Академический Документы
Профессиональный Документы
Культура Документы
1.0 Purpose
The purpose of this procedure is to repair and record systematically all defects
encountered during fabrication of structural/Piping/Pressure Vessel and shall serve
as a guideline methods/technique in proceeding with weld repair on defects
detected in weldment and base metal during fabrication.
2.0 Scope
This procedure is applicable for any repair base and weld metal for structural
fabrication work.
This is applicable for the repair of Major Weld Repair, Minor Weld Repair including
Weld Buttering for structural, piping, and pressure vessel.
This procedure provides the guideline for repair of weld defects, base metals and
buttering required on all weld and weld able steel material when repair by welding is
require due to excessive gaps in joint fit up. Repair and buttering shall be carried
out as per approved WPS
3.0 Definitions
4.0 References
5.1 Contractor shall repair or replace all welds made by contractor that do not meet
the requirement of Project spec #1 Projec spec #2, Approved for Construction
(AFC) drawing requirement and/or the applicable codes and standards.
5.2 This procedure shall be used as a guideline for repair of weld defects, base metal
defects, and restoration of base metals and weld metal buttering on weld edges for
joints having excessive gaps. Defects shall be located based on the results of NDT
including visual inspection to suit accessibility and completeness of repair area.
5.3 Each repair & buttering at site shall be reviewed on case-to-case basis prior to
commencement of actual repair or rectification work. Any repair or rectification
work to be carried out shall be requested by PMT and to be monitored by QC. If
required any specific repair sequence or procedure to be made depending on
welding problems encountered during fabrication. Written procedure for major and
minor repairs. Any major repair on weldment is subject for approval of
COMPANY’s authorized representative. Defects shall be clearly identified and its
nature written nears the area to be repair.
5.4 Weld repair shall be classified as major repairs and minor repairs. Identification of
Major and Minor repairs as per Appendix 1.
4. The root cause analysis shall consider the following areas when developing this
portion of the written procedure:
a. Data collection:
I. Conditions existing during welding.
II. Personnel involved.
III. Environmental factors.
IV. Any other information relevent to the repair area or component
b. Assessment.
I. Identifying the problem, such as type, location, and depth of the defect.
Also identify the type, grade and thickness of the base metal containing
the weld defect.
II. Significance of the problem.
III. Identify the cause leading up to and surrounding the problem
IV. Identify the reason why the cause existed.
c. Corrective action.
I. Identify the corrective action for each occurrence. Detail the method of
grinding and removal. The length of repair shall be tapered from the
defect ends by a minimum three times the groove depth or 60 mm
whichever is a greater. Include all work practice required to preheat,
inspect, and/or post weld heat treat the repair zone. The margin of the
preheated area shall be at least minimum three times the base metal
thickness or 50 mm, whichever is a greater.
II. Will the corrective action prevent reoccurrence.
III. Is the corrective action feasible.
d. Inform.
I. Discuss with and explain to COMPANY/CONTRACTOR the result of the
analysis, including corrective action.
e. Follow-up.
I. Identify the methodology that will be followed to determine the
effectiveness of the corrective actions taken e.g. the NDT method which
will detect post repair weld defects. Perform and record the post weld
hardness test, method of testing, and testing equipment being used.
II. A close-out report of each major repair shall form part of the as-built
records, including a copy of NDT report concerning the original detection
of the rejectable defect along with a copy of the NDT report of the repaired
weld. COMPANY approved weld repair procedure together with a sketch
of the type, location and the depth of the defects shall be attached for
project documentation.
1. Prior to the repair of minor defects, the fabricator shall consult with
COMPANY/CONTRACTOR representative to determine if “conditional
acceptance” applies to the minor defect without repair action. This will be
base on fitness for service criteria.
a. Determine rules for assigning minor repair of the weld. Only grinding shall
be utilized to correct subject defects. The defects removal area and
adjacent areas shall be blended to eliminate sharp transitions.
c. Incidental removal of metal within the weld joint in the process of welding
from root to cap is not considered as a repair.
