impact is severe, highly noticeable, and potentially permanent.
Temporary: Short-lived (i.e. during construction)
Short-term: The impact would last for 10 years or less.
Long-term: The impact would last for more than 10 years.
Cumulative impacts are the combined effect of past projects, specific planned projects, and other
reasonably foreseeable future actions (RFFAs) within the Project Area to which the Proposed Actions may
add incremental impacts. The geographic extent of cumulative impacts can vary by the type of resource and
resource issues and by the type of potential impact. Past and Present actions in the Project area that would
cumulative impact the same components of the environment as the Proposed Actions and No Action
alternative are:
14
DRAFT Environmental Assessment
Ash Creek Pipeline and Toquer Reservoir
Construction and use of water and wastewater systems, municipal and agricultural water diversions,
well development, and irrigation for municipal landscape and agricultural fields. Evidence of
agricultural diversions from Ash Creek and its tributaries predates recorded history
Authorized and unauthorized OHV use
Maintenance and use of existing transmission lines (overhead and buried) in the area
Maintenance and use of existing public roads in the area
Active sand and gravel pits
Physiographic Setting of the Project Area: The proposed Project Area is located in southwestern Utah in
a physiographic transition zone between the southern Basin and Range and the Colorado Plateau. Elevation
ranges from 4,660 feet at the existing Ash Creek Reservoir to 3,437 feet at the proposed Toquer Reservoir.
The regional climate is characterized by low precipitation and humidity, with hot summers and cool winters.
Temperature variations are extreme on a daily basis and throughout the year. Summer temperatures may
exceed 105 degrees Fahrenheit and winter temperatures can drop below 20 degrees Fahrenheit. Average
rainfall is approximately 7 inches per year, the majority of which occurs in late summer and winter months.
The frost period may last for a period of 150 to 200 days, depending upon elevation.
15
DRAFT Environmental Assessment
Ash Creek Pipeline and Toquer Reservoir
Uncertainty is the key word here in what the numbers mean and in how reliable they predict future stream
flows. Future climate change provides still greater uncertainty to predictions of volumes of surface water.
Lower Ash Creek has been diverted for agriculture since the late 1800s. Below the diversion, the remainder
of the water continues until flows seep into permeable stream sediments and into the local groundwater
system. Although these flows generally disappear shortly downstream of the diversions, in high water years
surface flows can reach Ash Creek. These intermittent flows periodically provide flows to downstream
waters, either through surface flows or groundwater recharge/ discharge (JBR 2013).
16
DRAFT Environmental Assessment
Ash Creek Pipeline and Toquer Reservoir
3.1.1.6 Springs
There are three large spring systems, a moderate size spring and many smaller springs in the Ash Creek
Watershed. Spring flows vary depending on the season and the annual precipitation amounts. Higher spring
flows occur in the winter/ spring seasons and in wetter years. Lower spring flows occur in summer/ fall
seasons and in years with lower precipitation amounts. Upstream of the springs, surface waters (Leap Creek,
South Ash Creek and Wet Sandy Creek) seep into the groundwater system and provide water to the spring
systems.
Deadman Hollow Spring is located in a small drainage east of the Ash Creek Reservoir, draining the
west side of the Hurricane Cliffs. Surface water from the spring flows 1400’ downstream and into Ash
Creek just downstream of the Ash Creek Reservoir. Surface flows sink into the Ash Creek stream bed just
below the confluence with Ash Creek (JBR 2013).
Sawyer Spring and Lower Sawyer Spring are in the northern portion of the watershed. Flows were
measured at Sawyer Spring in Oct 1995, with a flow of 1.51 cfs (Heilweil et al. 2000). Flows were measured
at lower Sawyer Spring in 2009, with a flow of 2.15 cfs (Player 2009). The importance of both springs is
that their water levels rise and fall independently of each other (barrier flow) but that large nearby irrigation
wells to the north interfere with lower Sawyer Spring because lower Sawyer Spring and these wells are in
the same fault and experience conduit flow (Rowley 2018).
Toquerville Springs, the largest spring system in Utah, is located upstream of the town of Toquerville.
Spring flows emerge from the eastern bank of Ash Creek, from the Pintura basalt flow, averaging 4,000
gpm. All spring flows are currently diverted for irrigation uses. All water rights to this spring system are
held by the cities of Toquerville, Hurricane, La Verkin and WCWCD, with priority dates of 1862 and 1912,
totaling over 4900 ac-ft of water. A flow measurement collected by USGS in 1996 at the spring was
approximately 22 cfs. The water quality of Toquerville Springs was excellent when sampled in 1987, with
typical total dissolved solids concentrations of about 460 milligrams per liter (mg/L) (Clyde, 1987). With
these very good water quality conditions, this spring could potentially be a potable water source for the
area.
Ash Creek Springs are located about one mile south of Toquerville and 2.5 miles downstream of
Toquerville Springs. Spring flows emanate from the banks of Ash Creek from the Pintura basalt flow. Flow
measurements range between 5.85 cfs (1968) and 6.92 cfs (1970), with a measurement taken by USGS in
1996 of 6.5 cfs. All spring flows are currently diverted for irrigation uses. Water has very good water quality
conditions and could potentially be a potable water source for the area.
3.1.2 Groundwater
The groundwater system in this area is complex and is significantly influenced by two geologic structures
– the Pine Valley Mountain laccolith and the Hurricane Fault. The Navajo Sandstone is found throughout
the watershed, both as outcrops at higher elevations and at depth underground, and is an important regional
aquifer.
There are three aquifers in the upper portion of the watershed including the shallow Quaternary basin-fill
aquifer, the older Tertiary-aged alluvium in fan deposits, and the Tertiary- aged Pine Valley Monzonite.
These aquifers are recharged by precipitation in the Pine Valley Mountains and by losing stream flows to
alluvium. The southern discharge boundary for these aquifers is near the Ash Creek Reservoir where
fractured basalts and coarse alluvium are present. Direction of groundwater flow within the upper basin
generally follows topography (Heilweil, 2000).
17
DRAFT Environmental Assessment
Ash Creek Pipeline and Toquer Reservoir
In the lower portion of the watershed (downstream of Ash Creek Reservoir) the Navajo Sandstone and the
Kayenta Formation are important aquifers as well as the localized, shallow, unconsolidated alluvial
aquifers. The Navajo Aquifer is the largest regional aquifers in this area, with local recharge from the Pine
Valley Mountains and possibly from the upper Ash Creek groundwater basin. Recharge to the Navajo
Aquifer may be also be from stream losses in Ash Creek and tributaries (JBR 2013).
According to Rowley, Dixon & Layton, “[i]t is likely that significant groundwater crosses into the [Ash
Creek] basin from Cedar basin, most of it from precipitation on the Hurricane Cliffs that moved by surface
flow to the Hurricane fault zone at the base of the Cliffs, then by fracture flow southward within the fault
zone. Groundwater also must be moving in thick Paleozoic aquifers beneath the surface of the Kolob
Terrace, then west across the Hurricane fault into the Miocene and Jurassic aquifers juxtaposed by the fault.
Yet the greatest recharge must come from the lofty Pine Valley Mountains, where precipitation enters a
highly faulted excellent (brittle) Miocene aquifer that forms most of the range, then eastward down gradient
to the basin. Finally, the graben of the Ash Creek basin is a complex hash of many faults underlain by basin-
fill sediments, the Miocene aquifer, and the Jurassic aquifer, thereby containing more groundwater in
storage than previously thought.”
Despite an inability to provide specific numbers on the volume of the groundwater resources of Ash Creek
drainage basin, Rowley and others (2016 and 2018) presented evidence that the basin contains far more
groundwater than estimated before. First of all, adjacent basins on the north, west, and east are in hydraulic
continuity with the Ash Creek basin and contribute recharge that has been ignored previously. Second, the
basin axis is a graben (geologically downthrown area) bounded by huge normal faults of opposing vertical
displacement that have highly brecciated and provided secondary permeability to already large aquifers
consisting of basin-fill sediments, Miocene igneous aquifers, and the Navajo Sandstone; in addition,
confining units are brecciated and also given secondary permeability. Third, high precipitation values from
adjacent highlands have resulted in high water tables, water wells with high yields, and mostly modern
(high Tritium) water. Fourth, the population and agricultural development in the basin are limited.
Therefore, it is likely that the Ash Creek basin has groundwater resources that are several times greater than
any previously estimated.
The stream water that seeps out through the floor of Ash Creek Reservoir is probably not recharging any
local down-gradient springs, streams, or groundwater. Arguments developed by Montgomery (1999) and
Rowley and others (2016) suggest that this stream flow enters the adjacent and underlying fractures of the
broad Hurricane fault zone, then moves southward (down gradient) by fracture flow along the fault zone,
passing beneath the Virgin River and on to Arizona.
Bedrock made up of the Jurassic Navajo Sandstone, a 2000-ft thick, permeable sandstone rock unit that is
by far the most important aquifer in Washington County, underlies the area proposed to be occupied by
Toquer Reservoir. Geologic mapping of the reservoir site by Rowley and Dixon (2010) showed that the
Navajo is cut by many fault splays that make up the western side of the Hurricane fault zone. These fault
splays increase the permeability of the Navajo, allowing greater seepage into the Navajo bedrock.
For the Ash Creek drainage basin, quantification of groundwater is especially problematic because its
southern boundary is the Virgin River instead of bedrock. There is no evidence that all the excess
groundwater in the Ash Creek basin recharges the Virgin River. It is more probable that some groundwater
continues south beneath the river in the Hurricane or Grand Wash faults and on to the Grand Canyon
(Rowley, et al., 2018).
18
DRAFT Environmental Assessment
Ash Creek Pipeline and Toquer Reservoir
intervals during a single sample year to provide reliable and comparable results. As is typical of most
streams in the area, sediment transport is expected to be high during seasonal flow events and, depending
on the upstream source of the sediments, these can affect water quality.
Groundwater quality associated with the Navajo sandstone aquifer is generally good, though some has been
reported to be slightly saline in some locations (Clyde 1987). Clyde (1987) reported that the water quality
of Toquerville Springs was excellent (with typical total dissolved solids concentrations of about 460
milligrams per liter (mg/L) and the springs are a potable water source for the area.
3.1.2 Environmental Impacts—Alternative A-No Action
Under the No Action Alternative, there would not be any federal action on federal lands; however,
WCWCD could implement water infrastructure upgrades/extensions on private and SITLA lands.
Long-term impacts to South Ash Creek downstream of the proposed diversion structure would occur, as
the proposed diversion structure would increase the amount of water diverted from the stream by an average
of 1,348 acre feet. This would be a beneficial and minor impact.
