CPM ACTIVITY

Space X is bringing a new product on line to be manufactured in their current facility in existing space. The owners
have identified 10 activities and their precedence relationships. Develop an AON for the project, determine the
Critical path and calculate for slack.

ACTIVITY IMMEDIATE PREDECESSOR DURATION


(Weeks)
A None 5
B A 2
C A 7
D B, C 15
E D 8
F D 6
G E 6
H F 5
I G, H 4
J I 9

CONNECTED PATHS

PATHS PATH DURATION


A,B,D,E,G,I,J 49
A,C,D,E,G,I,J 54
A,B,D,F,H,I,J 46
A,C,D,F,H,I,J 51

A,C,D,E,G,I,J is the project’s critical path.


ES=5 ES=27 ES=35
EF=7 EF=35 EF=41
ES= 0 LS=10 ES=12 LS=27 LS=35
EF= 5 LF=12 EF=27 LF=35 LF=41 ES=41 ES=45
LS= 0 LS=12 EF=45 EF=54
LF= 5 B (2) LF=27 E (18) G (6 LS=41 LS=45
LF=45 LF=54
A (5) D (15)
I (4) J (9)

C (7) F (6) H(5)

ES=5 ES=27 33
ES=33
EF=12 EF=30 EF=38
LS=5 LS=30 LS=36
LF=12 LF=36 LF=41

ACTIVITY LATE FINISH EARLY FINISH SLACK


A 5 5 0
B 12 7 5
C 12 12 0
D 27 27 0
E 35 35 0
F 36 33 3
G 41 41 0
H 41 38 3
I 45 45 0
J 54 54 0