Академический Документы
Профессиональный Документы
Культура Документы
The above matrix evaluates the risk, severity of the risk and the probability the risk will
occur and how difficult the detection is to discover. The project for Meridian Social Service
Agency included a fixed budget of $90,000 and a tight 30 day schedule. Both risks can be
managed with contingency plans; however they are interdependent upon each other. Simply
stated if delays occur, the more likely the budget could be impacted.
Risks need to be evaluated in terms of likelihood the event will occur and the impact or
consequences of the occurrence. (Meredith, 2009) In terms of the Peak LAN Project,
evaluating the risks proactively proved to be a challenge for the technical risks. Testing the
risks could not be completed prior to installation or deliver of the hardware. The project
manager would need to react to these situations and develop solutions that could result in
increased costs as well as schedule delays. In addition to technical delays, Peak LAN utilized
interns could lead to resource constraints during installation. The project manager could
eliminate this risk by obtaining schedule commitments from the interns so that additional
resources could be contracted to eliminate the shortage of resources.
c. Risk Response
Chapter 7
Excercise
1. Given the project information below, what is the probability of completing the National
Holiday Toy project in 93 time units?
Jawab
𝑂𝑇+4 ×𝑀𝑇+𝑃𝑇
AT = 6
Dimana,
AT : Actual time
OT : Optimum time
MT : Most probable time
PT : Presimistic time
𝑏−𝑎 2
Varians = ( )
6
Dimana,
b : Presimistic time
a : Optimum time
Contoh perhitungan pada ativitas 1:
24−6 2
Varians = ( ) =9
6
AON Network
𝑇𝑠−𝑇𝑒
Z=
√∑ 𝜎𝑡𝑒²
93−86
Z=
√9+4+9+25+1+1
7
Z= =1
√49
P didapatkan dari tabel statistic Standart normal probabilities yaitu 0,84. Dengan nilai z = 1,
maka probabilitasnya adalah 0,84 yang berarti terdapat peluang 84% menyelesaikan proyek
sebelum 86 unit waktu.
2. The Global Tea and Organic Juice companies have merged. The following information
has been collected for the “Consolidation Project.”
Act time
Act Description Predecessor a opt m ml b pess
te
Act Variance
Act Description Predecessor a opt m ml b pess
time te [(b-a)/6]^2
Te = 114
Critical path = 1,5,6,8,12,14,15
d. What is the probability of completing the project by day 112? Within 116 days?
𝑇𝑠−𝑇𝑒
Z=
√∑ 𝜎𝑡𝑒²
112−114
Z=
√4+25+1+9+9+1
−2
Z= = -0,28
√49
P didapatkan dari tabel statistic Standart normal probabilities yaitu 0,39. Dengan nilai z = -
0,28, maka probabilitasnya adalah 0,39 yang berarti terdapat peluang 39% menyelesaikan
proyek sebelum 114 unit waktu.
𝑇𝑠−𝑇𝑒
Z=
√∑ 𝜎𝑡𝑒²
116−114
Z=
√4+25+1+9+9+1
+2
Z= = +0.28
√49
P didapatkan dari tabel statistic Standart normal probabilities yaitu 0,61. Dengan nilai z =
+0,28, maka probabilitasnya adalah 0,61 yang berarti terdapat peluang 61% menyelesaikan
proyek sebelum 114 unit waktu.
Excercise