5.5 The welding for all repairs shall be carried out as per the approved WPS for repair
welding. Also it is suggested to clear repair in two attempts. If repair is not clear
even after second attempt, the case shall be brought to the attention of COMPANY
representative by notification. SUBCONTRACTOR Welding Engineer shall
propose appropriate measures repair procedure. All notifications shall be
submitted to COMPANY/CONTRACTOR representative before any repair works.
5.6 If any serious defect is observe in welding, the same shall be notified to
COMPANY/CONTRACTOR representative.
5.7 The repaired weld metal shall be retested by the NDT method originally used
including technique and acceptance criteria. No cracks shall be removed or
repaired by SUBCONTRACTOR without notification to COMPANY/CONTRACTOR
representative. All cracks shall be repaired in accordance with an approved weld
repair procedure.
5.8 Weld repair shall be made using the WPS that are orginally used for the weld joint.
5.9 Excavation of defect shall be verified by MT, as a minimum and could be extended
to other NDT methods, if deem necessary for confirmation.
5.10 If Company considers the proposed repair of the defect to be either non-productive
or detrimental to the completed facility, Contractor shall not repair the defect but
cut out the weld and redo the work.
Weld Repair Protocol
Activity Responsibility
QC Inspector
Request for repair PMT / SUBCONTRACTOR
(WRR)
QC Inspector
Repair PMT / SUBCONTRACTOR
Remove
Weld
Defect
Repair of
Base Metal
Arc burn
defects
Buttering
QC Inspector
NDT
PMT / SUBCONTRACTOR
Release
6.1 Inspection and identification repair
6.1.1 Inspection shall be done in accordance to QC inspector
standard and drawing. Any defects or PMT / Sub-con
discontunities shall be identified.
6.1.2 Refer to Appendix 1 to identified defect either
minor and major defect
6.2 Request for repair (WRR)
6.2.1 WRR shall be prepared prepared identifying QC inspector
. defect type, repair method/technique to be PMT / Sub-con
adapted, defect location & NDT to be
performed prior, in process and after
completion of final repair weld. WRR shall be
approved by COMPANY prior any repair
work. Template of WRR refer to Appendix 2
6.3 Repair
6.3.1 For 1st repair weld, welding shall follow as QC inspector
per initial WPS. For 2nd, 3rd, etc., all work PMT / Sub-con
shall require a weld repair PQR. All repair
method work shall be done as per WRR.
Defects shall be completely removed and
confirmed by NDT to avoid rework.
6.4 NDT
6.4.1 NDT shall be performed after final repair QC inspector
work for acceptance, inclusive of visual
examination and any NDT required as per
WRR
6.5 Release
6.5.1 The repaired items shall be released after all PMT / Sub-con
NDT found acceptable
7.0 Repair Technique.
5. Defect shall be removed by air-arc gouging and well faired while avoiding
unnecessary removal of weld metal and adjacent base metal.
6. Carbon deposited (i.e. dark gray color) and copper sheathing remnants (i.e.
copper inclusion) shall be removed by grinding.
7. Gouged area shall be ground and clean metal throughout the entire surface and
blend smoothly into adjacent weld metal and / or base metal surfaces.
8. Ground excavation shall provide clean weld metal throughout the entire surface –
absent from carbon deposit (i.e. dark grey color) and copper sheathing remnants
(i.e. copper inclusion)
9. The excavated groove shall be prepared for visual examination and if required
with MT for non-visual identifiable surface defects to ensure complete removal of
original defect.
10. Repair welding shall be in accordance with an approved WPS and performed by
a qualified welder;
a. Preheat shall be measured from the edge of the repair weld to a distance
of 75mm minimum in all direction including plate through thickness at the
point of welding.
b. Maximum interpass temperature shall be measured parallel and adjacent
to the weld joint length.
c. Temperature indicating crayon shall never be marked in the weld bevel,
welds beads or the weld surface.
d. The repair by welding shall blend smoothly into the surrounding weld
metal and / or base metal surface avoiding sharp notches, crevice, or
corners.
11. Examination after repair by welding shall follow NDT by the same requirement as
required for the original weld
7.2.1 Where defect are found in the base metal, Contractor shall notify the
COMPANY/CONTRACTOR prior to any repair.
1. Ground area shall be blended smoothly into adjacent base metal and weld
metal surface and be well faired.