19
DRAFT Environmental Assessment
Ash Creek Pipeline and Toquer Reservoir
degree because the construction footprint, in particular new disturbance, would be limited in acreage
compared to overall watershed size and disturbances would be dispersed among a number of tributary
drainages. Surface water quality impact potential from an unexpected release of hydrocarbons (e.g., diesel
fuel) or other contaminants (e.g., concrete mix) due to accidents or spills would be minimal given the lack
of nearby surface flows. There is no indication of shallow groundwater in or near the construction areas
that might be impacted by the work.
Only the South Ash Creek Diversion replacement would require construction within a flowing stream
channel that would be dewatered during construction, with erosion and runoff control methods resulting in
negligible or minor erosion-related loading. Temporary construction disturbance would be reclaimed so
that sediments would diminish over time. Refer to Section 3.1.2.1 for the South Ash Creek diversion
impacts to water resources. Construction impacts would be direct, short-term and negligible.
Post-Construction Impacts
3.1.3.1 Surface Water Resources
The amount of water available for the reservoir is limited by the available surface flows, the capacity of the
pipelines, and the diversion rights. Figure 3-2 shows the amount of water that would be diverted and the
amount that would overflow and pass downstream based upon pipeline capacity and reservoir capacity.
Figure 3-2. Average total monthly and average annual discharge values for Ash Creek Piping
system and Toquer Reservoir (Alpha 2019).
The majority of surface flows that reach the diversion points would overflow and continue downstream on
an average annual basis. Overall, the Project is expected to deplete an additional 18.6 percent of the 15,454
acre-feet total annual yield of the watershed (2,880 acre-feet). The total diversion for existing and new uses,
including 848 acre-feet already being used for irrigation (21.1 percent of project use) and 287 acre-feet
considered to be return flow that will return to the downstream environment, would amount to about 26
percent of the yield, averaging 4,015 acre-feet annually. The remaining 11,439 acre-feet would continue
downstream as surface flow, recharge groundwater, or evaporation and seepage to support riparian and
floodplain function. The annual inflows to the Toquer Reservoir are estimated to range from 548 acre-feet
to 6,498 acre-feet depending on the water year (Alpha 2014). Evaporation from the proposed Toquer
Reservoir is estimated at 330 acre-feet annually and seepage is estimated at 792 acre-feet annually (Alpha
2014).
20
DRAFT Environmental Assessment
Ash Creek Pipeline and Toquer Reservoir
Water resources upstream of the diversions would not be affected by the Proposed Action. Below the
diversions, data showing current use sufficient to accurately quantify how annual hydrographs would
change are not available. Furthermore, potential water losses to Ash Creek would likely be too small to
measure relative to existing flows. The stream reaches downstream of Ash Creek Reservoir and the Leap
Creek, South Ash and Wet Sandy diversions transition to intermittent, interrupted or ephemeral in a
downstream direction. The water rights for Toquerville Springs flows are fully allocated, so if there were
changes in flows from these springs, they would not change stream flow in lower Ash Creek.
All surface flows Anderson Junction Wash would be stopped at the Toquer Reservoir dam. The three miles
of wash downstream of the dam would transport localized runoff to the lower reach of Ash Creek. Flows
from the reservoir into the wash as a result of reservoir spills are not expected, since the amount of water
delivered to the reservoir would be managed at the diversion structures in accordance with capacity.
Water use in Pintura, Anderson Junction and TSWS would not change as a result of the project. Thus there
would be no measurable change to irrigation return flows to Ash Creek or the Virgin River as a result of
irrigation water use.
The Proposed Actions would rely upon existing water rights held by WCWCD and others. Changes in
points of diversion may redistribute withdrawals among the various tributary stream channels and would
enable WCWCD to utilize a greater proportion of existing water rights, as reflected in impacts to surface
flows and groundwater. Pursuant to applicable law, no changes would be authorized that would impair
existing water rights. Effects to the discharge of Toquerville and Ash Creek Springs would only impact the
WCWCD or its regional water supply partner, since the water needs of these entities are pooled under the
Regional Water Supply Agreement. Any impact to water rights would be undeterminable. Overall, impacts
to surface water, to the extent that they are determinable, would be negligible to minor, direct, and long-
term.
3.1.3.2 Ground Water Resources
Because the recovery wells would only capture water that has infiltrated beneath the proposed Toquer
Reservoir there would be a net zero change in groundwater storage. It is not possible to quantify other
impacts to groundwater with any degree of confidence. Recharge through the basalts at Ash Creek
Reservoir would be somewhat reduced. There would also be some reduction in recharge below the Leap,
South Ash, and Wet Sandy diversions but with even less effect on total recharge. There is also insufficient
data to quantify the reduction in recharge from the existing ditches, but it would be negligible. Combined,
reduced recharge from all these sources is expected to have negligible to minor impacts on total recharge.
Groundwater resources would potentially be impacted by the proposed recovery wells downstream of the
proposed reservoir. Monitoring wells would determine pumping rates, etc, to minimize withdrawal of
existing groundwater resources and only pump water that has seeped in to the Navajo aquifer from the
proposed reservoir. While there is not sufficient data to quantify the effects on groundwater discharge, given
the likely amount of groundwater in the area, the impacts are likely to be negligible.
21
DRAFT Environmental Assessment
Ash Creek Pipeline and Toquer Reservoir
Potential impacts to surface water quality from storm runoff and erosion from construction would be
minimal due to the required stormwater runoff control efforts including silt fences, wattles, etc. Potential
impacts to surface water quality from unexpected releases of hydrocarbons (e.g., diesel fuel) or other
contaminants (e.g., concrete mix) due to accidents or spills would be minimal given the lack of nearby
surface flows and the requirements for thorough spill cleanup.
Reductions in the quantity of sediment that loads to Anderson Junction Wash and lower Ash Creek would
be so negligible as to be unmeasurable. Overall effects to channel stability in lower Ash Creek due to
sediment management at the diversions are also negligible.
Long-term impacts from the proposed surface disturbance and increased erosion associated with new roads,
pipelines, wells, reservoir and associated facilities would be minimized by reclamation efforts after several
years.
22
DRAFT Environmental Assessment
Ash Creek Pipeline and Toquer Reservoir
The past actions, present actions, and RFFAs include those activities addressed in Section 3.1.4.1. The
Proposed Actions would collect surface water from approximately 166 square miles of the Ash Creek
Watershed, approximately 49 square miles (26%) of the watershed’s landmass would maintain the current
drainage patterns. Hydrological impacts to surface water and groundwater resources in the CIA would be
managed by manipulation of the diversion structures and storage. Overall, cumulative impacts from other
past, present, and reasonably foreseeable future projects, in combination with the Proposed Actions would
be indirect, local, short- and long-term minor. Cumulative impacts would be beneficial to anthropogenic
uses of the hydrological resources within the CIA.
The BLM determined that a literature review, Class III intensive pedestrian survey of the APE, and
consultations with American Indian Tribes that claim cultural affiliation to southwestern Utah, the USHPO,
and other interested parties were necessary to identify historic properties that might by affected by this
project. Identification efforts were conducted between 2008 and 2013 by professional archeological
consultants (Gourley et al. 2009; Gourley 2010, 2011a, 2013). Prior to initiating fieldwork, they conducted
Class I file searches and literature reviews at the BLM St. George Field Office and the Utah Division of
State History. Cadastral plats/General Land Office maps and other historic maps of the area were also
reviewed for the presence of historic features, such as roads, ditches, cabins, and trails.
Class III level inventories were completed on approximately 1,010 acres, 23 previously documented
archeological sites were relocated and site recordings updated, as needed, and 41 previously undocumented
sites were recorded by the identification efforts. The BLM engaged in Section 106 consultations with the
SHPO, after determining that of the 64 sites within the APE, 25 were eligible for listing to the NRHP as
they retained integrity and satisfied one or more of the eligibility criteria listed at 36 CFR 60.4 (a-d). See
Table 3-1.
Through Section 106 consultations, beginning in 2009, the USHPO concurred with the BLM’s
determinations of site eligibility for NRHP listing and project effects on historic properties. In 2011, the
BLM initiated consultations with the Paiute Indian Tribe of Utah and its respective Bands, the Kaibab
Paiute Tribe, the Hopi Tribe, the Pueblo of Zuni, and the Navajo Nation regarding the Project and the
potential adverse effects that could result from the federal and state authorization of this undertaking.
Past actions include environmental changes that have occurred in the CIA beginning in prehistoric times to
the recent past (5 years). Prehistorically, populations farmed the areas within the CIA. Farming activities
include clearing the landscape, digging and planting fields, construction of irrigation ditches, and
23
DRAFT Environmental Assessment
Ash Creek Pipeline and Toquer Reservoir
harvesting. Prehistoric activities may also have included slash and burn agricultural techniques. Historic
activities are related to settlement, agriculture, and mining. Settlement by pioneers included construction
of roads, highways, and transportation infrastructure. Homes and farms were built and established. An
extensive network of irrigation and culinary water ditches were constructed. The area has been used for
ranching activities, particularly grazing, including ranch improvements, such as, fences, roads, corrals,
troughs, etc. Mining activities within the CIA have been minimal and mainly include the transportation of
workers and goods from the surrounding areas where mining was underway. Accidental and purposeful
burns have occurred within the CIA. Other past actions that affected the cultural resources include the
scientific excavation, illegal collection, and looting of archeological sites.
Present actions include infrastructure construction, improvements, and population growth. The
municipalities are rapidly growing and expanding. I-15 continues to undergo major improvement projects.
New secondary highways and roads are being constructed and maintained. Other present actions include
upgrading and maintenance to irrigation and culinary water infrastructure. Gravel extraction occurs at two
locations within the CIA. However, expansion restrictions are in place. Farming and grazing persists and
results in continued maintenance to infrastructure and range improvements. Population growth and tourism
have brought increased recreational use to the CIA (camping, hiking, equestrian, OHVs) which occasionally
results in vandalism and looting of cultural resources as well as inadvertent impacts such as trampling of
resources.
24
DRAFT Environmental Assessment
Ash Creek Pipeline and Toquer Reservoir
approved Treatment Plan. This plan describe the methods that will be used to minimize or mitigate adverse
effects, generally through data recovery and analysis.
To lessen adverse effects on the 25 historic properties, professional archeological consultants drafted a
Treatment Plan in 2012. The BLM provided this plan to SITLA, the USHPO, and the Tribes for review and
comment. In 2014, the consulting parties accepted the Archeological Monitoring and Treatment Plan for
the Ash Creek Pipeline and Anderson Junction Reservoir, Washington County, Utah (Gourley and Hall
2014). An MOA was signed between that BLM-St. George Field Office, the USHPO, SITLA, and the
WCWCD in February of 2014 to ensure that the approved Treatment Plan would be implemented. The
Tribes were invited to become signatories as Concurring Parties to the MOA, with the Paiute Indian Tribe
of Utah and the Shivwits Band of Paiutes accepting the invitation.
The approved Treatment Plan includes avoidance and monitoring by qualified archeologists, phased
archeological testing and/or data recovery, or the development of historic contexts for historic period sites.
Phased archeological testing and/ or data recovery would involve the following, using standard professional
archeological field methods:
Detailed documentation of surface artifacts, materials; structures, features and use surfaces;
Excavation of structures, features, and use surfaces sufficient to address the research issues
identified in the research design presented for each site.
Documentation of all excavated components and associated features, and collection of materials
for further laboratory analysis, to include all artifacts as well as samples of macro and microflora,
stratigraphic profiles of pollen, appropriate charcoal or bulk samples for an extensive radiocarbon
assay program, and micro-refuse sampling from excavated components;
Detailed analysis of individual data sets as appropriate;
Synthesis of analytical data sets into a quality formatted technical publication.
Table 3-2 provides information on the 25 cultural resources included in the Treatment Plan, including the
site types, ownership, and proposed treatments. Cultural resources include archaeological sites, historic
structures, sacred sites, and traditional cultural properties (TCPs) that are important to a community’s
practices and beliefs and are necessary to maintain a community’s identity.
25
DRAFT Environmental Assessment
Ash Creek Pipeline and Toquer Reservoir
Table 3-2 Historic Properties and Proposed Treatments
26
DRAFT Environmental Assessment
Ash Creek Pipeline and Toquer Reservoir
In 2014, an MOA was signed to ensure that the approved Treatment Plan would be implemented for the
Proposed Actions to lessen the adverse effects to historic properties to the maximum extent possible.
Professional archeological field data recovery methods would be used at 10 sites to collect and analyze the
important scientific information from each site and the results documented in a technical report. Artifacts
and other materials recovered from these sites would be curated in a federally-approved repository and
would be available for further research studies. The technical reports would be filed with the BLM, SITLA,
or private owner, and the USHPO and would be available for future research studies. For three historic
period roads and an historic ditch, archival research would be completed to develop a detailed history of
each feature that would also be filed with BLM, SITLA, or private owner, and the UTSHPO, and would be
available for future research studies.
The Proposed Actions also include the installation of kiosk at the Recreation Area with interpretive panels
that include information from the data recovery conducted as mitigation for this project. This information
could enhance public understanding of the cultural history of southwestern Utah.
Implementation of the Proposed Actions would cause direct and indirect, short and long-term impacts on
15 historic properties. The characteristics of each property that qualify it for inclusion in the NRHP would
be altered, directly or indirectly, in a manner that would diminish the integrity of the property’s location,
design, setting, materials, workmanship, feeling, or association. Direct and indirect impacts on 10 historic
properties would be avoided, through project design and monitoring.
27
DRAFT Environmental Assessment
Ash Creek Pipeline and Toquer Reservoir
3.3 Socio-Economics
3.3.1 Affected Environment
Settlement of Washington County has been influenced prehistorically and historically by availability to
water, and in more modern times, by land ownership/administration. Historic settlement of the area began
with the colonization by Mormon Settlers in the mid-1800s. Approximately 76 percent of land in
Washington County is public, eight percent is state or reservation, and 16 percent is private. With 76 percent
of lands under federal administration, rural, and suburban developments are dispersed throughout private
lands in the County.
Located within the Project Area in Washington County, Utah are the Pintura and Anderson Junction
ranching communities with approximately 23 single-family ranch houses. Neither community has any
commercial or industrial development. The town of Toquerville is adjacent to the Project Area, with a
population of 1,615, and little commercial or industrial development. Many of the residents of these
communities commute to the Cedar City, Hurricane or St. George areas for work. Commercial gravel
operations near the Project Area include the Snowfield Pit located northeast of the I-15 Snowfield exit, the
Gilbert Pit located north of Anderson Junction, and the Pintura Pit west of the I-15 Anderson Junction exit.
28
DRAFT Environmental Assessment
Ash Creek Pipeline and Toquer Reservoir
approximately 40 years of growth in the immediate vicinity of the Project Area (Aguero 2013). This would
be a long-term economic benefit to residents of Washington County.
In addition, the long-term maintenance and operation of the system would require two full time WCWCD
employees. Long-term maintenance and operation of the recreation area would require one full time and
multiple part-time employees. At this time, the agreement between the WCWCD and Toquerville City for
management of the recreation area has not been finalized. The Utah State Parks have interest in the proposed
reservoir and recreation area and believe that if Toquerville City cannot manage the recreational area then
the area could be managed as a satellite facility from Quail Creek State Park. The socio-economic impact
of the Proposed Actions would be a long-term, moderate impact on regional communities, Washington
County, and subsequently the State of Utah.
3.3.4 Cumulative Effects
3.3.4.1 Alternative A-No Action
The past and present actions are expected to continue over the reasonably foreseeable future as outlined at
the beginning of Chapter 3. RFFAs include the continued development of private lands in and near the
Project Area and continued efforts by WCWCD to develop existing water rights within the Ash Creek
Watershed along with additional conservation measures.
Additionally, the population growth, ethnic makeup, income, and poverty rate would continue to depend
on factors such as social trends and overall economic conditions with the available water supply being the
ultimate limiting factor in economic conditions of the region.
Under the No Action Alternative, the WCWCD’s proposed Project would not be approved as applied for,
and the R&PP lease and ROW would not be granted to the WCWCD. The short-term economic contribution
during Project construction and the long-term incremental economic contribution of the reservoir and
recreation area would not occur. The cumulative effects of the No Action alternative on socio-economics
when combined with past, present, and reasonably foreseeable future actions would be negligible to minor.
29
DRAFT Environmental Assessment
Ash Creek Pipeline and Toquer Reservoir
3.3 Wetlands/Riparian
3.4.1 Affected Environment
Discussion on wetlands/riparian zones for the Project is derived mainly from the Anderson Junction
Hydrology report (Appendix J) completed by JBR Environmental Consultants, Inc in 2013 (JBR 2013). In
July 2012, JBR wetland scientists, Jill Hankins and Karla Knoop, conducted a wetlands and Waters of the
US (WofUS) delineation of the defined Project Area. The delineation was completed in compliance with
the US Army Corps of Engineers (COE) current regulatory guidance documents as pertaining to Section
404 of the Clean Water Act. A WofUS Delineation report was submitted to the COE requesting a
Preliminary Jurisdictional Determination (PJD) on water features recorded within the Project Area. The
COE replied to the WCWCD with a PJD dated February 12, 2014 with COE project number SPK-2011-
01121. The PJD concurred with the amount and location of water bodies within the Project Area as depicted
in the January 9, 2014 WofUS Delineation Report (JBR 2014) which included 18,647 linear feet of
intermittent or ephemeral streambed and no wetlands within the areas of surface disturbing activities. The
WofUS Delineation and PJD letter is on file in the project record. As there are no jurisdictional wetlands
within the Project Area, these are not further discussed in this analysis (JBR 2013).
The WofUS Delineation documents the ordinary high water mark (OHWM) of Ash Creek, Leap Creek,
Dry Wash, South Ash Creek, Dry Sandy, Wet Sandy, Anderson Junction Wash, and Anderson Valley Wash
found within the project study area. Leap Creek, South Ash Creek, and Wet Sandy are intermittent,
interrupted streams that flow into Ash Creek during seasonal runoff and during high flood events. Each of
these intermittent tributaries to Ash Creek has an agricultural diversion that currently and historically
impounds and/or diverts ordinary low flows. Ash Creek is also intermittent, interrupted through the Project
Area. Ordinary low flows of Ash Creek are impounded by the Ash Creek Reservoir dam. Ash Creek is
interrupted, ephemeral downstream from the Ash Creek dam to the Toquerville Springs area. Ash Creek is
perennial downstream of Toquerville Springs to the confluence with the Virgin River.
In 2012, JBR observed hydromesic riparian conditions in three areas within the study area: on Ash Creek
at the Ash Creek/Deadman Hollow confluence, along Ash Creek downstream of Toquerville Springs to its
confluence with the Virgin River, and on South Ash Creek upstream of the diversion structure. These three
areas have some developed riparian zone. Riparian conditions in these areas appear to be associated with a
perennial water source. All other intermittent stream corridors within the study area are more xeric with
spaced decadent/mature woody species and very little understory. Vegetation composition appears to be
associated with a deeper water table, intermittent or ephemeral surface flows (JBR 2013).
30
DRAFT Environmental Assessment
Ash Creek Pipeline and Toquer Reservoir
(Juncus spp.), muhly grass (Muhlenbergia spp.), rush (Juncus spp.), silver sage (Artemisia cana), and
hawthorn (Crataegus rivularis). Ash Creek's natural channel below the confluence consists of
decadent/mature and discontinuous cottonwood (Populus sp.) trees with little recruitment of saplings. High
magnitude flood events that reach the secondary spillway scour the overflow channel which is located north
of the Ash Creek natural channel. This overflow channel was heavily scoured during a flood in 2010. There
is no evidence of sediment deposition from low flow and moderate flood events that would successively
build sand bars and stream banks for riparian species propagation (Figure 3-3).
Figure 3-3: View downstream at Ash Creek below the Ash Creek Dam and the Deadman Hollow
confluence. Note the lack of developed riparian community and large cobble substrate. July 9, 2012.
31
DRAFT Environmental Assessment
Ash Creek Pipeline and Toquer Reservoir
Figure 3-5: View to the south at Leap Creek channel below the existing diversion. Note seasonal
water pockets in the stream channel sparse riparian trees and little to no riparian understory
vegetation. April 25, 2012.
32
DRAFT Environmental Assessment
Ash Creek Pipeline and Toquer Reservoir
Figure 3-5: View to the north at the existing diversion on South Ash Creek, July 9, 2012. This
sandbag diversion is rebuilt as needed by the Pintura irrigation users. The existing on-stream
diversion berm beneath the sand bags is evidence of the long-term, historical diversion efforts.
33
DRAFT Environmental Assessment
Ash Creek Pipeline and Toquer Reservoir
Figure 3-6: View to the west at Wet Sandy ephemeral channel near the I-15 culvert. Note large
monzonite cobbles and no riparian zone understory in the channel. July 9, 2012.
Figure 3-8: Anderson Junction Wash within the proposed reservoir basin. October 23, 2013.