7.3.1 Arc strike or burn marks outside welding grooves are not acceptable. The
repair process shall be monitored by COMPANY/CONTRACTOR. Method
for repair shall be as follow:
1. Blend grind the arc strike surface until evidence of the burns is no
longer visible. The ground area shall be not less than 100sq.mm in
area.
7.4 Buttering
7.4.1 All joint fit-ups to be buttered shall be carried out in accordance with
approved WPS for wide gaps as part of WPS qualifications.
7.4.2 No buttering shall be carried out without a written procedure for each
individual wide gap weld.
7.4.3 The written procedure shall be submitted to COMPANY/CONTRACTOR for
review and approval and shall include but not limited to the following:
1. Identification as to primary, secondary, tertiary member.
2. Dimensioned sketch detailing the magnitude of the gap, extend and
location.
3. Company-approved WPS to be used.
4. NDT of final weld area.
7.4.4 Major repair is when weld build-up or buttering to correct manufacturing or
assembly error resulting in a wide gap more than 20 mm.
7.4.6 The maximum allowable root opening for wide gap welding shall be 50 mm.
7.4.8 The wide gap WPS may include breaking the joint apart and buttering one or
more members, in-situ buttering of one or more members, or welding onto
backing material, as qualified in WPS. Any backing material shall be
removed prior to second side welding.
7.4.9 All buttered ends for wide gap welds shall be inspected by RT and be MT
inspected.
7.4.10 No buttering shall be allowed on square cut edges. All buttering shall be
done on base materials that have weld joint preparations.
7.4.11 Fit-ups with root opening exceeding that specified in the approved WPS
shall be re-fitted to bring the root opening within the dimensions allowed by
the WPS prior to commencement of welding.
7.4.12 Weld build up shall be accordance with an approved WPS and performed
by a qualified welder.
7.4.13 Weld build-up shall be performed with the joining members separated
sufficiently apart to provide good access for welding, grinding and
inspection.
7.4.14 A wide gap WPS shall be qualified on the thinnest material and the thickest
material to be used during fabrication.
7.4.15 For single sided welds where separation is not practicable, weld build up
shall be performed by a welder qualified for limited-access welding.
7.4.16 The approved WPS and WRR shall be posted at each welding work place
and shall be readily available to each welder, operator, tack welder,
supervisor and inspector.
7.4.17 Minimum preheat temperature shall be equal or greater than that indicated
within the approved WPS.
7.4.18 Preheat shall be measured along the weld joint length from the edge of the
weld joint to a distance of 75mm minimum in all directions including plate
through thickness.
7.4.19 Maximum interpass temperature shall not exceed that indicated within the
approved WPS.
7.4.20 Interpass temperature shall be measured parallel and adjacent to the weld
joint length.
7.4.21 Temperature indicating crayons shall never be marked on weld bevels, weld
beads or weld surfaces.
7.4.22 Weld build-up may be performed on one or both sides of abutting groove
faces. When abutting members intersect, the continuous through member
shall receive the weld build-up material.
7.4.23 All buttering welds shall be done by using low hydrogen type welding
consumables and preheat and interpass temperature as per approved
WPS.
7.4.24 Buttering shall be done with the smallest practicable diameter of low
hydrogen electrode as per approved WPS. The buttered surface must be
groove smooth to the desired dimension.
7.4.25 The final weld will be made only after the weld joint has been corrected to
the specified WPS root opening tolerance and weld joint dimensions as
indicated on the approved WPS.
7.4.26 The reconstructed weld joint (not the completed weld) shall be prepared for
visual examination, RT and MT to ensure weld metal soundness.
7.4.27 Final welding shall be in accordance with an approved WPS and performed
by a qualified welder
PROJECT : REPORT NO :
CONTRACT NO LOCATION :
JOB NO :
DESCRIPTION :
REPAIR PROCEDURE :
a) Affected area to preheat to _____Deg. Cel. e) Excavated area to be welded by using WPS :
( No-preheat if CRACK defect ) and re-visual.
SKETCH
COMMENT BY CONTRACTOR/COMPANY :
____________________________ ____________________________
(PMT / SUBCON QC INSPECTOR) (CONTRACTOR (COMPANY REPRESENTATIVE)
Date : INSPECTOR) Date :
Date :