34
DRAFT Environmental Assessment
Ash Creek Pipeline and Toquer Reservoir
3.4.2 Environmental Impacts—Alternative A-No Action
Under the No Action alternative, no federal action would be taken and the project would not be constructed
on federal lands. The reservoir and the Ash Creek pipeline would not be constructed. The Ash Creek
reservoir would be maintained in the short-term at current conditions; high spring run-off would
periodically inundate the reservoir during wet years. Upgrades of the South Ash Creek diversion and piping
the South Ash Creek ditch could still be implemented by the WCWCD on SITLA lands. These are analyzed
below.
3.4.2.1 Ash Creek
Under the No Action alternative, riparian conditions in Ash Creek would remain as they currently are
described in Section 3.4.1.1. and no new establishment of riparian vegetation would be expected. Riparian
resources in Deadman Hollow upstream from the confluence with Ash Creek immediately below the dam
are supported by spring flows in Deadman Hollow. Ash Creek's natural channel immediately below the
dam only receives subsurface hydrology and there is currently no evidence of deposition from low flow
and moderate flood events that would successively build sand bars and stream banks for riparian species
propagation. The No Action alternative would not have an effect on riparian resources in Ash Creek.
3.4.2.2 Leap Creek
Under the No Action alternative, riparian conditions at Leap Creek would remain as they currently are
described in Section 3.4.1.2. The No Action alternative would not have an effect on wetlands or riparian
resources in Leap Creek.
3.4.2.3 South Ash Creek
Under the No Action alternative, upgrades of the South Ash Creek diversion and piping the South Ash
Creek ditch could still be undertaken on SITLA lands. These actions would take an additional annual
average 1,348 acre feet of water from the South Ash Creek diversion than the current conditions, therefore
some impacts to riparian trees within the natural channel would occur. However, since the low flows of
South Ash are currently diverted during the entire growing season there would be little to no new or
additional impact to the low terrace understory of the natural stream channel. The existing larger hardwood
trees within the natural channel have adapted to the altered flow regime with deep root systems to withstand
high velocity flow events. In addition, these trees are likely supported by flows in the hyporheic zone rather
than springtime high velocity flow events. The upgrade of the South Ash Creek Diversion and piping the
South Ash Creek ditch could have long-term, negligible impacts on riparian resources downstream of the
diversion and along the existing canal.
3.4.2.4 Wet Sandy
Under the No Action alternative, riparian conditions at Wet Sandy Creek would remain as they currently
are described in Section 3.4.1.4. The low flows of Wet Sandy are currently diverted during the entire
growing season, and the natural channel has adapted to the altered flow regime during the growing season.
The No Action alternative would not have an effect on riparian resources in Wet Sandy Creek.
3.4.2.5 Anderson Junction Wash
Under the No Action alternative, riparian conditions at Anderson Junction Wash would remain as they
currently are described in Section 3.4.1.5. The approximated 185 acres of Anderson Valley Wash and
Anderson Junction Wash would not be inundated by the reservoir and recreation area. The approximate
15,716 linear feet of Anderson Junction Wash downstream of the dam would continue to convey surface
flows from the upstream portion of Anderson Junction Wash's watershed (approximately 5 square miles)
to Ash Creek. The No Action alternative would not have an effect on riparian resources in Anderson
Junction Wash.
35
DRAFT Environmental Assessment
Ash Creek Pipeline and Toquer Reservoir
3.4.3 Environmental Impacts—Alternative B-Proposed Actions
3.4.3.1 Ash Creek
The Ash Creek pipeline would not affect the spring flows in Deadman Hollow or the riparian community
near and upstream of its confluence with Ash Creek. The Proposed Actions would have a beneficial impact
on the riparian zone within the existing Ash Creek reservoir. With outflow into the proposed Ash Creek
pipeline, water retention time within the existing reservoir is estimated to be reduced to less than 30 days.
The riparian zone would be expected to increase within the existing Ash Creek Reservoir basin with the
reduced retention, reduced pool elevation, and continuous flow. Resident seed source is available in the soil
and this transition would occur over time as previously inundated soils dry out and continuous flow carves
a stream channel. This newly developed or restored riparian zone could increase the riparian zone by
approximately 3,200 linear feet throughout the length of the existing Ash Creek Reservoir. The Ash Creek
stream channel beneath the existing reservoir would be expected to eventually revert back to a riparian zone
dominated with tree species similar to conditions found upstream of Ash Creek Reservoir. The beneficial
impact is negligible in the short-term increasing to moderate over the long-term.
3.4.3.2 Leap Creek
The Proposed Actions would extend the existing pipeline from the existing Leap Creek diversion. The
pipeline would be extended approximately 11,179 linear feet to connect with the proposed South Ash Creek
pipeline near Pintura. Approximately 16,734 linear feet of Leap Creek's natural channel would convey an
estimated annual average of 399 acre-feet less water than the current conditions (Alpha 2019). It can be
expected that some impacts to riparian trees within the natural channel could occur. Since an estimated
annual average flow volume of 1,343 acre-feet (77% of annual surface flows) would bypass the diversion
and continue down the natural channel the potential impacts to the riparian zone are considered minor over
the long-term.
3.4.3.3 South Ash Creek
The impacts would be the same as analyzed in Section 3.4.2.3.
3.4.3.4 Wet Sandy
The Proposed Actions would provide additional storage capacity for the diversions from Wet Sandy. An
annual average 268 acre-feet of additional flows would be diverted at the Wet Sandy diversion with an
estimated annual average of 758 acre-feet bypassing the diversion. Since the low flows of Wet Sandy are
currently diverted during the entire growing season, there would be little to no new or additional impact to
the riparian species of the natural stream channel. Impacts to riparian zones along the natural Wet Sandy
channel are considered negligible over the long-term.
3.4.3.5 Anderson Junction Wash
The Proposed Actions would inundate 185 acres of Mojave Desert including two ephemeral washes within
the proposed Toquer Reservoir footprint, Anderson Valley Wash and the larger Anderson Junction Wash.
Approximately 2,515 linear feet of Anderson Valley Wash and approximately 5,874 linear feet of Anderson
Junction Wash would be inundated and their surface connection to Ash Creek would be truncated by the
proposed dam. Approximately 15,716 linear feet of Anderson Junction Wash downstream of the dam would
no longer convey surface flows from the upstream portion of Anderson Junction Wash's watershed
(approximately 5 square miles) to Ash Creek. The dam spillway could overflow into the downstream
portion of Anderson Junction Wash and flows from the spillway could therefore reach the perennial portion
of Ash Creek however; it is unlikely the spillway would ever be used as high flows would be handled at
each of the upstream diversions (Leap Cr, South Ash, Wet Sandy).
Cottonwood, coyote willow, velvet ash, desert willow, seep willow, and arrow weed are expected to
propagate around the shoreline after the reservoir fills. Riparian trees are expected to increase around the
reservoir site over time resulting in a riparian tree fringe around the reservoir. The reservoir water elevation
36
DRAFT Environmental Assessment
Ash Creek Pipeline and Toquer Reservoir
could range up to 40 feet depending on precipitation, snowpack, season, and water usage. This water level
drawdown zone includes approximately 68 acres of the outer circumference of the reservoir. Marsh wetland
would develop within this drawdown zone over time. The amount of wetland marsh is dependent upon
numerous factors; however it is reasonable to estimate 20 to 40 acres of wetland fringe around the reservoir
based upon similar conditions at Sand Hollow Reservoir. Both of these effects of the Proposed Actions
would be beneficial, long-term, and moderate with the creation of wetlands and the propagation of riparian
tree species in a previously dry upland area.
Biological surveys of the Project Area were conducted between 2009 and 2010 (JBR 2010). Survey target
species included the BLM and State of Utah sensitive species identified above. No sensitive species listed
in the UNHP letter were observed during the surveys, nor were any sensitive species’ nests, roosts, or
habitat areas identified in the Project Area. Surveys were also conducted within 0.5 mile of proposed
construction areas for raptor nests. Three red-tailed hawks (Buteo jamaicensis), one Cooper's hawk
(Accipiter cooperii), one raven (Corvus corax), and two unoccupied stick nests were recorded within the
0.5-mile buffered study area (JBR 2010).
The St George Field Office recognizes that the surveys referenced in this draft EA are outdated, and that
additional surveys for wildlife species will need to be completed in the spring of 2020. We anticipate that
these surveys will reflect the language in the current version of the EA. However, this EA is not to be
finalized until we consider the results of the new surveys. The draft EA may be changed dependent on the
findings of the upcoming surveys.
Virgin spinedace, a native minnow managed under a Conservation Agreement; desert suckers; and
flannelmouth suckers, all resident in the Virgin River, may be found in lower Ash Creek near its confluence
with the Virgin River but only during periods of high seasonal precipitation. When water is present in Ash
37
DRAFT Environmental Assessment
Ash Creek Pipeline and Toquer Reservoir
Creek, these fish may recolonize up to Ash Creek Springs. However, fish do not persist in Ash Creek
downstream of Ash Creek Spring due to ephemeral flows in this reach. Bonneville cutthroat trout, a state-
sensitive and BLM-sensitive species, have occurred naturally in the reaches of Leap Creek and South Ash
Creek above the proposed Project (Hepworth et al. 2003).
Habitat for Arizona toad includes rocky stream courses, streams bordered by willows and cottonwoods,
irrigation ditches, flooded/irrigated fields, and reservoirs (NatureServe 2018a). Such habitat may be found
around Ash Creek Reservoir and some locations south along the Ash Creek channel (UDWR 1997b). If
habitat for common chuckwalla occurs within the Project Area, it would likely be at the southern end in the
vicinity of the proposed Toquer Reservoir. Shelter for this species in the form of rock crevices in rocky
desert in the presence of creosote bush (Larrea tridentata, NatureServe 2018b) is largely absent where
proposed pipelines and the reservoir are to be constructed.
Townsend’s big-eared bats typically roost, hibernate, and give birth in caves and mines (NatureServe 2019)
or day roost in deep crevices in rocky slopes or cliffs. They forage in forested areas, including pinyon-
juniper forest, and are difficult to survey for. Habitat for this species in or near the Project Area would most
likely occur near the section of pipeline that would be constructed adjacent to the first mile of Ash Creek
Canyon downstream of Ash Creek Reservoir or where cliffs approach to less than 0.5 of the Ash Creek
pipeline route near Pintura and Anderson Junction, due to the potential for caves, mines, and deep rock
crevices in these areas.
Wildlife species found in the Project Area during surveys include side-blotched lizard (Uta stansburiana),
desert spiny lizard (Sceloporus magister), Great Basin collared lizard (Crotaphytus bicinctores), tiger
whiptail (Aspidoscelis tigris), Great Basin rattlesnake (Crotalus oreganus lutosus), desert horned lizard
(Phrynosoma platyrhinos), white-tailed antelope ground squirrel (Ammospermophilus leucurus), rock
squirrel (Spermophilus variegates), desert cottontail (Sylvilagus audubonii), black-tailed jack rabbit (Lepus
californicus), desert woodrat (Neotoma lepida), mule deer (Odocoileus hemionus), and kangaroo rat
(Dipodomys spp) (JBR 2010).
The Project Area overlaps with crucial mule deer winter range in the Zion Wildlife Management Unit east
of I-15 from about milepost 29 south to roughly halfway between mileposts 27 to 26. The overlap
encompasses the Ash Creek pipeline from just north of Dry Sandy Creek south to the proposed Toquer
Reservoir, and includes roughly the northern half of the reservoir. Project Area overlap with crucial winter
range west of I-15 in the Pine Valley Wildlife Management Unit encompasses all of the Leap Creek
proposed pipeline and south to include all of the South Ask Creek pipeline, the regulating pool at Pintura,
and all of the existing Wet Sandy Creek pipeline. It also includes all of Anderson Wash west of I-15. See
Figure 3-8 in the Appendix H for Project location and Wildlife Management Units overlap.
Given the size of the analysis area and the variation in land ownership, not all past and present actions
having an impact on fish and wildlife can be accurately identified. However, the primary past and present
actions have included: rural and agricultural development throughout adjacent private lands, municipal and
agricultural water developments, stream diversions, channel alterations, floodplain development,
development and use of recreational facilities, ponds, roads, trails, overhead utility lines, hunting, ranching,
wood harvesting, and mineral mining.
UDOT has installed wildlife fence along the I-15 ROWs through most of the Project Area south to mile
post 27 near the SR-17 Junction to reduce the numbers of car/wildlife collisions. Wildlife guzzlers were
installed along the buried Wet Sandy pipeline in 2010. Domestic livestock and pets associated with existing
homes and ranches are within the area.
38
DRAFT Environmental Assessment
Ash Creek Pipeline and Toquer Reservoir
3.5.2 Environmental Impacts—Alternative A-No Action
Under the No Action alternative, no federal action would occur on federal lands and the Project would not
be constructed as proposed. The existing habitat on BLM-managed lands would remain in its current
condition. Non-federal components of the Project such as the upgrade of the diversion on South Ash Creek
and piping the existing South Ash Creek canal would have a direct and indirect impact on local wildlife
habitat. Since the No Action alternative could still upgrade the existing diversion, it can be expected that
some impacts to riparian trees within the natural channel would also occur. However, since the low flows
of South Ash are currently diverted during the entire growing season there would be little to no new or
additional impact to the low terrace understory of the natural stream channel.
The South Ask Creek diversion and pipeline are within critical wintering range of the mule deer. Water
sources for mule deer and other terrestrial wildlife would be altered, as water from the open ditch diverted
from South Ash Creek would be eliminated. However, water would be made available through two wildlife
guzzlers to be installed on the South Ash Creek pipeline. The trees and vegetation within the 100 feet wide,
approximately 6,966 linear feet (16 acres) pipeline alignment from the South Ash Creek diversion to the
proposed Pintura regulating pond would be removed and any riparian zone that has developed along the
canal would no longer be supported by surface waters from the diversion. Post-construction, the South Ash
Creek pipeline alignment would be revegetated with native upland plant species with the exception of a 14-
foot wide dirt road on top of the pipeline to be used for access and maintenance. This would be a minor
indirect impact on riparian dependent wildlife.
Temporary displacement and harassment of local wildlife due to construction presence and noise
throughout the six month construction period of the South Ash Creek pipeline would occur. Direct impacts
to some small, less mobile individuals would likely occur as they may be killed or injured, or their dens
may be damaged or destroyed during construction activities. Mule deer and larger animals would not likely
be directly impacted by construction equipment because they typically move away from the disturbance
area. Anticipated impacts to fish and wildlife from the No Action alternative would be short-term and minor
to long-term and minor.
No long-term change in BCT habitat would occur since a diversion structure has been operated at South
Ash Creek for decades. The trash screen on the South Ash Creek replacement diversion would likely
prevent entrainment of large BCT. No impacts to BCT populations are anticipated.
3.5.3 Environmental Impacts—Alternative B-Proposed Actions
The construction and maintenance of the Proposed Actions would occur within a small portion of UDWR-
designated mule deer crucial winter range. Efforts to avoid construction in crucial winter range between
December 1 and April 15 would minimize disturbance to mule deer. There is ample suitable adjacent winter
range so impacts resulting from construction activity would be minor. Deer would be expected to return
once construction activity has been completed and no long-term adverse effects would be anticipated.
Impacts of the non-federal components along the South Ash Creek from the diversion upgrade and pipeline
would be the same as the No Action alternative analyzed in Section 3.5.2.
Other wildlife, including Townsend’s big-eared bat, also may be temporarily displaced by surface
disturbance, noise, and increased human presence during construction activities. These animals would be
expected to return after construction activities cease. Some smaller, less mobile wildlife may be killed
during construction activities. A small amount (4.7 acres) of habitat would be permanently lost due to the
construction access and maintenance roads. However, this loss would be negligible due to the abundance
of available habitat in the surrounding landscape and it is unlikely that local wildlife populations would be
affected long term.
The most frequent disturbance post-construction is expected to be the monthly opening and flushing of the
diversion dam sluice gates as well as managing water levels at Toquer Reservoir by manipulating the
39
DRAFT Environmental Assessment
Ash Creek Pipeline and Toquer Reservoir
diversion gates, requiring regular vehicle presence on the access roads and human presence at the
diversions.
Habitat in Ash Creek Reservoir would change from that of a usually dry lakebed to a linear riparian wetland
zone. Establishment of this riparian corridor could be beneficial to local and migrating avian species.
Surface flows in the stream channels below the Leap and Wet Sandy diversions would continue to overtop
the diversions during spring runoff, providing pockets of water for local wildlife populations. Potential
habitat for Arizona toad in Ash Creek Reservoir would shift over time from the current location to the
expected linear riparian area. It is expected that the species would follow the shift, so any corresponding
loss of individuals due to change in habitat location in Ash Creek Reservoir would be minor. Potential
Arizona toad habitat in Ash Creek could be diminished or lost, as overflow from Ash Creek Reservoir
would be reduced once the Ash Creek pipeline becomes operational.
The proposed Toquer Reservoir, spillway, and recreation site would displace local wildlife species to
adjacent suitable habitat on a long-term basis as long as the structures are in place. Some mortality of
resident individuals could occur during construction/filling of the reservoir or if displaced individuals do
not find suitable habitat nearby once construction has begun. While this loss cannot be quantified, it would
be anticipated to be low. In the long term, the reservoir would provide a water source, aquatic habitat, and
marsh/wetlands which, in combination with fish stocked in the reservoir serving as a prey source, would
attract waterfowl, resident or migrating bird populations, bats, and other species. Riparian vegetation
established around the reservoir would provide long-term habitat for a variety of species, to include BLM-
sensitive species. Effects to common chuckwalla would be minimal; habitat for this species is largely absent
in the southern end of the Project Area.
An indirect effect of the implementation of the Proposed Actions could include increased wildlife mortality
due to vehicle collisions on new access roads or increased use of existing access roads. Wildlife may also
be temporarily displaced during maintenance activities on the roads due to an increase in noise. The
projected losses of habitat and impacts to wildlife are not expected to exceed a threshold of significance
that would require new listings of species under the ESA. No long-term or significant impacts to populations
of wildlife, including BLM-sensitive species are anticipated.
40
DRAFT Environmental Assessment
Ash Creek Pipeline and Toquer Reservoir
3.5.5 Mitigation
WCWCD contractors will not be allowed to have firearms, air guns, or archery equipment or pets on the
project sites. To prevent entrapment of wildlife during construction, any open pits or trenches would be
monitored throughout the construction day. At the beginning of the construction day and before pits or
trenches are filled, they would be inspected for trapped animals. If any animals are found, they would be
moved out of harm’s way. No rodenticides would be used on project sites. Encounters with a protected
species (e.g., raptors, migratory birds, or listed or sensitive species) would be reported to the BLM and/or
the appropriate oversight agency (e.g., USFWS). Any contractor or employee who inadvertently kills or
injures a protected species would immediately report the incident to the BLM and/or the appropriate
oversight agencies.
During biological surveys conducted by JBR in 2010, out of the 12 migratory BCC, only the gray vireo
(Vireo vicinior). The gray vireo is a summer migrant, nesting in Washington County in pinyon-juniper
woodlands and mountain shrub habitat. JBR biologists also located one inactive and four active raptor nest
sites in the Project Area. The active nest sites included three red-tailed hawks and one Cooper’s hawk. No
raptor nests were located in or around the Proposed Toquer reservoir. Information on the remaining BCC
species identified by IPaC is in Appendix L.
The St George Field Office recognizes that the surveys referenced in this draft EA are outdated, and that
additional surveys for migratory birds will need to be completed in the spring of 2020. We anticipate that
these surveys will reflect the language in the current version of the EA. However, this EA is not to be
finalized until we consider the results of the new surveys. The draft EA may be changed dependent on the
findings of the upcoming surveys.
Past and present actions include various types of habitat alterations. Ash Creek Reservoir and the presence
of irrigation ponds and stock ponds have increased stopover habitat for migratory birds within the analysis
area. Lands within the Project Area have been planted into agricultural fields and fruit orchards.
Developments have been landscaped with lawns, water features, and planted with landscape ornamental
trees. Rangelands have been grazed and rangeland improvement measures have been implemented to
increase productivity. Historically, riparian trees as well as pinyon pine trees have been harvested for wood.
Several landscape scale wildland fires have impacted portions of the Project Area, the most recent occurring
about 10 years ago. Migratory bird habitat of varying acreages, particularly near and adjoining sections of
Leap Creek and South Ash Creek in the Project Area, was burned. Some burned riparian vegetation in
stream areas consistently receiving flow or ephemeral flow may have recovered; while vegetation in burned
41
DRAFT Environmental Assessment
Ash Creek Pipeline and Toquer Reservoir
upland areas may still be in recovery. The past and present actions in the analysis area have had a positive
impact on the recorded population numbers and species of migratory birds.
42
DRAFT Environmental Assessment
Ash Creek Pipeline and Toquer Reservoir
infrequent and would not be expected to lead to detectable changes in migratory bird populations or habitat.
Overall, impacts to migratory birds and raptors from the Project are expected to be long-term and minor.
3.6.4 Cumulative Effects
3.6.4.1 Alternative A-No Action
The past and present actions are expected to continue over the reasonably foreseeable future as outlined in
Section 3.6.1. Additional new developments with ornamental landscape vegetation could be planted in the
analysis area. Some agricultural fields could be developed into housing developments. Some private
rangelands could graze increased stock numbers or be converted into agricultural fields. Anthropogenic
impacts are expected to continue within the analysis area altering migratory bird habitat. Under the No
Action alternative, the cumulative impacts to migratory birds within the analysis area would be the same as
those described for fish and wildlife and BLM-sensitive species, excluding USFWS-designated species in
Section 3.5.4.1.
3.6.4.2 Alternative B-Proposed Actions
The past actions, present actions, and RFFAs include those activities addressed in Section 3.6.4.1. The
cumulative impact of the Proposed Actions on migratory birds when combined with past, present and
reasonably foreseeable future actions is negligible in the long-term similar to that described in Section
3.4.5.2 for fish and wildlife and BLM-sensitive species.
3.6.5 Mitigation
In order to avoid or reduce impacts on nesting success of raptors, activities would not occur within
recommended spatial and seasonal buffers, and would follow Utah BLM BMPs for Raptors and Their
Associated Habitats in Utah (August 2006). If existing topography limits actual line-of-sight of between an
active nest (i.e., the nest has eggs or young) and construction activities, the spatial and seasonal buffer may
be reduced. There would be no difference between the Project’s impacts described above and residual
impacts.
JBR surveys revealed no tortoise use in the project area in 2010. An additional survey in 2013 when the
Project footprint was realigned also revealed no tortoise or tortoise sign (Stantec 2016; JBR 2013). A small
portion of the Project Area for the Ash Creek pipeline overlaps Mexican spotted owl designated critical
habitat in the first mile downstream of Ash Creek Reservoir.
The St George Field Office recognizes that the surveys referenced in this draft EA are outdated, and that
additional surveys for Threatened, Endangered, and Candidate animal species will need to be completed
in the spring of 2020. We anticipate that these surveys will reflect the language in the current version of
the EA. However, this EA is not to be finalized until we consider the results of the new surveys. The draft
EA may be changed dependent on the findings of the upcoming surveys. The BLM will consult with the
USFWS accordingly.
43
DRAFT Environmental Assessment
Ash Creek Pipeline and Toquer Reservoir
Four listed plant species identified as potentially occurring in the Project Area—dwarf bear-poppy
(Arctomecon humilis), Holmgren milk-vetch (Astragalus holmgreniorum), Jones cycladenia (Cycladenia
humilis var. jonesii), and Shivwits milk-vetch (Astragalus ampullarioides)—have elevational limitations
or specific substrate requirements which preclude them from occurring in the vicinity of the Project Area.
Past actions include the federal listing of seven wildlife species that could occur within lands across the
Ash Creek Watershed. The USFWS, in cooperation with the Peregrine Fund and the BLM, released
experimental individuals of the endangered California condor from the Vermillion Cliffs Area in nearby
Arizona. With the release of the condor, an experimental population and range was established which
includes the east side of I-15 within the Ash Creek watershed. Individual condors that extend their range
beyond the boundaries of the experimental range receive full federal protection in accordance with the ESA.
Threats to condor include being struck by a vehicle while feeding on carrion on a road and lead poisoning
from eating carrion shot with lead bullets. UDOT in cooperation with UDWR installed large game fence
along the I-15 corridor through the Project Area to reduce wildlife collisions. Utah Highway Patrol actively
removes large carrion from I-15 as safety precautions for vehicles, which indirectly act as a safety
precaution for carrion scavengers. Wildlife managers and agencies have and continue to implement
educational awareness programs on the consequences of lead ammunition on wildlife as well as
reimbursement programs for lead ammunition.
3.7.1.1 Mexican spotted owl (MSO)
Currently, there is approximately 8.6 million acres of Designated Critical Habitat for the MSO in Arizona,
Colorado, New Mexico, and Utah. The Recovery Plan for the MSO (USFWS 1995) provides for three
levels of habitat management; protected areas, restricted areas, and other forest and woodland types. The
northern extent of Ash Creek Pipeline runs parallel to the eastern edge of MSO Recovery Unit CP-11. The
pipeline will encroach on approximately 19 acres of Designated Critical Habitat along the southwestern tip
of this recovery unit. The habitat at this location is not suitable nesting habitat for the MSO and lacks the
Primary Constituent Elements (PCE) such as canyon walls containing crevices, ledges, or caves, and the
forested areas are sparse pinyon-juniper habitat lacking a shade canopy of tree branches covering more than
40% of the ground.
No owl nests were recorded within a 3-mile radius search of the 100-foot buffered Project area (UDWR
2019). This area is BLM-managed land and it is not within the boundaries of the adjacent Black Ridge
Wilderness Area or Zion National Park. As per the Recovery Plan (USFWS 1995), this area is considered
“other forests and woodland types” and not “restricted” or “protected” habitat because it is not within a
wilderness area and the UDWR does not have records of existing nest sites.
3.7.1.2 Southwestern willow flycatcher
Designated Critical Habitat for the flycatcher in Utah includes the Virgin River and its 100-year floodplain
from the Arizona state line upstream to Berry Springs (located just upstream of the State Route 9 Bridge
over the Virgin River). Southern Utah contains the north-central limit of the flycatcher’s breeding range.
Throughout its range, the flycatcher’s distribution follows that of its riparian habitat; relatively small,
isolated, and, widely dispersed locales within a vast arid region.
There is no suitable nesting flycatcher habitat within the Ash Creek system, with riparian vegetation limited
by lack of streamflow in the lower reaches of Ash Creek, Leap Creek, South Ash Creek, and Wet Sandy
Creek. Along most sections of these streams, riparian vegetation is typically xeric with spaced mature
woody species and very little understory (JBR 2013a). Existing diversions, the Ash Creek dam, low summer
surface flows, topography, substrate, and seasonal run-off events limit the ability of Ash Creek to develop
the riparian habitat structure suitable for nesting SWFL; particularly the lack of substrate and low gradient
surface water. Some riparian vegetation is present on North Ash Creek at the inlet to the existing reservoir,
on Ash Creek at the Ash Creek/ Deadman Hollow confluence, along Lower Ash Creek downstream of
Toquerville Springs to the confluence with the Virgin River, and on South Ash Creek upstream of the
44
DRAFT Environmental Assessment
Ash Creek Pipeline and Toquer Reservoir
diversion structure. However, these small pockets of riparian vegetation are not suitable nesting sites as
they lack lentic waters with a mosaic of dense marsh and riparian shrub species that comprise suitable
nesting habitat. Transient flycatchers could use the riparian vegetation found at these areas as stop over
areas during migration.
The St. George BLM Field Office conducted a habitat assessment on Ash Creek upstream of Toquerville
on May 5, 2009 (BLM 2009). The area was determined unsuitable habitat due to scouring floods at
sufficient frequency and magnitude to prevent the maturation and maintenance of suitable habitat. Water
flows do not persist for sufficient duration to establish riparian vegetation suitable for nesting habitat. No
flycatchers were observed during field surveys performed from 2009-2010 (Stantec 2016). Designated
critical habitat or suitable habitat are not present in the Project Area.
45
DRAFT Environmental Assessment
Ash Creek Pipeline and Toquer Reservoir
effect on SWFL or its designated critical habitat. The No Action alternative would have no effect on the
Western yellow-billed cuckoo or its proposed designated critical habitat.
3.7.3.2 SWFL
Nesting is not expected within any portion of the Project Area as no suitable nesting habitat is present. The
Project Area lacks PCE 1 riparian vegetation. Some riparian trees will be removed for construction;
however, all vegetation removal will be planned to occur during the non-breeding season, September 1
through April 15. Any loss or alteration of riparian vegetation has the potential to cause an indirect effect
on flycatchers that could potentially migrate through the Project Area. These effects are expected to be
negligible in the short term as the habitat within the Project Area is sparse and not expected to be occupied
except potentially on a transient basis, if at all.
In the long term, the effects of habitat loss are also expected to be negligible due to the very small loss of
riparian vegetation and the lack of suitable nesting habitat in the Project Area. Additionally, restoration
efforts will contribute to the recovery of riparian vegetation that was disturbed during construction (refer to
Section 3.4). Noise and presence associated with construction could cause transient flycatchers to disperse
or alter their movement patterns. Since there are not any known nesting sites and/or occupied habitat is
greater than 0.5 miles from the planned construction areas, this indirect effect is considered negligible.
Due to the potential for Project disturbance to displace SWFL from any potential stop over habitat in the
Project Area and the potential for temporary construction presence or noise related effects on flycatcher
movement, it is determined that the Project may affect, but is not likely to adversely affect the SWFL.
The Project will not result in direct or indirect disturbance to Designated Critical Habitat for the SWFL.
Ash Creek watershed groundwater passes beneath and does not enter the Virgin River or its floodplain
46
DRAFT Environmental Assessment
Ash Creek Pipeline and Toquer Reservoir
(Rowley et al 2018), and so changes to the distribution or amount of groundwater resulting from the Project
is not anticipated to affect Designated Critical Habitat for the SWFL. Therefore, the Proposed Actions will
have no effect to Designated Critical Habitat for the SWFL.
3.7.3.3 WYBC
Because small amounts of riparian vegetation will be disturbed for construction of the South Ash Creek
diversion structure, the South Ash Creek pipeline, and the Ash Creek pipeline below the existing Ash Creek
dam, and because reduced water retention time in the existing Ash Creek Reservoir may result in some loss
or change of riparian vegetation at the inlet, the Project may have an indirect effect on potentially suitable
cuckoo habitat. Any change to riparian habitat has the potential to impact cuckoos that may be present as
they would be displaced into undisturbed habitat, adjacent to the site or elsewhere. These effects are
expected to be negligible in the short term as the habitat within the Project area is sparse and expected to
be occupied only on a seasonal transient basis. In the long term, the effects of habitat loss are also expected
to be woodlands within the Project area. Similarly, noise associated with construction could cause cuckoos
to disperse or alter their movement patterns. The effects of noise are expected to be negligible due to the
fact that the riparian habitat within the Project area is sparse and at most would only be occupied on a
seasonal basis.
The Project will not result in direct disturbance to proposed Designated Critical Habitat for the yellow-
billed cuckoo as the Project area is more than 10 air miles away from the closest proposed Designated
Critical Habitat. Any projected water uses associated with the Project will not be of a magnitude sufficient
to affect proposed Designated Critical Habitat of the cuckoo in Washington County.
Due to the potential for Project disturbance to displace cuckoo from any potentially suitable habitat in the
Project area and the potential for temporary construction or noise related effects, it is determined that the
Project may affect, but is not likely to adversely affect the yellow-billed cuckoo. There will be no effect to
the Designated Critical Habitat for the yellow-billed cuckoo from the Proposed Actions.
47
DRAFT Environmental Assessment
Ash Creek Pipeline and Toquer Reservoir
3.8 Vegetation, excluding USFW Designated Species
3.8.1 Affected Environment
Vegetation in the Project area is typical of the transition zone between the Mojave Desert, Great Basin
Desert, and the Colorado Plateau, comprised of seven ecological systems as delineated by Logan Simpson
Design (LSD 2011). A complete list of vegetation recorded during site surveys is included in the biological
report (JBR 2010) in Appendix J. No populations of the BLM-sensitive species are known to occur within
the Project area.
The most prevalent vegetation community located in the Project area is the Great Basin pinyon-juniper
woodland. Primary species in this upland community include Utah juniper (Juniperus osteosperma)
singleleaf pinyon (Pinus monophylla), blackbrush (Coleogyne ramosissima), Mormon tea (Ephedra spp.),
pointleaf manzanita (Arctostaphylos pungens), broom snakeweed (Gutierrezia sarothrae), big sagebrush
(Artemisia tridentata), live oak (Quercus virginiana), and skunkbush sumac (Rhus trilobata). Utah
serviceberry (Amelanchier utahensis) is dominant on the basalt cliffs, talus, and steep slopes of lava flows.
Mojave Desert vegetation occurs only at the southernmost portion of the Project area at the proposed Toquer
Reservoir site. Dominant species include blackbrush, Mormon tea, Utah juniper, sand sage (Artemisia
filifolia), and Fremont's indigo bush (Psorothamnus fremontii), with some creosote bush (Larrea tridentata)
and white bursage (Ambrosia dumosa).
The potential occurrence of the BLM listed sensitive species, pinyon penstemon (Penstemon pinorum), to
occur within the Project area was evaluated. Surveys of the Project area by JBR did not locate this species
(JBR 2010). The nearest known populations of the species are located in southern Iron County on the Dixie
National Forest. Therefore, it has been determined that the penstemon does not occur within the Project
area.
Riparian vegetation found in some reaches along Ash Creek and its tributaries are described in Section 3.4.
Some vegetation in the Project Area may have been disturbed by past activities resulting in the vegetation
being crushed, invasion of weeds and nonnative species, the altering of native vegetation or even the
permanent loss of vegetation. Past actions that have disturbed vegetation also include historic harvesting of
woodlands for building materials and firewood. Disturbances also include buried utilities, overhead utilities,
dirt roads, paved roads, water diversion structures, cattle grazing, recreational OHV impacts, sand and
gravel operations, rangeland improvement efforts, agricultural uses, and development of private lands.
Presently no woodland harvesting is permitted on public lands within the Project Area.
Wildfires have been the primary impact to vegetation within the project area. Approximately 70-80%
percent of the Ash Creek watershed, over the past 25 years, has burned. The BLM has implemented
reseeding efforts on the burned areas when it has been determined that the efforts would be beneficial.
Wildfire prevention and management effort involving the thinning of Pinyon and Juniper trees, primarily
along I-15 has also impacted vegetation in those areas.
48
DRAFT Environmental Assessment
Ash Creek Pipeline and Toquer Reservoir
3.8.3 Environmental Impacts—Alternative B-Proposed Actions
The proposed pipelines, reservoir, spillway, recreation area, access roads, and other facilities associated
with the Proposed Actions would result in the temporary construction disturbance of 266.9 surface acres
(182.7 acres of BLM-managed lands) and the permanent new disturbance of 161.1 surface acres (128.7
acres of BLM-managed lands). See Table 2-1 in Chapter 2 for total temporary and permanent surface
disturbance of BLM, private, and SITLA lands.
The pipelines would be buried and most of the proposed pipeline route is in already disturbed areas,
however some disturbance is still necessary. Terrestrial vegetation found where the proposed Toquer
Reservoir, spillway, and recreation area (approximately 171 acres of BLM-managed lands and 14 acres
private lands of the total 428 disturbed acres) would be lost as long as the structures are in place. Outside
of the construction ground disturbance, impacts within the 100-foot temporary construction ROW would
consist of the transport and staging of vehicles, equipment, and materials; parking; and foot traffic.
Vegetation removal would be kept to that necessary to install and maintain the project and temporarily
disturbed areas (266.9 acres) would be seeded using a certified weed-free seed mix approved by the BLM.
Any brush removed during construction would be used as mulch after reclamation activities and any trees
felled would either be left on site as down woody debris or removed. It is anticipated that vegetation would
return within the 50-foot-wide permanent ROW, narrowing the ROW into a 14-foot pipeline service route
over time.
Impacts from project implementation to native vegetation would continue in the long-term until reclamation
is complete and vegetation is re-established. Vegetation would be negatively affected in the short-term, but
positively affected in the long-term. The amount of change within the area would be small but detectable.
Therefore, the Proposed Actions would have a direct, minor, negligible impact on vegetation in the short-
term, but an indirect, minor, positive impact on native vegetation in the long-term.
3.8.4 Cumulative Effects
3.8.4.1 Alternative A-No Action
The past and present actions are expected to continue over the reasonably foreseeable future as outlined in
Section 3.8.1. The RFFAs, and other future actions that would contribute the most to direct loss of
vegetation are activities that involve ground disturbance, which could occur on both private and public
lands in the CIA. Development of linear ROWs like a waterline or powerline results in mostly temporary
disturbances that are rehabilitated and much of the construction footprints of the ROWs revegetate over
time (e.g., the area under a powerline or the surface above a buried waterline). Furthermore, all ROWs are
required to adhere to construction practices and reclaim temporary disturbance areas to pre-construction
conditions, which minimizes adverse effects on vegetation. The amount of impact expected from the other
future actions described cannot be quantified at this time. The potential for catastrophic wildland fires exists
but effects of any future fires on vegetation are also unquantifiable.
The cumulative impacts of the No Action alternative combined with past, present, and the RFFAs would
not cause noticeable changes to native vegetation communities within the CIA, and any impacts would be
at or below the level of detection. Therefore, the No Action alternative, when combined with the past and
present actions and the RFFAs in the CIA would have short-term and negligible cumulative impacts to
vegetation.
3.8.4.2 Alternative B-Proposed Actions
The past actions, present actions, and reasonably foreseeable future actions include those activities
addressed in Section 3.8.4.1. The Proposed Actions would involve revegetation activities which could have
a short-term, negative impact but a positive long-term impact to 266.9 acres (182.7 on BLM-managed
lands) of vegetation as the area is rehabilitated.
The Proposed Actions would temporarily and permanently disturb vegetation. Disturbance from the
49
DRAFT Environmental Assessment
Ash Creek Pipeline and Toquer Reservoir
Proposed Actions is expected to be a short-term, minor impact since all temporary disturbance would be
revegetated with native species. Successful reclamation would lessen vegetation impacts as
reseeded/planted areas become established. Reclamation practices for future disturbances would reduce
impacts overall; the seeded areas would likely take many years to begin showing a natural growth of shrubs
seeding in from adjacent areas, in addition to the planted species. Vegetation structure and composition
would be altered in developed, disturbed, and reclaimed areas. When considered with past, present, and the
RFFAs, the cumulative impact of the Proposed Actions on vegetation is long-term and minor.
3.9 Lands/Access
3.9.1 Affected Environment
Lands/access disturbances from past and present actions within the area is evident. These include buried
utilities, overhead utilities, dirt roads, paved roads, water diversion structures, cattle grazing, recreational
OHV impacts, sand and gravel operations, wildfire prevention, wildfire management, rangeland
improvement efforts, agricultural uses, and development of private lands.
The proposed project is subject to the following rights-of-way:
UTU-028808 Federal Highway Administration
UTU-19787 UTU-72228 Qwest Corporation
UTU-62308 Questar Gas
UTU-93106 Diamond G Ranches
UTU-80299 Town of Toquerville
UTU-76673 UTU-79333 Pacificorp dba Rocky Mtn Power
UTU-63260 BLM, Utah Trust Lands
The proposed Ash Creek pipeline would parallel a portion of a Dominion Energy (Questar Gas) mainline
that was installed in the late 1980s along I-15. An overhead Rocky Mountain Power line parallels the east
side of I-15 and the south side of SR-17. The proposed South Ash/Leap Creek combined pipeline would
cross under the UDOT I-15 interchange at Pintura. The proposed Ash Creek pipeline would cross under
SR-17 at Anderson Junction and a portion of the Ash Creek pipeline would be installed within the existing
UDOT-owned I-15 frontage road through Pintura and Anderson Junction.
The Ash Creek Special Service District owns a wastewater lift station near the northern arm of the proposed
Toquer Reservoir, which is not currently in use. The lift station would be relocated onto nearby land owned
by WCWCD in coordination with Ash Creek Special Service District.
Twenty-three single family homes have been identified along the pipeline routes; 11 homes in Pintura and
12 homes in Anderson Junction.
WCWCD holds the following property interests for use in connection with the Proposed Action:
A proposed 20-acre material borrow pit.
Approximately 20 acres at the west end of the proposed reservoir for access from the frontage road,
some of the recreation area, the west staging area, and the proposed borrow site north of the
proposed reservoir.
An easement for a portion of the pipeline from the proposed dam to the TSWS pond.
The reservoir would be located with the incorporated boundaries of Toquerville City approximately 19
miles northeast of St. George, along the east side of interstate 15 (refer to the POD). The recreation area
included in the R&PP is a 13-acre parcel of BLM land located at the southwestern end of the reservoir. The
reservoir, dam, and the trail around the reservoir include an additional 125.6 acres of BLM-managed land
that will be authorized under the ROW grant. Access to the reservoir and the recreation area will be from
50
DRAFT Environmental Assessment
Ash Creek Pipeline and Toquer Reservoir
SR-17 and will follow the pipeline route across WCWCD owned land (refer to Figure 1). WCWCD will
coordinate with current ROW holders regarding utility needs for the R&PP and ROW holders will request
amendments to their current authorizations for connection spurs.
If the No Action alternative is selected, the WCWCD would likely at some point in the future need to
reconstruct the primitive system on the Ash Creek Reservoir to prevent water loss and would need to find
an alternative alignment on private lands to provide the secondary water transport system to Toquerville.
51
DRAFT Environmental Assessment
Ash Creek Pipeline and Toquer Reservoir
3.9.4 Cumulative Effects
3.9.4.1 Alternative A-No Action Alternative
The past and present actions are expected to continue in the CIA over the reasonably foreseeable future as
outlined in Section 3.9.1. Undoubtedly, the use of the existing paved roads would increase with population
growth. New roads would likely be constructed in the area with development of the surrounding private
lands. Overhead and buried utilities would need to be maintained or upgraded. New utility companies or
cellular telephone companies could likely utilize this existing I-15 corridor given the geographic confines
of the region. Under the No Action alternative, no ROW or R&PP lease would be approved on BLM-
managed lands, therefore the No Action alternative would not have an impact on lands and access. When
combined with past, present, and the RFFAs, no cumulative impacts of the No Action alternative within
the CIA would occur.
3.10 Recreation
3.10.1 Affected Environment
Currently, there is little recreational use of the Project Area. The road along the pipeline alignment and
through the reservoir site experiences limited OHV, mountain bike, and horseback riding use. Although
there are no designated trails for these uses, the public lands surrounding the Project Area are designated
“open” for mountain bike use and horseback riding.
The Ash Creek Reservoir is located on private land and is not managed for recreational uses. There are no
developed recreational facilities such as a boat ramp, parking area, or picnic tables. Access to the reservoir
is not controlled, so when the reservoir is dry, some local residents ride horses and hike within the
reservoir’s water storage area. When there is water present, there are some occasional recreational water
activities such as non-motorized boating that take place on the reservoir.
52
DRAFT Environmental Assessment
Ash Creek Pipeline and Toquer Reservoir
riding. The long-term recreation benefits of the reservoir would not be realized. This would be a long-term,
minor impact.
3.10.3 Environmental Impacts—Alternative B-Proposed Actions
Impacts to current recreational use of the Project Area would be negligible. The new recreation area and
multi-use non-motorized trail around Toquer Reservoir would be a long-term beneficial impact to outdoor
recreation in Washington County. Outdoor recreation within the Project Area could be disrupted during the
15-month construction period of the Proposed Actions. However, recreation use within the Project Area is
currently limited so any disruptions resulting from construction activities would be limited in scope. If
needed, alternate access routes to adjacent public lands are available.
Development of the proposed Toquer Reservoir and adjacent Toquer Recreation Area would provide
additional recreation opportunities, increasing the area available for:
Water surface for small non-motorized watercraft and fishing boats
Hiking trails
Primitive camping and RV sites
Day use activities
Birding
Other added recreational-related facilities would include a paved boat ramp, parking, picnic tables,
barbeque pits, toilets, interpretive and regulatory kiosks, and a covered pavilion.
The long-term impact of the proposed Toquer Reservoir and adjacent Toquer Recreation Area would be to
increase the availability of aquatic recreation in Washington County and could impact aquatic recreational
use on existing recreational sites in Washington County such as Quail Creek State Park, Sand Hollow State
Park, Zion National Park, and other areas of dispersed camping on public lands. Presence of the reservoir
near the I-15/SR-17 interchange would likely attract some use from Zion National Park visitors on SR-17.
The tent and RV sites at the recreation area would help to alleviate some general camping congestion
connected to Zion. Given there are only 10 tent sites and 10 RV sites, the impact to camping would be long-
term and negligible.
3.10.4 Cumulative Effects
3.10.4.1 Alternative A-No Action
The past and present actions are expected to continue over the reasonably foreseeable future as discussed
in Section 3.10.1. Pressure on public lands is expected to continue in Washington County with population
growth and public need, particularly when coupled with the current management direction of city officials
and the public land agencies. Various recreation support facilities would be constructed on public and
private lands in the foreseeable future. Under the No Action alternative, the Proposed Actions would not
be approved, however the impacts to recreation would be minor increasing to moderate over time; therefore
the cumulative impacts of the No Action Alternative in conjunction with past, present, and the RFFAs on
recreation would be minor for the short-term and increase to moderate in the long-term as the need for
recreational areas within the Washington County increase.
53
DRAFT Environmental Assessment
Ash Creek Pipeline and Toquer Reservoir
the analysis area would increase the recreational resource value of the area. Adding the Toquer Reservoir
and camping facility to the wide variety of existing recreation facilities in the county would not have
noticeable effect on visitor use of the existing facilities because the proposed facility is relatively small and
increasing public need would outpace a noticeable effect. The cumulative impacts of the Proposed Actions
on recreation in conjunction with past, present, and reasonably foreseeable future actions would be long-
term and minor.
54
DRAFT Environmental Assessment
Ash Creek Pipeline and Toquer Reservoir
KOP 1 Figure: View to the south from KOP 1 at the existing conditions.
KOP 2 is located along I-15, just east of the north bound lanes. The view from KOP 2 is looking southeast
at VRM Class III lands in the Project Area (KOP 2 Figure). This KOP is situated between two hills where
the project would be visible. At KOP 2, people in vehicles traveling north bound on I-15, or on the frontage
road east of I-15, would have a view of the reservoir and dam. The viewing time would be short as the hills
located on either side would block the view as the vehicles pass by. The open landscape is dominated by
the diagonal and horizontal lines created by the hills against the skyline, and irregular and patchy shapes of
vegetation on low rises and plains. A fence line in the foreground adds vertical and horizontal human
elements to the surrounding natural landscape, as would the existing roads being traveled on.
55
DRAFT Environmental Assessment
Ash Creek Pipeline and Toquer Reservoir
existing roads being traveled on.
KOP 3 Figure: View to the east from KOP 3 near the frontage road south of KOP 2.
56
DRAFT Environmental Assessment
Ash Creek Pipeline and Toquer Reservoir
KOP 1 Simulated Figure: View to the south from KOP 1 with the proposed reservoir simulated. Note that
the building and rock debris are gone.
At KOP 2, people in vehicles traveling north bound on I-15, or on the frontage road east of I-15, would
have a short viewing time limited by the two hills on either side of the reservoir. Overall the visual change
at KOP 2 is minor in terms of color and horizontal lines, the change would be long-term. This impact is
within the limitations of the Class III visual resource objectives.
KOP 2 Figure: View of KOP 2 with the constructed dam and reservoir at high water elevation
simulated.
3.11.4 Cumulative Effects
3.11.4.1 Alternative A-No Action
The past and present actions are expected to continue over the reasonably foreseeable future as outlined in
Section 3.11.1. Future actions on BLM-managed lands would be consistent with the current RMP and any
new Proposed Actions would be subject to NEPA analysis. Actions on state lands would be consistent with
the current state lands guidelines. Private lands are within Toquerville municipal boundaries and current
zoning would apply. Some development of private lands consistent with normal growth projections within
57
DRAFT Environmental Assessment
Ash Creek Pipeline and Toquer Reservoir
the analysis area is anticipated. Under the No Action alternative, the Proposed Actions would not be
approved, and no visual resources would be impacted; therefore, no cumulative impacts to visual resources
would occur.
3.11.4.2 Alternative B-Proposed Actions
The past actions, present actions, and the RFFAs include those activities addressed in Section 3.11.4.1. The
visual impact of the Proposed Actions would contribute to changing the visual impression of the area from
undeveloped to more developed. The long-term cumulative impacts to visual resources when considered
with past, present and the RFFAs would depend on the location of the viewer, but would be minor.
4.0 CONSULTATION AND COORDINATION
4.1 Summary of Consultation and Coordination
List of all Persons, Agencies, and Organizations Consulted for Purposes of this EA
Purpose & Authorities for
Name Findings & Conclusions
Consultation or Coordination
United States Fish & Informal Consultation, under Biological Assessment findings and conclusions
Wildlife Service Section 7 of the ESA (16 USC are outlined in this document. USFWS review of
1531) the final Biological Assessment is in process.
United States Army Consultation for undertakings, as Preliminary Jurisdictional Determination SPK-
Corps of Engineers required by the CWA (33 USC 2011-01121 to WCWCD dated February 12, 2014.
1251) Section 404 permit application will be submitted
with the BLM Decision Record.
Utah State Historic Consultation for undertakings, as MOU from SHPO to BLM dated March 11, 2014,
Preservation Office required by the NHPA (16 USC Case # 09-1388, Concurrence with the proposed
470) Treatment Plan (USHPO 2014).
58
DRAFT Environmental Assessment
Ash Creek Pipeline and Toquer Reservoir
4.3.1 Public Comments Analysis
A document summarizing comments received from the public, agencies, and other interested parties during
both the informal and formal scoping periods was prepared and is on file in the Project record (comment
analysis report provided in Appendix C). Each response was individually read and coded to ensure that
individual comments, concerns, and issues were captured. Coding consists of identifying discrete comments
within each response (letter) and delineating them. Comments were then summarized into “Public
Concerns” by resource topic. When similar comments were combined under a single resource, the scope of
the resource was expanded in the EA. Six scoping responses were extremely similar (or identical) to those
submitted during the pre-scoping by the same individual, official, or organization. In these cases, the pre-
scoping response was replaced by the scoping response within the analysis to avoid duplication.
Comments were received from the following organizations or affiliations.
● Landowner adjacent to Project Area (2).
● Director, NEPA Compliance and Review, EPA.
● Resident, Washington County.
● Resident, Brookside, Utah.
● Mayor, City of Hurricane.
● Director, Washington County Utah Economic Development Council.
● Landowner
● Director, Western Lands Project
● Pintura Irrigation Water Company
● Mayor, Town of New Harmony
● Forest Supervisor, Dixie National Forest
● State Directory, Utah Division of Wildlife Resources
● Director, Hopi Tribe Cultural Preservation Office
● State Directory, Utah Public Lands Policy Coordination Office
● Resident, New Harmony, Utah
● Senior Environmental Specialist, Kern River Gas Company
● Senior Planner, Washington County Department of Planning and Zoning
● Chair, Washington County Commission
● Conservation Biologist, Center for Biological Diversity
● Project Manager, US Army Corps of Engineers
● Region 4 Director, UDOT
● Utah Field Office Supervisor, USFWS
The current Proposed Actions described in Section 2.2 is a result of modifications to the original proposal
based on the public comments received.
5.0 LIST OF APPENDICES
Appendix A- 2019 ID Team Checklist
Appendix B- Scoping Report
Appendix C- Scoping Comment Analysis Report
Appendix D- Plan of Development
Appendix E- Conservation Programs Incorporated into 2015 Water Conservation Plan
Appendix F- Water Rights Analysis
Appendix G- List of Preparers
Appendix H- Figures
59
DRAFT Environmental Assessment
Ash Creek Pipeline and Toquer Reservoir
Appendix I- Tables
Appendix J- Biological Survey and Hydrology Reports
Appendix K- Utah Natural Heritage Program (UNHP)
Appendix L- IPaC Migratory BCC
Appendix M- Hydrogeology Report (Rowley, Dixon, and Layton 2018)
Appendix N- References
60
DRAFT Environmental Assessment
Ash Creek Pipeline and Toquer Reservoir